Bid Tab_AK FWS KNA 74525(1)_Signed.pdf
PDF 659 KB Posted
- Attached to
- AK FWS KNA 74525(1) Swan Lake Road Project
- Solicitation number
- 69056723B000020
About this file
This document is a tabulation of bids report for solicitation number 69056723B000020 from the Department of Transportation Federal Highway Administration. STG Pacific, LLC provided the lowest bid of $2,458,065 for the AK FWS KNA 74525(1) Swan Lake Road Project, which includes items such as mobilization, construction survey and staking, soil erosion control measures, excavation and borrow, culverts, riprap, aggregate placement, traffic control, housing and vehicles for workers, and stream mitigation work. Four bids were received by the December 7, 2023 deadline and ranged from $2,458,065 to $4,176,346.50. The engineer's estimate was $2,102,475. The contract is anticipated to be awarded by December 2023.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tabulation of Bids Report Date: 12/07/23
1 out of 9
Project No: AK FWS KNA 74525(1)
Project Name: Swan Lake Road Project
Schedule: A
Schedule Type: Base
Solcitation No: 69056723B000020
Division: Western Federal Lands
State: AK County: Kenai Peninsula
Federal Land: Opened at: FHWA Vancouver, WA Office
Opened by: Marino Chea
Date: 12/07/23
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
STG Pacific, LLC $2,458,065.00 3700 Centerpoint Drive, Suite 8155 Anchorage, AK 99503
C.I. Contractors, Inc. $3,313,195.00 229 E. Whitney Road Anchorage, AK 99501
Tutka, LLC $3,418,986.00 2485 E Zak Circle, Suite A Wasilla, AK 99654
Doyon Management Services, LLC $4,176,346.50 3450 South 344th Way Federal Way, WA 98001
Engineer's Estimate $2,102,475.00
2 out of 9
Project No: AK FWS KNA 74525(1)
Project Name: Swan Lake Road Project
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0010 15101-0000 MOBILIZATION
STG Pacific, LLC Lump Sum $229,000.00 C.I. Contractors, Inc. Lump Sum $380,000.00 Tutka, LLC Lump Sum $526,000.00 Doyon Management Services, LLC Lump Sum $524,828.00 Engineer's Estimate ALL LPSM Lump Sum $156,000.00
A0030 15201-0000 CONSTRUCTION SURVEY AND STAKING
STG Pacific, LLC Lump Sum $42,000.00 C.I. Contractors, Inc. Lump Sum $118,000.00 Tutka, LLC Lump Sum $34,000.00 Doyon Management Services, LLC Lump Sum $37,579.00 Engineer's Estimate ALL LPSM Lump Sum $41,000.00
A0050 15301-0010 CONTRACTOR QUALITY CONTROL AND ASSURANCE
STG Pacific, LLC Lump Sum $145,000.00 C.I. Contractors, Inc. Lump Sum $214,000.00 Tutka, LLC Lump Sum $115,000.00 Doyon Management Services, LLC Lump Sum $62,632.00 Engineer's Estimate ALL LPSM Lump Sum $119,000.00
A0070 15401-0000 CONTRACTOR TESTING
STG Pacific, LLC Lump Sum $82,000.00 C.I. Contractors, Inc. Lump Sum $52,500.00 Tutka, LLC Lump Sum $44,000.00 Doyon Management Services, LLC Lump Sum $26,306.00 Engineer's Estimate ALL LPSM Lump Sum $36,000.00
A0090 15501-0000 CONSTRUCTION SCHEDULE
STG Pacific, LLC Lump Sum $10,000.00 C.I. Contractors, Inc. Lump Sum $34,000.00 Tutka, LLC Lump Sum $21,000.00 Doyon Management Services, LLC Lump Sum $31,316.00 Engineer's Estimate ALL LPSM Lump Sum $12,000.00
A0110 15702-6000 SOIL EROSION CONTROL, TEMPORARY STREAM DIVERSION
STG Pacific, LLC Lump Sum $94,500.00 C.I. Contractors, Inc. Lump Sum $206,000.00 Tutka, LLC Lump Sum $140,000.00 Doyon Management Services, LLC Lump Sum $250,527.00 Engineer's Estimate ALL LPSM Lump Sum $48,000.00
3 out of 9
Project No: AK FWS KNA 74525(1)
Project Name: Swan Lake Road Project
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0130 15703-1500 SOIL EROSION CONTROL, TEMPORARY SOIL TACKIFIER
STG Pacific, LLC $9,200.00 $16,560.00 C.I. Contractors, Inc. $11,600.00 $20,880.00 Tutka, LLC $8,700.00 $15,660.00 Doyon Management Services, LLC $6,264.00 $11,275.20 Engineer's Estimate 1.8 ACRE $4,600.00 $8,280.00
A0150 15705-0100 SOIL EROSION CONTROL, SILT FENCE
STG Pacific, LLC $5.00 $2,750.00 C.I. Contractors, Inc. $13.00 $7,150.00 Tutka, LLC $8.00 $4,400.00 Doyon Management Services, LLC $19.00 $10,450.00 Engineer's Estimate 550 LNFT $19.00 $10,450.00
A0170 15705-1400 SOIL EROSION CONTROL, FIBER ROLL
STG Pacific, LLC $4.00 $9,320.00 C.I. Contractors, Inc. $11.00 $25,630.00 Tutka, LLC $8.00 $18,640.00 Doyon Management Services, LLC $19.00 $44,270.00 Engineer's Estimate 2,330 LNFT $12.00 $27,960.00
A0190 15705-1400 SOIL EROSION CONTROL, FIBER ROLL (AT INLET AND OUTLET)
STG Pacific, LLC $4.00 $880.00 C.I. Contractors, Inc. $13.00 $2,860.00 Tutka, LLC $8.00 $1,760.00 Doyon Management Services, LLC $19.00 $4,180.00 Engineer's Estimate 220 LNFT $16.00 $3,520.00
A0210 15706-0200 SOIL EROSION CONTROL, CHECK DAM (FIBER ROLL)
STG Pacific, LLC $90.00 $1,440.00 C.I. Contractors, Inc. $250.00 $4,000.00 Tutka, LLC $200.00 $3,200.00 Doyon Management Services, LLC $314.00 $5,024.00 Engineer's Estimate 16 EACH $240.00 $3,840.00
A0230 15802-0000 WATERING FOR DUST CONTROL
STG Pacific, LLC Lump Sum $26,500.00 C.I. Contractors, Inc. Lump Sum $32,000.00 Tutka, LLC Lump Sum $18,000.00 Doyon Management Services, LLC Lump Sum $50,106.00 Engineer's Estimate ALL LPSM Lump Sum $29,000.00
4 out of 9
Project No: AK FWS KNA 74525(1)
Project Name: Swan Lake Road Project
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0250 20101-0000 CLEARING AND GRUBBING
STG Pacific, LLC $15,000.00 $27,000.00 C.I. Contractors, Inc. $18,000.00 $32,400.00 Tutka, LLC $40,000.00 $72,000.00 Doyon Management Services, LLC $50,106.00 $90,190.80 Engineer's Estimate 1.8 ACRE $40,000.00 $72,000.00
A0270 20301-1900 REMOVAL OF PIPE CULVERT
STG Pacific, LLC $4,500.00 $9,000.00 C.I. Contractors, Inc. $4,500.00 $9,000.00 Tutka, LLC $11,000.00 $22,000.00 Doyon Management Services, LLC $6,264.00 $12,528.00 Engineer's Estimate 2 EACH $5,000.00 $10,000.00
A0290 20401-0000 ROADWAY EXCAVATION
STG Pacific, LLC $50.00 $73,500.00 C.I. Contractors, Inc. $27.00 $39,690.00 Tutka, LLC $51.00 $74,970.00 Doyon Management Services, LLC $26.00 $38,220.00 Engineer's Estimate 1,470 CUYD $51.00 $74,970.00
A0310 20403-0000 UNCLASSIFIED BORROW
STG Pacific, LLC $110.00 $103,400.00 C.I. Contractors, Inc. $83.00 $78,020.00 Tutka, LLC $87.00 $81,780.00 Doyon Management Services, LLC $151.00 $141,940.00 Engineer's Estimate 940 CUYD $68.00 $63,920.00
A0330 20425-1000 DITCH, EXCAVATION
STG Pacific, LLC $100.00 $3,000.00 C.I. Contractors, Inc. $220.00 $6,600.00 Tutka, LLC $66.00 $1,980.00 Doyon Management Services, LLC $664.00 $19,920.00 Engineer's Estimate 30 LNFT $27.00 $810.00
A0350 25101-0200 PLACED RIPRAP, METHOD A, CLASS 2 (HEADWALL)
STG Pacific, LLC $400.00 $19,200.00 C.I. Contractors, Inc. $2,000.00 $96,000.00 Tutka, LLC $305.00 $14,640.00 Doyon Management Services, LLC $376.00 $18,048.00 Engineer's Estimate 48 CUYD $270.00 $12,960.00
5 out of 9
Project No: AK FWS KNA 74525(1)
Project Name: Swan Lake Road Project
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0370 25101-2300 PLACED RIPRAP, METHOD B, CLASS 3 (HEADWALL)
STG Pacific, LLC $375.00 $75,000.00 C.I. Contractors, Inc. $725.00 $145,000.00 Tutka, LLC $356.00 $71,200.00 Doyon Management Services, LLC $376.00 $75,200.00 Engineer's Estimate 200 CUYD $290.00 $58,000.00
A0390 30202-2000 ROADWAY AGGREGATE, METHOD 2
STG Pacific, LLC $90.00 $218,700.00 C.I. Contractors, Inc. $65.00 $157,950.00 Tutka, LLC $68.00 $165,240.00 Doyon Management Services, LLC $88.00 $213,840.00 Engineer's Estimate 2,430 TON $45.00 $109,350.00
A0410 60201-0800 24-INCH PIPE CULVERT
STG Pacific, LLC $320.00 $16,640.00 C.I. Contractors, Inc. $500.00 $26,000.00 Tutka, LLC $286.00 $14,872.00 Doyon Management Services, LLC $627.00 $32,604.00 Engineer's Estimate 52 LNFT $180.00 $9,360.00
A0430 60201-1000 36-INCH PIPE CULVERT
STG Pacific, LLC $370.00 $27,380.00 C.I. Contractors, Inc. $285.00 $21,090.00 Tutka, LLC $343.00 $25,382.00 Doyon Management Services, LLC $376.00 $27,824.00 Engineer's Estimate 74 LNFT $360.00 $26,640.00
A0450 60201-2200 108-INCH PIPE CULVERT (AOP)
STG Pacific, LLC $1,050.00 $216,300.00 C.I. Contractors, Inc. $1,750.00 $360,500.00 Tutka, LLC $2,957.00 $609,142.00 Doyon Management Services, LLC $4,009.00 $825,854.00 Engineer's Estimate 206 LNFT $850.00 $175,100.00
A0470 60302-0000 STRUCTURAL PLATE PIPE-ARCH CULVERT (19 FT. 6 IN. SPAN x 12 FT. 6 IN. RISE) (AOP)
STG Pacific, LLC $2,560.00 $184,320.00 C.I. Contractors, Inc. $5,400.00 $388,800.00 Tutka, LLC $5,336.00 $384,192.00 Doyon Management Services, LLC $6,890.00 $496,080.00 Engineer's Estimate 72 LNFT $4,875.00 $351,000.00
6 out of 9
Project No: AK FWS KNA 74525(1)
Project Name: Swan Lake Road Project
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0490 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY
STG Pacific, LLC $200.00 $8,000.00 C.I. Contractors, Inc. $305.00 $12,200.00 Tutka, LLC $200.00 $8,000.00 Doyon Management Services, LLC $251.00 $10,040.00 Engineer's Estimate 40 HOUR $200.00 $8,000.00
A0510 62201-0450 BACKHOE LOADER, 4 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 18-INCH WIDTH
STG Pacific, LLC $200.00 $8,000.00 C.I. Contractors, Inc. $370.00 $14,800.00 Tutka, LLC $256.00 $10,240.00 Doyon Management Services, LLC $251.00 $10,040.00 Engineer's Estimate 40 HOUR $180.00 $7,200.00
A0530 62201-1000 WHEEL LOADER, 4 CUBIC YARD MINIMUM RATED CAPACITY
STG Pacific, LLC $225.00 $9,000.00 C.I. Contractors, Inc. $415.00 $16,600.00 Tutka, LLC $256.00 $10,240.00 Doyon Management Services, LLC $314.00 $12,560.00 Engineer's Estimate 40 HOUR $260.00 $10,400.00
A0550 62201-2050 ROLLER
STG Pacific, LLC $200.00 $8,000.00 C.I. Contractors, Inc. $350.00 $14,000.00 Tutka, LLC $194.00 $7,760.00 Doyon Management Services, LLC $251.00 $10,040.00 Engineer's Estimate 40 HOUR $200.00 $8,000.00
A0570 62201-2800 MOTOR GRADER, 8 FOOT MINIMUM BLADE
STG Pacific, LLC $240.00 $9,600.00 C.I. Contractors, Inc. $575.00 $23,000.00 Tutka, LLC $211.00 $8,440.00 Doyon Management Services, LLC $314.00 $12,560.00 Engineer's Estimate 40 HOUR $260.00 $10,400.00
A0590 62201-3150 HYDRAULIC EXCAVATOR, CRAWLER MOUNTED, 1.0 CUBIC YARD MINIMUM CAPACITY WITH THUMB
ATTACHMENT
STG Pacific, LLC $150.00 $6,000.00 C.I. Contractors, Inc. $540.00 $21,600.00 Tutka, LLC $205.00 $8,200.00 Doyon Management Services, LLC $314.00 $12,560.00 Engineer's Estimate 40 HOUR $220.00 $8,800.00
7 out of 9
Project No: AK FWS KNA 74525(1)
Project Name: Swan Lake Road Project
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0610 62201-3750 CHAIN SAW
STG Pacific, LLC $125.00 $1,250.00 C.I. Contractors, Inc. $185.00 $1,850.00 Tutka, LLC $121.00 $1,210.00 Doyon Management Services, LLC $188.00 $1,880.00 Engineer's Estimate 10 HOUR $140.00 $1,400.00
A0630 62301-0000 GENERAL LABOR
STG Pacific, LLC $110.00 $4,400.00 C.I. Contractors, Inc. $140.00 $5,600.00 Tutka, LLC $109.00 $4,360.00 Doyon Management Services, LLC $188.00 $7,520.00 Engineer's Estimate 40 HOUR $125.00 $5,000.00
A0650 62406-0300 PLACING CONSERVED TOPSOIL, 4-INCH DEPTH
STG Pacific, LLC $20,000.00 $42,000.00 C.I. Contractors, Inc. $10,500.00 $22,050.00 Tutka, LLC $19,500.00 $40,950.00 Doyon Management Services, LLC $31,316.00 $65,763.60 Engineer's Estimate 2.1 ACRE $23,000.00 $48,300.00
A0670 62501-0000 TURF ESTABLISHMENT
STG Pacific, LLC $32,000.00 $67,200.00 C.I. Contractors, Inc. $15,000.00 $31,500.00 Tutka, LLC $34,880.00 $73,248.00 Doyon Management Services, LLC $37,579.00 $78,915.90 Engineer's Estimate 2.1 ACRE $15,000.00 $31,500.00
A0690 62701-0000 SOD (VEGETATIVE MAT)
STG Pacific, LLC $140.00 $22,400.00 C.I. Contractors, Inc. $60.00 $9,600.00 Tutka, LLC $163.00 $26,080.00 Doyon Management Services, LLC $188.00 $30,080.00 Engineer's Estimate 160 SQYD $32.00 $5,120.00
A0710 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
STG Pacific, LLC $100.00 $800.00 C.I. Contractors, Inc. $500.00 $4,000.00 Tutka, LLC $1,300.00 $10,400.00 Doyon Management Services, LLC $627.00 $5,016.00 Engineer's Estimate 8 EACH $425.00 $3,400.00
8 out of 9
Project No: AK FWS KNA 74525(1)
Project Name: Swan Lake Road Project
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0730 63502-1250 TEMPORARY TRAFFIC CONTROL, TUBULAR MARKER, TYPE 42-INCH
STG Pacific, LLC $35.00 $1,575.00 C.I. Contractors, Inc. $125.00 $5,625.00 Tutka, LLC $130.00 $5,850.00 Doyon Management Services, LLC $63.00 $2,835.00 Engineer's Estimate 45 EACH $81.00 $3,645.00
A0750 63503-0400 TEMPORARY TRAFFIC CONTROL, CONCRETE BARRIER
STG Pacific, LLC $250.00 $50,000.00 C.I. Contractors, Inc. $58.00 $11,600.00 Tutka, LLC $160.00 $32,000.00 Doyon Management Services, LLC $63.00 $12,600.00 Engineer's Estimate 200 LNFT $160.00 $32,000.00
A0770 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
STG Pacific, LLC $40.00 $15,200.00 C.I. Contractors, Inc. $200.00 $76,000.00 Tutka, LLC $46.00 $17,480.00 Doyon Management Services, LLC $38.00 $14,440.00 Engineer's Estimate 380 SQFT $65.00 $24,700.00
A0790 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER
STG Pacific, LLC $80.00 $60,000.00 C.I. Contractors, Inc. $147.00 $110,250.00 Tutka, LLC $96.00 $72,000.00 Doyon Management Services, LLC $119.00 $89,250.00 Engineer's Estimate 750 HOUR $111.00 $83,250.00
A0810 63507-0700 TEMPORARY TRAFFIC CONTROL, TRAFFIC CONTROL SUPERVISOR
STG Pacific, LLC $250.00 $17,500.00 C.I. Contractors, Inc. $2,250.00 $157,500.00 Tutka, LLC $1,450.00 $101,500.00 Doyon Management Services, LLC $1,879.00 $131,530.00 Engineer's Estimate 70 DAY $1,200.00 $84,000.00
A0830 63703-0000 RESIDENTIAL HOUSING
STG Pacific, LLC $22,500.00 $45,000.00 C.I. Contractors, Inc. $22,500.00 $45,000.00 Tutka, LLC $18,000.00 $36,000.00 Doyon Management Services, LLC $37,579.00 $75,158.00 Engineer's Estimate 2 EACH $32,000.00 $64,000.00
9 out of 9
Project No: AK FWS KNA 74525(1)
Project Name: Swan Lake Road Project
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0850 63704-0000 VEHICLE
STG Pacific, LLC $37,500.00 $75,000.00 C.I. Contractors, Inc. $50,000.00 $100,000.00 Tutka, LLC $20,000.00 $40,000.00 Doyon Management Services, LLC $28,849.00 $57,698.00 Engineer's Estimate 2 EACH $50,000.00 $100,000.00
A0870 64704-1000 MITIGATION, STREAMBED MATERIAL (SIMULATED STREAM CULVERT TREATMENT)
STG Pacific, LLC $375.00 $247,500.00 C.I. Contractors, Inc. $225.00 $148,500.00 Tutka, LLC $182.00 $120,120.00 Doyon Management Services, LLC $251.00 $165,660.00 Engineer's Estimate 660 CUYD $90.00 $59,400.00
A0890 64704-1600 MITIGATION, STREAMBED CHANNEL RECONSTRUCTION (CHANNEL GRADING)
STG Pacific, LLC $165.00 $8,250.00 C.I. Contractors, Inc. $260.00 $13,000.00 Tutka, LLC $117.00 $5,850.00 Doyon Management Services, LLC $126.00 $6,300.00 Engineer's Estimate 50 CUYD $76.00 $3,800.00
A0910 65001-1000 CONSTRUCT AND MAINTAIN DIVERSION (TRAFFIC)
STG Pacific, LLC Lump Sum $118,000.00 C.I. Contractors, Inc. Lump Sum $10,850.00 Tutka, LLC Lump Sum $300,000.00 Doyon Management Services, LLC Lump Sum $313,158.00 Engineer's Estimate ALL LPSM Lump Sum $41,000.00
Total Schedule - All Items
STG Pacific, LLC $2,458,065.00 C.I. Contractors, Inc. $3,313,195.00 Tutka, LLC $3,418,986.00 Doyon Management Services, LLC $4,176,346.50 Engineer's Estimate $2,102,475.00
| 2023-12-07T16:37:24-0800 | |