This document contains bid documents for the ID FS ERFO 2017(1)-29(1), Stoddard Bridge federal contract opportunity. The bid package seeks bids for construction of the Stoddard Bridge, including structural excavation, concrete work, reinforcing steel, structural steel fabrication and erection, timber and lumber, bearings, micropiles, cables, fencing, and temporary traffic control. Bids are due by March 30th, 2022. Two amendments provide revisions to quantities, drawings, and special contract requirements. Amendment A002 adjusts quantities for structural timber, revises drawings to reflect quantity changes and add structural details, and adds soil nail wall, painting, and structural steel requirements. The contract will be awarded by the Department of Transportation Federal Highway Administration.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| BidSum_Stoddard_5.3.2022.pdf | ||
| QA_04-29-2022.pdf | ||
| QA_04-28-2022.pdf | ||
| Amendment 3_Stoddard Bridge.pdf | ||
| QA_04-27-2022.pdf | ||
| QA2_04-27-2022.pdf | ||
| QA2_04-25-2022.pdf | ||
| QA_04-25-2022.pdf | ||
| QA_04-19-2022.pdf | ||
| QA_04-18-2022.pdf | ||
| Amendment 1_Stoddard Bridge.pdf | ||
| QA2_04-12-2022.pdf | ||
| GR 06-21 ID FS ERFO 2017(1)-29(1) Final.pdf | ||
| EW_Calc_Report_20210510.pdf | ||
| Stoddard_HA_Report_20210510.pdf | ||
| Stoddard Full Set - Plans - Signed.pdf | ||
| IFB_Stoddard Bridge.pdf | ||
| Stoddard_Bridge_TSL_Hydraulics_Report.pdf | ||
| Stoddard_VA_Report_20210510.pdf | ||
| Stoddard_Bridge_ControlSheet.xlsx | XLSX spreadsheet | |
| ID USFS Stoddard Pack Suspension - 2010.pdf | ||
| FS ERFO 2017(1)-29(1)_XS_20210510.pdf |
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
N/A
PAGE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)
A002 04/25/2022 N/A See Box 14
6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A
Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.
X
69056719B000031
9B. DATED (SEE ITEM 11)
03/30/2022
10A. MODIFICATION OF CONTRACT/ORDER NO.
N/A
10B. DATED (SEE ITEM 13)
CODE: N/A FACILITY CODE: N/A
N/A
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
(__ ) is extended, ( x ) is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN
ITEM 10A.
N/A
B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D OTHER (Specify type of modification and authority)
N/A
E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
ID FS ERFO 2017(1)-29(1), Stoddard Bridge
See page 2.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
N/A
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITION NOT USABLE
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Amendment No. A002, dated 04-25-2022 ID FS ERFO 2017(1)-29(1)
Solicitation No. 69056719B000031 Stoddard Bridge
REVISIONS ARE AS FOLLOWS:
BID SCHEDULE
Pages A-7 through A-11. Revises pages to adjust quantities for Pay Item 55701-2000.
CONTRACT CLAUSES
SPECIAL CONTRACT REQUIREMENTS
Page E-10, Subsection 105.04, Handling and Storing Material. Adds Forest Service contact information.
Pages E-17 through E-18, Subsection 108.01, Commencement, Prosecution, and Completion of Work.. Revises last paragraph of Subsection, and adjusts page contents
Page F-11, Section 259, Soil Nail Retaining Walls. Adds requirements under Subsections
259.02, 259.10, and 259.14.
Pages F-33 through F-33a, Section 555, Steel Structures. Adds requirements under
Subsection 555.16.
Pages G-9 through G-11, Subsection 725.10A, Wall Drainage Network Components. Adds requirements under this Subsection and adjusts page contents.
PLANS
Plan Sheets B.1 through B.2 Revises Sheets to adjust quantities for Pay Item 55701-2000.
Plan Sheet J.01 Revises Item No. 55701-2000 and Micropile Note.
Plan Sheet J.14 Adds and Revises callouts on Section B-B.
ENCLOSURES
Pages:
A-7 through A-11 / E-10 / E-17 through E-18 / F-11 / F-33 through F-33a /
G-9 through G-11
Plan Sheets:
B.1 through B.2 / J.01 / J.14
Notice to Bidders: Please submit revised pages A-7 through A-11 with your bid.
A-7
BID SCHEDULE
Bidder/Offeror please note: Before preparing the bid, carefully read the Solicitation Provisions.
Insert a unit bid price, in figures, for each pay item for which a quantity appears in the bid schedule. Multiply the unit price by the quantity for each pay item and show the amount bid. Should any mathematical check made by the Government show a mistake in the amount bid, the corrected unit price extension shall govern.
When the word "LPSM" (Lump Sum) appears as a unit bid price, insert an amount for each lump sum pay item.
When a sum based on a fixed rate appears for any pay item in the amount bid column, include the Government inserted amount bid for the item in the total bid amount.
Total all of the amounts bid for each pay item and show the total bid amount.
BRAND NAME OR EQUAL
If providing other than the brand name products, complete the following (See FAR Provision 52.211-6, Brand Name or Equal).
For work under Section 563.–PAINTING, to be performed on materials for Pay Item 26001-0000 Rock Bolt (50 kips); our firm offers in lieu of the brand name Natina® Steel specified in Subsection 725.19 Weathering Agent.
Brand: ______________________________________________________
Manufacturer’s Name: _________________________________________
Include with your bid, all documents needed by the Government to determine if the proposed product meets the requirements listed in the appropriate Section(s). The determination as to the equality of the product offered is the responsibility of the Government and will be based on the information furnished by the bidder as well as other information reasonably available to the contracting office. If proposed “equal” is determined by the government to be “not equal”, the bid will be considered non-responsive.
Bid Schedule
Project No:ID FS ERFO 2017(1)-29(1)
Project Name:Stoddard Bridge
Revised by Amendment A002
A - 8
Contract Quantity Pay Items
20801-0000 STRUCTURE EXCAVATION
55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)
55210-1400 PRECAST STRUCTURAL CONCRETE, CLASS D (AE), DECK
55401-1000 REINFORCING STEEL
55502-0000 STRUCTURAL STEEL, FURNISHED, FABRICATED, AND ERECTED (TRUSS)
55502-0000 STRUCTURAL STEEL, FURNISHED, FABRICATED, AND ERECTED (TOWER)
55502-0000 STRUCTURAL STEEL, FURNISHED, FABRICATED, AND ERECTED (MAIN CABLE SADDLES)
55601-1300 BRIDGE RAILING, TIMBER (HYBRID TIMBER/CABLE RAIL)
55701-2000 STRUCTURAL TIMBER AND LUMBER, TREATED (TIMBER RUNNERS)
55701-2000 STRUCTURAL TIMBER AND LUMBER, TREATED (TIMBER RUNNERS)
56401-4000 BEARING DEVICE, DISK
63306-1700 POST, WOOD, 4-INCH X 4-INCH
Amendment Item No. Pay Item No. Description Quantity Unit Unit Price Amount
A0020 15101-0000 MOBILIZATION
ALL LPSM $___LPSM_____ $____________
A0040 15201-0000 CONSTRUCTION SURVEY AND STAKING
ALL LPSM $___LPSM_____ $____________
A0060 15301-0010 CONTRACTOR QUALITY CONTROL AND ASSURANCE
ALL LPSM $___LPSM_____ $____________
A0080 15401-0000 CONTRACTOR TESTING
ALL LPSM $___LPSM_____ $____________
A0100 15501-0000 CONSTRUCTION SCHEDULE
ALL LPSM $___LPSM_____ $____________
A0120 15705-1400 SOIL EROSION CONTROL, FIBER ROLL
375 LNFT $____________ $____________
A0140 20103-0000 CLEARING AND GRUBBING
4,500 SQYD $____________ $____________
A0160 20301-0400 REMOVAL OF BRIDGE
1 EACH $____________ $____________
A0180 20401-0000 ROADWAY EXCAVATION
21 CUYD $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:ID FS ERFO 2017(1)-29(1)
A - 9
A0200 20801-0000 STRUCTURE EXCAVATION
329 CUYD $____________ $____________
A0220 20803-0000 STRUCTURAL BACKFILL
90 CUYD $____________ $____________
A0240 25602-0000 GROUND ANCHOR
2,580 LNFT $____________ $____________
A0260 25605-0000 PERFORMANCE TEST
2 EACH $____________ $____________
A0280 25902-0000 SOIL NAIL RETAINING WALL
841 SQFT $____________ $____________
A0300 25903-0000 VERIFICATION TEST NAIL
3 EACH $____________ $____________
A0320 26001-0000 ROCK BOLT (50 KIPS)
201 LNFT $____________ $____________
A0340 30201-1000 ROADWAY AGGREGATE, METHOD 1
12 CUYD $____________ $____________
A0360 30210-0000 BEDDING AND BACKFILL AGGREGATE
42 CUYD $____________ $____________
A0380 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)
242 CUYD $____________ $____________
A0400 55210-0400 PRECAST STRUCTURAL CONCRETE, CLASS A(AE), ABUTMENT
5 CUYD $____________ $____________
A0420 55210-1400 PRECAST STRUCTURAL CONCRETE, CLASS D (AE), DECK
44 CUYD $____________ $____________
A0440 55401-1000 REINFORCING STEEL
39,400 LB $____________ $____________
A0460 55502-0000 STRUCTURAL STEEL, FURNISHED, FABRICATED, AND ERECTED (TRUSS)
224,000 LB $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:ID FS ERFO 2017(1)-29(1)
A - 10
A0480 55502-0000 STRUCTURAL STEEL, FURNISHED, FABRICATED, AND ERECTED (TOWER)
35,900 LB $____________ $____________
A0500 55502-0000 STRUCTURAL STEEL, FURNISHED, FABRICATED, AND ERECTED (MAIN
CABLE SADDLES)
23,300 LB $____________ $____________
A0520 55601-1300 BRIDGE RAILING, TIMBER (HYBRID TIMBER/CABLE RAIL)
728 LNFT $____________ $____________
A002 A0540 55701-2000 STRUCTURAL TIMBER AND LUMBER, TREATED (TIMBER RUNNERS)
49 MFBM $____________ $____________
A002 A0545 55701-2000 STRUCTURAL TIMBER AND LUMBER, TREATED (TIMBER RUNNERS)
9 MFBM $____________ $____________
A0560 56201-0000 BRIDGE ERECTION SYSTEM (TRUSS ADJUSTMENT SYSTEM)
ALL LPSM $___LPSM_____ $____________
A0580 56201-0000 BRIDGE ERECTION SYSTEM (ACCESS EQUIPMENT)
ALL LPSM $___LPSM_____ $____________
A0600 56201-0000 BRIDGE ERECTION SYSTEM (HIGHLINE SYSTEM)
ALL LPSM $___LPSM_____ $____________
A0620 56202-0000 TEMPORARY SUPPORT STRUCTURE (TEMP TOWER SUPPORT)
ALL LPSM $___LPSM_____ $____________
A0640 56401-4000 BEARING DEVICE, DISK
5 EACH $____________ $____________
A0660 56701-0000 MICROPILE
528 LNFT $____________ $____________
A0680 56705-0000 MICROPILE LOAD VERIFICATION TEST
1 EACH $____________ $____________
A0700 56706-0000 MICROPILE PROOF LOAD TEST
1 EACH $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:ID FS ERFO 2017(1)-29(1)
A002 Revised by Amendment A002
A - 11
A0720 58101-1000 CABLES AND ANCHOR COMPONENTS, MAIN CABLE SYSTEM
ALL LPSM $___LPSM_____ $____________
A0740 61901-2250 FENCE, RAIL (TIMBER/CABLE HYBRID)
59 LNFT $____________ $____________
A0760 63306-1700 POST, WOOD, 4-INCH X 4-INCH
12 EACH $____________ $____________
A0780 63502-1050 TEMPORARY TRAFFIC CONTROL, TUBULAR MARKER
66 EACH $____________ $____________
A0800 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B
66 EACH $____________ $____________
A0820 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
99 SQFT $____________ $____________
A0840 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER
720 HOUR $____________ $____________
A0860 63507-0700 TEMPORARY TRAFFIC CONTROL, TRAFFIC CONTROL SUPERVISOR
45 DAY $____________ $____________
A0880 63701-0000 FIELD OFFICE
1 EACH $____________ $____________
Submitted by:____________________________________ Schedule Total:____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:ID FS ERFO 2017(1)-29(1)
E-10 DIVISION 100
Special Contract Requirements Project: ID FS ERFO 2017(1)-29(1), Stoddard Bridge
Subsection 107.10(d). Submit copies of agreements and documents and do not use property until approved by CO.
Add the following:
Do not use Cache Bar and Cupper Canyon as a staging and stockpile area. Equipment used will be fueled and serviced at the staging areas only. Obtain Forest Service approval for fuel storage locations at staging areas and keep spill cleanup kits onsite at all times. There will be no fuel storage below the ordinary high-water line or within the active floodplain. When not in use, vehicles will be parked in the designated staging areas indicated above.
Contractor shall have access to Ebenezer Campground facility (river side of Salmon River Road) and is responsible for coordinating access to the north side of the road with the Forest service.
Contractor will be responsible for personal/business equipment and items. A fence will be allowed at open area located at SW corner of campground.
The southside of Ebenezer Campground (river side of Salmon River Road) site is available for contractors to camp. Coordinate camping fees and ordinances to follow for camping at Ebenezer Campground with the Forest Service.
The Forest Service contact information for coordinating camping fees and ordinances for camping at Ebenezer Campground is as follows.
Michael Carroll USDA-FS Engineer 1206 South Challis Street Phone: (208) 756-5101 Email: michael.d.carroll@usda.gov
Revised by Amendment A001
E-17 DIVISION 100
Project: ID FS ERFO 2017(1)-29(1), Stoddard Bridge
Section 108. — PROSECUTION AND PROGRESS
04/02/21– FP-14
108.01 Commencement, Prosecution, and Completion of Work. Add the following:
Furnish at least a 48-hour advanced notice before changing the current work schedule. Work schedule changes that include additional shifts require a 14-day advanced notice.
Perform work under this contract by limiting work as provided for in Sections 104, 105, 107, 156, and 157; and do not interfere with waterway traffic.
108.01A Labor. (Added Subsection).
Follow the requirements of FAR Clause 52.222-6 Construction Wage Rate Requirements.
Adjacent or virtually adjacent work sites, as used in FAR Clause 52.222-6, are defined to be work sites within ½ mile of the project. Application of Construction Wage Rate Requirements (Davis- Bacon Act) for work sites beyond ½ mile of the project will be determined by the CO
108.03 Determination and Extension of Contract Time. Add the following to paragraph (c):
No adjustment in contract time or amount will be made for stop orders issued under Subsection 108.05(a) or (b), except an adjustment in contract time, as provided by FAR Clause 52.249-10 Default (Fixed-Price Construction), may be made when the Contractor is able to demonstrate that the weather was unusually severe based on the most recent 10 years of historical data.
108.04 Failure to Complete Work on Time. Delete this Subsection and substitute the following:
Follow the requirements of FAR Clause 52.211-12 Liquidated Damages — Construction.
Liquidated damages in the amount specified in Table 108-1 will be assessed for each day beyond the time specified in the contract until substantial completion of the work.
Liquidated damages will not be assessed for the following:
(a) The day of the final inspection.
(b) Days required to perform work added to the contract after substantial completion including items identified during the final inspection that were not required before that time.
(c) Delays by the Government after all work is complete and before a formal acceptance is executed.
(d) Periods of time when all work is complete but acceptance is delayed pending the plant establishment period or similar warranty period.
E-18 DIVISION 100
Project: ID FS ERFO 2017(1)-29(1), Stoddard Bridge
(e) During winter shutdown periods ordered by the CO.
Table 108-1 Charge for Liquidated Damages for Each Day
Work Is Not Substantially Completed
Original Contract Price Daily
Charge From More Than —
To and Including —
$ 0 $ 1,000,000 $ 1,000
$ 1,000,000 $ 2,000,000 $ 1,800
$ 2,000,000 $ 5,000,000 $ 3,500
$ 5,000,000 $ 10,000,000 $ 4,400
$ 10,000,000 and more $ 5,200
108.05 Stop Order. Delete the last paragraph.
108.06 Suspension. (Added Subsection).
Follow the requirements of FAR Clause 52.242-14 - Suspension of Work.
Suspend work, either in whole or in part, for such periods deemed necessary due to human burials, cultural resources, historic properties, paleontological remains, or archeological specimens discovered within the construction area. See Subsection 107.02.
Furnish steel pipe casings with minimum wall thickness of 0.312 inches.
04/14/22 S.B.Revises Item No. 55701-2000 quantity & Micropile Note.
8" square floor drain drain pipe
3" dia.
S.B. Adds and revises callouts on Section B-B.04/14/22