Amendment 1_Stoddard Bridge.pdf
PDF 96 KB Posted
- Attached to
- ID FS ERFO 2017(1)-29(1), Stoddard Bridge Federal contract opportunity
- Solicitation number
- 69056719B000031
About this file
This document is an amendment to a solicitation for the ID FS ERFO 2017(1)-29(1), Stoddard Bridge project. The amendment revises special contract requirements to prohibit the use of Cache Bar and Cupper Canyon as staging and stockpile areas. Fuel storage locations at designated staging areas must be approved by the Forest Service, and spill cleanup kits must remain onsite while fuel is present. There will be no fuel storage below the ordinary high-water line or within the active floodplain. Personal equipment may be kept at the Ebenezer Campground site, where contractors may also camp pending coordination of access and fees with the Forest Service. The solicitation number is 69056719B000031 and is issued by the Department of Transportation Federal Highway Administration for bid documents involving bridge work over the Stoddard Bridge.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| BidSum_Stoddard_5.3.2022.pdf | ||
| QA_04-29-2022.pdf | ||
| QA_04-28-2022.pdf | ||
| Amendment 3_Stoddard Bridge.pdf | ||
| QA_04-27-2022.pdf | ||
| QA2_04-27-2022.pdf | ||
| QA2_04-25-2022.pdf | ||
| Amendment 2_Stoddard Bridge.pdf | ||
| QA_04-25-2022.pdf | ||
| QA_04-19-2022.pdf | ||
| QA_04-18-2022.pdf | ||
| QA2_04-12-2022.pdf | ||
| GR 06-21 ID FS ERFO 2017(1)-29(1) Final.pdf | ||
| EW_Calc_Report_20210510.pdf | ||
| Stoddard_HA_Report_20210510.pdf | ||
| Stoddard Full Set - Plans - Signed.pdf | ||
| IFB_Stoddard Bridge.pdf | ||
| Stoddard_Bridge_TSL_Hydraulics_Report.pdf | ||
| Stoddard_VA_Report_20210510.pdf | ||
| Stoddard_Bridge_ControlSheet.xlsx | XLSX spreadsheet | |
| ID USFS Stoddard Pack Suspension - 2010.pdf | ||
| FS ERFO 2017(1)-29(1)_XS_20210510.pdf |
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
N/A
PAGE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)
A001 04/13/2022 N/A See Box 14
6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A
Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.
X
69056719B000031
9B. DATED (SEE ITEM 11)
03/30/2022
10A. MODIFICATION OF CONTRACT/ORDER NO.
N/A
10B. DATED (SEE ITEM 13)
CODE: N/A FACILITY CODE: N/A
N/A
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
(__ ) is extended, ( x ) is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN
ITEM 10A.
N/A
B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D OTHER (Specify type of modification and authority)
N/A
E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
ID FS ERFO 2017(1)-29(1), Stoddard Bridge
Amendment A001 is issued to revise the following:
SPECIAL CONTRACT REQUIREMENTS Page E-10. Subsection 105.04, Handling and Storing Material. Adds requirements.
ENCLOSURES: Page E-10
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
N/A
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITION NOT USABLE
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
E-10 DIVISION 100
Special Contract Requirements Project: ID FS ERFO 2017(1)-29(1), Stoddard Bridge
Subsection 107.10(d). Submit copies of agreements and documents and do not use property until approved by CO.
Add the following:
Do not use Cache Bar and Cupper Canyon as a staging and stockpile area. Equipment used will be fueled and serviced at the staging areas only. Obtain Forest Service approval for fuel storage locations at staging areas and keep spill cleanup kits onsite at all times. There will be no fuel storage below the ordinary high-water line or within the active floodplain. When not in use, vehicles will be parked in the designated staging areas indicated above.
Contractor shall have access to Ebenezer Campground facility (river side of Salmon River Road) and is responsible for coordinating access to the north side of the road with the Forest service.
Contractor will be responsible for personal/business equipment and items. A fence will be allowed at open area located at SW corner of campground.
The southside of Ebenezer Campground (river side of Salmon River Road) site is available for contractors to camp. Coordinate camping fees and ordinances to follow for camping at Ebenezer Campground with the Forest Service.
Revised by Amendment A001