This document contains a series of questions and answers related to solicitation number 69056719b000024 for construction work at the North Entrance of Yellowstone National Park. Key details include questions about concrete pavement reinforcement, drainage pipe specifications, asphalt emulsion types, floor access door fire ratings and load capacities, traffic detector system component requirements, utility box specifications, appliance specifications, interior window treatments, trench construction depths and duct encasement specifications. The agency is the Department of Transportation Federal Highway Administration for work at Yellowstone National Park.
View the file
Other files
Show all 43
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MT NPS YELL 11(2)
North Entrance
# General Technical Question Answer Date
1 X
We respectfully submit for your consideration a request to approve products as an accepted substitute on Entrance Station (19‐819223);
please find substitution request form attached for Tufftec Lockers manufactured by Scranton Products. With over 30 years of experience, Scranton Products is the industry leader in plastic (HDPE) bathroom partitions and lockers.
Constructed from premium, American‐made solid plastic, our products resist dents, scratches, corrosion, graffiti and mildew. More information regarding the benefits of our products as well as technical data sheets and MSDS forms for the appropriate product(s), confirming performance as specified, can be reviewed via the links below:
• Health Product Declaration ‐ Tufftec
• SP Artisan Woodgrain Collection
• LEED Points
• Tufftec Specifications
• Tufftec Lockers Brochure
• Tufftec HDPE vs Metal Brochure
• Warranty
• Engraving Brochure
See FAR Provision 52.211‐6 for requirements on submitting proposed equal brand‐name products with your bid; and see FAR Clause 52.236‐5 for requirements on submitting proposed equal brand‐name products post award.
4/15/2020
Check General or Technical
2 X
I would like to submit a sub request for door hardware for the North Station Entrance project at Yellowstone National Park. I noticed we are approved on closers and there are no subs for locks so I would like to see if we can get approved for exit devices too. Please see my attached sub request for Precision Apex 2000 Series Door Hardware, manufactured by dormakaba; and let me know if you need anything else from me.
In accordance with the first sentence under Brand Name or Equal Notification on Page A‐ 7 of the Bid Schedule; this product is not allowed.
4/15/2020
3 X Bid Item No. 50101‐2800 MINOR CONCRETE
PAVEMENT, PLAIN, 8‐INCH DEPTH
Is there any type of reinforcement in this item?
Pay Item 50101‐2800 for Minor concrete pavement, plain, 8‐inch depth shows no reinforcement requirements in Plan Section C where the work is being called for.
4/29/2020
4 X
I would like to get some clarification on the drainage quantities on sheet H.1. The column of allowable pipes doesn’t seem to be lined up properly. The station 104+90 looks to be like the same as 47+58, 52+02 and 65+96. The other stations appear to be more storm sewers.
We have received your question, and will be providing an appropriate response.
5/4/2020
5 X
What emulsified asphalt product is specified for item A0680. Section 309 indicates material is
702.02. Per 702.02, there are three types:
a. Emulsified for chip seal
b. Emulsified for micro surfacing
c. Emulsified for prime coat.
Which product is specified, or is a SS‐1 desired?
See the first sentence of FP‐14 Subsection 702.02.
5/6/2020
6 X
I am with Bauer construction and am bidding on the 3 new buildings. I have a question about the floor access doors. The spec's call for a fire rated door with a 300lb loading capacity. All fire rated floor access doors must be set in concrete. We have wood floors. The fire rated doors only have 150lbs per sq.ft. loading capacity. Also the fire rated doors are 5K each versus 800 each fire non rated. Can you please specify if the fire rating is needed for these doors and if so we need to encapsulate in concrete. Please advise.
We have received your question and will be providing an appropriate response.
5/6/2020
7 X For Item #A2640 “System Installation, Traffic Detector System”. Are pre‐formed loops polypropylene inductive loops acceptable?
We have received you question and will provide an appropriate response.
5/6/2020
8 X
For Item #A2640 “System Installation, Traffic Detector System”. Other than the SCR F89
636.07 and FP 14 636.07 are there any more specification requirements available for the traffic detector system that will be installed in the main building?
Yes. Other requirements are within the documents listed under Subsection 104.04, as well as, Volume 1 Plan Section M; and FP‐ 14 Subsection 636.03. Also see the E‐ Sheets in Plan Volume 2; and Division 26 in Section K, to determine any power limitations for the traffic detector system you choose to install.
5/6/2020
9 X
For Item #A2640 “System Installation, Traffic Detector System”. What type of communications/monitoring provisions are required to NPS?
NPS communications/monitoring provisions for the traffic detector system have not been specified. Comply with the requirements in the soliciation documents and bid accordingly.
10 X
For Item #A2640 “System Installation, Traffic Detector System”. SCR 636.13 F‐89 mentions “Additional Pull boxes and junction cans for the traffic detectors, not shown on plans, will not be measured and paid for separately but included in 63602‐6020 System Installation, Detector Wire Loop.” Please provide details and specifications for the size, type, and labeling for the additional pull boxes mentioned.
Additional information will not be provided.
Determine what’s needed to perform the Section 636 work for the traffic detector system you’re installing and bid accordingly.
5/6/2020
11 X
For Item #A2740 Utility Box, Junction Box. Plan sheet M‐1 calls out one “Utility Junction Box” and one “Primary Junction Can”. Please clarify if these both belong to bid item #A2740.
We have received you question and will provide an appropriate response.
5/6/2020
12 X For Item #A2740 Utility Box, Junction Box.
Please provide specifications, dimensions, labeling, and drawing details for this bid item.
Additional information will not be provided.
Furnish and install Utility box, junction box that meets the requirements of Section 636; and accommodates installation of the facilities shown on the plans.
5/6/2020
13 X
I am only seeing specifications for the cook top, but plans do not call out the cook top. I see a refrigerator but no call out or spec also the potential of a microwave, but no call out or spec. Please advise and let me know if we are missing anything else regarding the appliances.
The cooktop is called out on Volume 2 Sheet A101 (See Plan Keynote 6). A refrigerator and microwave shelf are shown in elevation views of the architectural drawings, and microwave is shown under Panel A in the Electrical Drawings; but because a refrigerator or microwave are not called out in the architectural drawings, and not specified in Section 113013 of Section K, so furnishing and installing a refrigerator or microwave is not part of the work to be performed.
14 X There is an interior window on the west wall of room #109. Does this also get a roller shade or just the exterior windows? Please advise.
The interior window your referencing is the east wall of Room 108, because Room 109 does not have interior windows (See dashed lines on Volume 2 Plan Sheets G102 and A101 for room limits). See Note 4 on Volume 2 Plan Sheet A501.
5/6/2020
15 X
For the utility/conduit trench project requirements, SCR 636.05 page F‐87 states different burial depths than trench details in Vol 1 plan sheet M.3 and drawings in Vol 2 plan sheet E013. Which rules, the details or SCR? If details rule please list which one, Vol 1 M.3 or Vol 2 EO13?
We have received you question and will be providing an appropriate response.
5/6/2020
16 X
For the utility/conduit trench project requirements, Vol 2 plan sheet detail E013 call out concrete encased duct/conduit, while Vol 1 plan sheet M.3 does not. Which rules, the details or SCR? If details rule please list which one, Vol 1 M.3 or Vol 2 EO13?
We have received you question and will be providing an appropriate response.
5/6/2020
17 X
For the utility/conduit trench project requirements, if concrete duct/conduit encasement is required, please provide concrete specifications.
We have received you question and will be providing an appropriate response.
5/6/2020
18 X
Are there supplemental provisions available for FP14? SCR 636.02 on page F87 refers to sections
725.12 and 725.33 which do not appear in the SCR or FP14. Or what is listed in FP14 under these numbers does not seem to apply.
We have received you question and will be providing an appropriate response.