Sol_68HERC19R0011.pdf

PDF 476 KB Posted

Attached to
Zero-dollar PR for recompete of EP-C-15-006, APP-O Federal contract opportunity
Solicitation number
68HERC19R0011
Issued by
Environmental Protection Agency Cincinatti Procurement Operations Division

About this file

This pre-solicitation notice announces a forthcoming solicitation for testing and analytical services to support emissions characterization, technology assessment, test procedure development, and equipment development activities for vehicle and engine regulations. Services will be acquired through a single-award ID/IQ contract with a ceiling of $25 million over a 5-year ordering period.

The anticipated solicitation will be released in late May via FedConnect and proposals will be due approximately 30 days thereafter. Services will include support for the Assessment and Standards Division and Testing and Advanced Technology Division of EPA's Office of Transportation and Air Quality. A performance work statement is attached providing additional details on required services. No organizational conflicts of interest will be permitted for entities engaged in vehicle, engine, or fuel manufacturing or distribution. The NAICS code is 541330 for engineering services and the size standard is $15 million in average annual receipts.

68HERC19R0011

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY

CINCINNATI PROCUREMENT OPERATIONS DIVISION

CINCINNATI, OHIO 45268

May 24, 2019

MEMORANDUM

From: Matthew J. Growney, Contracting Officer

To: Prospective Offerors

Subject: Solicitation 68HERC19R0011, Testing and Analytical Services for Regulation of Motor Vehicles, Engines, Fuels, and Fuel Additives

The closing date and time for Government receipt of your proposal is June 24th, 2019 by 4:30pm Eastern Standard time EST. Proposals shall be submitted via ww.fedconnect.net in accordance with the provision at L-23, Local Clause EPA-L 15-104, Electronic Submission of Proposals/Bids/Offers/Quotes shall be submitted via Fedconnect according to the requirements provided in the provision at Section L, L-26 Local Clauses EPA-L-36-101 Proposal Instructions.

The fill in under Block 12 of the SF 33 shall provide for a period of 180 calendar days for acceptance from the date of receipt of the offers.

Offerors with any questions are encouraged to submit technical questions through FedConnect no later than 10 calendar days after the issuance date of this solicitation in accordance with the provision at L-22, Local Clause EPA- L-15-102 Technical Questions.

Sincerely, Matthew J. Growney

Matthew J. Growney Contracting Officer

Attachment: Solicitation 68HERC19R0011

68HERC19R0011

SOLICITATION, OFFER AND AWARD

4. TYPE OF SOLICITATION2. CONTRACT NUMBER 3. SOLICITATION NUMBER

7. ISSUED BY CODE 8. ADDRESS OFFER TO (If other than Item 7)

ORDER UNDER DPAS (15 CFR 700)

6. REQUISITION/PURCHASE NUMBER

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

NEGOTIATED (RFP)

SEALED BID (IFB)

5. DATE ISSUED

1. THIS CONTRACT IS A RATED RATING PAGE OF PAGES

1 91

C. E-MAIL ADDRESS

EXT.NUMBERAREA CODE

B. TELEPHONE (NO COLLECT CALLS)A. NAME

10. FOR

INFORMATION

CALL:

CAUTION: LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.

(Date)(Hour) local timeuntildepository located in copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if hand carried, in the

SOLICITATION

9. Sealed offers in original and

PART IV - REPRESENTATIONS AND INSTRUCTIONS

OTHER STATEMENTS OF OFFERORS

EVALUATION FACTORS FOR AWARD

INSTRS., CONDS., AND NOTICES TO OFFERORS

REPRESENTATIONS, CERTIFICATIONS AND

LIST OF ATTACHMENTS

CONTRACT CLAUSES

PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACH.

I

J

K

L

M SPECIAL CONTRACT REQUIREMENTS

CONTRACT ADMINISTRATION DATA

DELIVERIES OR PERFORMANCE

INSPECTION AND ACCEPTANCE

PACKAGING AND MARKING

DESCRIPTION/SPECS./WORK STATEMENT

SUPPLIES OR SERVICES AND PRICES/COSTS

SOLICITATION/CONTRACT FORM

PART II - CONTRACT CLAUSESPART I - THE SCHEDULE

H

G

F

E

D

C

B

A

SEC. DESCRIPTION PAGE(S) (X) DESCRIPTION SEC. (X)

11. TABLE OF CONTENTS

18. OFFER DATE17. SIGNATURE

SUCH ADDRESS IN SCHEDULE.

IS DIFFERENT FROM ABOVE - ENTER

15C. CHECK IF REMITTANCE ADDRESS

EXT.NUMBERAREA CODE

15B. TELEPHONE NUMBER

(Type or print)AND

ADDRESS

OF

OFFEROR

CODE FACILITY

16. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER15A. NAME

DATEAMENDMENT NO.DATEAMENDMENT NO.

and related documents numbered and dated):

amendments to the SOLICITATION for offerors

(The offeror acknowledges receipt of

14. ACKNOWLEDGEMENT OF AMENDMENTS

CALENDAR DAYS (%)30 CALENDAR DAYS (%)20 CALENDAR DAYS (%)10 CALENDAR DAYS (%)

(See Section I, Clause No. 52.232.8)

13. DISCOUNT FOR PROMPT PAYMENT

designated point(s), within the time specified in the schedule.

by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

OFFER (Must be fully completed by offeror)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

28. AWARD DATE

(Signature of Contracting Officer)

27. UNITED STATES OF AMERICA

25. PAYMENT WILL BE MADE BY

26. NAME OF CONTRACTING OFFICER (Type or print)

CODE 24. ADMINISTERED BY (If other than Item 7)

ITEM

(4 copies unless otherwise specified)

23. SUBMIT INVOICES TO ADDRESS SHOWN IN

41 U.S.C. 253 (c) ( 10 U.S.C. 2304 (c) (

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

21. ACCOUNTING AND APPROPRIATION20. AMOUNT19. ACCEPTED AS TO ITEMS NUMBERED

AWARD (To be completed by government)

CODE

PR-OAR-18-0137405/24/2019

X

CPOD

CPOD

US Environmental Protection Agency 26 West Martin Luther King Drive Mail Code: W136 Cincinnati OH 45268-0001

1630 ET 06/24/2019

Clare Hingsbergen hingsbergen.clare@epa.gov

PAGE(S)

Matthew Growney

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition is unusable

STANDARD FORM 33 (Rev. 9-97)

Prescribed by GSA - FAR (48 CFR) 53.214(c)

12. In compliance with the above, the undersigned agrees, if this offer is accepted within _____180_________ calendar days (60 calendar days unless a different period is inserted

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 91

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

68HERC19R0011

(A) (B) (C) (D) (E) (F)

Delivery Location Code: CPOD

CPOD

US Environmental Protection Agency

26 West Martin Luther King Drive

Mail Code: W136

Cincinnati OH 45268-0001 USA

9999 REQUEST FOR ZERO DOLLAR ACTION

OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

NSN 7540-01-152-8067

SECTION A - Solicitation/Contract Form

SECTION B - Supplies or Services/Prices

B-1 EPAAR 1552.216-72 ORDERING-BY DESIGNATED ORDERING OFFICERS. (JUL 2014)

A. Ordering Officers The government will order any supplies and services to be furnished under this contract by issuing task/delivery orders on Optional Form 347, or an agency prescribed form, from the effective date of the contract through the expiration date of the contract. In addition to the Contracting Officer, the following individuals are authorized ordering officers.

None

B. Request for Offer

(1) When the government has a requirement for work to be performed under this contract, the Contracting Officer shall notify the contractor of (i) the work to be performed, (ii) the desired performance schedule, (iii) identify the task order as fixed price or time and materials, and (iv) any other information that may be considered to be of assistance to the contractor in preparing a cost proposal, such as format and submission due date.

(2) The request for offer (RFO) shall not obligate the government to issue task orders under this contract nor shall it authorize the Contractor to perform any work pursuant to such RFO prior to receipt of a fully executed task order.

(3) The Contracting Officer may telephone the contractor to identify resource availability for simple, well-defined tasks which only require the contractor to meet a stated schedule.

(4) The Contracting Officer may telephone or issue written requests by hard copy, facsimile, or e-mail to the contractor requesting the submission of an offer for complex tasks, where a technical approach, as well as resource availability and price/cost need to be considered. The request may include a page limitation for the offer based on the complexity of the task.

C. Submission of Offers

(1) Upon receipt of an RFO from the Contracting Officer, the Contractor shall:

(a) acknowledge receipt of the RFO; and

(b) furnish an offer within the time specified in the RFO and in the format requested.

(2) Offers shall be submitted orally, or if in writing, in duplicate, and shall include the following:

(a) Names of the personnel performing and the labor category in which each proposed individual is employed.

(b) A table or chart demonstrating for each individual proposed that they meet the minimum qualifications for the labor category they are proposed under, and number of hours proposed.

(c) cost of ODC's, if applicable.

(d) Cost of travel and per diem, if applicable; travel destination must be specified.

(e) Schedule of performance.

(f) Government furnished material/documents required to accomplish the work, if applicable.

(g) Resumes of all personnel working on the order, if not previously provided.

(h) All task order offers shall include a conflict of interest certification. Before submitting the conflict of interest certification, the contractor shall search its records accumulated, at a minimum, over the past three years immediately prior to the receipt of the request for offer or similar tasking document. In the COI certification, the contractor must certify that to the best of the contractor's knowledge and belief, all actual or potential organizational conflicts of interest have been reported to the Contracting Officer or that, to the best of the contractor's knowledge and belief, no actual or potential organizational conflicts of interest exist. In addition, the contractor must certify that its personnel who are proposed to perform work under the particular task order, or relating to the task order, have been informed of their obligation to report personal and organizational conflicts of interest to the contractor. The certification shall also include a statement that the contractor recognizes its continuing obligation to identify and report any actual or potential conflicts of interest arising during performance of the task order.

D. Task Order Type and Placement This is an indefinite delivery/indefinite quantity task order contract pursuant to FAR 16.504. Work shall be ordered by the issuance of task orders. Task Orders issued under this contract may be issued on a firm-fixed-price or time and material basis. The proposals are subject to negotiation. The Ordering Officer and the Contractor shall reach agreement on all the material terms of each order prior to the order being issued. Each task/delivery order issued will incorporate the Contractor's technical and cost proposals as negotiated with the Government, and will have a ceiling price which the contractor shall not exceed. When the Contractor has reason to believe that the labor payment and support costs for the order which will accrue in the next thirty (30) days will bring total cost to over 85 percent of the ceiling price specified in the order, the Contractor shall notify the Ordering Officer.

Under no circumstances will the Contractor start work prior to the issue date of the task/delivery order unless specifically authorized to do so by the Ordering Officer. Any verbal authorization will be confirmed in writing by the Ordering Officer or Contracting Officer within 3 calendar days.

E. Additional Proposal Instructions Proposals submitted for time and material task orders and firm fixed price task orders will be based on the fixed fully loaded labor rates set forth in the above clause entitled "Fixed Rates for Services-INDEFINITE DELIVERY/INDEFINITE QUANTITY CONTRACT (APR 1984)." Offerors can discount these rates if they choose, but cannot use higher rates.

F. Time and Materials Orders - Other Direct Costs

Costs for material and other direct costs will be negotiated on a task order specific basis as appropriate. Reasonable and allocable material handling costs or material indirect costs may be included in the charge for material or other direct costs to the extent they are clearly excluded from the fully loaded hourly labor rates and are in accordance with the Contractor's usual accounting practices consistent with Subpart 31.2 of the Federal Acquisition Regulation (End of clause)

B-2 Local Clauses 1552.216-73(DEVIATION) FIXED RATES FOR SERVICES - INDEFINITE

DELIVERY/INDEFINITE QUANTITY CONTRACT

See Attachment 4, entitled “Custom Contract Clauses,” for B-2 clause content.

B-3 Local Clauses EPA-B-16-101 MINIMUM AND MAXIMUM AMOUNTS

During the period specified in the "Ordering" clause, the Government shall place orders totaling a minimum of $100,000.00. The amount of all orders shall not exceed $25,000,000.00.

B-4 Local Clauses EPA-B-32-103 LIMITATION OF GOVERNMENT'S OBLIGATION

(a) Severable services may be incrementally funded. Non-severable services shall not be incrementally funded.

Contract line items TO BE COMPLETED IN APPLICABLE TASK ORDERS through TO BE COMPLETED IN APPLICABLE TASK ORDERS are severable and may be incrementally funded. For these items, the sum of $ TO

BE COMPLETED IN APPLICABLE TASK ORDERS of the total price is presently available for payment and allotted to this contract.

(b) For items identified in paragraph (a) of this clause, the Contractor agrees to perform up to the point at which the total amount payable by the Government, including reimbursement in the event of termination of those items for the Government's convenience, approximates the total amount currently allotted for those items to the contract. The Contractor shall not continue work on those items beyond that point. Subject to the clause entitled "Termination for Convenience of the Government," the Government will not be obligated, under any circumstances, to reimburse the Contractor in excess of the amount payable by the Government in the event of the termination of applicable contract line items for convenience including costs, profit, and estimated termination costs for those line items.

(c) Notwithstanding the dates specified in the allotment schedule in paragraph (h) of this clause, the Contractor will notify the Contracting Officer, in writing, at least 10 days prior to the date when, in the Contractor's best judgment, the work will reach the point at which the total amount payable by the Government, including any cost for termination for convenience, will approximate 85 percent of the total amount currently allotted to the contract for performance of the applicable items. The notification will state (1) the estimated date when that point will be reached and (2) an estimate of additional funding, if any, needed to continue performance of the applicable line items up to the next scheduled date for the allotment of funds identified in paragraph (a) of this clause, or to a substitute date as determined by the Government pursuant to paragraph (d) of this clause. If, after such notification, additional funds are not allotted by the date identified in the Contractor's notification, or by an agreed substitute date, the Contracting Officer will terminate any item(s) for which additional funds have not been allotted, pursuant to the clause entitled "Termination for Convenience of the Government."

(d) The parties contemplate that, subject to the availability of appropriations, the Government may allot additional funds for continued performance of the contract line items identified in paragraph (a) of this clause and will determine the estimated period of contract performance which will be covered by the funds. If additional funds are allotted, the Contracting Officer will notify the Contractor in writing. The Contractor shall not resume performance of the contract line items identified in paragraph (a) until the written notice is received. The provisions of paragraphs

(b) through (d) of this clause will apply in like manner to the additional allotted funds and to the new estimated period of contract performance. The contract will be modified accordingly.

(e) The Government may, at any time prior to termination, allot additional funds for the performance of the contract line items identified in paragraph (a) of this clause.

(f) The termination provisions of this clause do not limit the rights of the Government under the clause entitled "Default". The provisions of this clause are limited to the work and allotment of funds for the contract line items set forth in paragraph (a) of this clause. This clause no longer applies once the contract is fully funded.

(g) Nothing in this clause affects the right of the Government to otherwise terminate this contract pursuant to the contract clause entitled "Termination for Convenience of the Government".

(h) The parties contemplate that the Government may obligate funds to this contract in accordance with the following schedule:

RECAPITULATION:

PRIOR THIS NEW

AMOUNT MOD AMOUNT

Base Period

Total Maximum Amount: TO BE COMPLETED IN APPLICABLE TASK ORDERS

Funded Amount: TO BE COMPLETED IN APPLICABLE TASK ORDERS

SECTION C - Description/Specifications

C-1 EPAAR 1552.211-79 COMPLIANCE WITH EPA POLICIES FOR INFORMATION RESOURCES

MANAGEMENT. (JUL 2016)

(a) Definition. Information Resources Management (IRM) is defined as any planning, budgeting, organizing, directing, training, promoting, controlling, and managing activities associated with the burden, collection, creation, use and dissemination of information. IRM includes both information itself and the management of information and related resources such as personnel, equipment, funds, and technology.

Examples of these services include but are not limited to the following:

(1) The acquisition, creation, or modification of a computer program or automated data base for delivery to EPA or use by EPA or contractors operating EPA programs.

(2) The analysis of requirements for, study of the feasibility of, evaluation of alternatives for, or design and development of a computer program or automated data base for use by EPA or contractors operating EPA programs.

(3) Services that provide EPA personnel access to or use of computer or word processing equipment, software, or related services.

(4) Services that provide EPA personnel access to or use of: Data communications; electronic messaging services or capabilities; electronic bulletin boards, or other forms of electronic information dissemination; electronic record-keeping; or any other automated information services.

(b) General. The Contractor shall perform any IRM-related work under this contract in accordance with the IRM policies, standards, and procedures set forth on the Office of Environmental Information policy Web site. Upon receipt of a work request (i.e. delivery order, task order, or work assignment), the Contractor shall check this listing of directives. The applicable directives for performance of the work request are those in effect on the date of issuance of the work request. The 2100 Series (2100-2199) of the Agency's Directive System contains the majority of the Agency's IRM policies, standards, and procedures.

(c) Section 508 requirements (accessibility). Contract deliverables are required to be compliant with Section 508 requirements (accessibility for people with disabilities). The Environmental Protection Agency policy for 508 compliance can be found at www.epa.gov/accessibility.

(d) Electronic access. A complete listing, including full text, of documents included in the 2100 Series of the Agency's Directive System is maintained on the EPA Public Access Server on the Internet at http://www2.epa.gov/irmpoli8/current-information-directives.

(End of clause)

C-2 Local Clauses EPA-C-10-101 STATEMENT OF WORK/PERFORMANCE WORK

STATEMENT/SPECIFICATIONS

The Contractor shall furnish the necessary personnel, material, equipment, services, and facilities (except as otherwise specified), to perform the Performance Work Statement included in Attachment 1. Work will be ordered against the subject Performance Work Statement through Contracting Officer issuance of task orders.

C-3 Local Clauses EPA-C-10-103 INCORPORATION OF CONTRACTOR'S QUALITY ASSURANCE (QA)

PLAN

The Contractor shall adhere to the procedures set forth in its QA plan dated TO BE COMPLETED AT CONTRACT AWARD, which is incorporated by reference.

SECTION D - Packaging and Marking

SECTION E - Inspection and Acceptance

E-1 FAR 52.246-4 INSPECTION OF SERVICES - FIXED-PRICE. (AUG 1996)

E-2 FAR 52.246-6 INSPECTION - TIME-AND-MATERIAL AND LABOR-HOUR. (MAY 2001)

E-3 FAR 52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT. (DEC 2014)

(a) The Contractor shall comply with the higher-level quality standard(s) listed below.

Title Numbering Date Tailoring [X] Specifications and ANSI/ASQC E4 1994 See below

Guidelines for Quality Systems for Environ mental Data Collection and Environmental Technology Programs

As authorized by FAR 52.246-11, the higher-level quality standard ANSI/ASQC E4 is tailored as follows:

The solicitation and contract require the offeror/contractor to demonstrate conformance to ANSI/ASQC E4 by submitting the quality documentation described below.

In addition, after award of the contract, the Contractor shall revise, when applicable, quality documentation submitted before award to address specific comments provided by EPA and submit the revised documentation to the Contracting Officer’s Representative.

After award of the contract, the Contractor shall also implement all quality documentation approved by the Government.

A. Pre-award Documentation: The offeror must submit the following quality system documentation as a separate and identifiable part of its technical proposal:

Documentation Specifications

[X] Quality Management Plan EPA Requirements for Quality Management Plans (QA/R-2) [dated 03/20/01]

[ ] Joint Quality Management EPA Requirements for Quality Plan/Quality Assurance Management Plans (QA/R-2) [dated Project Plan for the 03/20/01] and EPA Requirements for contract Quality Assurance Project Plans (QA/R) [dated 03/20/01]

[ ] Programmatic Quality EPA Requirements for Quality Assurance Project Plan Assurance Project Plans (QA/R-5) for the entire program [dated 03/20/01] (contract)

[ ] Other Equivalent:

This documentation will be prepared in accordance with the specifications identified above, or equivalent specifications defined by EPA. The offeror shall describe their plan for covering the costs associated with the required documentation. Work involving environmental data generation or use shall not commence until the Government has approved this documentation and incorporated it into the contract.

B. Post-award Documentation: The Contractor shall submit the following quality system documentation to the Contracting Officer’s Representative at the time frames identified below:

Documentation Specification Due After

[ ] Quality Management Plan EPA Requirements for Award of Quality Management Plans contract (QA/R-2) [dated 03/20/01]

[ ] Joint Quality Management EPA Requirements for Award of Plan/Quality Assurance Quality Management Plans contract Project Plan for the (QA/R-2) [dated 03/20/01] contract and EPA Requirements for

Quality Assurance Project Plans (QA/R-5) [dated 03/20/02]

[ ] Quality Assurance EPA Requirements for Award of Project Plan for the Quality Assurance Project contract contract Plans (QA/R-5 [dated

03/20/01]

[ ] Programmatic Quality EPA Requirements for Award of Assurance Project Plan Quality Assurance Project contract for the entire program Plans (QA/R-5) [dated (contract) 03/20/01]

[X ] Quality Assurance EPA Requirements for Issuance of Project Plan for each Quality Assurance Project statement of applicable project Plans (QA/R-5 [dated work for the

03/20/01] project

[ ] Project-specific EPA Requirements for Issuance of supplement to Quality Assurance Project statement of Programmatic Quality Plans (QA/R-5 [dated work for the Assurance Project Plan 03/20/01] project for each applicable project.

[ ] Other Equivalent: [ ] award of contract [ ] issuance of statement of work for the project

This documentation will be prepared in accordance with the specifications identified above or equivalent specifications defined by EPA. The offeror shall describe their plan for covering the costs associated with the required documentation.

The Government will review and return the quality documentation, with comments, and indicating approval or disapproval. If necessary, the contractor shall revise the documentation to address all comments and shall submit the revised documentation to the government for approval.

The Contractor shall not commence work involving environmental data generation or use until the Government has approved the quality documentation.

(Note: Statement of work includes statements of work to perform projects under work assignments, task orders, delivery orders, etc.)

(b) The Contractor shall include applicable requirements of the higher-level quality standard(s) listed in paragraph (a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts, in-

(1) Any subcontract for critical and complex items (see 46.203(b) and (c)); or

(2) When the technical requirements of a subcontract require-

(i) Control of such things as design, work operations, in-process control, testing, and inspection; or

(ii) Attention to such factors as organization, planning, work instructions, documentation control, and advanced metrology.

(End of clause)

SECTION F - Deliveries or Performance

F-1 FAR 52.242-15 STOP-WORK ORDER. (AUG 1989)

F-2 52.242-17 GOVERNMENT DELAY OF WORK. (APR 1984)

F-3 EPAAR 1552.211-70 REPORTS OF WORK. (OCT 2000)

The Contractor shall prepare and deliver reports, including plans, evaluations, studies, analyses and manuals in accordance with Attachment 2. Each report shall cite the contract number, identify the U.S. Environmental Protection Agency as the sponsoring agency, and identify the name of the Contractor preparing the report.

The OMB clearance number for progress reports delivered under this contract is 2030-0005.

(End of clause)

F-4 EPAAR 1552.211-72 MONTHLY PROGRESS REPORT. (JUN 1996)

F-5 EPAAR 1552.211-75 WORKING FILES. (APR 1984)

The Contractor shall maintain accurate working files (by task or work assignment) on all work documentation including calculations, assumptions, interpretations of regulations, sources of information, and other raw data required in the performance of this contract. The Contractor shall provide the information contained in the contractor's working files upon request of the Contracting Officer.

(End of clause)

F-6 EPAAR 1552.211-78 ADVISORY AND ASSISTANCE SERVICES. (JUL 2016)

All reports containing recommendations to the Environmental Protection Agency shall include the following information on the cover of each report: (a) Name and business address of the contractor; (b) contract number; (c) contract dollar amount; (d) whether the contract was subject to full and open competition or a sole source acquisition; (e) name of the EPA Contracting Officer's Representative (COR) and the COR's office identification and location; and (f) date of report.

(End of clause)

F-7 Local Clauses EPA-F-12-101 PERIOD OF PERFORMANCE

The period of performance of this contract shall be from the effective date of award through 5 years for the ordering period, with an additional 12 months for completion of all orders inclusive of all required reports.

SECTION G - Contract Administration Data

G-1 EPAAR 1552.245-70 GOVERNMENT PROPERTY. (SEP 2009)

(a) The contractor shall not fabricate or acquire, on behalf of the Government, either directly or indirectly through a subcontract, any item of property without prior written approval from the Contracting Officer. If the Contracting Officer authorizes the contractor to acquire and/or fabricate equipment for use in the performance of this contract, the equipment shall be subject to the provisions of the "Government Property" clause and listed on the contract via contract modification.

(b) If the Government provides item(s) of Government property to the contractor for use in the performance of this contract, this property shall be used and maintained by the contractor in accordance with the provisions of the "Government Property" clause.

The "EPA Contract Property Administration Requirements" provided below apply to this contract.

U.S. Environmental Protection Agency

Contract Property Administration Requirements

1. Purpose. This document sets forth the requirements for the U.S. Environmental Protection Agency (EPA) contractors performing Government property management responsibilities under EPA contracts.

These requirements supplement those contained in the Government Property clause(s) and Part 45 Government Property of the Federal Acquisition Regulation (FAR).

2. Contract Property Administration (CPAR)

a. EPA Delegation. EPA delegates all contract property administration to the EPA Contract Property Coordinator (CPC). The delegations apply to all EPA contracts issued with or that have the potential to receive, purchase or acquire Government Property or include the Government Property clauses. In addition to administering all contract property, the CPC provides technical expertise and assistance to the Contracting Officer (CO) and Contracting Officer Technical Representative (COTR) relative to Government Property.

b. DCMA Re-delegation. The CPC may request support for contract property management oversight, including property administration and plant clearance, from the Defense Contract Management Agency (DCMA). If DCMA agrees to provide support, DCMA will notify the contractor of the assigned property administrator (PA) and plant clearance officer (PLCO). The DCMA PA is available to the contractor for assistance in all matters of property administration. Notwithstanding the delegation, as necessary, the contractor may contact the EPA CO. In the event of a disagreement between the contractor and the DCMA PA, the contractor should seek resolution from the CO. Unless, otherwise directed in the contract, or this document, all originals of written information or reports, except direct correspondence between the contractor and the DCMA PA, relative to Government property, should be forwarded to the administrative CO assigned to this contract and the CPC.

c. Disagreements. Notwithstanding the delegation(s), as necessary, the contractor may contact the CO. In the event of a disagreement between the contractor and the PA or the CPC the contractor should seek resolution from the CO.

3. Requests for Government Property.

In accordance with FAR 45.102, the contractor shall furnish all property required for performing Government contracts. If a contractor believes that Government property is required for performance of the contract, the contractor shall submit a written request to the CO. At a minimum, the request shall contain the following elements:

a. Contract number for which the property is required.

b. An item(s) description, quantity and estimated cost.

c. Certification that no like contractor property exists which could be utilized.

d. A detailed description of the task-related purpose of the property.

e. Explanation of negative impact if property is not provided by the Government.

f. Lease versus purchase analysis shall be furnished with the request to acquire property on behalf of the Government, with the exception of requests for material purchases. The contractor may not proceed with acquisition of property on behalf of the Government until receipt of written authorization from the Contracting Officer.

4. Transfer of Government Property. The Contracting Officer initiates the transfer of the government property via a contract modification. The transferor (EPA or another contractor) shall provide to the transferee, the receiving contractor, the information needed to establish and maintain the property records required of FAR 52.245-1, as well as all of the applicable data elements required by Attachment 1 of this clause. The transferee, the receiving contractor, should perform a complete inventory of the property before signing the acceptance document for the property. Accountability will transfer to the receiving contractor upon receipt and acceptance of the property, in accordance with FAR 45.106.

5. Records of Government Property.

a. In accordance with FAR 52.245-1, the contractor shall create and maintain records of all Government property, regardless of value, including property provided to and in the possession of a subcontractor.

Material provided by the Government or acquired by the contractor and billed as a direct charge to the contract is Government property and records must be established as such.

b. The Contractor shall identify all Superfund property and designate it as such both on the item and on the Government property record. If it is not practicable to tag the item, the contractor shall write the ID number on a tag, card or other entity that may be kept with the item or in a file.

c. Support documentation used for posting entries to the property record shall provide complete, current and auditable data. Entries shall be posted to the record in a timely manner following an action.

d. For Government vehicles, in addition to the data elements required by EPA, the contractor shall also comply with the General Services Administration (GSA) and Department of Energy (DOE) record and report requirements supplied with all EPA provided motor vehicles. If the above requirements were not provided with the vehicle, the contractor shall notify the designated CPC and the Fleet Manager.

e. When Government property is disclosed to be in the management and/or control of the contractor but not provided under any contract, the contractor shall record and report the property in accordance with FAR 52.245-1.

6. Inventories of Government Property. The contractor shall conduct a complete physical inventory of EPA property at least once per year. The contractor shall report the results of the inventory, including any discrepancies, to the CO. Reconciliation of discrepancies shall be completed in accordance with the schedule negotiated with the CO. See section 10 herein, Contract Closeout, for information on final inventories.

7. Reports of Government Property. EPA requires an annual summary report, for each contract, by contract number, of Government property in the contractor's possession. The annual summary is due as of September 30th of each year, and upon contract termination or expiration.

a. For each classification listed on the EPA Property Report form, with the exception of material, the contractor shall provide the total acquisition cost and total quantity. If there are zero items in a classification, or if there is an ending balance of zero, the classification must be listed with zeros in the quantity and acquisition cost columns.

b. For material, the contractor shall provide the total acquisition cost only.

c. Property classified as Plant Equipment, Superfund and Special Test Equipment must be reported on two separate lines. The first line shall include the total acquisition cost and quantity of all items or systems with a unit acquisition cost of $25,000 or more. The second line shall include the total acquisition cost and quantity of all items with a unit acquisition cost of less than $25,000.

d. For items comprising a system, which is defined as "a group of interacting items functioning as a complex whole," the contractor may maintain the record as a system noting all components of the system under the main component or maintain individual records for each item. However, for the annual report of Government property the components must be reported as a system with one total dollar amount for the system, if that system total is $25,000 or more.

e. The reports are to be received at EPA by the CPC by October 5th of each year.

f. Distribution shall be as follows:

Original to: CPC

One copy: CO

g. Contractors are required to comply with GSA and DOE special reporting requirements for motor vehicles. A statement of these requirements will be provided by the EPA Facility Management and Services Division (FMSD) concurrent with receipt of each vehicle.

h. The contractor shall provide detailed reports on an as-needed basis, as may be requested by the CO or the

CPC.

8. Disposition of Government Property. The disposition process is composed of three distinct phases:

identification, reporting, and final disposition.

a. Identification. The disposition process begins with the contractor identifying Government property that is no longer required for contract performance. Effective contract property management systems provide for identification of excess as it occurs. Once Government property has been determined to be excess to the accountable contract, it must be screened against the contractor's other EPA contracts for further use. If the property may be reutilized, the contractor shall notify the CO in writing. Government property will be transferred via contract modifications to other contracts only when the COs on both the current contract and the receiving contract authorize the transfer.

b. Reporting.

(i) EPA. Government property shall be reported in accordance with FAR 52.245-1. The Standard Form, SF 1428, Inventory Disposal Schedule, provides the format for reporting excess Government property.

Instructions for completing and when to use the form may be found at FAR 52.245-1(j). Forward the completed SF 1428 to the CPC. The SF 1428 is available at http://www.arnet.gov/far/current/html/FormsStandard54.html. Superfund property must contain a Superfund notification and the following language must be displayed on the form: "Note to CO:

Reimbursement to the EPA Superfund is required."

(ii) DCMA. If the EPA contract has been re-delegated to DCMA, the excess items will be entered into the Plant Clearance Automated Reutilization Screening System (PCARSS). Access and information pertaining to this system may be addressed to the DCMA Plant Clearance Officer (PLCO).

c. Disposition Instructions.

(i) Retention. When Government property is identified as excess, the CO may direct the contractor in writing to retain all or part of the excess Government Property under the current contract for possible future requirements.

(ii) Return to EPA. When Government property is identified as excess, the CO may direct the contractor in writing to return those items to EPA inventory. The contractor shall ship/deliver the property in accordance with the instructions provided by the CO.

(iii) Transfer. When Government property is identified as excess, the CO may direct the contractor in writing to transfer the property to another EPA contractor. The contractor shall transfer the property by shipping it in accordance with the instructions provided by the CO. To effect transfer of accountability, the contractor shall provide the recipient of the property with the applicable data elements set forth in Attachment 1 of this clause.

(iv) Sale. If GSA or the DCMA PLCO conducts a sale of the excess Government property, the contractor shall allow prospective bidders access to property offered for sale.

(v) Abandonment. Abandoned property must be disposed of in a manner that does not endanger the health and safety of the public. If the contract is delegated to DCMA and the contractor has input EPA property into the PCARSS system, the EPA Property Utilization Officer (PUO) shall notify the CO. The CO shall notify the contractor in writing of those items EPA would like to retain, have returned or transferred to another EPA contractor. The contractor shall notify the DCMA PLCO and request withdrawal of those items from the inventory schedule. The contractor shall update the Government property record to indicate the disposition of the item and to close the record. The contractor shall also obtain either a signed receipt or proof of shipment from the recipient. The contractor shall notify the CO when all actions pertaining to disposition have been completed. The contractor shall complete an EPA Property report with changes, to include supporting documentation of completed disposition actions and submit it to the CPC.

9. Decontamination. In addition to the requirements of the "Government Property" clause and prior to performing disposition of any EPA Government Property, the contractor shall certify in writing that the property is free from contamination by any hazardous or toxic substances.

10. Contract Closeout. The contractor shall complete a physical inventory of all Government property at contract completion and the results, including any discrepancies, shall be reported to the CO. If the contract is delegated to DCMA, the physical inventory report will be submitted to the EPA CO and a copy submitted to the DCMA PA. In the case of a terminated contract, the contractor shall comply with the inventory requirements set forth in the applicable termination clause. The results of the inventory, as well as a detailed inventory listing, must be forwarded to the CO and if delegated, a copy to the DCMA PA. In order to expedite the disposal process, contractors may be required to, or may elect to submit to the CPC, an inventory schedule for disposal purposes up to six (6) months prior to contract completion. If such an inventory schedule is prepared, the contractor must indicate the earliest date that each item may be disposed. The contractor shall update all property records to show disposal action. The contractor shall notify the CO, and, if delegated, the DCMA PA, in writing, when all work has been completed under the contract and all Government property accountable to the contract has been disposed. The contractor shall complete a FINAL EPA Property report with all supporting documentation to the CPC.

Attachment 1

Required Data Element--In addition to the requirements of FAR 52.245-1(f)(vi), Reports of Government Property, the contractor is required to maintain, and report the following data elements for EPA Government property (all elements are not applicable to material):

Name and address of the administrative Contracting Officer; Name of the contractor representative;

Business type; Name and address of the contract property coordinator; Superfund (Yes/No); No. of Subcontractor/Alternate Locations.

Note: For items comprising a system which is defined as, "a group of interacting items functioning as a complex whole," the contractor may maintain the record as a system noting all components of the system under the main component or maintain individual records for each item. However, for the Annual Report of Government Property, the components must be reported as a system with one total dollar amount for the system, if that system total is $25,000 or more.

G-2 EPAAR 1552.245-71 GOVERNMENT-FURNISHED DATA. (SEP 2009)

(a) The Government shall deliver to the Contractor the Government-furnished data described in the contract. If the data, suitable for its intended use, is not delivered to the Contractor, the Contracting Officer shall equitably adjust affected provisions of this contract in accordance with the "Changes" clause when:

(1) The Contractor submits a timely written request for an equitable adjustment; and

(2) The facts warrant an equitable adjustment.

(b) Title to Government-furnished data shall remain in the Government.

(c) The Contractor shall use the Government-furnished data only in connection with this contract.

(d) The following data will be furnished to the Contractor on or about the time indicated: TO BE

IDENTIFIED IN APPLICABLE TASK ORDERS

(End of clause)

G-3 Local Clauses 1552.232-70 DEV ALT1 SUBMISSION OF INVOICES (OCT 1997) DEVIATION ALT I

In order to be considered properly submitted, an invoice or request for contract financing payment must meet the following contract requirements in addition to the requirements of FAR 32.905:

(a) Unless otherwise specified in the contract, an invoice or request for contract financing payment shall be submitted as an original and five copies. The Contractor shall submit the invoice or request for contract financing payment to the following offices/individuals designated in the contract: the original and two copies to the Accounting Operations Office shown in Block [] on the cover of the contract; two copies to the Project Officer (the Project Officer may direct one of these copies to a separate address); and one copy to the Contracting Officer.

(b) The Contractor shall prepare its invoice or request for contract financing payment on the prescribed Government forms. Standard Forms Number 1034, Public Voucher for Purchases and Services other than Personal, shall be used by contractors to show the amount claimed for reimbursement. Standard Form 1035, Public Voucher for Purchases and Services other than Personal - Continuation Sheet, shall be used to furnish the necessary supporting detail or additional information required by the Contracting Officer. The Contractor may submit self-designed forms which contain the required information.

(c)(1) The Contractor shall prepare a contract level invoice or request for contract financing payment in accordance with the invoice preparation instructions identified as a separate attachment in Section J of the contract. If contract work is authorized by individual work assignments, the invoice or request for contract financing payment shall also include a summary of the current and cumulative amounts claimed by cost element for each work assignment and for the contract total, as well as any supporting data for each work assignment as identified in the instructions.

(2) The invoice or request for contract financing payment shall include current and cumulative charges by major cost element such as direct labor, overhead, travel, equipment, and other direct costs. For current costs, each major cost element shall include the appropriate supporting schedule identified in the invoice preparation instructions.

Cumulative charges represent the net sum of current charges by cost element for the contract period.

(d)(1) The charges for subcontracts shall be further detailed in a supporting schedule showing the major cost elements for each subcontract.

(d)(2) On a case-by-case basis, when needed to verify the reasonableness of subcontractor costs, the Contracting Officer may require that the contractor obtain from the subcontractor cost information in the detail set forth in (c)(2).

This information should be obtained through a means which maintains subcontractor confidentiality (for example, via sealed envelopes), if the subcontractor expresses CBI concerns.

(e) Invoices or requests for contract financing payment must clearly indicate the period of performance for which payment is requested. Separate invoices or requests for contract financing payment are required for charges applicable to the basic contract and each option period.

(f)(1) Notwithstanding the provisions of the clause of this contract at FAR 52.216-7, Allowable Cost and Payment, invoices or requests for contract financing payment shall be submitted once per month unless there has been a demonstrated need and Contracting Officer approval for more frequent billings. When submitted on a monthly basis, the period covered by invoices or requests for contractor financing payments shall be the same as the period for monthly progress reports required under this contract.

(2) If the Contracting Officer allows submissions more frequently than monthly, one submittal each month shall have the same ending period of performance as the monthly progress report.

(3) Where cumulative amounts on the monthly progress report differ from the aggregate amounts claimed in the invoice(s) or request(s) for contract financing payments covering the same period, the contractor shall provide a reconciliation of the difference as part of the payment request.

Alternate I (JUN 1996). If used in a fixed-rate type contract, substitute the following paragraphs (c)(1) and (2) for paragraphs (c)(1) and (2) of the basic clause:

(c)(1) The Contractor shall prepare a contract level invoice or request for contract financing payment in accordance with the invoice preparation instructions identified as a separate attachment in Section J of the contract. If contract work is authorized by individual delivery orders, the invoice or request for contract financing payment shall also include a summary of the current and cumulative amounts claimed by cost element for each delivery order and for the contract total, as well as any supporting data for each delivery order as identified in the instructions.

(2) The invoice or request for contract financing payment that employs a fixed rate feature shall include current and cumulative charges by contract labor category and by other major cost elements such as travel, equipment, and other direct costs. For current costs, each cost element shall include the appropriate supporting schedules identified in the invoice preparation instructions.

INVOICE PREPARATION INSTRUCTIONS

SF 1034

The information which a contractor is required to submit in its Standard Form 1034 is set forth as follows:

(1) U.S. Department, Bureau, or establishment and location - insert the names and address of the servicing finance office unless the contract specifically provides otherwise.

(2) Date Voucher Prepared - insert date on which the public voucher is prepared and submitted.

(3) Contract/Delivery Order Number and Date - insert the number and date of the contract and delivery order, if applicable, under which reimbursement is claimed.

(4) Requisition Number and Date - leave blank.

(5) Voucher Number - insert the appropriate serial number of the voucher. A separate series of consecutive numbers, beginning with Number 1, shall be used by the contractor for each new contract. When an original voucher was submitted, but not paid in full because of suspended costs, resubmission vouchers should be submitted in a separate invoice showing the original voucher number and designated with the letter "R" as the last character of the number. If there is more than one resubmission, use the appropriate suffix (R2, R3, etc.)

(6) Schedule Number; Paid By; Date Invoice Received - leave blank.

(7) Discount Terms - enter terms of discount, if applicable.

(8) Payee's Account Number - this space may be used by the contractor to record the account or job number(s) assigned to the contract or may be left blank.

(9) Payee's Name and Address - show the name of the contractor exactly as it appears in the contract and its correct address, except when an assignment has been made by the contractor, or the right to receive payment has been restricted, as in the case of an advance account. When the right to receive payment is restricted, the type of information to be shown in this space shall be furnished by the Contracting Officer.

(10) Shipped From; To; Weight Government B/L Number - insert for supply contracts.

(11) Date of Delivery or Service - show the…