656-19-307_GI001.pdf
PDF 3 MB Posted
- Attached to
- Y1DA--656-19-307 Remodel of Building 51-1, Eastside at the Saint Cloud VA, Saint Cloud, MN
- Solicitation number
- 36C26325B0007_0003
About this file
This document is a cover sheet for a federal construction project to remodel Building 51, First Floor East Side for CLC (Clinical Logistics Center) at the VA Medical Center in St. Cloud, Minnesota. The project number is 656-19-307, with a planned bid opening date of June 26, 2025, and questions due by June 17, 2025. The project involves comprehensive renovation work, including architectural, mechanical, electrical, and structural modifications across multiple building zones, with involvement from Anderson Engineering of MN (architect/structural engineer), Dunham Associates (mechanical/electrical engineering), and Institute for Environmental Assessment for hazardous material assessment.
The cover sheet provides detailed project information, including the VA contract representative (Michael McEniry), project location (4801 Veterans Drive, St. Cloud, MN), and a comprehensive sheet index covering areas such as general documentation, hazardous materials, demolition, architectural plans, finishes, furniture, equipment, structural, mechanical, and electrical drawings. The project appears to be a significant renovation effort for the VA Medical Center, with multiple engineering disciplines involved and extensive documentation to support the construction and remodeling process.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment B VAAR 852.219-75 Limitations on Subcontracting Cert of Compliance.pdf | ||
| ST CLOUD VA BLDG. 51_103896_SET_B.pdf | ||
| 20250520_Bid Doc Addendum.pdf | ||
| 36C26325B0007 0003.pdf | ||
| Bid questions B51-1 E AE VA.doc | DOC document | |
| Drawings.pdf | ||
| S04 - Site Visit Agenda 36C26325B0007 2.docx | DOCX document | |
| 20240823_STC-B51_CP_SpecVol2.pdf | ||
| Pre bid site visit sign in sheet.pdf | ||
| Volume 3 Specs.pdf | ||
| 20240823_STC-B51_CP_SpecVol1.pdf | ||
| Wage Determination Stearns MN20250099 05.02.2025.pdf | ||
| photos for bid questions B51-1.docx | DOCX document | |
| Bed.Lift.Detail.4.png | PNG image |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
51-1E
48-1W
PLAN
NORTH
PLAN
NORTH
█ ISSUED
NOT ISSUED
ISSUED FOR REFERENCE ONLY
ISSUED AS NOTED
R
N
No DATEREVISION
DRAWING TITLE
CHECKED BY
ST.CLOUD, MN 56303
VA MEDICAL CENTER
BUILDING No
LOCATION
DRAWING NO.DRAWN
DWG. OF
PROJECT TITLE
PLOT SCALE
PROJECT NO.
COVER
DATE:
APPROVED: APPROVED: PROJECTS SECTION MANAGER
APPROVED: OIT MANAGER DATE: APPROVED: ASSISTANT CHIEF ENGINEER DATE:
APPROVED: SAFETY MANAGER
APPROVED: CHIEF OF POLICE
APPROVED: PATIENT SAFETY
DATE:
DATE:
DATE: APPROVED: EMS MANAGER
APPROVED: M/O MANAGER
DATE:
DATE:
DATE:DATE:
APPROVED: MEDICAL CENTER DIRECTOR
APPROVED: PROJECT COR DATE:
APPROVED: INFECTION CONTROL NURSE DATE:
APPROVED: SERVICE LINE DIRECTOR
APPROVED: GEMS COORDINATOR DATE:
DATE:
APPROVED: NURSE EXECUTIVE
APPROVED: CHIEF OF STAFF DATE:
APPROVED: DIRECTOR FMS
APPROVED: ASSOCIATE DIRECTOR
DATE:
DATE:
DATE:
DATE:APPROVED: DATE:
APPROVED: DATE:
APPROVED: DATE:
ST. CLOUD, MN 56303
4801 VETERANS DRIVE
CONSULTANT ARCHITECT/ENGINEER OF RECORD STAMP
FULLY
SPRINKLERED
A
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10 C
U s e rs
\P u b li c \D o c u m e n ts \R e v it
P ro je c ts
\1 B
L D
G s t
F lo o r_
A E
M a rk fo rt
.r v t
/1
/2
:1 :2
P
M
GI001
COVER SHEET
REMODEL BUILDING 51-1
EAST FOR CLC
656-19-307
05/20/2025
MC EM
15479
REMODEL BUILDING 51, FIRST FLOOR EAST SIDE FOR CLC
VA COR:
CONTACT:
ADDRESS:
PHONE:
MICHAEL MCENIRY
4801 VETERANS DRIVE
SAINT CLOUD, MN 55303
320-252-1670
ARCHITECT:
NAME:
ADDRESS:
CONTACT:
ANDERSON ENGINEERING OF MN, LLC
13605 1ST AVE NORTH, SUITE 100
PLYMOUTH, MN 55441
ED MARKFORT
PHONE: 763-412-4000
STRUCTURAL ENGINEER:
NAME:
ADDRESS:
CONTACT:
ANDERSON ENGINEERING OF MN, LLC
13605 1ST AVE NORTH, SUITE 100
PLYMOUTH, MN 55441
ADAM ADAMS
PHONE: 763-412-4000
MECH/PLUMB/FIRE ENGINEER:
NAME:
ADDRESS:
CONTACT:
DUNHAM ASSOCIATES INC
50 SOUTH SIXTH STREET / SUITE 1100
MINNEAPOLIS, MN 55402-1540
JASON GOTTWALT
PHONE: 612-465-7648
ELECTRICAL ENGINEER:
NAME:
ADDRESS:
CONTACT:
DUNHAM ASSOCIATES INC
50 SOUTH SIXTH STREET / SUITE 1100
MINNEAPOLIS, MN 55402-1540
BEN ZURN
PHONE: 612-465-7626
SITE LOCATION MAP VA CAMPUS: KEY REFERENCE PLAN: VICINITY MAP SAINT CLOUD, MN:
SHEET INDEX
SHEET NO. SHEET TITLE C
ON
ST
RU
CT
IO
N
DO
CU
M
EN
TS
/23
/24
U
PD
AT
E
TO
B
ID
D
OC
UM
EN
TS
/20
/25
00 GENERAL
GI001 COVER SHEET █ █
GI002 ABBREVIATIONS █
GI110 LIFE SAFETY PLANS █
GC110 INFECTION CONTROL & PHASING PLANS █ █
GC111 INFECTION CONTROL & PHASING NOTES █
GC500 ICRA DETAIL █ █
01 HAZARD
48-HA001 FIRST FLOOR HAZARDOUS MATERIALS PLAN - ASBESTOS / LEAD █
51-HA001 FIRST FLOOR HAZARDOUS MATERIALS PLAN - ASBESTOS █
02 DEMOLITION
48-AD111 FIRST FLOOR DEMOLITION PLAN █ █
51-AD111 FIRST FLOOR DEMOLITION PLAN █ █
03 ARCHITECTURAL
48-AE110 FIRST FLOOR - FLOOR PLAN AND PARTIAL REFLECTED CEILING PLAN █
51-AE110 FIRST FLOOR OVERALL PLAN █
51-AE111 FIRST FLOOR PLAN - ZONE 1 █ █
51-AE112 FIRST FLOOR PLAN - ZONE 2 █ █
51-AE113 FIRST FLOOR DIMENSION PLAN █
51-AC111 FIRST FLOOR REFLECTED CEILING PLAN █
51-AE211 INTERIOR ELEVATIONS █
51-AE212 INTERIOR ELEVATIONS █
AE550 DETAILS █ █
AE601 INTERIOR PARTITION TYPES AND DETAILS █ █
AE602 DOOR SCHEDULE AND ELEVATIONS █ █
AE650 MOUNTING HEIGHTS █
04 FINISHES AND FURNITURE
48-AF110 FIRST FLOOR FINISH PLAN █ █
51-AF110 FIRST FLOOR FINISH PLAN █ █
AF600 MATERIAL AND ROOM FINISH SCHEDULE █ █
51-AW110 FIRST FLOOR WAYFINDING PLAN █
AW600 WAYFINDING MESSAGE SCHEDULES & SIGNAGE DETAILS █
48-IF110 FIRST FLOOR FURNITURE PLAN █
51-IF110 FIRST FLOOR FURNITURE PLAN █
05 ARCHITECTURAL EQUIPMENT
51-QH110 FIRST FLOOR EQUIPMENT PLAN █
51-1E
48-1W
TRUE
NORTH
TRUE
NORTH
TRUE
NORTH
VA CAMPUS
BUILDING 1
HAZARDOUS MATERIAL:
NAME:
ADDRESS:
CONTACT:
INSTITUTE FOR ENVIRONMENTAL ASSESSMENT,
INC (IEA, INC.)
9201 WEST BROADWAY #600
BROOKLYN PARK, MN 55445
BRANDON VOIGT
PHONE: 763-315-7900
SHEET INDEX - STRUCTURAL
S101 FIRST AND SECOND FLOOR PLAN █
SHEET INDEX - MECHANICAL
M000 MECHANICAL TITLE SHEET █
48-PP101 48-0W BASEMENT - PLUMBING PLAN █
48-PP111 48-1W FIRST FLOOR - PLUMBING AND FIRE PROTECTION PLAN █
48-MHD110 48-1W FIRST FLOOR - DEMOLITION HVAC PLAN █
48-MH110 48-1E FIRST FLOOR - HVAC PLAN █
48-MP110 48-1E FIRST FLOOR - PIPING PLAN █
51-FPD110 51-1E FIRST FLOOR - DEMOLITION FIRE PROTECTION PLAN █
51-FP110 51-1E FIRST FLOOR - FIRE PROTECTION PLAN █
51-PPD100 51-0E BASEMENT - DEMOLITION PLUMBING PLAN █
51-PPD110 51-1E FIRST FLOOR - DEMOLITION PLUMBING PLAN █
51-PMD110 51-1E FIRST FLOOR - DEMOLITION MEDICAL GAS PLAN █
51-PP100 51-0E BASEMENT - PLUMBING PLAN ZONE 1 █
51-PP101 51-0E BASEMENT - PLUMBING PLAN ZONE 2 █
51-PP110 51-1E FIRST FLOOR - PLUMBNG PLAN ZONE 1 █
51-PP111 51-1E FIRST FLOOR - PLUMBNG PLAN ZONE 2 █
51-PM110 51-1E FIRST FLOOR - MEDICAL GAS PLAN █
P500 PLUMBING DETAILS AND SCHEDULES █
P501 PLUMBING RISER DIAGRAMS - WASTE AND VENT █
P502 PLUMBING RISER DIAGRAMS - DOMESTIC WATER █
51-MHD110 51-1E FIRST FLOOR - DEMOLITION HVAC PLAN █
51-MPD100 51-0E BASEMENT - DEMOLITION PIPING PLAN █
51-MPD110 51-1E FIRST FLOOR - DEMOLITION PIPING PLAN █
51-MH110 51-1E FIRST FLOOR - HVAC PLAN ZONE 1 █
51-MH111 51-1E FIRST FLOOR - HVAC PLAN ZONE 2 █
51-MP100 51-0E BASEMENT - PIPING PLAN ZONE 1 █
51-MP101 51-0E BASEMENT - PIPING PLAN ZONE 2 █
51-MP110 51-1E FIRST FLOOR - PIPING PLAN ZONE 1 █
51-MP111 51-1E FIRST FLOOR - PIPING PLAN ZONE 2 █
M500 MECHANICAL DETAILS AND SCHEDULES █
M600 SEQUENCES OF OPERATIONS █
SHEET INDEX - ELECTRICAL
E000 ELECTRICAL TITLE SHEET █
48-ED110 FIRST FLOOR DEMOLITION ELECTRICAL PLANS █
51-ED110 FIRST FLOOR DEMOLITION ELECTRICAL PLANS █
51-ED111 FIRST FLOOR DEMOLITION SYSTEM PLAN █
48-EL110 FIRST FLOOR LIGHTING PLAN █ █
48-EP110 FIRST FLOOR POWER PLAN █
48-ES110 FIRST FLOOR SYSTEMS PLAN █
48-EF110 FIRST FLOOR FIRE ALARM PLAN █
51-EE100 BASEMENT ELECTRICAL PLAN █ █
51-EL110 FIRST FLOOR LIGHTING PLAN - ZONE 1 █ █
51-EL111 FIRST FLOOR LIGHTING PLAN - ZONE 2 █
51-EP110 FIRST FLOOR POWER PLAN - ZONE 1 █
51-EP111 FIRST FLOOR POWER PLAN - ZONE 2 █ █
51-ES110 FIRST FLOOR SYSTEMS PLAN - ZONE 1 █ █
51-ES111 FIRST FLOOR SYSTEMS PLAN - ZONE 2 █ █
51-EF110 FIRST FLOOR FIRE ALARM - ZONE 1 █
51-EF111 FIRST FLOOR FIRE ALARM PLAN - ZONE 2 █
E300 ELECTRICAL RISER █
E500 ELECTRICAL DETAILS █
E501 ELECTRICAL DETAILS █
E600 ELECTRICAL SCHEDULES █
LEGEND - SHEET INDEX
GULDMANN CEILING MOUNTED PATIENT LIFTS - FOR REFERENCE
GUL101 FACILITY SIGNOFF
GUL102 GEN. INFO.
GUL103 ATTACHMENT
GUL104 PROJECT DETAILS
GUL105 RM. 111
GUL106 RM. 117
GUL107 RM. 124 & 125
GUL108 RM. 127
1 UPDATE TO BID DOCUMENTS 05/20/25
| Sheets |
| GI001 - COVER SHEET |
File details come from the government source that posted it. Updated .