620-20-201 Drawings Phase 1.pdf
PDF 30 MB Posted
- Attached to
- Y1DZ--620-20-201 Replace Mission Critical Roofs Phase I (Buildings 3, 6, 13, 14, 17 and 36)
- Solicitation number
- 36C24224B0014
About this file
This document appears to be a set of drawings related to Solicitation Number 36C24224B0014, which is a solicitation for the replacement of mission critical roofs in Phase I for Buildings 3, 6, 13, 14, 17, and 36. The solicitation is issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2. The project is titled "Y1DZ--620-20-201 Replace Mission Critical Roofs Phase I". No additional details about the required products, services, pricing, or solicitation timeline are provided in this particular file.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24224B0014 0010.docx | DOCX document | |
| 36C24224B0014 0009.docx | DOCX document | |
| 36C24224B0014 0008.docx | DOCX document | |
| 240612 VMON-001 Detail Revisions.pdf | ||
| 36C24224B0014 0007.docx | DOCX document | |
| 36C24224B0014 0006.docx | DOCX document | |
| RFI Responses Contd.docx | DOCX document | |
| 36C24224B0014 0005.docx | DOCX document | |
| Mission Critical Roofs Phase I Responses RFI.xlsx | XLSX spreadsheet | |
| 36C24224B0014 0004.docx | DOCX document | |
| VMON-002-Haz_Mat_Testing_Report-01.07.22.pdf | ||
| 36C24224B0014 0003.docx | DOCX document | |
| 36C24224B0014 0002.docx | DOCX document | |
| 36C24224B0014 0001.docx | DOCX document | |
| P07 - Wage Determination Dutchess County NY.txt | TXT text file | |
| 52-225-2-Buy-American-Certificate.pdf | ||
| 620-20-201 Specifications Phase 1 (2).pdf | ||
| 36C24224B0014.docx | DOCX document |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
Sprinkler Status
AE Works, LTD.
418 Beaver Street
Sewickley, PA 15143
Phone: 412-287-7333 www.ae-works.comAE WORKS®
A u to d e s k D o c s /V
M O
N -0
M o n tr o s e R o o f R e p la c e m e n t/ V
M O
N -0
M o n tr o s e
R o o f R e p la c e m e n t
P h a s e
.r v t
/2
/2
:5
:4
A
M
G001
COVER SHEET MISSION CRITICAL ROOFS,
MONTROSE, PHASE 1
2094 ALBANY POST RD, MONTROSE, NY 10548
620-20-201
08.24.23 RS AC
BID DOCUMENTS
MISSION CRITICAL ROOFS, MONTROSE, PHASE 1
MONTROSE VAMC
2094 ALBANY POST RD
MONTROSE, NY 10548
PROJECT DIRECTORY
OWNER:
MONTROSE VAMC
2094 ALBANY POST RD
MONTROSE, NY 10548
ARCHITECT/ENGINEER:
AE WORKS, LTD
418 BEAVER ST
SEWICKLEY, PA 15143
(412) 287-7333 EXT. 209
ENIVIRONMENTAL ENGINEER:
PENNONI
501 BOYLSTON ST
BOSTON, MA 02116
(857) 214-4285
CAMPUS MAP
LOCATION MAP
SHEET INDEX
GENERAL
G001 COVER SHEET
G002 SITE PLAN
G111 PHASING PLANS
G112 PHASING PLANS
ABATEMENT
ASB103 BLDG 3 ROOF ABATEMENT PLAN
ASB106 BLDG 6 ROOF ABATEMENT PLAN
ASB113 BLDG 13 ROOF ABATEMENT PLAN
ASB114 BLDG 14 ROOF ABATEMENT PLAN
ASB117 BLDG 17 ROOF ABATEMENT PLAN
ASB136 BLDG 36 ROOF ABATEMENT PLAN
STRUCTURAL
S001 STRUCTURAL NOTES
S103 BLDG 3 ROOF FRAMING PLAN
S106 BLDG 6 ROOF FRAMING PLAN
S113 BLDG 13 ROOF FRAMING PLAN
S114 BLDG 14 ROOF FRAMING PLAN
S501 SECTIONS AND DETAILS
S502 SECTIONS AND DETAILS
FALL PROTECTION
FP-103 BLDG 3 ROOF FALL PROTECTION PLAN
FP-106 BLDG 6 ROOF FALL PROTECTION PLAN
FP-113 BLDG 13 ROOF FALL PROTECTION PLAN
FP-114 BLDG 14 ROOF FALL PROTECTION PLAN
FP-117 BLDG 17 ROOF FALL PROTECTION PLAN
FP-136 BLDG 36 ROOF FALL PROTECTION PLAN
FP-601 GUARDRAIL DETAILS
FP-602 GUARDRAIL AND FIXED LADDER DETAILS
FP-603 REPLACEMENT ROOF HATCH DETAILS
FP-604 FALL PROTECTION ANCHOR DETAILS
SITE
CONTACT: NICOLAS VASQUEZCONTACT:
KYLE MORGAN
VA CONTRACTING OFFICER'S REPRESENTATIVE
(845) 522-1338
DANY HUMPHREYS
CONTRACT SPECIALIST
(914) 737-4400 EXT. 2066
STRUCTURAL ENGINEER:
WOODS PEACOCK
5285 SHAWNEE RD
SUITE 100
ALEXANDRIA, VA 22312
(703) 658-4400
CONTACT: ERIC FRADY
COMMISSIONING:
COMMANDER'S CONCEPTS
COMMISIONING
1173 RESEARCH WAY
FOREST, VA 24523
(713) 492-1922
CONTACT: RICH DIDDAMS
CONSULTING ENGINEER:
VERTICAL ACCESS
PO BOX 4135
ITHACA, NY 14852
(607) 257-4049
CONTACT: KELLY STREETER
ESTIMATING:
TROPHY POINT
4588 SOUTH PARK AVE
BLASDELL, NY 14219
(716) 823-0006
CONTACT: RICH CHUDZIK
CONTACT: CHRIS HUTCHINS
# Revisions Date
SHEET INDEX
ARCHITECTURAL
A001 ABBREVIATIONS, NOTES AND SYMBOLS
A103 BLDG 3 ROOF PLANS & SECTION
A106 BLDG 6 ROOF PLANS & SECTION
A113 BLDG 13 ROOF PLANS & SECTION
A114 BLDG 14 ROOF PLANS & SECTION
A117 BLDG 17 ROOF PLANS & SECTION
A136 BLDG 36 ROOF PLANS & SECTION
A201 REFERENCE PARTIAL ELEVATIONS & SECTIONS BLDG 17
A202 REFERENCE ELEVATIONS TYPICAL BUILDING
A401 DETAILS
A402 DETAILS
A403 DETAILS
A404 DETAILS
ELECTRICAL
E001 ELECTRICAL SYMBOLS AND ABBREVIATIONS
E101 BLDGS 3 AND 6 LIGHTNING PROTECTION ROOF PLANS
E102 BLDGS 13 AND 14 LIGHTNING PROTECTION ROOF PLANS
E103 BLDGS 17 AND 36 LIGHTNING PROTECTION ROOF PLANS
E401 LIGHTNING PROTECTION DETAILS
KEY:
APPROXIMATE LOCATION OF
CONSTRUCTION MATERIAL LAYDOWN
AREA AND CONTRACTOR TRAILER.
CONFIRM WITH OWNER. PROVIDE 8'
CONSTRUCTION FENCING AS REQUIRED.
POTENTIAL LOCATION FOR
CONTRACTOR PARKING.
CONFIRM WITH OWNER.
FDR VETERANS HOSPITAL RD
FDR VETERANS HOSPITAL RD
BATTERY PL
BUILDING, CONNECTING CORRIDOR, OR OTHER
ELEMENT NOT WITHIN PROJECT SCOPE
EXISTING EXTERIOR
OVERHEAD DUCT
EXISTING CONNECTING
CORRIDOR - NOT IN SCOPE
EXISTING
CONNECTING
CORRIDOR - NOT
IN SCOPE
EXISTING
CONNECTING
CORRIDOR - NOT
IN SCOPE
EXISTING CONNECTING
CORRIDOR - NOT IN SCOPE
EXISTING CONNECTING
CORRIDOR - NOT IN SCOPE
EXISTING
CONNECTING
CORRIDOR - NOT IN
SCOPE
EXISTING
CONNECTING
CORRIDOR - NOT
IN SCOPE
EXISTING
CONNECTING
CORRIDOR - NOT
IN SCOPE
EXISTING
CONNECTING
CORRIDOR - NOT
IN SCOPE
BUILDING WITHIN PROJECT SCOPE
EXISTING EXTERIOR
OVERHEAD DUCT
NEW YORK STATE
VETERAN'S HOME
PARKING
LOT A
PARKING
LOT B
PARKING
LOT C
PARKING
LOT G
PARKING
LOT H
PARKING
LOT I
ELECTRICAL GENERATOR -
MAINTAIN ACCESS
ELECTRICAL TRANSFORMER -
MAINTAIN ACCESS
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
Sprinkler Status
AE Works, LTD.
418 Beaver Street
Sewickley, PA 15143
Phone: 412-287-7333 www.ae-works.comAE WORKS®
A u to d e s k D o c s /V
M O
N -0
M o n tr o s e R o o f R e p la c e m e n t/ V
M O
N -0
M o n tr o s e
R o o f R e p la c e m e n t
P h a s e
.r v t
/2
/2
:5
:5
A
M
G002
SITE PLAN MISSION CRITICAL ROOFS,
MONTROSE, PHASE 1
2094 ALBANY POST RD, MONTROSE, NY 10548
620-20-201
06.23.23 RS AC
100% CONSTRUCTION
DOCUMENTS
1" = 100'-0"
SITE PLAN
N
SITE PLAN & PHASING NOTES
1 ALL CONSTRUCTION WORK TO CONFORM WITH THE APPLICABLE CODES AND ORDINANCES OF
THE LOCAL JURISDICTION, THE STATE OF NEW YORK, AND THE CURRENT ADOPTED VERSION
OF THE INTERNATIONAL BUILDING CODE FAMILY. THE CONTRACTOR TO POST NOTICES AND
COMPLY WITH THE GOVERNING LAWS OF THE JURISDICTION.
2 THE SITE WORK TO BE PROPERLY SUPERVISED BY THE CONTRACTORS JOB SITE
SUPERINTENDANT. SUFFICIENT PERSONNEL WILL BE EMPLOYED TO COMPLETE THE WORK
WITHIN THE CONTRACTED TIME. PERSONNEL TO BE SKILLED IN THE TASK ASSIGNED.
3 MAINTAIN ADEQUATE PROTECTION TO SAFEGUARD THE PUBLIC AND ALL PERSONS ENGAGED
IN THE PERFORMANCE OF THE WORK.
4 THE DRAWINGS REFLECT CONDITIONS AS CAN BE INFERRED FROM VISIBLE CONDITIONS, OR
FROM DRAWINGS AND INFORMATION FURNISHED BY THE OWNER, BUT CANNOT BE
GUARANTEED. VERIFY ALL GRADES, LINE LEVELS AND DIMENSIONS INDICATED ON THE
DRAWNGS AND REPORT ALL INCONSISTENCIES TO THE ARCHITECT PRIOR TO THE EXECUTION
OF THE WORK. RECHECK ALL DIMENSIONS PRIOR TO ORDERING MANUFACTURED AND/OR
FABRICATED ITEMS.
5 ASSUME FULL RESPONSIBILITY FOR PROTECTION AND SAFEKEEPING OF PRODUCTS
PURCHASED FOR THIS PRODUCT AND STORED ON THE PROJECT SITE. COORDINATE WITH THE
OWNER ON PREFERRED LOCATIONS FOR STORED MATERIALS ON THE PROJECT SITE.
6 MAINTAIN AREAS UNDER THE CONTRACTOR'S CONTROL TO BE FREE OF WASTE MATERIALS,
DEBRIS, AND RUBBISH. CONTAINERS FOR DEPOSIT OF DEBRIS AND RUBBISH WILL BE PROVIDED
BY THE CONTRACTOR. COORDINATE LOCATION OF CONTAINERS WITH THE OWNER'S
REPRESENTATIVE PRIOR TO PLACEMENT. REMOVE AND DISPOSE OF DEMOLITION MATERIAL
OFF SITE IN ACCORDANCE WITH APPLICABLE CODES AND/OR SPECIFICATIONS.
7 EXTRANEOUS MATERIALS TO BE PERIODICALLY REMOVED, AND AT THE CONCLUSION OF THE
PROJECT.
8 DURING CONSTRUCTION THE CONTRACTOR WILL WORK ADJACENT TO PATIENT OCCUPIED
FLOORS. CONSTRUCTION RELATED ACTIVITIES ARE NOT TO ADVERSELY IMPACT THESE AREAS.
CONSTRUCTION RELATED ACTIVITIES THAT MIGHT AFFECT THESE AREAS MUST BE
COORDINATED WITH AND APPROVED BY THE VA PRIOR TO OCCURRENCE.
9 THE FACILITY IS OPERATIONAL. CONTRACTOR TO MAKE PROVISIONS FOR OWNER AND PUBLIC USE OF THE BUILDING AROUND THE CONSTRUCTION AREA. DELIVERIES, STAGING, STORAGE OF
MATERIALS AND OTHER CONSTRUCTION RELATED ACTIVITIES TO BE COORDINATED WITH THE
CONTRACTING OFFICER SO AS TO NOT ADVERSELY AFFECT THE BUILDING OPERATIONS.
10 PROTECTIVE MEASURES TO BE TAKEN BY THE CONTRACTOR TO PROTECT ADJACENT
PROPERTY AT ALL TIMES DURING CONSTRUCTION.
11 ALL TEMPORARY BRACING AND SHORING TO BE DESIGNED TO SUSTAIN ALL CONSTRUCTION
LOADS, SOIL PRESSURE, LATERAL AND OTHER LOADS TO WHICH THE STRUCTURE MAY BE
SUBJECTED.
12 INSTALL TEMPORARY PROTECTION FENCING AROUND TREES AND SHRUBS TO PROTECT FROM
CONSTRUCTION. THE FENCING, IF POSSIBLE, SHOULD EXTEND IN A CIRCLE AROUND THE TREES CRITICAL ROOT ZONE. THIS AREA SHOULD BE POSTED WITH SIGNAGE AS "OFF LIMITS TO ALL
CONSTRUCTION ACTIVITIES. MAINTAIN FENCE AND REMOVE WHEN CONSTRUCTION IS
COMPLETE. TREES INDICATED ON PLAN ARE FOR REFERENCE AND IN APPROXIMATE
LOCATIONS AND MAY NOT INCLUDE ALL TREES REQUIRING PROTECTION. REFER TO
SPECIFICATIONS FOR ADDITIONAL INFO.
13 PROVIDE TEMPORARY SIDEWALK AS REQUIRED TO MAINTAIN PEDESTRIAN ACCESS DURING
CONSTRUCTION. ALL EXISTING SIDEWALK AND CURBS ARE TO BE PROTECTED DURING
CONSTRUCTION. NOTE EXISTING SIDEWALKS ARE 4" THICK AND DO NOT CONTAIN
REINFORCING.
14 CONTRACTOR IS RESPONSIBLE FOR VERIFICATION THAT THERE IS NO BLOCKAGE OF SECURITY
CAMERA COVERAGE BY SCAFFOLDING OR OTHER CONSTRUCTION ITEMS. IF BLOCKAGE
OCCURS, CONSTRACTOR IS RESPONSIBLE FOR RELOCATION OF THOSE CAMERAS. ALL OTHER
SECURITY CAMERAS WITHIN THE AREA OF WORK SHALL BE PROTECTED IN PLACE.
15 NO UTILITIES, OTHER THAN THOSE INDICATED, SHALL BE INTERUPTED OR DISTURBED. ALL FIRE
HYDRANTS, MANHOLES, AND UTILITIES SHALL BE MAINTAINED AND PROTECTED AS NECESSARY
TO PREVENT DAMAGE DURING CONSTRUCTION.
16 ALL AREAS DISTURBED DURING CONSTRUCTION ARE TO BE RESTORED TO
PRE-CONSTRUCTION CONDITIONS.
17 CONSTRUCTION FENCE TO BE UTILIZED FOR ALL CONSTRUCTION WORK (NOT LIMITED TO
ABATEMENT WORK). FINAL LOCATIONS OF CONSTRUCTION GATES TO BE DETERMINED BY
CONTRACTOR AND INCLUDED ON APPROVED SITE PLAN
18 RELOCATED PARKING AND ANY NECESSARY ROAD CLOSURES TO BE COORDINATED BETWEEN
VA AND CONTRACTOR. PARKING AND ANY IMPACTS TO TRAFFIC ARE TO BE INCLUDED ON
CONTRACTOR'S APPROVED SITE PLAN.
19 DETAIL AND ENGINEERING OF SCAFFOLDING IS THE RESPONSIBILITY OF THE CONTRACTOR.
CONTRACTOR TO ERECT SCAFFOLDING DURING OFF HOURS. CONTRACTOR TO PROVIDE
TEMPORARY SIGNAGE DIRECTING BUILDING OCCUPANTS TO NEAREST EXIT WHILE SCAFFOLD
CONSTRUCTION OR DEMOLITION OCCURS. NO MORE THAN ONE EXIT FROM THE BUILDING CAN
BE CLOSED AT ANY TIME DURING THE ERECTION OR REMOVAL OF THE SCAFFOLDING.
20 ACCESS MUST BE MAINTAINED TO ALL ELECTRICAL SECTIONALIZING SWITCHES,
TRANSFORMERS, AND GENERATORS ON THE PROJECT SITE. LOCATIONS TO BE CONFIRMED
PRIOR TO CONSTRUCTION.
21 CONTRACTOR RESPONSIBLE FOR PROVIDING JERSEY BARRIERS AT PROTECTION
SCAFFOLDING IN ANY LOADING OR VEHICULAR AREAS AND ELSEWHERE AS REQUIRED IN THE
VA PHYSICAL SECURITY GUIDE.
22 CONTRACTOR MUST MAINTAIN FREE ACCESS FROM THE STREET TO ALL FIRE HYDRANTS,
SPRINKLER SYSTEM FIRE DEPARTMENT CONNECTIONS, AND STANDPIPES WITHIN STAIRWELLS
AT ALL TIMES.
# Revisions Date
Project Title
Location
Issue Date Checked Drawn
Phase
Sprinkler Status
MISSION CRITICAL ROOFS,
MONTROSE, PHASE 1
2094 ALBANY POST RD, MONTROSE, NY 10548
08.24.23 RS AC
BID DOCUMENTS
BLDG 36
TEMPORARY
PROTECTION
SCAFFOLDING
8' CONSTRUCTION
FENCE WITH GATES
AS REQUIRED
BLDG 37
MH
MH
MH
FH
DANGER TAPE
EXISTING
PARKING AREA
ELECTRICAL
MANHOLE
BLDG 13
EXISTING EXTERIOR
OVERHEAD DUCT
- NOT IN SCOPE
EXISTING CONNECTING CORRIDOR
- NOT IN SCOPE
EXISTING CONNECTING CORRIDOR
- NOT IN SCOPE
T Y
P
TEMPORARY
PROTECTION
SCAFFOLDING
TEMPORARY
PROTECTION
SCAFFOLDING
8' CONSTRUCTION
FENCE WITH GATES AS
REQUIRED
TEMPORARY PROTECTION SCAFFOLDING
OVER CONNECTING CORRIDOR
TEMPORARY PROTECTION
SCAFFOLDING OVER
CONNECTING CORRIDOR
MH
MH
MH
MH
MH
MH
TEMPORARY SIDEWALK
EXISTING SECURITY CAMERA -
PROTECT / RELOCATE AS
REQUIRED - CONFIRM WITH VA;
LOCATIONS TO BE CONFIRMED
EXISTING SECURITY CAMERA -
PROTECT / RELOCATE AS
REQUIRED - CONFIRM WITH VA;
LOCATIONS TO BE CONFIRMED
EXISTING SECURITY CAMERA -
PROTECT / RELOCATE AS
REQUIRED - CONFIRM WITH VA;
LOCATIONS TO BE CONFIRMED
EXISTING SECURITY CAMERA -
PROTECT / RELOCATE AS REQUIRED -
CONFIRM WITH VA; LOCATIONS TO BE
CONFIRMED
EXISTING LOADING DOCK
FUTURE STAIR TOWER -
NOT IN SCOPE
FUTURE STAIR TOWER -
NOT IN SCOPE
ELECTRICAL
MANHOLE
EXISTING EQUIPMENT
EXISTING
EQUIPMENT
FUTURE CHILLERS
TEMPORARY PROTECTION
SCAFFOLDING
FIRE DEPARTMENT CONNECTION
- MAINTAIN ACCESS
TEMPORARY PROTECTION SCAFFOLDING
BLDG 16 - NOT IN SCOPE
BLDG 17
T Y
P
TEMPORARY
PROTECTION
SCAFFOLDING
TEMPORARY SIDEWALK
8' CONSTRUCTION FENCE
WITH GATES AS REQUIRED
CB
MH
FH
MHMH
MH MH
MH
MH
MH
MH
FH
TEMPORARY
PROTECTION
SCAFFOLDING
STAIR TOWER ADDITION
(NOT IN SCOPE)
MH
EXISTING SECURITY
CAMERA - PROTECT /
RELOCATE AS REQUIRED -
CONFIRM WITH VA;
LOCATIONS TO BE
CONFIRMED
EXISTING SECURITY CAMERA -
PROTECT / RELOCATE AS
REQUIRED - CONFIRM WITH VA;
LOCATIONS TO BE CONFIRMED
PARKING AREA TO BE CLOSED
DURING BLDG PHASE I
EXISTING LOADING DOCK
EXISTING PARKING SPACES
8' CONSTRUCTION FENCE
WITH GATES AS
NECESSARY FOR
CONSTRUCTION
ROAD CLOSURE AS NECESSARY
FOR CONSTRUCTION DURING
BUILDING PHASE II. PROVIDE
TRAFFIC BARRIERS AS
NECESSARY. INCLUDE ON
SUBMITTED CONSTRUCTION SITE
PLAN FOR APPROVAL.
NOTE: CONSTRUCTION ON BUILDING 17 TO BE
DIVIDED INTO TWO PRIMARY PHASES - EAST
AND WEST PHASES TO ALLOW FOR DELIVERY
ACCESS TO ONE END OF THE LOADING DOCK
OR THE OTHER AT ALL TIMES. BLDG PHASE IBLDG PHASE II
PARKING AREA TO BE CLOSED
DURING BLDG PHASE I & II
25' - 0" 25' - 0"
AREA ENCLOSED DURING PHASE II.
AREA ENCLOSED DURING PHASE I & II.
AREA ENCLOSED DURING PHASE I.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
Sprinkler Status
AE Works, LTD.
418 Beaver Street
Sewickley, PA 15143
Phone: 412-287-7333 www.ae-works.comAE WORKS®
A u to d e s k D o c s /V
M O
N -0
M o n tr o s e R o o f R e p la c e m e n t/ V
M O
N -0
M o n tr o s e
R o o f R e p la c e m e n t
P h a s e
.r v t
/2
/2
:5
:5
A
M
G111
PHASING PLANS MISSION CRITICAL ROOFS,
MONTROSE, PHASE 1
2094 ALBANY POST RD, MONTROSE, NY 10548
620-20-201
06.23.23 RS AC
100% CONSTRUCTION
DOCUMENTS
SITE PLAN & PHASING NOTES
1 ALL CONSTRUCTION WORK TO CONFORM WITH THE APPLICABLE CODES AND ORDINANCES OF
THE LOCAL JURISDICTION, THE STATE OF NEW YORK, AND THE CURRENT ADOPTED VERSION
OF THE INTERNATIONAL BUILDING CODE FAMILY. THE CONTRACTOR TO POST NOTICES AND
COMPLY WITH THE GOVERNING LAWS OF THE JURISDICTION.
2 THE SITE WORK TO BE PROPERLY SUPERVISED BY THE CONTRACTORS JOB SITE
SUPERINTENDANT. SUFFICIENT PERSONNEL WILL BE EMPLOYED TO COMPLETE THE WORK
WITHIN THE CONTRACTED TIME. PERSONNEL TO BE SKILLED IN THE TASK ASSIGNED.
3 MAINTAIN ADEQUATE PROTECTION TO SAFEGUARD THE PUBLIC AND ALL PERSONS ENGAGED
IN THE PERFORMANCE OF THE WORK.
4 THE DRAWINGS REFLECT CONDITIONS AS CAN BE INFERRED FROM VISIBLE CONDITIONS, OR
FROM DRAWINGS AND INFORMATION FURNISHED BY THE OWNER, BUT CANNOT BE
GUARANTEED. VERIFY ALL GRADES, LINE LEVELS AND DIMENSIONS INDICATED ON THE
DRAWNGS AND REPORT ALL INCONSISTENCIES TO THE ARCHITECT PRIOR TO THE EXECUTION
OF THE WORK. RECHECK ALL DIMENSIONS PRIOR TO ORDERING MANUFACTURED AND/OR
FABRICATED ITEMS.
5 ASSUME FULL RESPONSIBILITY FOR PROTECTION AND SAFEKEEPING OF PRODUCTS
PURCHASED FOR THIS PRODUCT AND STORED ON THE PROJECT SITE. COORDINATE WITH THE
OWNER ON PREFERRED LOCATIONS FOR STORED MATERIALS ON THE PROJECT SITE.
6 MAINTAIN AREAS UNDER THE CONTRACTOR'S CONTROL TO BE FREE OF WASTE MATERIALS,
DEBRIS, AND RUBBISH. CONTAINERS FOR DEPOSIT OF DEBRIS AND RUBBISH WILL BE PROVIDED
BY THE CONTRACTOR. COORDINATE LOCATION OF CONTAINERS WITH THE OWNER'S
REPRESENTATIVE PRIOR TO PLACEMENT. REMOVE AND DISPOSE OF DEMOLITION MATERIAL
OFF SITE IN ACCORDANCE WITH APPLICABLE CODES AND/OR SPECIFICATIONS.
7 EXTRANEOUS MATERIALS TO BE PERIODICALLY REMOVED, AND AT THE CONCLUSION OF THE
PROJECT.
8 DURING CONSTRUCTION THE CONTRACTOR WILL WORK ADJACENT TO PATIENT OCCUPIED
FLOORS. CONSTRUCTION RELATED ACTIVITIES ARE NOT TO ADVERSELY IMPACT THESE AREAS.
CONSTRUCTION RELATED ACTIVITIES THAT MIGHT AFFECT THESE AREAS MUST BE
COORDINATED WITH AND APPROVED BY THE VA PRIOR TO OCCURRENCE.
9 THE FACILITY IS OPERATIONAL. CONTRACTOR TO MAKE PROVISIONS FOR OWNER AND PUBLIC USE OF THE BUILDING AROUND THE CONSTRUCTION AREA. DELIVERIES, STAGING, STORAGE OF
MATERIALS AND OTHER CONSTRUCTION RELATED ACTIVITIES TO BE COORDINATED WITH THE
CONTRACTING OFFICER SO AS TO NOT ADVERSELY AFFECT THE BUILDING OPERATIONS.
10 PROTECTIVE MEASURES TO BE TAKEN BY THE CONTRACTOR TO PROTECT ADJACENT
PROPERTY AT ALL TIMES DURING CONSTRUCTION.
11 ALL TEMPORARY BRACING AND SHORING TO BE DESIGNED TO SUSTAIN ALL CONSTRUCTION
LOADS, SOIL PRESSURE, LATERAL AND OTHER LOADS TO WHICH THE STRUCTURE MAY BE
SUBJECTED.
12 INSTALL TEMPORARY PROTECTION FENCING AROUND TREES AND SHRUBS TO PROTECT FROM
CONSTRUCTION. THE FENCING, IF POSSIBLE, SHOULD EXTEND IN A CIRCLE AROUND THE TREES CRITICAL ROOT ZONE. THIS AREA SHOULD BE POSTED WITH SIGNAGE AS "OFF LIMITS TO ALL
CONSTRUCTION ACTIVITIES. MAINTAIN FENCE AND REMOVE WHEN CONSTRUCTION IS
COMPLETE. TREES INDICATED ON PLAN ARE FOR REFERENCE AND IN APPROXIMATE
LOCATIONS AND MAY NOT INCLUDE ALL TREES REQUIRING PROTECTION. REFER TO
SPECIFICATIONS FOR ADDITIONAL INFO.
13 PROVIDE TEMPORARY SIDEWALK AS REQUIRED TO MAINTAIN PEDESTRIAN ACCESS DURING
CONSTRUCTION. ALL EXISTING SIDEWALK AND CURBS ARE TO BE PROTECTED DURING
CONSTRUCTION. NOTE EXISTING SIDEWALKS ARE 4" THICK AND DO NOT CONTAIN
REINFORCING.
14 CONTRACTOR IS RESPONSIBLE FOR VERIFICATION THAT THERE IS NO BLOCKAGE OF SECURITY
CAMERA COVERAGE BY SCAFFOLDING OR OTHER CONSTRUCTION ITEMS. IF BLOCKAGE
OCCURS, CONSTRACTOR IS RESPONSIBLE FOR RELOCATION OF THOSE CAMERAS. ALL OTHER
SECURITY CAMERAS WITHIN THE AREA OF WORK SHALL BE PROTECTED IN PLACE.
15 NO UTILITIES, OTHER THAN THOSE INDICATED, SHALL BE INTERUPTED OR DISTURBED. ALL FIRE
HYDRANTS, MANHOLES, AND UTILITIES SHALL BE MAINTAINED AND PROTECTED AS NECESSARY
TO PREVENT DAMAGE DURING CONSTRUCTION.
16 ALL AREAS DISTURBED DURING CONSTRUCTION ARE TO BE RESTORED TO
PRE-CONSTRUCTION CONDITIONS.
17 CONSTRUCTION FENCE TO BE UTILIZED FOR ALL CONSTRUCTION WORK (NOT LIMITED TO
ABATEMENT WORK). FINAL LOCATIONS OF CONSTRUCTION GATES TO BE DETERMINED BY
CONTRACTOR AND INCLUDED ON APPROVED SITE PLAN
18 RELOCATED PARKING AND ANY NECESSARY ROAD CLOSURES TO BE COORDINATED BETWEEN
VA AND CONTRACTOR. PARKING AND ANY IMPACTS TO TRAFFIC ARE TO BE INCLUDED ON
CONTRACTOR'S APPROVED SITE PLAN.
19 DETAIL AND ENGINEERING OF SCAFFOLDING IS THE RESPONSIBILITY OF THE CONTRACTOR.
CONTRACTOR TO ERECT SCAFFOLDING DURING OFF HOURS. CONTRACTOR TO PROVIDE
TEMPORARY SIGNAGE DIRECTING BUILDING OCCUPANTS TO NEAREST EXIT WHILE SCAFFOLD
CONSTRUCTION OR DEMOLITION OCCURS. NO MORE THAN ONE EXIT FROM THE BUILDING CAN
BE CLOSED AT ANY TIME DURING THE ERECTION OR REMOVAL OF THE SCAFFOLDING.
20 ACCESS MUST BE MAINTAINED TO ALL ELECTRICAL SECTIONALIZING SWITCHES,
TRANSFORMERS, AND GENERATORS ON THE PROJECT SITE. LOCATIONS TO BE CONFIRMED
PRIOR TO CONSTRUCTION.
21 CONTRACTOR RESPONSIBLE FOR PROVIDING JERSEY BARRIERS AT PROTECTION
SCAFFOLDING IN ANY LOADING OR VEHICULAR AREAS AND ELSEWHERE AS REQUIRED IN THE
VA PHYSICAL SECURITY GUIDE.
22 CONTRACTOR MUST MAINTAIN FREE ACCESS FROM THE STREET TO ALL FIRE HYDRANTS,
SPRINKLER SYSTEM FIRE DEPARTMENT CONNECTIONS, AND STANDPIPES WITHIN STAIRWELLS
AT ALL TIMES.
N
# Revisions Date
1" = 40'-0"
PHASING PLAN
Project Title
Location
Issue Date Checked Drawn
Phase
Sprinkler Status
MISSION CRITICAL ROOFS,
MONTROSE, PHASE 1
2094 ALBANY POST RD, MONTROSE, NY 10548
BLDG 3
EXISTING CONNECTING CORRIDOR
- NOT IN SCOPE
EXISTING CONNECTING CORRIDOR
- NOT IN SCOPE
T Y
P
TEMPORARY
PROTECTION
SCAFFOLDING
TEMPORARY
PROTECTION
SCAFFOLDING
8' CONSTRUCTION
FENCE WITH GATES
AS REQUIRED
TEMPORARY PROTECTION
SCAFFOLDING OVER
CONNECTING CORRIDOR
TEMPORARY PROTECTION
SCAFFOLDING OVER CONNECTING
CORRIDOR
TEMPORARY
PROTECTION
SCAFFOLDING
TEMPORARY PROTECTION SCAFFOLDING
OVER CONNECTING CORRIDOR
MH
MH
MH
MH
MH
MH
FH
FH
TEMPORARY
PROTECTION
SCAFFOLDING
EXISTING SECURITY CAMERA -
PROTECT / RELOCATE AS
REQUIRED - CONFIRM WITH VA;
LOCATIONS TO BE CONFIRMED
EXISTING SECURITY CAMERA -
PROTECT / RELOCATE AS
REQUIRED - CONFIRM WITH VA;
LOCATIONS TO BE CONFIRMED
EXISTING
PARKING LOT
EXISTING PARKING
TEMPORARY PROTECTION
SCAFFOLDING
EXISTING
EQUIPMENT
EXISTING EQUIPMENT
EXISTING EQUIPMENT
EXISTING EQUIPMENT
ELECTRICAL
MANHOLE
EXISTING TRANSFORMER
TEMPORARY
PROTECTION
SCAFFOLDING
FIRE DEPARTMENT CONNECTION
- MAINTAIN ACCESS
TEMPORARY PROTECTION SCAFFOLDING
BLDG 14
EXISTING CONNECTING CORRIDOR
- NOT IN SCOPE
EXISTING CONNECTING CORRIDOR
- NOT IN SCOPE
EXISTING EXTERIOR OVERHEAD DUCT
- NOT IN SCOPE
T Y
P
TEMPORARY SIDEWALK
TEMPORARY PROTECTION
SCAFFOLDING
TEMPORARY PROTECTION
SCAFFOLDING
TEMPORARY PROTECTION
SCAFFOLDING
8' CONSTRUCTION FENCE
WITH GATES AS REQUIRED
TEMPORARY PROTECTION
SCAFFOLDING OVER
CONNECTING CORRIDOR
TEMPORARY PROTECTION
SCAFFOLDING OVER
CONNECTING CORRIDOR
MH
MH
MH
MH
MH
MH MH
MH
FH
TEMPORARY PROTECTION
SCAFFOLDING
EXISTING SECURITY CAMERA -
PROTECT / RELOCATE AS
REQUIRED - CONFIRM WITH VA;
LOCATIONS TO BE CONFIRMED
EXISTING SECURITY CAMERA -
PROTECT / RELOCATE AS
REQUIRED - CONFIRM WITH VA;
LOCATIONS TO BE CONFIRMED
EXISTING SECURITY CAMERA -
PROTECT / RELOCATE AS
REQUIRED - CONFIRM WITH VA;
LOCATIONS TO BE CONFIRMED
EXISTING SECURITY CAMERA -
PROTECT / RELOCATE AS
REQUIRED - CONFIRM WITH VA;
LOCATIONS TO BE CONFIRMED
EXISTING FUEL TANK
EXISTING LOADING DOCK
EXISTING GENERATOR
BUILDING - MAINTAIN ACCESS
EXISTING EQUIPMENT
EXISTING EQUIPMENT
TEMPORARY PROTECTION
SCAFFOLDING
FIRE DEPARTMENT CONNECTION -
MAINTAIN ACCESS
BLDG 6
EXISTING CONNECTING CORRIDOR
- NOT IN SCOPE
EXISTING CONNECTING CORRIDOR
- NOT IN SCOPE
T Y
P
TEMPORARY SIDEWALK
TEMPORARY
PROTECTION
SCAFFOLDING
TEMPORARY PROTECTION
SCAFFOLDING
TEMPORARY PROTECTION
SCAFFOLDING
8' CONSTRUCTION FENCE WITH
GATES AS REQUIRED
EXISTING EQUIPMENTTEMPORARY PROTECTION
SCAFFOLDING
TEMPORARY PROTECTION SCAFFOLDING
OVER CONNECTING CORRIDOR
TEMPORARY SIDEWALK
TEMPORARY SIDEWALK
EXISTING COMMUNITY GARDEN
- PROVIDE FENCING AND PROTECT
FROM CONSTRUCTION
FH
MH
MH
MH
FH
MH
MH
EXISTING SECURITY CAMERA -
PROTECT / RELOCATE AS
REQUIRED - CONFIRM WITH VA;
LOCATIONS TO BE CONFIRMED
TEMPORARY
PROTECTION
SCAFFOLDING
EXISTING SECURITY CAMERA -
PROTECT / RELOCATE AS
REQUIRED - CONFIRM WITH VA;
LOCATIONS TO BE CONFIRMED
EXISTING LOADING
DOCK
EXISTING PARKING LOT
FIRE DEPARTMENT CONNECTION -
MAINTAIN ACCESS
ROOF NOT IN SCOPE
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
Sprinkler Status
AE Works, LTD.
418 Beaver Street
Sewickley, PA 15143
Phone: 412-287-7333 www.ae-works.comAE WORKS®
A u to d e s k D o c s /V
M O
N -0
M o n tr o s e R o o f R e p la c e m e n t/ V
M O
N -0
M o n tr o s e
R o o f R e p la c e m e n t
P h a s e
.r v t
/2
/2
:5
:0
A
M
G112
PHASING PLANS MISSION CRITICAL ROOFS,
MONTROSE, PHASE 1
2094 ALBANY POST RD, MONTROSE, NY 10548
620-20-201
06.23.23 RS AC
100% CONSTRUCTION
DOCUMENTS
SITE PLAN & PHASING NOTES
1 ALL CONSTRUCTION WORK TO CONFORM WITH THE APPLICABLE CODES AND ORDINANCES OF
THE LOCAL JURISDICTION, THE STATE OF NEW YORK, AND THE CURRENT ADOPTED VERSION
OF THE INTERNATIONAL BUILDING CODE FAMILY. THE CONTRACTOR TO POST NOTICES AND
COMPLY WITH THE GOVERNING LAWS OF THE JURISDICTION.
2 THE SITE WORK TO BE PROPERLY SUPERVISED BY THE CONTRACTORS JOB SITE
SUPERINTENDANT. SUFFICIENT PERSONNEL WILL BE EMPLOYED TO COMPLETE THE WORK
WITHIN THE CONTRACTED TIME. PERSONNEL TO BE SKILLED IN THE TASK ASSIGNED.
3 MAINTAIN ADEQUATE PROTECTION TO SAFEGUARD THE PUBLIC AND ALL PERSONS ENGAGED
IN THE PERFORMANCE OF THE WORK.
4 THE DRAWINGS REFLECT CONDITIONS AS CAN BE INFERRED FROM VISIBLE CONDITIONS, OR
FROM DRAWINGS AND INFORMATION FURNISHED BY THE OWNER, BUT CANNOT BE
GUARANTEED. VERIFY ALL GRADES, LINE LEVELS AND DIMENSIONS INDICATED ON THE
DRAWNGS AND REPORT ALL INCONSISTENCIES TO THE ARCHITECT PRIOR TO THE EXECUTION
OF THE WORK. RECHECK ALL DIMENSIONS PRIOR TO ORDERING MANUFACTURED AND/OR
FABRICATED ITEMS.
5 ASSUME FULL RESPONSIBILITY FOR PROTECTION AND SAFEKEEPING OF PRODUCTS
PURCHASED FOR THIS PRODUCT AND STORED ON THE PROJECT SITE. COORDINATE WITH THE
OWNER ON PREFERRED LOCATIONS FOR STORED MATERIALS ON THE PROJECT SITE.
6 MAINTAIN AREAS UNDER THE CONTRACTOR'S CONTROL TO BE FREE OF WASTE MATERIALS,
DEBRIS, AND RUBBISH. CONTAINERS FOR DEPOSIT OF DEBRIS AND RUBBISH WILL BE PROVIDED
BY THE CONTRACTOR. COORDINATE LOCATION OF CONTAINERS WITH THE OWNER'S
REPRESENTATIVE PRIOR TO PLACEMENT. REMOVE AND DISPOSE OF DEMOLITION MATERIAL
OFF SITE IN ACCORDANCE WITH APPLICABLE CODES AND/OR SPECIFICATIONS.
7 EXTRANEOUS MATERIALS TO BE PERIODICALLY REMOVED, AND AT THE CONCLUSION OF THE
PROJECT.
8 DURING CONSTRUCTION THE CONTRACTOR WILL WORK ADJACENT TO PATIENT OCCUPIED
FLOORS. CONSTRUCTION RELATED ACTIVITIES ARE NOT TO ADVERSELY IMPACT THESE AREAS.
CONSTRUCTION RELATED ACTIVITIES THAT MIGHT AFFECT THESE AREAS MUST BE
COORDINATED WITH AND APPROVED BY THE VA PRIOR TO OCCURRENCE.
9 THE FACILITY IS OPERATIONAL. CONTRACTOR TO MAKE PROVISIONS FOR OWNER AND PUBLIC USE OF THE BUILDING AROUND THE CONSTRUCTION AREA. DELIVERIES, STAGING, STORAGE OF
MATERIALS AND OTHER CONSTRUCTION RELATED ACTIVITIES TO BE COORDINATED WITH THE
CONTRACTING OFFICER SO AS TO NOT ADVERSELY AFFECT THE BUILDING OPERATIONS.
10 PROTECTIVE MEASURES TO BE TAKEN BY THE CONTRACTOR TO PROTECT ADJACENT
PROPERTY AT ALL TIMES DURING CONSTRUCTION.
11 ALL TEMPORARY BRACING AND SHORING TO BE DESIGNED TO SUSTAIN ALL CONSTRUCTION
LOADS, SOIL PRESSURE, LATERAL AND OTHER LOADS TO WHICH THE STRUCTURE MAY BE
SUBJECTED.
12 INSTALL TEMPORARY PROTECTION FENCING AROUND TREES AND SHRUBS TO PROTECT FROM
CONSTRUCTION. THE FENCING, IF POSSIBLE, SHOULD EXTEND IN A CIRCLE AROUND THE TREES CRITICAL ROOT ZONE. THIS AREA SHOULD BE POSTED WITH SIGNAGE AS "OFF LIMITS TO ALL
CONSTRUCTION ACTIVITIES. MAINTAIN FENCE AND REMOVE WHEN CONSTRUCTION IS
COMPLETE. TREES INDICATED ON PLAN ARE FOR REFERENCE AND IN APPROXIMATE
LOCATIONS AND MAY NOT INCLUDE ALL TREES REQUIRING PROTECTION. REFER TO
SPECIFICATIONS FOR ADDITIONAL INFO.
13 PROVIDE TEMPORARY SIDEWALK AS REQUIRED TO MAINTAIN PEDESTRIAN ACCESS DURING
CONSTRUCTION. ALL EXISTING SIDEWALK AND CURBS ARE TO BE PROTECTED DURING
CONSTRUCTION. NOTE EXISTING SIDEWALKS ARE 4" THICK AND DO NOT CONTAIN
REINFORCING.
14 CONTRACTOR IS RESPONSIBLE FOR VERIFICATION THAT THERE IS NO BLOCKAGE OF SECURITY
CAMERA COVERAGE BY SCAFFOLDING OR OTHER CONSTRUCTION ITEMS. IF BLOCKAGE
OCCURS, CONSTRACTOR IS RESPONSIBLE FOR RELOCATION OF THOSE CAMERAS. ALL OTHER
SECURITY CAMERAS WITHIN THE AREA OF WORK SHALL BE PROTECTED IN PLACE.
15 NO UTILITIES, OTHER THAN THOSE INDICATED, SHALL BE INTERUPTED OR DISTURBED. ALL FIRE
HYDRANTS, MANHOLES, AND UTILITIES SHALL BE MAINTAINED AND PROTECTED AS NECESSARY
TO PREVENT DAMAGE DURING CONSTRUCTION.
16 ALL AREAS DISTURBED DURING CONSTRUCTION ARE TO BE RESTORED TO
PRE-CONSTRUCTION CONDITIONS.
17 CONSTRUCTION FENCE TO BE UTILIZED FOR ALL CONSTRUCTION WORK (NOT LIMITED TO
ABATEMENT WORK). FINAL LOCATIONS OF CONSTRUCTION GATES TO BE DETERMINED BY
CONTRACTOR AND INCLUDED ON APPROVED SITE PLAN
18 RELOCATED PARKING AND ANY NECESSARY ROAD CLOSURES TO BE COORDINATED BETWEEN
VA AND CONTRACTOR. PARKING AND ANY IMPACTS TO TRAFFIC ARE TO BE INCLUDED ON
CONTRACTOR'S APPROVED SITE PLAN.
19 DETAIL AND ENGINEERING OF SCAFFOLDING IS THE RESPONSIBILITY OF THE CONTRACTOR.
CONTRACTOR TO ERECT SCAFFOLDING DURING OFF HOURS. CONTRACTOR TO PROVIDE
TEMPORARY SIGNAGE DIRECTING BUILDING OCCUPANTS TO NEAREST EXIT WHILE SCAFFOLD
CONSTRUCTION OR DEMOLITION OCCURS. NO MORE THAN ONE EXIT FROM THE BUILDING CAN
BE CLOSED AT ANY TIME DURING THE ERECTION OR REMOVAL OF THE SCAFFOLDING.
20 ACCESS MUST BE MAINTAINED TO ALL ELECTRICAL SECTIONALIZING SWITCHES,
TRANSFORMERS, AND GENERATORS ON THE PROJECT SITE. LOCATIONS TO BE CONFIRMED
PRIOR TO CONSTRUCTION.
21 CONTRACTOR RESPONSIBLE FOR PROVIDING JERSEY BARRIERS AT PROTECTION
SCAFFOLDING IN ANY LOADING OR VEHICULAR AREAS AND ELSEWHERE AS REQUIRED IN THE
VA PHYSICAL SECURITY GUIDE.
22 CONTRACTOR MUST MAINTAIN FREE ACCESS FROM THE STREET TO ALL FIRE HYDRANTS,
SPRINKLER SYSTEM FIRE DEPARTMENT CONNECTIONS, AND STANDPIPES WITHIN STAIRWELLS
AT ALL TIMES.
N
# Revisions Date
1" = 40'-0"
PHASING PLAN
Project Title
Location
Issue Date Checked Drawn
Phase
Sprinkler Status
MISSION CRITICAL ROOFS,
MONTROSE, PHASE 1
2094 ALBANY POST RD, MONTROSE, NY 10548
A103
BUILDING ADDITION
ROOF BELOW
(NOT IN SCOPE)
EXISTING
MECH
EQUIP
BUILDING ADDITION
ROOF BELOW
(NOT IN SCOPE)
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.ae-works.com®
Au to de sk
D oc s:
//V
M O
N -0
M on tro se R oo f R ep la ce m en t/V
M O
N -0
M on tro se R oo f R ep la ce m en t.r vt
/3 /2
3:
:4
PM
ASB103
BLDG 3 ROOF ABATEMENT PLAN MISSION CRITICAL ROOFS,
MONTROSE, PHASE 2
2094 ALBANY POST RD, MONTROSE, NY 10548
620-23-205
8.24.2023 NV
BID DOCUMENTS
ABATEMENT LEGEND
# Revisions Date
1/16" = 1'-0"1 BUILDING 3 ROOF ABATEMENT PLAN
REMOTE DECONTAMINATION UNIT
ACM ROOFING AND CAULKING
25 FT PERIMETER CONSTRUCTION FENCING
WASTE CONTAINER
AIR SAMPLE LOCATION
WASTE DECONTAMINATION UNIT
GENERAL ABATEMENT NOTES
1. MATERIALS AND QUANTITIES SCHEDULED FOR ABATEMENT:
1,075 SQUARE FEET OF GREEN EPOXY GUTTER COATING ASSOCIATED
WITH THE PITCHED ROOF
500 SQUARE FEET AND 1,175 LINEAR FEET OF WHITE FLASHING
ASSOCIATED WITH THE ROOF EDGE ON THE PITCHED ROOF AND THE
ROOF VALLEYS
12,750 SQUARE FEET OF FELT PAPER UNDER CLAY TILE ASSOCIATED
WITH THE PITCHED ROOF
90 LINEAR FEET OF BLACK PATCH FLASHING TAR ASSOCIATED WITH
THE PITCHED ROOF
40 SQUARE FEET OF RED NAIL CAULK AT COPPER ASSOCIATED WITH
THE PITCHED ROOF
200 SQUARE FEET OF BLACK FLASHING ASSOCIATED WITH THE FLAT
ROOF
120 LINEAR FEET OF WHITE CAPSTONE FLASHING ASSOCIATED WITH
THE FLAT ROOF
40 LINEAR FEET OF MECHANICAL EQUIPMENT CAULKING ASSOCIATED
WITH THE FLAT ROOF
2. ABATEMENT IS NOT NECESSARILY LIMITED TO WHAT IS SHOWN ON THE
DRAWINGS. THE INTENT IS TO INDICATE THE GENERAL SCOPE OF
ABATEMENT REQUIRED TO COMPLETE THE WORK IN ACCORDANCE WITH
THE CONTRACT DRAWINGS.
3. THE CONTRACTOR SHALL COORDINATE WITH THE VETERANS
ADMINISTRATION (VA) FOR SEQUENCE AND PHASING OF ABATEMENT,
WASTE RECEPTACLE PLACEMENT, ELEVATOR USAGE, HVAC ISOLATION,
AND OTHER SHUT DOWNS SO AS NOT TO DISRUPT THE ONGOING
OPERATION OF THE MEDICAL CENTER FACILITIES.
4. CONTRACTOR SHALL BE RESPONSIBLE FOR THE PROPER STATING OF
WORK AS TO PROTECT AND ENSURE THAT IT WILL NOT HAVE ANY
INTERFERENCE OF ACCESS TO OR FROM FIRE EGRESSES, ELEVATORS,
ETC. COORDINATE PHASING WITH VA.
5. REMOVE ALL SLATE SHINGLES TO IN ORDER TO FACILITATE COMPLETE
REMOVAL OF ASBESTOS CONTAINING FELT PAPER.
6. THE CONTRACTOR IS RESPONSIBLE FOR SELECTIVE
DEMOLITION/REMOVAL OF ITEMS REQUIRE FOR ASBESTOS ABATEMENT
NOT INDICATED ON THE DEMOLITION PLANS. THE CONTRACTOR IS TO
PATCH/REPAIR/REPLACE ITEMS REMOVED OR EFFECTED BY ASBESTOS
ABATEMENT AS REQUIRED FOR CODE COMPLIANCE AND LIFE SAFETY.
7. THE CONTRACTOR SHALL COMPLY WITH ALL APPLICABLE PROVISIONS
OF THE INFECTION CONTROL RISK ASSESSMENT (IRCA) AND INTERIM LIFE
SAFETY MEASURES (ILSM) PLANS PERTAINING TO ABATEMENT ACTIVITIES.
8. ROOF TEAR OFF SHALL BE COMPLETED IN SECTIONS WHICH WILL
ALLOW FOR THE COMPLETE REPLACEMENT BY THE END OF EACH SHIFT.
THE REGULATED WORK AREAS SHALL BE REDUCED SEQUENTIALLY AS
TEAR OFF IS COMPLETED TO ALLOW FOR ROOF REPLACEMENT.
9. CONTRACTOR SHALL UTILIZE ONSITE WATER SUPPLY AND SANITARY
SEWER FOR ABATEMENT ACTIVITIES.
10. CONTRACTOR SHALL PROVIDE AN 8' CHAIN LINK CONSTRUCTION FENCE
AROUND THE CONSTRUCTION AREA INDICATED ON THE DRAWINGS. GATES
EQUIPPED WITH HASPS AND PADLOCKS SHALL BE PROVIDED AS REQUIRED
FOR ACCESS. FINAL LOCATIONS OF GATES TO BE DETERMINED BY
CONTRACTOR AND INCLUDED ON APPROVED SITE PLAN. FENCE FABRIC
SHALL BE FASTENED TO TERMINAL POSTS WITH TENSION BANDS AND TO
LINE POSTS AND TO TOP AND BOTTOM RAILS WITH TIE WIRES. POSTS ARE
TO BE ANCHORED ON SURFACE STANDS WITH FOUR SANDBAGS AT EACH
POST. STEEL PIPE IS NOT TO BE DRIVEN BELOW GRADE. ASBESTOS
DANGER SIGNAGE COMPLIANT WITH 29 CFR 1926.1101 SHALL BE SECURED
TO FENCING DELINEATING THE REGULATED AREA AT INTERVALS OF NO
LESS THAN 20 FEET.
11. CONTRACTOR SHALL PLACE WASTE RECEPTACLE AT LEAST 30' AWAY
FROM THE BUILDING.
12. CONTRACTOR SHALL BE RESPONSIBLE FOR PROTECTING EXISTING
CONNECTING CORRIDOR FROM DAMAGE.
13. THE HVAC SYSTEM ON BUILDING 3 CANNOT BE SHUTDOWN DUE TO
ONGOING HOSPITAL OPERATIONS OCCURRING WITHIN THE BUILDING. THE
CONTRACTOR MUST SUBMIT A PLAN TO REROUTE INTAKE AND EXHAUST
AIR AWAY FROM THE ROOFTOP DURING ABATEMENT ACTIVITIES.
14. RELOCATED PARKING AND ANY NECESSARY ROAD CLOSURES TO BE
COORDINATED BETWEEN VA AND CONTRACTOR. PARKING AND ANY
IMPACTS TO TRAFFIC ARE TO BE INCLUDED ON CONTRACTOR'S APPROVED
SITE PLAN.
15. CONTRACTOR TO ERECT SCAFFOLDING DURING OFF HOURS.
CONTRACTOR TO PROVIDE TEMPORARY SIGNAGE DIRECTING BUILDING
OCCUPANTS TO NEAREST EXIT WHILE SCAFFOLD CONSTRUCTION OR
DEMOLITION OCCURS.
16. CONTRACTOR SHALL PERFORM ABATEMENT IN A MANNER THAT DOES
NOT DAMAGE REMAINING MATERIALS.
RC
N
620-20-201
A106
EXISTING
MECH
EQUIP
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.ae-works.com
Au to de sk
D oc s:
//V
M O
N -0
M on tro se R oo f R ep la ce m en t/V
M O
N -0
M on tro se R oo f R ep la ce m en t.r vt
/3 /2
3:
:4
PM
ASB106
BLDG 6 ROOF ABATEMENT PLAN MISSION CRITICAL ROOFS,
MONTROSE, PHASE 2
2094 ALBANY POST RD, MONTROSE, NY 10548
620-23-205
8.24.2023 RC NV
BID DOCUMENTS
# Revisions Date
1/16" = 1'-0"1 BUILDING 6 ROOF ABATEMENT PLAN
ABATEMENT LEGEND
REMOTE DECONTAMINATION UNIT
ACM ROOFING AND CAULKING
25 FT PERIMETER CONSTRUCTION FENCING
WASTE CONTAINER
AIR SAMPLE LOCATION
WASTE DECONTAMINATION UNIT
GENERAL ABATEMENT NOTES
N
1. MATERIALS AND QUANTITIES SCHEDULED FOR ABATEMENT:
1,075 SQUARE FEET OF GREEN EPOXY GUTTER COATING ASSOCIATED
WITH THE PITCHED ROOF
500 SQUARE FEET AND 1,175 LINEAR FEET OF WHITE FLASHING
ASSOCIATED WITH THE ROOF EDGE ON THE PITCHED ROOF AND THE
ROOF VALLEYS
12,750 SQUARE FEET OF FELT PAPER UNDER CLAY TILE ASSOCIATED
WITH THE PITCHED ROOF
90 LINEAR FEET OF BLACK PATCH FLASHING TAR ASSOCIATED WITH
THE PITCHED ROOF
40 SQUARE FEET OF RED NAIL CAULK AT COPPER ASSOCIATED WITH
THE PITCHED ROOF
200 SQUARE FEET OF FELT PAPER ASSOCIATED WITH THE PARAPET
WALLS ON THE FLAT ROOF
200 SQUARE FEET OF BLACK FLASHING ASSOCIATED WITH THE FLAT
ROOF
120 LINEAR FEET OF WHITE CAPSTONE FLASHING ASSOCIATED WITH
THE FLAT ROOF
40 LINEAR FEET OF MECHANICAL EQUIPMENT CAULKING ASSOCIATED
WITH THE FLAT ROOF
2. ABATEMENT IS NOT NECESSARILY LIMITED TO WHAT IS SHOWN ON THE
DRAWINGS. THE INTENT IS TO INDICATE THE GENERAL SCOPE OF
ABATEMENT REQUIRED TO COMPLETE THE WORK IN ACCORDANCE WITH
THE CONTRACT DRAWINGS.
3. THE CONTRACTOR SHALL COORDINATE WITH THE VETERANS
ADMINISTRATION (VA) FOR SEQUENCE AND PHASING OF ABATEMENT,
WASTE RECEPTACLE PLACEMENT, ELEVATOR USAGE, HVAC ISOLATION,
AND OTHER SHUT DOWNS SO AS NOT TO DISRUPT THE ONGOING
OPERATION OF THE MEDICAL CENTER FACILITIES.
4. CONTRACTOR SHALL BE RESPONSIBLE FOR THE PROPER STATING OF
WORK AS TO PROTECT AND ENSURE THAT IT WILL NOT HAVE ANY
INTERFERENCE OF ACCESS TO OR FROM FIRE EGRESSES, ELEVATORS,
ETC. COORDINATE PHASING WITH VA.
5. REMOVE ALL SLATE SHINGLES TO IN ORDER TO FACILITATE COMPLETE
REMOVAL OF ASBESTOS CONTAINING FELT PAPER.
6. THE CONTRACTOR IS RESPONSIBLE FOR SELECTIVE
DEMOLITION/REMOVAL OF ITEMS REQUIRE FOR ASBESTOS ABATEMENT
NOT INDICATED ON THE DEMOLITION PLANS. THE CONTRACTOR IS TO
PATCH/REPAIR/REPLACE ITEMS REMOVED OR EFFECTED BY ASBESTOS
ABATEMENT AS REQUIRED FOR CODE COMPLIANCE AND LIFE SAFETY.
7. THE CONTRACTOR SHALL COMPLY WITH ALL APPLICABLE PROVISIONS
OF THE INFECTION CONTROL RISK ASSESSMENT (IRCA) AND INTERIM LIFE
SAFETY MEASURES (ILSM) PLANS PERTAINING TO ABATEMENT ACTIVITIES.
8. ROOF TEAR OFF SHALL BE COMPLETED IN SECTIONS WHICH WILL
ALLOW FOR THE COMPLETE REPLACEMENT BY THE END OF EACH SHIFT.
THE REGULATED WORK AREAS SHALL BE REDUCED SEQUENTIALLY AS
TEAR OFF IS COMPLETED TO ALLOW FOR ROOF REPLACEMENT.
9. CONTRACTOR SHALL UTILIZE ONSITE WATER SUPPLY AND SANITARY
SEWER FOR ABATEMENT ACTIVITIES.
10. CONTRACTOR SHALL PROVIDE AN 8' CHAIN LINK CONSTRUCTION FENCE
AROUND THE CONSTRUCTION AREA INDICATED ON THE DRAWINGS. GATES
EQUIPPED WITH HASPS AND PADLOCKS SHALL BE PROVIDED AS REQUIRED
FOR ACCESS. FINAL LOCATIONS OF GATES TO BE DETERMINED BY
CONTRACTOR AND INCLUDED ON APPROVED SITE PLAN. FENCE FABRIC
SHALL BE FASTENED TO TERMINAL POSTS WITH TENSION BANDS AND TO
LINE POSTS AND TO TOP AND BOTTOM RAILS WITH TIE WIRES. POSTS ARE
TO BE ANCHORED ON SURFACE STANDS WITH FOUR SANDBAGS AT EACH
POST. STEEL PIPE IS NOT TO BE DRIVEN BELOW GRADE. ASBESTOS
DANGER SIGNAGE COMPLIANT WITH 29 CFR 1926.1101 SHALL BE SECURED
TO FENCING DELINEATING THE REGULATED AREA AT INTERVALS OF NO
LESS THAN 20 FEET.
11. CONTRACTOR SHALL PLACE WASTE RECEPTACLE AT LEAST 30' AWAY
FROM THE BUILDING.
12. CONTRACTOR SHALL BE RESPONSIBLE FOR PROTECTING EXISTING
CONNECTING CORRIDOR FROM DAMAGE.
13. THE HVAC SYSTEM ON BUILDING 6 CANNOT BE SHUTDOWN DUE TO
ONGOING HOSPITAL OPERATIONS OCCURRING WITHIN THE BUILDING. THE
CONTRACTOR MUST SUBMIT A PLAN TO REROUTE INTAKE AND EXHAUST
AIR AWAY FROM THE ROOFTOP DURING ABATEMENT ACTIVITIES.
14. RELOCATED PARKING AND ANY NECESSARY ROAD CLOSURES TO BE
COORDINATED BETWEEN VA AND CONTRACTOR. PARKING AND ANY
IMPACTS TO TRAFFIC ARE TO BE INCLUDED ON CONTRACTOR'S APPROVED
SITE PLAN.
15. CONTRACTOR TO ERECT SCAFFOLDING DURING OFF HOURS.
CONTRACTOR TO PROVIDE TEMPORARY SIGNAGE DIRECTING BUILDING
OCCUPANTS TO NEAREST EXIT WHILE SCAFFOLD CONSTRUCTION OR
DEMOLITION OCCURS.
16. CONTRACTOR SHALL PERFORM ABATEMENT IN A MANNER THAT DOES
NOT DAMAGE REMAINING MATERIALS.
A113
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.ae-works.com
Au to de sk
D oc s:
//V
M O
N -0
M on tro se R oo f R ep la ce m en t/V
M O
N -0
M on tro se R oo f R ep la ce m en t.r vt
/3 /2
3:
:4
PM
ASB113
BLDG 13 ROOF ABATEMENT PLAN MISSION CRITICAL ROOFS,
MONTROSE, PHASE 2
2094 ALBANY POST RD, MONTROSE, NY 10548
620-23-205
8.24.2023 RC NV
BID DOCUMENTS
# Revisions Date
1/16" = 1'-0"1 BUILDING 13 ROOF ABATEMENT PLAN
ABATEMENT LEGEND
REMOTE DECONTAMINATION UNIT
ACM ROOFING AND CAULKING
25 FT PERIMETER CONSTRUCTION FENCING
WASTE CONTAINER
AIR SAMPLE LOCATION
WASTE DECONTAMINATION UNIT
GENERAL ABATEMENT NOTES
N
1. MATERIALS AND QUANTITIES SCHEDULED FOR ABATEMENT:
40 SQUARE FEET OF RED NAIL CAULK AT COPPER ASSOCIATED WITH
THE PITCHED ROOF
12,750 SQUARE FEET OF FELT PAPER UNDER CLAY TILE ASSOCIATED
WITH THE PITCHED ROOF
500 SQUARE FEET AND 1,175 LINEAR FEET OF WHITE FLASHING
ASSOCIATED WITH THE ROOF EDGE ON THE PITCHED ROOF AND THE
ROOF VALLEYS
40 LINEAR FEET OF MECHANICAL EQUIPMENT CAULKING ASSOCIATED
WITH THE FLAT ROOF
200 SQUARE FEET OF BLACK ASPHALTIC FLASHING ASSOCIATED WITH
THE FLAT ROOF
120 LINEAR FEET OF WHITE CAPSTONE CAULKING ASSOCIATED WITH
THE FLAT ROOF
800 SQUARE FEET OF BUILT-UP ASPHALT ROOF ASSOCIATED WITH THE
FLAT ROOF
2. ABATEMENT IS NOT NECESSARILY LIMITED TO WHAT IS SHOWN ON THE
DRAWINGS. THE INTENT IS TO INDICATE THE GENERAL SCOPE OF
ABATEMENT REQUIRED TO COMPLETE THE WORK IN ACCORDANCE WITH
THE CONTRACT DRAWINGS.
3. THE CONTRACTOR SHALL COORDINATE WITH THE VETERANS
ADMINISTRATION (VA) FOR SEQUENCE AND PHASING OF ABATEMENT,
WASTE RECEPTACLE PLACEMENT, ELEVATOR USAGE, HVAC ISOLATION,
AND OTHER SHUT DOWNS SO AS NOT TO DISRUPT THE ONGOING
OPERATION OF THE MEDICAL CENTER FACILITIES.
4. CONTRACTOR SHALL BE RESPONSIBLE FOR THE PROPER STATING OF
WORK AS TO PROTECT AND ENSURE THAT IT WILL NOT HAVE ANY
INTERFERENCE OF ACCESS TO OR FROM FIRE EGRESSES, ELEVATORS,
ETC. COORDINATE PHASING WITH VA.
5. REMOVE ALL SLATE SHINGLES TO IN ORDER TO FACILITATE COMPLETE
REMOVAL OF ASBESTOS CONTAINING FELT PAPER.
6. THE CONTRACTOR IS RESPONSIBLE FOR SELECTIVE
DEMOLITION/REMOVAL OF ITEMS REQUIRE FOR ASBESTOS ABATEMENT
NOT INDICATED ON THE DEMOLITION PLANS. THE CONTRACTOR IS TO
PATCH/REPAIR/REPLACE ITEMS REMOVED OR EFFECTED BY ASBESTOS
ABATEMENT AS REQUIRED FOR CODE COMPLIANCE AND LIFE SAFETY.
7. THE CONTRACTOR SHALL COMPLY WITH ALL APPLICABLE PROVISIONS
OF THE INFECTION CONTROL RISK ASSESSMENT (IRCA) AND INTERIM LIFE
SAFETY MEASURES (ILSM) PLANS PERTAINING TO ABATEMENT ACTIVITIES.
8. ROOF TEAR OFF SHALL BE COMPLETED IN SECTIONS WHICH WILL
ALLOW FOR THE COMPLETE REPLACEMENT BY THE END OF EACH SHIFT.
THE REGULATED WORK AREAS SHALL BE REDUCED SEQUENTIALLY AS
TEAR OFF IS COMPLETED TO ALLOW FOR ROOF REPLACEMENT.
9. CONTRACTOR SHALL UTILIZE ONSITE WATER SUPPLY AND SANITARY
SEWER FOR ABATEMENT ACTIVITIES.
10. CONTRACTOR SHALL PROVIDE AN 8' CHAIN LINK CONSTRUCTION FENCE
AROUND THE CONSTRUCTION AREA INDICATED ON THE DRAWINGS. GATES
EQUIPPED WITH HASPS AND PADLOCKS SHALL BE PROVIDED AS REQUIRED
FOR ACCESS. FINAL LOCATIONS OF GATES TO BE DETERMINED BY
CONTRACTOR AND INCLUDED ON APPROVED SITE PLAN. FENCE FABRIC
SHALL BE FASTENED TO TERMINAL POSTS WITH TENSION BANDS AND TO
LINE POSTS AND TO TOP AND BOTTOM RAILS WITH TIE WIRES. POSTS ARE
TO BE ANCHORED ON SURFACE STANDS WITH FOUR SANDBAGS AT EACH
POST. STEEL PIPE IS NOT TO BE DRIVEN BELOW GRADE. ASBESTOS
DANGER SIGNAGE COMPLIANT WITH 29 CFR 1926.1101 SHALL BE SECURED
TO FENCING DELINEATING THE REGULATED AREA AT INTERVALS OF NO
LESS THAN 20 FEET.
11. CONTRACTOR SHALL PLACE WASTE RECEPTACLE AT LEAST 30' AWAY
FROM THE BUILDING.
12. CONTRACTOR SHALL BE RESPONSIBLE FOR PROTECTING EXISTING
CONNECTING CORRIDOR FROM DAMAGE.
13. THE HVAC SYSTEM ON BUILDING 13 CANNOT BE SHUTDOWN DUE TO
ONGOING HOSPITAL OPERATIONS OCCURRING WITHIN THE BUILDING. THE
CONTRACTOR MUST SUBMIT A PLAN TO REROUTE INTAKE AND EXHAUST
AIR AWAY FROM THE ROOFTOP DURING ABATEMENT ACTIVITIES.
14. RELOCATED PARKING AND ANY NECESSARY ROAD CLOSURES TO BE
COORDINATED BETWEEN VA AND CONTRACTOR. PARKING AND ANY
IMPACTS TO TRAFFIC ARE TO BE INCLUDED ON CONTRACTOR'S APPROVED
SITE PLAN.
15. CONTRACTOR TO ERECT SCAFFOLDING DURING OFF HOURS.
CONTRACTOR TO PROVIDE TEMPORARY SIGNAGE DIRECTING BUILDING
OCCUPANTS TO NEAREST EXIT WHILE SCAFFOLD CONSTRUCTION OR
DEMOLITION OCCURS.
16. CONTRACTOR SHALL PERFORM ABATEMENT IN A MANNER THAT DOES
A114
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.ae-works.com
Au to de sk
D oc s:
//V
M O
N -0
M on tro se R oo f R ep la ce m en t/V
M O
N -0
M on tro se R oo f R ep la ce m en t.r vt
/3 /2
3:
:4
PM
ASB114
BLDG 14 ROOF ABATEMENT PLAN MISSION CRITICAL ROOFS,
MONTROSE, PHASE 2
2094 ALBANY POST RD, MONTROSE, NY 10548
620-23-205
8.24.2023 RC NV
BID DOCUMENTS
# Revisions Date
1/16" = 1'-0"1 BUILDING 14 ROOF ABATEMENT PLAN
ABATEMENT LEGEND
REMOTE DECONTAMINATION UNIT
ACM ROOFING AND CAULKING
25 FT PERIMETER CONSTRUCTION FENCING
WASTE CONTAINER
AIR SAMPLE LOCATION
WASTE DECONTAMINATION UNIT
GENERAL ABATEMENT NOTES
N
1. MATERIALS AND QUANTITIES SCHEDULED FOR ABATEMENT:
1,075 SQUARE FEET OF GREEN EPOXY GUTTER COATING ASSOCIATED
WITH THE PITCHED ROOF
500 SQUARE FEET AND 1,175 LINEAR FEET OF WHITE FLASHING
ASSOCIATED WITH THE ROOF EDGE ON THE PITCHED ROOF AND THE
ROOF VALLEYS
12,750 SQUARE FEET OF FELT PAPER UNDER CLAY TILE ASSOCIATED
WITH THE PITCHED ROOF
90 LINEAR FEET OF BLACK PATCH FLASHING TAR ASSOCIATED WITH
THE PITCHED ROOF
40 SQUARE FEET OF RED NAIL CAULK AT COPPER ASSOCIATED WITH
THE PITCHED ROOF
200 SQUARE FEET OF BLACK FLASHING ASSOCIATED WITH THE FLAT
ROOF
120 LINEAR FEET OF WHITE CAPSTONE FLASHING ASSOCIATED WITH
THE FLAT ROOF
40 LINEAR FEET OF MECHANICAL EQUIPMENT CAULKING ASSOCIATED
WITH THE FLAT ROOF
2. ABATEMENT IS NOT NECESSARILY LIMITED TO WHAT IS SHOWN ON THE
DRAWINGS. THE INTENT IS TO INDICATE THE GENERAL SCOPE OF
ABATEMENT REQUIRED TO COMPLETE THE WORK IN ACCORDANCE WITH
THE CONTRACT DRAWINGS.
3. THE CONTRACTOR SHALL COORDINATE WITH THE VETERANS
ADMINISTRATION (VA) FOR SEQUENCE AND PHASING OF ABATEMENT,
WASTE RECEPTACLE PLACEMENT, ELEVATOR USAGE, HVAC ISOLATION,
AND OTHER SHUT DOWNS SO AS NOT TO DISRUPT THE ONGOING
OPERATION OF THE MEDICAL CENTER FACILITIES.
4. CONTRACTOR SHALL BE RESPONSIBLE FOR THE PROPER STATING OF
WORK AS TO PROTECT AND ENSURE THAT IT WILL NOT HAVE ANY
INTERFERENCE OF ACCESS TO OR FROM FIRE EGRESSES, ELEVATORS,
ETC. COORDINATE PHASING WITH VA.
5. REMOVE ALL SLATE SHINGLES TO IN ORDER TO FACILITATE COMPLETE
REMOVAL OF ASBESTOS CONTAINING FELT PAPER.
6. THE CONTRACTOR IS RESPONSIBLE FOR SELECTIVE
DEMOLITION/REMOVAL OF ITEMS REQUIRE FOR ASBESTOS ABATEMENT
NOT INDICATED ON THE DEMOLITION PLANS. THE CONTRACTOR IS TO
PATCH/REPAIR/REPLACE ITEMS REMOVED OR EFFECTED BY ASBESTOS
ABATEMENT AS REQUIRED FOR CODE COMPLIANCE AND LIFE SAFETY.
7. THE CONTRACTOR SHALL COMPLY WITH ALL APPLICABLE PROVISIONS
OF THE INFECTION CONTROL RISK ASSESSMENT (IRCA) AND INTERIM LIFE
SAFETY MEASURES (ILSM) PLANS PERTAINING TO ABATEMENT ACTIVITIES.
8. ROOF TEAR OFF SHALL BE COMPLETED IN SECTIONS WHICH WILL
ALLOW FOR THE COMPLETE REPLACEMENT BY THE END OF EACH SHIFT.
THE REGULATED WORK AREAS SHALL BE REDUCED SEQUENTIALLY AS
TEAR OFF IS COMPLETED TO ALLOW FOR ROOF REPLACEMENT.
9. CONTRACTOR SHALL UTILIZE ONSITE WATER SUPPLY AND SANITARY
SEWER FOR ABATEMENT ACTIVITIES.
10. CONTRACTOR SHALL PROVIDE AN 8' CHAIN LINK CONSTRUCTION FENCE
AROUND THE CONSTRUCTION AREA INDICATED ON THE DRAWINGS. GATES
EQUIPPED WITH HASPS AND PADLOCKS SHALL BE PROVIDED AS REQUIRED
FOR ACCESS. FINAL LOCATIONS OF GATES TO BE DETERMINED BY
CONTRACTOR AND INCLUDED ON APPROVED SITE PLAN. FENCE FABRIC
SHALL BE FASTENED TO TERMINAL POSTS WITH TENSION BANDS AND TO
LINE POSTS AND TO TOP AND BOTTOM RAILS WITH TIE WIRES. POSTS ARE
TO BE ANCHORED ON SURFACE STANDS WITH FOUR SANDBAGS AT EACH
POST. STEEL PIPE IS NOT TO BE DRIVEN BELOW GRADE. ASBESTOS
DANGER SIGNAGE COMPLIANT WITH 29 CFR 1926.1101 SHALL BE SECURED
TO FENCING DELINEATING THE REGULATED AREA AT INTERVALS OF NO
LESS THAN 20 FEET.
11. CONTRACTOR SHALL PLACE WASTE RECEPTACLE AT LEAST 30' AWAY
FROM THE BUILDING.
12. CONTRACTOR SHALL BE RESPONSIBLE FOR PROTECTING EXISTING
CONNECTING CORRIDOR FROM DAMAGE.
13. THE HVAC SYSTEM ON BUILDING 14 CANNOT BE SHUTDOWN DUE TO
ONGOING HOSPITAL OPERATIONS OCCURRING WITHIN THE BUILDING. THE
CONTRACTOR MUST SUBMIT A PLAN TO REROUTE INTAKE AND EXHAUST
AIR AWAY FROM THE ROOFTOP DURING ABATEMENT ACTIVITIES.
14. RELOCATED PARKING AND ANY NECESSARY ROAD CLOSURES TO BE
COORDINATED BETWEEN VA AND CONTRACTOR. PARKING AND ANY
IMPACTS TO TRAFFIC ARE TO BE INCLUDED ON CONTRACTOR'S APPROVED
SITE PLAN.
15. CONTRACTOR TO ERECT SCAFFOLDING DURING OFF HOURS.
CONTRACTOR TO PROVIDE TEMPORARY SIGNAGE DIRECTING BUILDING
OCCUPANTS TO NEAREST EXIT WHILE SCAFFOLD CONSTRUCTION OR
DEMOLITION OCCURS.
16. CONTRACTOR SHALL PERFORM ABATEMENT IN A MANNER THAT DOES
A117
BLDG PHASE II BLDG PHASE I
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
OFFICE OF
CONSTRUCTION
AND FACILITIES
MANAGEMENT
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseArchitect/Engineer of Record StampConsultant
321 4 5 6 7 8 9 10
Sprinkler Status
AE Works, LTD.
418 Beaver Street Sewickley, PA 15143 Phone: 412-287-7333 www.ae-works.com
Au to de sk
D oc s:
//V
M O
N -0
M on tro se R oo f R ep la ce m en t/V
M O
N -0
M on tro se R oo f R ep la ce m en t.r vt
/3 /2
3:
:5
PM
ASB117
BLDG 17 ROOF ABATEMENT PLAN MISSION CRITICAL ROOFS,
MONTROSE, PHASE 2
2094 ALBANY POST RD, MONTROSE, NY 10548
620-23-205
8.24.2023 RC NV
BID DOCUMENTS
# Revisions Date
1/16" = 1'-0"1 BUILDING 17 ROOF ABATEMENT PLAN
ABATEMENT LEGEND
REMOTE DECONTAMINATION UNIT
ACM ROOFING AND CAULKING
25 FT PERIMETER CONSTRUCTION FENCING
WASTE CONTAINER
AIR SAMPLE LOCATION
WASTE DECONTAMINATION UNIT
GENERAL ABATEMENT NOTES
1. MATERIALS AND QUANTITIES SCHEDULED FOR ABATEMENT:
10,000 SQUARE FEET OF BUILT-UP ASPHALT ROOF
500 SQUARE FEET OF FLASHING
2. ABATEMENT ON BUILDING 17 TO BE DIVIDED INTO TWO PRIMARY PHASES
- EAST AND WEST TO ALLOW FOR DELIVERY ACCESS TO ONE END OF THE
LOADING DOCK OR THE OTHER AT ALL TIMES.
3. ABATEMENT IS NOT NECESSARILY LIMITED TO WHAT IS SHOWN ON THE
DRAWINGS. THE INTENT IS TO INDICATE THE GENERAL SCOPE OF
ABATEMENT REQUIRED TO COMPLETE THE WORK IN ACCORDANCE WITH
THE CONTRACT DRAWINGS.
4. THE CONTRACTOR SHALL COORDINATE WITH THE VETERANS
ADMINISTRATION (VA) FOR SEQUENCE AND PHASING OF ABATEMENT,
WASTE RECEPTACLE PLACEMENT, ELEVATOR USAGE, HVAC ISOLATION,
AND OTHER SHUT DOWNS SO AS NOT TO DISRUPT THE ONGOING
OPERATION OF THE MEDICAL CENTER FACILITIES.
5. CONTRACTOR SHALL BE RESPONSIBLE FOR THE PROPER STATING OF
WORK AS TO PROTECT AND ENSURE THAT IT WILL NOT HAVE ANY
INTERFERENCE OF ACCESS TO OR FROM FIRE EGRESSES, ELEVATORS,
ETC. COORDINATE PHASING WITH VA.
6. THE CONTRACTOR IS RESPONSIBLE FOR SELECTIVE
DEMOLITION/REMOVAL OF ITEMS REQUIRE FOR ASBESTOS ABATEMENT
NOT INDICATED ON THE DEMOLITION PLANS. THE CONTRACTOR IS TO
PATCH/REPAIR/REPLACE ITEMS REMOVED OR EFFECTED BY ASBESTOS
ABATEMENT AS REQUIRED FOR CODE COMPLIANCE AND LIFE SAFETY.
7. THE CONTRACTOR SHALL COMPLY WITH ALL APPLICABLE PROVISIONS
OF THE INFECTION CONTROL RISK ASSESSMENT (IRCA) AND INTERIM LIFE
SAFETY MEASURES (ILSM) PLANS PERTAINING TO ABATEMENT ACTIVITIES.
8. ROOF TEAR OFF SHALL BE COMPLETED IN SECTIONS WHICH WILL
ALLOW FOR THE COMPLETE REPLACEMENT BY THE END OF EACH SHIFT.
THE REGULATED WORK AREAS SHALL BE REDUCED SEQUENTIALLY AS
TEAR OFF IS COMPLETED TO ALLOW FOR ROOF REPLACEMENT.
9. CONTRACTOR SHALL UTILIZE ONSITE WATER SUPPLY AND SANITARY
SEWER FOR ABATEMENT ACTIVITIES.
10. CONTRACTOR SHALL PROVIDE AN 8' CHAIN LINK CONSTRUCTION FENCE
AROUND THE CONSTRUCTION AREA INDICATED ON THE DRAWINGS. GATES
EQUIPPED WITH HASPS AND PADLOCKS SHALL BE PROVIDED AS REQUIRED
FOR ACCESS. FINAL LOCATIONS OF GATES TO BE DETERMINED BY
CONTRACTOR AND INCLUDED ON APPROVED SITE PLAN. FENCE FABRIC
SHALL BE FASTENED TO TERMINAL POSTS WITH TENSION BANDS AND TO
LINE POSTS AND TO TOP AND BOTTOM RAILS WITH TIE WIRES. POSTS ARE
TO BE ANCHORED ON SURFACE STANDS WITH FOUR SANDBAGS AT EACH
POST. STEEL PIPE IS NOT TO BE DRIVEN BELOW GRADE. ASBESTOS
DANGER SIGNAGE COMPLIANT WITH 29 CFR 1926.1101 SHALL BE SECURED
TO FENCING AT INTERVALS OF NO LESS THAN 20 FEET.
11. CONTRACTOR SHALL PLACE WASTE RECEPTACLE AT LEAST 30' AWAY
FROM THE BUILDING.
12. RELOCATED PARKING AND ANY NECESSARY ROAD CLOSURES TO BE
COORDINATED…