Early Procurement Package Rotary-Screw Compressor Water Chiller Walker Complex HVAC and BAS Repairs (SCO ID# 25-29576-02B)
Solicitation number
61-IFB25033
Issued by
Durham County, North Carolina

About this file

This is a Summary of Work document for an early procurement package bid issued by North Carolina Central University (NCCU) for the Walker Complex HVAC and BAS Upgrades project. NCCU is seeking a qualified vendor to furnish and deliver one rotary-screw compressor water chiller as an early procurement item. The chiller must be delivered to the site between February 15, 2027 and March 1, 2027, with delivery date identified as a critical consideration. The equipment will be owner-purchased directly from the equipment supplier and subsequently installed by a contractor through a separate forthcoming bidding process. Vendors are encouraged to submit multiple delivery options and reasonable deviations from technical specifications to improve delivery timelines, though major deviations will not be considered.

The equipment supplier is responsible for providing shop drawings and submittal data, delivering the chiller with coordination of exact delivery date, ensuring compatibility with existing concrete housekeeping pads, providing internal VFD cabling and wiring, leading chiller and VFD checkout and refrigerant charging, supplying required insulation and touch-up paint, coordinating delivery logistics with the contractor, providing owner training, and furnishing operations and maintenance documentation. The supplier will also support system startup and commissioning activities. No specific pricing terms, set-asides, or contract duration details are outlined in this summary document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Walker HVAC & BAS Renovation- Early Procurement CD Bid North Carolina Central University

Rotary-Screw Compressor Water Chillers 236426-1

SUMMARY OF WORK 1

Equipment required for the project shall be pre-purchased by the Owner directly from the Equipment Supplier. The 4 Owner purchased equipment will be installed by a contractor (through a forthcoming bidding process). 5 The Equipment Supplier will work with the Contractor to arrange/coordinate delivery of equipment to the project site. 7 Coordination efforts will include date and time of delivery, receipt and unloading of equipment at the job site and 8 services to support system startup and commissioning. 9 Equipment Supplier shall be responsible for the following to support the Contractor: 11

• Provide shop drawings and submittal data. 13

• Provide the chillers and all appurtenances in accordance with the equipment schedule and 14 specifications. 15

• Delivery of chillers including coordination of exact delivery date. 16

• Coordinate chiller design with existing concrete housekeeping pads. 17

• Provide internal VFD cabling and wiring. 18

• Lead chiller and VFD check-out, refrigerant charging, testing, and start-up process. 19

• Furnish insulation required to Contractor 20

• Provide touch up paint. 21

• Provide Owner training. 22

• Provide O&M documentation. 23