605-18-202 Surg Clinic - 100_SPEC V2 - Davy.pdf
PDF 4 MB Posted
- Attached to
- 2ES 2EN Renovation at Loma Linda VAMC
- Solicitation number
- 36C25820R0043
About this file
This federal contract solicitation seeks demolition and construction services for renovations to the 2nd floor of the Loma Linda VA Medical Center located in Loma Linda, California. The contractor shall demolish and rebuild approximately 23,000 square feet according to specifications from Davy Architecture and SC Engineers. The contractor must follow all drawings and specifications, comply with Davis-Bacon wage determinations, and adhere to applicable wage, hour and labor laws. The contracting agency is the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 22.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Renovate Surgery Clinic 2E South Loma Linda VA Health Care System
Loma Linda, CA
SPECIFICATIONS
Volume 2 of 2
100% Construction Documents Date: April 15, 2020
605-18-202 LOMA LINDA VA MEDICAL CENTER April 15, 2020
RENOVATE SURGERY CLINIC 2E SOUTH
00 01 10-1
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. SECTION TITLE AUTHOR DATE
COVER VOLUME 1 – DIVISIONS 00 THRU 14
DIVISION 00 - SPECIAL SECTIONS
00 01 07 Seals Page* DAVY 04-20
00 01 10 Table of Contents DAVY 04-20
00 01 15 List of Drawing Sheets DAVY 04-20
00 31 26 Existing Hazardous Material Information* DAVY 04-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements DAVY 01-20
01 10 00 Summary* DAVY 04-20
01 32 16.15 Project Schedules (Small Projects –
Design/Bid/Build
DAVY 01-20
01 33 23 Shop Drawings, Product Data, and Samples DAVY 01-20
01 35 26 Safety Requirements DAVY 01-20
01 42 19 Reference Standards DAVY 01-20
01 45 00 Quality Control DAVY 01-20
01 45 29 Testing Laboratory Services VA 11-18
01 45 35 Special Inspections AARK 04-20
01 57 19 Temporary Environmental Controls DAVY 04-20
01 58 16 Temporary Interior Signage VA 07-15
01 74 19 Construction Waste Management VA 09-13
01 81 13 Sustainable Construction Requirements DAVY 01-20
01 91 00 General Commissioning Requirements SOB 04-20
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition DAVY 04-20
02 82 11 Traditional Asbestos Abatement ENC 04-20
02 82 13.19 Asbestos Floor Tile and Mastic Abatement ENC 04-20
02 83 33.13 Lead-Based Paint Removal and Disposal ENC 04-20
DIVISION 03 – CONCRETE
03 55 11 Gypsum Concrete Floor Decks AARK 04-20
DIVISION 04 – MASONRY – NOT USED
DIVISION 05 – METALS
05 50 00 Metal Fabrications AARK 04-20
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
00 01 10-2
06 20 00 Finish Carpentry GKDG 04-20
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 24 00 Exterior Insulation and Finish Systems VA 02-16
07 60 00 Flashing and Sheet Metal VA 07-14
07 84 13 Through Penetration Firestopping* DAVY 04-20
07 92 19 Acoustical Joint Sealant* DAVY 04-20
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames VA 08-16
08 14 23 Acrovyn Flush Doors DAVY 01-20
08 42 29.23 Sliding Automatic Entrances* DAVY 01-20
08 42 29.33 Swinging Automatic Entrances* DAVY 01-20
08 71 00 Door Hardware VA 05-19
08 71 13 Automatic Door Operators VA 02-16
08 71 13.11 Low Energy Power Assist Door Operators VA 08-16
08 90 00 Louvers and Vents VA 05-15
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes GKDG 04-20
09 06 00 Schedule for Finishes GKDG 01-20
09 22 16 Non-Structural Metal Framing GKDG 04-20
09 29 00 Gypsum Board GKDG 04-20
09 30 13 Ceramic/Porcelain Tiling GKDG 04-20
09 51 00 Acoustical Ceilings GKDG 04-20
09 54 23 Linear Metal Ceilings GKDG 04-20
09 65 13 Resilient Base and Accessories GKDG 04-20
09 65 16 Resilient Sheet Flooring GKDG 04-20
09 67 23.20 Resinous Epoxy Base With Vinyl Chip Broadcast
(RES 2)
GKDG 04-20
09 67 23.50 Resinous (Epoxy Terrazzo) Flooring (RES-5) GKDG 04-20
09 68 00 Carpeting GKDG 04-20
09 72 16 Vinyl-Coated Fabric Wall Coverings GKDG 04-20
09 91 00 Painting GKDG 04-20
DIVISION 10 – SPECIALTIES
10 21 23 Cubicle Curtain Tracks GKDG 04-20
10 26 00 Wall and Door Protection VA 10-15
10 28 00 Toilet, Bath, and Laundry Accessories VA 02-16
10 28 13.19 Specimen Pass-Thru Cabinet* DAVY 04-20
10 44 13 Fire Extinguisher Cabinets* DAVY 04-20
DIVISION 11 – EQUIPMENT – NOT USED
DIVISION 12 – FURNISHINGS
12 32 00 Manufactured Wood Casework GKDG 04-20
00 01 10-3
12 36 00 Countertops GKDG 04-20
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-
Structural Components
AARK 04-20
DIVISION 14– CONVEYING EQUIPMENT – NOT USED
COVER VOLUME 2 – DIVISIONS 21 THRU 32 & APPENDIX
DIVISION 21- FIRE SUPPRESSION
21 08 00 Commissioning of Fire Suppression System SOB 04-20
21 13 13 Wet-Pipe Sprinkler Systems CE 04-20
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing CE 04-20
22 05 23 General-Duty Valves for Plumbing Piping CE 04-20
22 07 11 Plumbing Insulation CE 04-20
22 08 00 Commissioning of Plumbing Systems SOB 04-20
22 11 00 Facility Water Distribution CE 04-20
22 13 00 Facility Sanitary and Vent Piping CE 04-20
22 40 00 Plumbing Fixtures CE 04-20
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC CE 04-20
23 05 41 Noise and Vibration Control for HVAC Piping and
Equipment
CE 04-20
23 05 93 Testing, Adjusting, and Balancing for HVAC CE 04-20
23 07 11 HVAC and Boiler Plant Insulation CE 04-20
23 08 00 Commissioning of HVAC Systems SOB 04-20
23 09 23 Direct-Digital Control System for HVAC CE 04-20
23 21 13 Hydronic Piping CE 04-20
23 31 00 HVAC Ducts and Casings CE 04-20
23 36 00 Air Terminal Units CE 04-20
23 37 00 Air Outlets and Inlets CE 04-20
DIVISION 25 – NOT USED
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations CE 04-20
26 05 19 Low-Voltage Electrical Power Conductors and
Cables
CE 04-20
26 05 26 Grounding and Bonding for Electrical Systems CE 04-20
26 05 33 Raceway and Boxes for Electrical Systems CE 04-20
26 08 00 Commissioning of Electrical Systems SOB 01-20
26 09 23 Lighting Controls CE 04-20
00 01 10-4
26 24 16 Panelboards CE 04-20
26 27 26 Wiring Devices CE 04-20
26 29 21 Enclosed Switches and Circuit Breakers CE 04-20
26 43 13 Surge Protective Devices CE 04-20
26 51 00 Interior Lighting CE 04-20
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations CE 04-20
27 05 33 Raceways and Boxes for Communications Systems CE 04-20
27 15 00 Communications Structured Cabling CE 04-20
27 51 16 Public Address and Mass Notification Systems CE 04-20
27 51 23 Intercommunications and Program Systems CE 04-20
27 52 23 Nurse Call and Code Blue Systems CE 04-20
27 52 41 Miscellaneous Medical Systems CE 04-20
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 31 00 Fire Detection and Alarm CE 04-20
DIVISION 31 – EARTHWORK – NOT USED
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements VA 08-16
DIVISION 33 – UTILITIES – NOT USED
DIVISION 34 – TRANSPORTATION – NOT USED
DIVISION 48 – Elec. Power Generation – NOT USED
APPENDIX
Appendix A Submittal Register (per section 01 33 23)
Appendix B Asbestos and Lead-Based Inspection Report
Appendix C Amico: Casework & Countertop Shop Drawings
FOOTNOTES
* Asterisk denotes Spec Section from non-VA source
AUTHOR ABBREVIATIONS
VA US Department of Veterans Affairs
DAVY Davy Architecture
CE Coffman Engineers Inc.
AARK Aark Engineering
SOB Salas O’Brien Engineering
ENC Encorp
GKDG Gretchen Kennelly Design Group
01 91 00 - 1
SECTION 01 91 00
GENERAL COMMISSIONING REQUIREMENTS
PART 1 - GENERAL
1.1 COMMISSIONING DESCRIPTION
A. This Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS shall form the basis of the construction phase commissioning process and procedures. The Commissioning Agent shall add, modify, and refine the commissioning procedures, as approved by the Department of Veterans Affairs (VA), to suit field conditions and actual manufacturer's equipment, incorporate test data and procedure results, and provide detailed scheduling for all commissioning tasks.
B. Various sections of the project specifications require equipment startup, testing, and adjusting services. Requirements for startup, testing, and adjusting services specified in the Division 21, Division 22, Division 23, and Division 26 series sections of these specifications are intended to be provided in coordination with the commissioning services and are not intended to duplicate services. The Contractor shall coordinate the work required by individual specification sections with the commissioning services requirements specified herein.
C. Where individual testing, adjusting, or related services are required in the project specifications and not specifically required by this commissioning requirements specification, the specified services shall be provided and copies of documentation, as required by those specifications shall be submitted to the VA and the Commissioning Agent to be indexed for future reference.
D. Where training or educational services for VA are required and specified in other sections of the specifications, including but not limited to Division 21, Division 22, Division 23, and Division 26 series sections of the specification, these services are intended to be provided in addition to the training and educational services specified herein.
E. Commissioning is a systematic process of verifying that the building systems perform interactively according to the construction documents and the VA’s operational needs. The commissioning process shall encompass and coordinate the system documentation, equipment startup, control system calibration, testing and balancing, performance testing and training. Commissioning during the construction and post-occupancy phases is intended to achieve the following specific objectives according to the contract documents:
1. Verify that the applicable equipment and systems are installed in accordance with the contact documents and according to the manufacturer's recommendations.
2. Verify and document proper integrated performance of equipment and systems.
3. Verify that Operations & Maintenance documentation is complete.
4. Verify that all components requiring servicing can be accessed, serviced and removed without disturbing nearby components including ducts, piping, cabling or wiring.
5. Verify that the VA’s operating personnel are adequately trained to enable them to operate, monitor, adjust, maintain, and repair building systems in an effective and energy-efficient manner.
01 91 00 - 2
6. Document the successful achievement of the commissioning objectives listed above.
F. The commissioning process does not take away from or reduce the responsibility of the Contractor to provide a finished and fully functioning product.
1.2 CONTRACTUAL RELATIONSHIPS
A. For this construction project, the Department of Veterans Affairs contracts with a Contractor to provide construction services. The contracts are administered by the VA Contracting Officer and the Resident Engineer as the designated representative of the Contracting Officer. On this project, the authority to modify the contract in any way is strictly limited to the authority of the Contracting Officer.
B. In this project, only two contract parties are recognized and communications on contractual issues are strictly limited to VA Resident Engineer and the Contractor. It is the practice of the VA to require that communications between other parties to the contracts (Subcontractors and Vendors) be conducted through the Resident Engineer and Contractor. It is also the practice of the VA that communications between other parties of the project (Commissioning Agent and Architect/Engineer) be conducted through the Resident Engineer.
C. Whole Building Commissioning is a process that relies upon frequent and direct communications, as well as collaboration between all parties to the construction process. By its nature, a high level of communication and cooperation between the Commissioning Agent and all other parties (Architects, Engineers, Subcontractors, Vendors, third party testing agencies, etc.) is essential to the success of the Commissioning effort.
D. With these fundamental practices in mind, the commissioning process described herein has been developed to recognize that, in the execution of the Commissioning Process, the Commissioning Agent must develop effective methods to communicate with every member of the construction team involved in delivering commissioned systems while simultaneously respecting the exclusive contract authority of the Contracting Officer and Resident Engineer. Thus, the procedures outlined in this specification must be executed within the following limitations:
1. No communications (verbal or written) from the Commissioning Agent shall be deemed to constitute direction that modifies the terms of any contract between the Department of Veterans Affairs and the Contractor.
2. Commissioning Issues identified by the Commissioning Agent will be delivered to the Resident Engineer and copied to the designated Commissioning Representatives for the Contractor and subcontractors on the Commissioning Team for information only in order to expedite the communication process. These issues must be understood as the professional opinion of the Commissioning Agent and as suggestions for resolution.
3. In the event that any Commissioning Issues and suggested resolutions are deemed by the Resident Engineer to require either an official interpretation of the construction documents or require a modification of the contract documents, the Contracting Officer or Resident Engineer will issue an official directive to this effect.
4. All parties to the Commissioning Process shall be individually responsible for alerting the Resident Engineer of any issues that they
01 91 00 - 3 deem to constitute a potential contract change prior to acting on these issues.
5. Authority for resolution or modification of design and construction issues rests solely with the Contracting Officer or Resident Engineer, with appropriate technical guidance from the Architect/Engineer and/or Commissioning Agent.
1.3 RELATED WORK
A. Section 01 00 00 GENERAL REQUIREMENTS.
B. Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
C. Section 01 45 00 QUALITY CONTROL
D. Section 21 08 00 COMMISSIONING OF FIRE PROTECTION SYSTEMS.
E. Section 22 08 00 COMMISSIONING OF PLUMBING SYSTEMS.
F. Section 23 08 00 COMMISSIONING OF HVAC SYSTEMS.
G. Section 26 08 00 COMMISSIONING OF ELECTRICAL SYSTEMS.
1.4 SUMMARY
A. This Section includes general requirements that apply to implementation of commissioning without regard to systems, subsystems, and equipment being commissioned.
B. The commissioning activities have been developed to support the VA requirements to meet guidelines for Federal Leadership in Environmental, Energy, and Economic Performance.
1.5 ACRONYMS
List of Acronyms
Acronym Meaning
A/E Architect / Engineer Design Team
AHJ Authority Having Jurisdiction
ASHRAE
Association Society for Heating Air Condition and Refrigeration Engineers
BOD Basis of Design
BSC Building Systems Commissioning
CCTV Closed Circuit Television
CD Construction Documents
CMMS Computerized Maintenance Management System
CO Contracting Officer (VA)
COR Contracting Officer’s Representative (see also VA-RE)
COBie Construction Operations Building Information Exchange
CPC Construction Phase Commissioning
Cx Commissioning
CxA Commissioning Agent
CxM Commissioning Manager
CxR Commissioning Representative
DPC Design Phase Commissioning
FPT Functional Performance Test
GBI-GG Green Building Initiative - Green Globes
HVAC Heating, Ventilation, and Air Conditioning
01 91 00 - 4
List of Acronyms
Acronym Meaning
LEED Leadership in Energy and Environmental Design
NC Department of Veterans Affairs National Cemetery
NCA
Department of Veterans Affairs National Cemetery Administration
NEBB National Environmental Balancing Bureau
O&M Operations & Maintenance
OPR Owner’s Project Requirements
PFC Pre-Functional Checklist
PFT Pre-Functional Test
SD Schematic Design
SO Site Observation
TAB Test Adjust and Balance
VA Department of Veterans Affairs
VAMC VA Medical Center
VA CFM VA Office of Construction and Facilities Management
VACO VA Central Office
VA PM VA Project Manager
VA-RE VA Resident Engineer
USGBC United States Green Building Council
1.6 DEFINITIONS
Acceptance Phase Commissioning: Commissioning tasks executed after most construction has been completed, most Site Observations and Static Tests have been completed and Pre-Functional Testing has been completed and accepted. The main commissioning activities performed during this phase are verification that the installed systems are functional by conducting Systems Functional Performance tests and Owner Training.
Accuracy: The capability of an instrument to indicate the true value of a measured quantity.
Back Check: A back check is a verification that an agreed upon solution to a design comment has been adequately addressed in a subsequent design review
Basis of Design (BOD): The Engineer’s Basis of Design is comprised of two components: the Design Criteria and the Design Narrative, these documents record the concepts, calculations, decisions, and product selections used to meet the Owner’s Project Requirements (OPR) and to satisfy applicable regulatory requirements, standards, and guidelines.
Benchmarks: Benchmarks are the comparison of a building’s energy usage to other similar buildings and to the building itself.. For example, ENERGY STAR Portfolio Manager is a frequently used and nationally recognized building energy benchmarking tool.
Building Information Modeling (BIM): Building Information Modeling is a parametric database which allows a building to be designed and constructed virtually in 3D, and provides reports both in 2D views and as schedules. This electronic information can be extracted and reused for pre-populating facility management CMMS systems. Building Systems Commissioning (BSC): NEBB acronym used to designate its commissioning program.
01 91 00 - 5
Calibrate: The act of comparing an instrument of unknown accuracy with a standard of known accuracy to detect, correlate, report, or eliminate by adjustment any variation in the accuracy of the tested instrument.
CCTV: Closed circuit Television. Normally used for security surveillance and alarm detections as part of a special electrical security system.
COBie: Construction Operations Building Information Exchange (COBie) is an electronic industry data format used to transfer information developed during design, construction, and commissioning into the Computer Maintenance Management Systems (CMMS) used to operate facilities. See the Whole Building Design Guide website for further information (http://www.wbdg.org/resources/cobie.php)
Commissionability: Defines a design component or construction process that has the necessary elements that will allow a system or component to be effectively measured, tested, operated and commissioned
Commissioning Agent (CxA): The qualified Commissioning Professional who administers the Cx process by managing the Cx team and overseeing the Commissioning Process. Where CxA is used in this specification it means the Commissioning Agent, members of his staff or appointed members of the commissioning team. Note that LEED uses the term Commissioning Authority in lieu of Commissioning Agent.
Commissioning Checklists: Lists of data or inspections to be verified to ensure proper system or component installation, operation, and function.
Verification checklists are developed and used during all phases of the commissioning process to verify that the Owner’s Project Requirements (OPR) is being achieved.
Commissioning Design Review: The commissioning design review is a collaborative review of the design professionals design documents for items pertaining to the following: owner’s project requirements; basis of design;
operability and maintainability (O&M) including documentation; functionality;
training; energy efficiency, control systems’ sequence of operations including building automation system features; commissioning specifications and the ability to functionally test the systems.
Commissioning Issue: A condition identified by the Commissioning Agent or other member of the Commissioning Team that adversely affects the commissionability, operability, maintainability, or functionality of a system, equipment, or component. A condition that is in conflict with the Contract Documents and/or performance requirements of the installed systems and components. (See also – Commissioning Observation).
Commissioning Manager (CxM): A qualified individual appointed by the Contractor to manage the commissioning process on behalf of the Contractor.
Commissioning Observation: An issue identified by the Commissioning Agent or other member of the Commissioning Team that does not conform to the project OPR, contract documents or standard industry best practices. (See also Commissioning Issue)
01 91 00 - 6
Commissioning Plan: A document that outlines the commissioning process, commissioning scope and defines responsibilities, processes, schedules, and the documentation requirements of the Commissioning Process.
Commissioning Process: A quality focused process for enhancing the delivery of a project. The process focuses upon verifying and documenting that the facility and all of its systems, components, and assemblies are planned, designed, installed, tested, can be operated, and maintained to meet the Owner's Project Requirements.
Commissioning Report: The final commissioning document which presents the commissioning process results for the project. Cx reports include an executive summary, the commissioning plan, issue log, correspondence, and all appropriate check sheets and test forms.
Commissioning Representative (CxR): An individual appointed by a sub-contractor to manage the commissioning process on behalf of the sub-contractor.
Commissioning Specifications: The contract documents that detail the objective, scope and implementation of the commissioning process as developed in the Commissioning Plan.
Commissioning Team: Individual team members whose coordinated actions are responsible for implementing the Commissioning Process.
Construction Phase Commissioning: All commissioning efforts executed during the construction process after the design phase and prior to the Acceptance Phase Commissioning.
Contract Documents (CD): Contract documents include design and construction contracts, price agreements and procedure agreements. Contract Documents also include all final and complete drawings, specifications and all applicable contract modifications or supplements.
Construction Phase Commissioning (CPC): All commissioning efforts executed during the construction process after the design phase and prior to the Acceptance Phase Commissioning.
Coordination Drawings: Drawings showing the work of all trades that are used to illustrate that equipment can be installed in the space allocated without compromising equipment function or access for maintenance and replacement.
These drawings graphically illustrate and dimension manufacturers’ recommended maintenance clearances. On mechanical projects, coordination drawings include structural steel, ductwork, major piping and electrical conduit and show the elevations and locations of the above components.
Data Logging: The monitoring and recording of temperature, flow, current, status, pressure, etc. of equipment using stand-alone data recorders.
Deferred System Test: Tests that cannot be completed at the end of the acceptance phase due to ambient conditions, schedule issues or other conditions preventing testing during the normal acceptance testing period.
Deficiency: See “Commissioning Issue”.
01 91 00 - 7
Design Criteria: A listing of the VA Design Criteria outlining the project design requirements, including its source. These are used during the design process to show the design elements meet the OPR.
Design Intent: The overall term that includes the OPR and the BOD. It is a detailed explanation of the ideas, concepts, and criteria that are defined by the owner to be important. The design intent documents are utilized to provide a written record of these ideas, concepts and criteria.
Design Narrative: A written description of the proposed design solutions that satisfy the requirements of the OPR.
Design Phase Commissioning (DPC): All commissioning tasks executed during the design phase of the project.
Environmental Systems: Systems that use a combination of mechanical equipment, airflow, water flow and electrical energy to provide heating, ventilating, air conditioning, humidification, and dehumidification for the purpose of human comfort or process control of temperature and humidity.
Executive Summary: A section of the Commissioning report that reviews the general outcome of the project. It also includes any unresolved issues, recommendations for the resolution of unresolved issues and all deferred testing requirements.
Functionality: This defines a design component or construction process which will allow a system or component to operate or be constructed in a manner that will produce the required outcome of the OPR.
Functional Test Procedure (FTP): A written protocol that defines methods, steps, personnel, and acceptance criteria for tests conducted on components, equipment, assemblies, systems, and interfaces among systems.
Industry Accepted Best Practice: A design component or construction process that has achieved industry consensus for quality performance and functionality. Refer to the current edition of the NEBB Design Phase Commissioning Handbook for examples.
Installation Verification: Observations or inspections that confirm the system or component has been installed in accordance with the contract documents and to industry accepted best practices.
Integrated System Testing: Integrated Systems Testing procedures entail testing of multiple integrated systems performance to verify proper functional interface between systems. Typical Integrated Systems Testing includes verifying that building systems respond properly to loss of utility, transfer to emergency power sources, re-transfer from emergency power source to normal utility source; interface between HVAC controls and Fire Alarm systems for equipment shutdown, interface between Fire Alarm system and elevator control systems for elevator recall and shutdown; interface between Fire Alarm System and Security Access Control Systems to control access to spaces during fire alarm conditions; and other similar tests as determined for each specific project.
Issues Log: A formal and ongoing record of problems or concerns – and their resolution – that have been raised by members of the Commissioning Team during the course of the Commissioning Process.
01 91 00 - 8
Lessons Learned Workshop: A workshop conducted to discuss and document project successes and identify opportunities for improvements for future projects.
Maintainability: A design component or construction process that will allow a system or component to be effectively maintained. This includes adequate room for access to adjust and repair the equipment. Maintainability also includes components that have readily obtainable repair parts or service.
Manual Test: Testing using hand-held instruments, immediate control system readouts or direct observation to verify performance (contrasted to analyzing monitored data taken over time to make the ‘observation’).
Owner’s Project Requirements (OPR): A written document that details the project requirements and the expectations of how the building and its systems will be used and operated. These include project goals, measurable performance criteria, cost considerations, benchmarks, success criteria, and supporting information.
Peer Review: A formal in-depth review separate from the commissioning review processes. The level of effort and intensity is much greater than a typical commissioning facilitation or extended commissioning review. The VA usually hires an independent third-party (called the IDIQ A/E) to conduct peer reviews.
Precision: The ability of an instrument to produce repeatable readings of the same quantity under the same conditions. The precision of an instrument refers to its ability to produce a tightly grouped set of values around the mean value of the measured quantity.
Pre-Design Phase Commissioning: Commissioning tasks performed prior to the commencement of design activities that includes project programming and the development of the commissioning process for the project
Pre-Functional Checklist (PFC): A form used by the contractor to verify that appropriate components are onsite, correctly installed, set up, calibrated, functional and ready for functional testing.
Pre-Functional Test (PFT): An inspection or test that is done before functional testing. PFT’s include installation verification and system and component start up tests.
Procedure or Protocol: A defined approach that outlines the execution of a sequence of work or operations. Procedures are used to produce repeatable and defined results.
Range: The upper and lower limits of an instrument’s ability to measure the value of a quantity for which the instrument is calibrated.
Resolution: This word has two meanings in the Cx Process. The first refers to the smallest change in a measured variable that an instrument can detect. The second refers to the implementation of actions that correct a tested or observed deficiency.
Site Observation Visit: On-site inspections and observations made by the Commissioning Agent for the purpose of verifying component, equipment, and
01 91 00 - 9 system installation, to observe contractor testing, equipment start-up procedures, or other purposes.
Site Observation Reports (SO): Reports of site inspections and observations made by the Commissioning Agent. Observation reports are intended to provide early indication of an installation issue which will need correction or analysis.
Special System Inspections: Inspections required by a local code authority prior to occupancy and are not normally a part of the commissioning process.
Static Tests: Tests or inspections that validate a specified static condition such as pressure testing. Static tests may be specification or code initiated.
Start Up Tests: Tests that validate the component or system is ready for automatic operation in accordance with the manufactures requirements.
Systems Manual: A system-focused composite document that includes all information required for the owners operators to operate the systems.
Test Procedure: A written protocol that defines methods, personnel, and expectations for tests conducted on components, equipment, assemblies, systems, and interfaces among systems.
Testing: The use of specialized and calibrated instruments to measure parameters such as: temperature, pressure, vapor flow, air flow, fluid flow, rotational speed, electrical characteristics, velocity, and other data in order to determine performance, operation, or function.
Testing, Adjusting, and Balancing (TAB): A systematic process or service applied to heating, ventilating and air-conditioning (HVAC) systems and other environmental systems to achieve and document air and hydronic flow rates. The standards and procedures for providing these services are referred to as “Testing, Adjusting, and Balancing” and are described in the Procedural Standards for the Testing, Adjusting and Balancing of Environmental Systems, published by NEBB or AABC.
Thermal Scans: Thermographic pictures taken with an Infrared Thermographic Camera. Thermographic pictures show the relative temperatures of objects and surfaces and are used to identify leaks, thermal bridging, thermal intrusion, electrical overload conditions, moisture containment, and insulation failure.
Training Plan: A written document that details, in outline form the expectations of the operator training. Training agendas should include instruction on how to obtain service, operate, startup, shutdown and maintain all systems and components of the project.
Trending: Monitoring over a period of time with the building automation system.
Unresolved Commissioning Issue: Any Commissioning Issue that, at the time that the Final Report or the Amended Final Report is issued that has not been either resolved by the construction team or accepted by the VA. Validation:
The process by which work is verified as complete and operating correctly:
1. First party validation occurs when a firm or individual verifying the task is the same firm or individual performing the task.
01 91 00 - 10
2. Second party validation occurs when the firm or individual verifying the task is under the control of the firm performing the task or has other possibilities of financial conflicts of interest in the resolution (Architects, Designers, General Contractors and Third Tier Subcontractors or Vendors).
3. Third party validation occurs when the firm verifying the task is not associated with or under control of the firm performing or designing the task.
Verification: The process by which specific documents, components, equipment, assemblies, systems, and interfaces among systems are confirmed to comply with the criteria described in the Owner’s Project Requirements.
Warranty Phase Commissioning: Commissioning efforts executed after a project has been completed and accepted by the Owner. Warranty Phase Commissioning includes follow-up on verification of system performance, measurement and verification tasks and assistance in identifying warranty issues and enforcing warranty provisions of the construction contract.
Warranty Visit: A commissioning meeting and site review where all outstanding warranty issues and deferred testing is reviewed and discussed.
Whole Building Commissioning: Commissioning of building systems such as Building Envelope, HVAC, Electrical, Special Electrical (Fire Alarm, Security & Communications), Plumbing and Fire Protection as described in this specification.
1.7 SYSTEMS TO BE COMMISSIONED
A. Commissioning of a system or systems specified for this project is part of the construction process. Documentation and testing of these systems, as well as training of the VA’s Operation and Maintenance personnel, is required in cooperation with the VA and the Commissioning Agent.
B. The following systems will be commissioned as part of this project:
Systems To Be Commissioned
System Description
Fire Suppression
Fire Sprinkler Systems Wet pipe system, dry pipe system, pre-action system, special agent systems
Plumbing
Domestic Hot Water Systems
New Point-of-use
HVAC
Direct Digital Control System
New DDC equipment, graphics, and integration with existing system.
Steam/Heating Hot Water System
New equipment and integration with existing system.
HVAC Air Handling Systems
. New equipment and integration with existing system.
HVAC
Ventilation/Exhaust Systems
New equipment and integration with existing system.
01 91 00 - 11
Systems To Be Commissioned
System Description
HVAC Terminal Unit Systems
New VAV Terminal Units
Humidity Control Systems controls, interface with facility DDC
Hydronic Distribution Systems
New reheat coils and integration with existing system.
Electrical
Lighting & Lighting Control Systems
Emergency lighting, occupancy sensors, lighting control systems
Integrated Systems Tests
Fire Alarm Response Integrated System Response to Fire Alarm Condition and Return to Normal
1.8 COMMISSIONING TEAM
A. The commissioning team shall consist of, but not be limited to, representatives of Contractor, including Project Superintendent and subcontractors, installers, schedulers, suppliers, and specialists deemed appropriate by the Department of Veterans Affairs (VA) and Commissioning Agent.
B. Members Appointed by Contractor:
1. Contractor’ Commissioning Manager: The designated person, company, or entity that plans, schedules and coordinates the commissioning activities for the construction team.
2. Contractor’s Commissioning Representative(s): Individual(s), each having authority to act on behalf of the entity he or she represents, explicitly organized to implement the commissioning process through coordinated actions.
C. Members Appointed by VA:
1. User: Representatives of the facility user and operation and maintenance personnel.
2. A/E: Representative of the Architect and engineering design professionals.
1.9 VA'S COMMISSIONING RESPONSIBILITIES
A. Assign operation and maintenance personnel and schedule them to participate in commissioning team activities including, but not limited to, the following:
1. Coordination meetings.
2. Training in operation and maintenance of systems, subsystems, and equipment.
3. Testing meetings.
4. Witness and assist in Systems Functional Performance Testing.
5. Demonstration of operation of systems, subsystems, and equipment.
B. Provide the Construction Documents, prepared by Architect and approved by VA, to the Commissioning Agent and for use in managing the commissioning process, developing the commissioning plan, systems manuals, and reviewing the operation and maintenance training plan.
01 91 00 - 12
1.10 CONTRACTOR'S COMMISSIONING RESPONSIBILITIES
A. The Contractor shall assign a Commissioning Manager to manage commissioning activities of the Contractor, and subcontractors.
B. The Contractor shall ensure that the commissioning responsibilities outlined in these specifications are included in all subcontracts and that subcontractors comply with the requirements of these specifications.
C. The contractor shall provide the Commissioning Agent with overall and look-ahead construction schedules.
D. The contractor shall provide all documents listed in the submittal requirements related to the commissioning process that are specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.
E. The Contractor shall ensure that each installing subcontractor shall assign representatives with expertise and authority to act on behalf of the subcontractor and schedule them to participate in and perform commissioning team activities including, but not limited to, the following:
1. Participate in commissioning coordination meetings.
2. Conduct operation and maintenance training sessions in accordance with approved training plans.
3. Verify that Work is complete and systems are operational according to the
Contract Documents, including calibration of instrumentation and controls.
4. Contractor to complete the equipment Pre-Functional Checklists provided by the Commissioning Agent
4. Evaluate commissioning issues and commissioning observations identified in the Commissioning Issues Log, field reports, test reports or other commissioning documents. In collaboration with entity responsible for system and equipment installation, recommend corrective action.
5. Review and comment on commissioning documentation.
6. Participate in meetings to coordinate Systems Functional Performance
Testing.
7. Provide schedule for operation and maintenance data submittals, equipment startup, and testing to Commissioning Agent for incorporation into the commissioning plan.
8. Provide information to the Commissioning Agent for developing commissioning plan.
9. Develop and conduct the systems Operation and Maintenance Training program/plan for VA's operation and maintenance personnel.
10. Provide all calibrated instruments and tools necessary to fulfill the Commissioning Agents requirements in the Systems Functional Performance Tests.
11. Provide technicians who are familiar with the construction and operation of installed systems and who shall develop specific test procedures to conduct Systems Functional Performance Testing of installed systems.
12. Compile and provide Operation and Maintenance data and a Systems Manual as outlined in Paragraph 1.25, Section 01 00 00 GENERAL REQUIREMENTS.
1.11 COMMISSIONING AGENT’S RESPONSIBILITIES
A. Organize and lead the commissioning team.
B. Prepare the commissioning plan. See Paragraph 1.11-A of this specification Section for further information.
01 91 00 - 13
C. Review and comment on selected submittals from the Contractor for general conformance with the Construction Documents. Review and comment on the ability to test and operate the system and/or equipment, including providing gages, controls and other components required to operate, maintain, and test the system. Review and comment on performance expectations of systems and equipment and interfaces between systems relating to the Construction Documents.
D. At the beginning of the construction phase, conduct an initial construction phase coordination meeting for the purpose of reviewing the commissioning activities and establishing tentative schedules for operation and maintenance submittals; operation and maintenance training sessions; TAB Work; Pre- Functional Checklists, Systems Functional Performance Testing; and project completion.
E. Convene commissioning team meetings for the purpose of coordination, communication, and conflict resolution; discuss status of the commissioning processes. Responsibilities include arranging for facilities, preparing agenda and attendance lists, and notifying participants. The Commissioning Agent shall prepare and distribute minutes to commissioning team members and attendees within five workdays of the commissioning meeting.
F. Observe construction and report progress, observations and issues. Observe systems and equipment installation for adequate accessibility for maintenance and component replacement or repair, and for general conformance with the Construction Documents.
G. Prepare Project specific Pre-Functional Checklists and Systems Functional Performance Test procedures.
H. Coordinate Systems Functional Performance Testing schedule with the Contractor.
I. Witness selected systems startups.
J. Verify selected Pre-Functional Checklists completed and submitted by the Contractor.
K. Witness and document Systems Functional Performance Testing.
L. Compile test data, inspection reports, and certificates and include them in the systems manual and commissioning report.
M. Review and comment on operation and maintenance (O&M) documentation and systems manual outline for compliance with the Contract Documents. Operation and maintenance documentation requirements are specified in Paragraph 1.25, Section 01 00 00 GENERAL REQUIREMENTS.
N. Review operation and maintenance training program developed and provided by the Contractor. Verify training plans provide qualified instructors to conduct operation and maintenance training.
O. Prepare commissioning Field Observation Reports.
P. Prepare the Final Commissioning Report.
01 91 00 - 14
R. Assemble the final commissioning documentation, including the Final Commissioning Report and Addendum to the Final Commissioning Report.
1.12 COMMISSIONING DOCUMENTATION
A. Commissioning Plan: A document, prepared by Commissioning Agent, that outlines the schedule, allocation of resources, and documentation requirements of the commissioning process, and shall include, but is not limited, to the following:
1. Plan for delivery and review of submittals, systems manuals, and other documents and reports. Identification of the relationship of these documents to other functions and a detailed description of submittals that are required to support the commissioning processes. Submittal dates shall include the latest date approved submittals must be received without adversely affecting commissioning plan.
2. Description of the organization, layout, and content of commissioning documentation (including systems manual) and a detailed description of documents to be provided along with identification of responsible parties.
3. Identification of systems and equipment to be commissioned.
4. Schedule of Commissioning Coordination meetings.
5. Identification of items that must be completed before the next operation can proceed.
6. Description of responsibilities of commissioning team members.
7. Description of observations to be made.
8. Description of requirements for operation and maintenance training.
9. Schedule for commissioning activities with dates coordinated with overall construction schedule.
10. Process and schedule for documenting changes on a continuous basis to appear in Project Record Documents.
11. Process and schedule for completing prestart and startup checklists for systems, subsystems, and equipment to be verified and tested.
12. Preliminary Systems Functional Performance Test procedures.
B. Systems Functional Performance Test Procedures: The Commissioning Agent will develop Systems Functional Performance Test Procedures for each system to be commissioned, including subsystems, or equipment and interfaces or interlocks with other systems. Systems Functional Performance Test Procedures will include a separate entry, with space for comments, for each item to be tested.
Preliminary Systems Functional Performance Test Procedures will be provided to the VA, Architect/Engineer, and Contractor for review and comment. The Systems Performance Test Procedure will include test procedures for each mode of operation and provide space to indicate whether the mode under test responded as required. Each System Functional Performance Test procedure, regardless of system, subsystem, or equipment being tested, shall include, but not be limited to, the following:
1. Name and identification code of tested system.
2. Test number.
3. Time and date of test.
4. Indication of whether the record is for a first test or retest following correction of a problem or issue.
5. Individuals present for test.
6. Observations and Issues.
7. Issue number, if any, generated as the result of test.
C. Pre-Functional Checklists: The Commissioning Agent will prepare Pre- Functional Checklists. Pre-Functional Checklists shall be completed and
01 91 00 - 15 signed by the Contractor, verifying that systems, subsystems, equipment, and associated controls are ready for testing. The Commissioning Agent will spot check Pre-Functional Checklists to verify accuracy and readiness for testing.
Inaccurate or incomplete Pre-Functional Checklists shall be returned to the Contractor for correction and resubmission.
D. Test and Inspection Reports: The Commissioning Agent will record test data, observations, and measurements on Systems Functional Performance Test Procedure. The report will also include recommendation for system acceptance or non-acceptance. Photographs, forms, and other means appropriate for the application shall be included with data. Commissioning Agent Will compile test and inspection reports and test and inspection certificates and include them in systems manual and commissioning report.
E. Corrective Action Documents: The Commissioning Agent will document corrective action taken for systems and equipment that fail tests. The documentation will include any required modifications to systems and equipment and/or revisions to test procedures, if any. The Commissioning Agent will witness and document any retesting of systems and/or equipment requiring corrective action and document retest results. The contractor is liable for any costs incurred for retesting of failed system tests.
F. Commissioning Issues Log: The Commissioning Agent will prepare and maintain Commissioning Issues Log that describes Commissioning Issues and Commissioning Observations that are identified during the Commissioning process. These observations and issues include, but are not limited to, those that are at variance with the Contract Documents. The Commissioning Issues Log will identify and track issues as they are encountered, the party responsible for resolution, progress toward resolution, and document how the issue was resolved. The Master Commissioning Issues Log will also track the status of unresolved issues.
1. Creating a Commissioning Issues Log Entry:
a. Identify the issue with unique numeric or alphanumeric identifier by which the issue may be tracked.
b. Identify date and time of the issue.
c. Identify system, subsystem, and equipment to which the issue applies.
d. Identify location of system, subsystem, and equipment.
e. Include information that may be helpful in diagnosing or evaluating the issue.
f. Note recommended corrective action.
2. Documenting Issue Resolution:
a. Log date correction is completed or the issue is resolved.
b. Describe corrective action or resolution taken. Include description of diagnostic steps taken to determine root cause of the issue, if any.
c. Identify changes to the Contract Documents that may require action.
d. State that correction was completed and system, subsystem, and equipment are ready for retest, if applicable.
G. Final Commissioning Report: The Commissioning Agent will document results of the commissioning process, including unresolved issues, and performance of systems, subsystems, and equipment. The Commissioning Report will indicate whether systems, subsystems, and equipment have been properly installed and are performing according to the Contract Documents. This report will be used by the Department of Veterans Affairs when determining that systems will be accepted. This report will be used to evaluate systems, subsystems, and equipment and will serve as a future reference document during VA occupancy and operation. It shall describe components and performance that exceed
01 91 00 - 16 requirements of the Contract Documents and those that do not meet requirements of the Contract Documents. The commissioning report will include, but is not limited to, the following:
1. Lists and explanations of substitutions; compromises; variances with the
Contract Documents; record of conditions; and, if appropriate, recommendations for resolution. Design Narrative documentation maintained by the Commissioning Agent.
2. Commissioning plan.
3. Pre-Functional Checklists completed by the Contractor, with annotation of the Commissioning Agent review and spot check.
4. Systems Functional Performance Test Procedures, with annotation of test results and test completion.
5. Commissioning Issues Log.
H. Addendum to Final Commissioning Report (if applicable): The Commissioning Agent will prepare an Addendum to the Final Commissioning Report near the end of the Warranty Period. The Addendum will indicate whether systems, subsystems, and equipment are complete and continue to perform according to the Contract Documents. The Addendum to the Final Commissioning Report shall include, but is not limited to, the following:
1. Documentation of deferred and off season test(s) results.
2. Completed Systems Functional Performance Test Procedures for off season test(s).
3. Documentation that unresolved system performance issues have been resolved.
4. Updated Commissioning Issues Log, including status of unresolved issues.
5. Identification of potential Warranty Claims to be corrected by the
Contractor.
I. Systems Manual: The Contractor will gather required information and compile the Systems Manual. The Systems Manual will include, but is not limited to, the following:
1. Design Narrative, including system narratives, schematics, single-line diagrams, flow diagrams, equipment schedules, and changes made throughout the Project.
2. Reference to Final Commissioning Plan.
3. Reference to Final…