This is Bid Addendum No. 4, issued by the Connecticut Department of Mental Health and Addiction Services on September 8, 2026, for project MHA-1457 involving transformer replacement at Whiting Forensic Hospital in Middletown, Connecticut. The addendum clarifies and modifies the original contract documents dated July 10, 2026, and addresses ten pre-bid request for information questions submitted by prospective bidders. The original bid due date remains September 17, 2026 at 10:00 a.m., and prospective bidders are required to acknowledge receipt of all four addenda on the Bid Proposal Form Section 00 41 00 or face disqualification. No site visits or pre-bid conferences are referenced in the addendum.
Key clarifications provided in the addendum establish contractor responsibilities for survey costs (including pre- and post-construction surveys with self-established control points), soil characterization and disposal of excavated materials with reuse prioritized on-site, and groundwater management if unexpectedly encountered during excavation. The State retains responsibility for testing and abating groundwater remediation wastewater discovered during construction, with a four-day response requirement for testing requests and ten-day disposal arrangement requirement. The addendum confirms that temporary compacted aggregate base material may be installed with a 30-day cure period before permanent pavement restoration, specifies that pre-cast bollards are not acceptable and must conform to detailed specifications on Sheet C-2, and clarifies that transformer pad sizing must follow the manufacturer's recommendations as shown on the drawings. Line striping restoration is excluded from the scope of work, and existing site line striping is identified as minimal.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Connecticut Department of Mental Health and Addiction Services 6030A
Bid Addendum
Addendum No.: 4 Date of Addendum: 9/8/2026
CT DMHAS 6030A (Rev. 08.11.2026) MHA-1457
CT DMHAS Engineering and Capital Projects Whiting Forensic Hospital Transformer Replacement
Middletown, CT
MHA-1457
Original Bid Due Date / Time: 9/17/2026 10:00 AM
Previous Addenda: 3
TO: Prospective Bid Proposers:
This Addendum forms part of the “Contract Documents” and modifies or clarifies the original “Contract Documents” for this Project dated 07/10/2026. Prospective Bid Proposers shall acknowledge receipt of the total number of Addenda issued for this Project on the space provided on Section 00 41 00 Bid Proposal Form.
Failure to acknowledge receipt of the total number of Addenda issued for this Project on the space provided on Section 00 41 00 Bid Proposal Form shall subject Bid Proposers to disqualification.
The following clarifications are applicable to the Drawings and Project Manual for the project referenced above.
Item 1:
PLEASE SEE RESPONSES TO PRE-BID RFIS SUBMITTED BELOW:
QUESTION 1. Please confirm if the contractor is to carry the cost of a Licensed Land Surveyor to perform a pre-construction & post construction survey as noted in 01 71 23.
ANSWER 1. Yes.
QUESTION 2. Will the Owner / Engineer be providing survey control points to the Contractor’s surveyor?
ANSWER 2. No. The control points are to be established by the Surveyor.
QUESTION 3. Please confirm if the existing soils can be directly loaded and exported offsite for disposal. Based on the contract documents there will not be a suitable place onsite to re-use any of the existing material. The environmental reports are not clear as to whether the existing soil can be directly exported or if it has to be stockpiled and tested prior to export.
ANSWER 3. Excavated soil should be reused on Site to the extent possible in areas that require filling. Excess soils can be directly loaded and exported offsite for disposal at a disposal facility approved by the Owner and/or TRC. Refer to the Soil Management Plan prepared by TRC, dated January 2025 included in the Project Manual Section 50 20 00 – Environmental Assessment Information, Section 4.0.
QUESTION 4. Please confirm if the contractor is responsible for carrying any costs to test and dispose of potentially impacted soil within the base bid.
ANSWER 4. Yes, the Contractor is responsible for characterization of soil to be transported offsite for disposal.
QUESTION 5. Please confirm if the contractor should carry any costs for handling / disposing of impacted groundwater that may be encountered during excavation and would require proper dewatering to install the subsurface utilities.
Connecticut Department of Mental Health and Addiction Services 6030A
Bid Addendum
Addendum No.: 4 Date of Addendum: 9/8/2026
CT DMHAS 6030A (Rev. 08.11.2026) MHA-1457
ANSWER 5. Groundwater was not encountered during previous site investigations and is not expected to be encountered based on the proposed extents and depths of excavation for the Project. In accordance with Project Manual Section 00 30 00 – General Statements for Available Information, 2.2:
If the Contractor should encounter any Groundwater Remediation Wastewater that was not previously identified, characterized, permitted, and assigned as the Contractor’s responsibility, he should immediately notify the Construction Administrator in writing of same. It is the State’s responsibility to have the groundwater tested and abated (if necessary). The Owner will respond within four (4) Calendar Days after receiving the Contractor’s written request to the Construction Administrator for testing the suspect groundwater The Owner shall arrange for the permitting and disposal of the Groundwater Remediation Wastewater if necessary) within a reasonable time period, i.e. within ten (10) calendar days.
QUESTION 6. Is the intent to install temporary pavement and wait 30 days to complete the permanent pavement restoration?
ANSWER 6. No.
QUESTION 7. Can the contractor install compacted processed aggregate base material flush with the existing pavement and let that sit for 30 days prior to completing the permanent pavement restoration?
ANSWER 7. Yes.
QUESTION 8. Would it be acceptable to install pre-cast concrete bollards as manufactured by United Concrete products in lieu of the bollards that are detailed on Sheet C-2? The pre-cast bollards would be a substantial cost savings if allowed.
ANSWER 8. No. Pre-cast bollards are not acceptable.
QUESTION 9. The pre-cast transformer pad and base as shown on Sheet E-2 is not a standard size within the local pre-cast industry. Would the contractor be allowed to installed a standard sized pre-cast transformer pad and base with exterior dimensions of 96” x 96”?
ANSWER 9. This is not a standard Utility Company transformer pad. The footprint size of the transformer pad should be as recommended by the transformer manufacturer. The pad size detailed on the drawings is per Eaton.
QUESTION 10. Is the contractor responsible for restoration of line striping within the base bid?
ANSWER 10. The existing line striping on site is minimal and restoration/repainting of the striping is not part of the scope of work.