6 SEC 415_ogi.pdf
PDF 366 KB Posted
- Attached to
- RESURFACING OF LAKEVIEW DR, BROAD ST, CEDAR DR, BLUE JAY CT, QUAIL RIDGE DR, WOODPECKER LN, STAPLER
- Solicitation number
- PE-66298-NONST-2026-000000002
- Issued by
- Barrow County, Georgia
About this file
This specification document details the technical requirements for Section 415 - Asphaltic Concrete Open Graded Crack Relief Interlayer (OGI) for use by the Georgia Department of Transportation and local agencies, including the City of Nicholson. The City of Nicholson has issued a sealed bid invitation for approximately 3.14 miles of road resurfacing work across multiple streets, with major work elements including patching, OGI placement, recycled asphaltic concrete resurfacing, striping, and shoulder filling on Lakeview Drive, Broad Street, Cedar Drive, Blue Jay Court, Quail Ridge Drive, Woodpecker Lane, Stapler Drive, New Hope Drive, Peach Street, and James Maxwell Road. The project will be awarded as a single contract with bids due by 9:00 a.m. on April 23, 2026, at the City of Nicholson Office. All work must be completed in accordance with the latest edition of GDOT Standard Specifications and the Manual on Uniform Traffic Control Devices. The project timeline includes a question deadline of April 15, 2026, at 3:00 p.m., with answers provided by April 20, 2026, at 5:00 p.m. Contract documents are available from Irma Robles, City Clerk, at 706-757-3408.
The OGI specification establishes specific technical requirements for mixture design and construction, including an open-graded mixture with 18 to 23 percent in-place air voids designed to mitigate reflective cracking. Materials must comply with GDOT specifications for asphalt cement (grade specified per Section 820), aggregates, mineral filler, and approved additives. The mixture must be produced and placed at 250°F with a tolerance of ±20°F at a compacted lift thickness of 1 inch, with a controlled spread rate of no more than 10 pounds per square yard variance from the calculated target. Acceptance is determined on a lot-by-lot basis through visual inspection for texture, segregation, bleeding, and in-place air void content, with an adjustment period granted for the first lot or day produced. Compensation is provided per ton of material, with full payment covering all materials, labor, equipment, and surface preparation, though excess material exceeding upper spread rate limits will not be paid for.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 5 ROADWAY TYPICAL ASPH _STAPLER_PEACH.docx | DOCX document | |
| 6 SEC 652.pdf | ||
| 5 ROADWAY TYPICAL ASPH_JAMES MAXWELL_NEW HOPE.docx | DOCX document | |
| 6 SEC 162_165.pdf | ||
| 1COVER SHEET.doc | DOC document | |
| 5_F 150.pdf | ||
| AGREEMENT.doc | DOC document | |
| 5 ROADWAY TYPICAL ASPH_BROAD ST.docx | DOCX document | |
| E_verify affidavit.pdf | ||
| 5_B ss105.pdf | ||
| 5_A104.pdf | ||
| 6 SEC 400.pdf | ||
| 5 BID FORM.doc | DOC document | |
| i_9 2027.pdf | ||
| 5 Nicholson Roads PAVING MAP.pdf | ||
| BID BOND.doc | DOC document | |
| 5_E ss109.pdf | ||
| Security and Immigration AFfidavit.doc | DOC document | |
| 5_D ss108.pdf | ||
| 5 ROADWAY TYPICAL ASPH.docx | DOCX document | |
| 4 Instruction to Bidder.doc | DOC document | |
| 5 SPECIAL PROVISION.docx | DOCX document | |
| CITY OF NICHOLSON.docx | DOCX document | |
| Corporate Certification.doc | DOC document | |
| 5_C ss107.pdf |
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section 415 — Asphaltic Concrete Open Graded Crack Relief Interlayer
Section 415—Asphaltic Concrete Open Graded Crack Relief Interlayer
415.1 General Description
This work includes constructing a bituminous plant produced Asphaltic Concrete Open Graded Crack Relief Interlayer (OGI) over the existing roadway surface. The mixture shall serve as asphaltic concrete leveling over irregular surfaces and provide mitigation for reflective cracking prior to the placement of the final surface pavement. The mixture shall conform to the lines, grades, thicknesses, typical sections and cross sections shown on the plans or established by the Engineer.
This section includes the requirements for Asphaltic Concrete Open Graded Crack Relief Interlayer mixtures regardless of the gradation of the aggregates, type and amount of bituminous material, or pavement use. Follow the requirements in Section 400, Section 402 and Section 828 for production and placement, materials, equipment, and acceptance plans except as noted or modified in this specification.
Acceptance of work is on a lot-to-lot basis according to the requirements of this Section, Section 400, Section 402 and Section 106.
415.1.01 Definitions
Asphaltic Concrete Open Graded Crack Relief Interlayer: an open graded mixture placed at a lift thickness that yields stone on stone contact that provides in-place air void content of 18 to 23 percent to mitigate existing cracking within asphaltic concrete pavements.
415.1.02 Related References
A. Standard Specifications Section 106—Control of Materials
Section 109—Measurement and Payment
Section 152—Field Laboratory Building
Section 400 – Hot Mix Asphaltic Concrete Construction
Section 402 – Hot Mix Recycled Asphaltic Concrete
Section 413—Bituminous Tack Coat
Section 800 – Coarse Aggregate
Section 802 - Aggregate for Asphaltic Concrete
Section 820 – Asphalt Cement
Section 828—Hot Mix Asphaltic Concrete Mixtures
Section 831 – Admixtures
Section 882 – Lime
Section 883 – Mineral Filler
452452452452452452452
B. Referenced Documents
AASHTO T 209
AASHTO T 202
AASHTO T 49
AASHTO T 315
Department of Transportation Standard Operating Procedure (SOP) 27
Department of Transportation Standard Operating Procedure (SOP) 15
Department of Transportation Standard Operation Procedure (SOP) 40
GDT 38
GDT 73
GDT 83
GDT 114
GDT 119
GDT 125
GDT 126
GSP 15
GSP 21
QPL 1
QPL 2
QPL 7
QPL 26
QPL 39
QPL 41
QPL 45
415.1.03 Submittals
A. Invoices
Furnish formal written invoices from a supplier for all materials used in production of HMA when requested by Department. Show the following on the Bill of Lading:
• Date shipped
• Quantity in tons (megagrams)
• Included with or without additives (for asphalt cement)
Purchase asphaltic cement directly from a supplier listed on Qualified Products List 7 and provide copies of Bill of Lading at the Department’s request.
453453453453453453453
B. Paving Plan Before starting asphaltic concrete construction, submit a written paving plan to the Engineer for approval. Include the following on the paving plan:
• Proposed starting date
• Location of plant(s)
• Rate of production
• Average haul distance(s)
• Number of haul trucks
• Paver speed feet (meter)/minute for each placement operation
• Mat width for each placement operation
• Number and type of rollers for each placement operation
• Sketch of the typical section showing the paving sequence for each placement operation
• Electronic controls used for each placement operation
• Temporary pavement marking plan
If staged construction is designated in the plans or contract, provide a paving plan for each construction stage.
If segregation is detected, submit a written plan of measures and actions to prevent segregation. Work will not continue until the plan is submitted to and approved by the Department.
C. Job Mix Formula Submit to the Engineer a written job mix formula proposed for each mixture type to be used based on an approved mix design. Furnish the following information for each mix:
• Specific project for which the mixture will be used
• Source and description of the materials to be used
• Mixture I.D. Number
• Proportions of the raw materials to be combined in the paving mixture
• Single percentage of the combined mineral aggregates passing each specified sieve
• Single percentage of asphalt by weight of the total mix to be incorporated in the completed mixture
• Single temperature at which to discharge the mixture from the plant
• Theoretical specific gravity of the mixture at the designated asphalt content
• Name of the person or agency responsible for quality control of the mixture during production
Do the following to have the formulas approved in accordance with SOP 40 Approval of Contractor Job Mix Formulas and to ensure their quality:
1. Submit proposed job mix formulas for review at least two weeks before beginning the mixing operations.
2. Do not start hot mix asphaltic concrete work until the Engineer has approved a job mix formula for the mixture to be used. No mixture will be accepted until the Engineer has given approval.
3. Provide mix designs for all Asphaltic Concrete Open Graded Crack Relief Interlayer mixtures to be used.
4. After a job mix formula has been approved, assume responsibility for the quality control of the mixtures supplied to the Department according to Subsection 106.01, Source of Supply and Quantity of Materials.
D. Quality Control Program Submit a Quality Control Plan to the Office of Materials and Testing for approval. The Quality Control Program will be included as part of the certification in the annual plant inspection report.
454454454454454454454
415.2 Materials
The requirements established in Section 400 are to be followed for Asphaltic Concrete Open Crack Relief Interlayer production and placement, materials, equipment, and acceptance plans except as noted or modified in this specification.
Ensure that materials comply with the specifications listed in Table 1.
TABLE 1—MATERIALS SPECIFICATIONS
Material Subsection
Asphalt Cement, Grade Specified 820.2
Coarse Aggregates for Asphaltic Concrete 802.2.02
Fine Aggregates for Asphaltic Concrete 802.2.01
Mineral Filler 883.1
Heat Stable Anti-Stripping Additive 831.2.04
Hydrated Lime 882.2.03
Silicone Fluid (When approved by the Office of Materials and Testing) 831.2.05
Bituminous Tack Coat: PG 58-22, PG 64-22, PG 67-22 820.2
Hot Mix Asphaltic Concrete Mixtures 828
455455455455455455455
415.2.01 Mix Design Requirements
The Open Graded Crack Relief Interlayer Mixture shall be formulated to contain approximately 18 to 23 percent in-place air voids after compaction. Use approved mixtures that meet the following mixture control tolerances and design criteria:
TABLE 2 – ASPHALTIC CONCRETE OPEN GRADED CRACK RELIEF
INTERLAYER MIXTURE DESIGN AND CONTROL
Sieve Size
Mixture Control
Tolerance, Design Gradation Limits, % Passing
Open Graded Crack Relief Interlayer
3/4 in. (19 mm) sieve ±0.0 100
1/2 in. (12.5 mm) sieve ±6.1 80 - 100
3/8 in. (9.5 mm) sieve ±5.6 40 - 65
No. 4 (4.75 mm) sieve ±5.7 10 - 25
No. 8 (2.36 mm) sieve ±4.6 2 - 10
No. 200 (75 µm) sieve ±2.0 2 - 5
Range for % AC ±0.4 4.50 – 5.25
Class of stone (Section 800) “A” only
Drain-down (AASHTO T305), % <0.3
Design optimum air voids (%) 20% ± 2%
Control Sieves used in Acceptance Schedule 3/8 in., No. 8 (9.5 mm, 2.36 mm) and Asphalt Cement
Notes:
1. Use only PG 64-22 or PG 67-22 asphalt cement (specified in Section 820).
2. Use no less than 1.0% hydrated lime regardless of aggregates group or source(s) used.
3. Ensure no more than 10 percent Recycled Asphalt Pavement (RAP) is used in Asphaltic Concrete Open Graded Interlayer mixtures.
4. Quality Acceptance Test Results for AC content deviating > ± 0.3 % from the approved Job Mix Formula (JMF) consistently over three Lots may subject the mix to a revised AC content on the project JMF at the discretion of the State Materials Engineer based on statistical trend.
5. Range for % AC is Original Optimum AC (OOAC) at 25 blow Marshall prior to the Corrected Optimum
AC (COAC) calculation detailed in SOP 2 (Appendix D).
456456456456456456456 http://www.dot.ga.gov/doingbusiness/TheSource/sop/sop02.pdf http://www.dot.ga.gov/doingbusiness/TheSource/sop/sop02.pdf
415.3 Construction Requirements
The requirements established in Section 400 are to be followed for asphaltic concrete mixture production and placement, materials, equipment, and acceptance plans except as noted or modified in this specification.
415.3.01 Personnel
General Provisions 101 through 150.
415.3.02 Construction
Asphaltic concrete plants that produce mix for Department use are governed by Quality Assurance for Hot Mix Asphaltic Concrete Plants in Georgia, Laboratory Standard Operating Procedure No. 27.
Follow requirements established in Section 400 for production and placement, materials, equipment, acceptance plans and adjustments except as noted or modified in this specification.
A. Apply a bituminous tack coat according to Section 413. The Engineer will determine the application rate, which must be within the limits of 0.06 gal/yd2 to 0.10 gal/yd2 (0.27 L/m2 to 0.45 L/m2) (residual asphalt cement).
B. The mix shall be produced and placed at a temperature of 250°F with a tolerance of ± 20°F.
C. Place the mix to a compacted lift thickness of 1-inch (25 mm). For construction purposes, the target thickness will be converted to spread rate based on the bulk specific gravity of the asphaltic concrete mixture being used as shown in the following equation:
Spread rate (lbs./yd2) = t * Gmb* 46.8 (Spread rate (kg/ m2) = t * Gmb) Where: t = Compacted lift thickness (inches, mm) Gmb= bulk specific gravity of the mix from the approved mix design
The spread rate shall be controlled within 10 lbs./yd2 (6 kg/m2).
D. Do not place mix at air temperatures below 50 °F (10 °C).
E. The mix shall be compacted in a manner to achieve 18 to 23 percent in-place air voids. Steel wheel rollers operating in static mode only will be used to seat the lift of Asphaltic Concrete Open Graded Crack Relief Interlayer mixture. Pneumatic tire rollers shall not be allowed on the Asphaltic Concrete Open Graded Crack Relief Interlayer mat.
415.4. Measurement
Asphaltic Concrete Open Graded Crack Relief Interlayer mixture, complete, in place and accepted, is measured in tons (megagrams). If the spread rate exceeds the upper limits outlined in Subsection 415.3.02.C by > 15 lbs./yd2, the mix in excess will not be paid for. If the rate of the spread is ≤ 10 lbs./yd2 than the lower limit, the deficient course is subject to correction by overlaying the entire lot. The mixture used for correcting deficient areas is paid for at the Contract Unit Price of the course being corrected and is subject to mixture control requirements established in Table 2
– Asphaltic Concrete Open Graded Crack Relief Interlayer Mixture Design and Control. After the deficient course has been corrected, the total spread rate for that lot is recalculated, and the mix in excess of the upper limits outlined in Subsection 415.3.02.C will not be paid for.
415.5 Payment
Asphaltic Concrete Open Graded Crack Relief Interlayer mix is paid for at the Contract Unit Price per ton (megagram).
Payment is full compensation for furnishing and placing materials including asphalt cement, hydrated lime, approved additives, and for cleaning and repairing, preparing surfaces, hauling, mixing, spreading, rolling, and performing other operations to complete the Contract Item.
457457457457457457457
Payment will be made under:
Item No. 415 Asphaltic Concrete Open Graded Crack Relief Interlayer, group-blend, Including bituminous materials and hydrated lime
Per ton (megagram)
415.5.01 Adjustments
A. Materials Produced and Placed During the Adjustment Period
Follow requirements established in Section 400 for production and placement, materials, equipment, acceptance plans and adjustments except as noted or modified in this specification.
Asphaltic Concrete Open Graded Crack Relief Interlayer shall be granted an adjustment period for the first Lot or day, whichever is less, produced for the Contract. A new adjustment period shall not be granted for a change of producer, mix design or asphalt plant location. The adjustment period is provided to adjust or correct the mix and to establish the construction procedures and sequence of operations. Test the mixture in accordance with Section
400.3.06. Maintain the asphalt cement content and gradation within the limits provided in Table 2 – Asphaltic Concrete Open Graded Interlayer Mixture Design and Control. The Engineer will not use these test results in the acceptance for payment decision, but production and placement operations shall cease for failure to meet mixture control tolerances established in Table 2 – Asphaltic Concrete Open Graded Interlayer Mixture Design and Control.
415.5.02 Determine Lot Acceptance
The Engineer will accept the mixture based on visual inspection. The mixture shall be inspected for texture, segregation, bleeding, fat spots, raveling, delamination, tearing, targeted in-place air void content and slippage areas.
Remove and replace any areas determined to be unacceptable to the Engineer.
458458458458458458458
| 2021StandardSpecifications 462 |
| 2021StandardSpecifications 463 |
| 2021StandardSpecifications 464 |
| 2021StandardSpecifications 465 |
| 2021StandardSpecifications 466 |
| 2021StandardSpecifications 467 |
| 2021StandardSpecifications 468 |
File details come from the government source that posted it. Updated .