This is a Measurement and Payment schedule document that establishes the basis for compensating completed work items under a construction contract for rural water and wastewater infrastructure systems.
The contract encompasses installation of comprehensive septic and water systems, with payment made based on actual quantities completed at specified unit prices or lump sum amounts. Major work items include mobilization and demobilization; solid sewer pipe installation (paid per linear foot); underground cleanouts (paid per unit); a 1,000-gallon, 2-compartment septic tank (lump sum); a 1,000-gallon, 1-compartment pump tank with pump and controls including electrical integration (lump sum); a 2-inch PVC Schedule 40 effluent transport line from pump chamber to drainfield (paid per linear foot); a low-pressure dosed gravelless mound drainfield system with imported sand fill, chambers, and related components (lump sum); HDPE water service line (paid per linear foot); and water meter assembly with pressure reducing valve (paid per unit). All prices include full compensation for excavation, backfill, compaction, materials, labor, equipment, testing, permitting, taxes, and all other work necessary to deliver complete and operational systems. The scope applies to work performed for the Indian Health Service under Solicitation Number 75H70126Q00035 for the Bill Parkin project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 75H70126Q00035-A00001.pdf | ||
| 3-Drawings.pdf | ||
| 2-Technical Provisions.pdf | ||
| 5-Aerial II.pdf | ||
| 1-SOW.docx | DOCX document | |
| 4-Aerial.pdf | ||
| A11 Pre-Solicitation SAM Notice.pdf | ||
| 7-US DOL WD WA20260081 Dated 5-18-2026.pdf | ||
| B01 75H70126Q00035.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MEASUREMENT AND PAYMENT FOR BID SCHEDULE LINE ITEMS
Completed items of work shall be measured and paid for in accordance to the items listed below. All work shall be done in accordance with the Specifications and Drawings. Payment shall be provided based on the actual quantities completed and shall represent full compensation under the contract. The price paid for the completed item of work shall include full compensation for furnishing all labor, materials, tools, equipment, site restoration and performing all work required by the provisions of the contract to furnish and install the item of work, complete in place. In all cases, the finished product shall be a complete, operational system or component. The price for the completed item of work shall include all applicable State, Federal, County, Tribal and local sales or other taxes, permits, and fees.
MOBILIZATION AND DEMOBILIZATION
Payment for transportation of equipment, material, and personnel to and from the job site location (regardless of trips required), required permits and fees, taxes, and all other necessary items to complete the work.
SOLID SEWER PIPE
Payment for solid sewer pipe, as specified in the Design and Specification, shall be made at the contract unit price for the sizes of pipe listed based on the number of linear feet installed. Payment shall include excavation, backfill and compaction; all pipe and fittings; connection of the solid sewer pipe to existing sewer service line or home; testing; and all other necessary items for a complete and operational installation.
UNDERGROUND CLEANOUT, DOUBLESWEEP
Payment for the underground cleanout, as specified in the Design and Specification, shall be made at the contract unit price based on the number of underground cleanouts installed. Payment shall include excavation, backfill and compaction, all pipe and fittings, and all other necessary items for a complete and operational installation. No payment shall be made for cleanouts installed above grade as part of the connection to existing house, or as part of drop manholes.
SEPTIC TANK, 1,000 GALLONS, 2 COMPARTMENT
Payment for trash tank, as specified in the Design and Specification, shall be made at the contract lump sum price based on a complete system. Payment shall include excavation, backfill, compaction, sand or gravel where un-uniform native soil or groundwater is present, concrete tank, risers, lids, effluent filter, plumbing, fittings, and all other necessary items for a complete and operational installation.
PUMP TANK WITH PUMP AND CONTROLS, 1,000 GALLONS, 1 COMPARTMENT
Payment for the pump tank, as specified in the Design and Specification, shall be made at the contract lump sum price based on a complete system. Payment shall include excavation, backfill, compaction, sand or gravel where non-uniform native soil or groundwater is present, single compartment concrete tank, riser, lid, waterproofing, plumbing, ball valve, check valve, fittings, screened pump vault, pump (Liberty FL30-Series, or equal), floats, conduit, electrical disconnect (when required), water tight junction box, subpanel, alarm, control panel, connection to the existing home electric panel, testing, and all other necessary items for a complete and operational installation.
EFFLUENT TRANSPORT LINE 2 INCH PVC SCH 40
Payment for the effluent transport line from the pump chamber to the drainfield shall be made at the contract unit price for the sizes of pipe listed based on the number of linear feet installed. Compensation shall include payment for excavation, backfilling, pipe and fittings, connections using 2” 2” PVC Schedule 40, force service line, center-fed manifold pipes, distributing valves, and all other necessary items for a complete and
LOW PRESSURE DOSED GRAVELLESS MOUND DRAINFIELD SYSTEM
Payment for a low-pressure dosed mound drainfield as specified in Technical Provision 15.0 and detail drawings shall be made at the contract lump sum price based on a complete system. Compensation shall include payment for imported ASTM C-33 Sand fill, chambers, filter fabric, distribution laterals, inspection ports, plowing, imported material, topsoil, seeding, valve box, cleanouts, fittings, final grading, and all other necessary items needed for a complete and operational system.
HDPE WATER SERVICE LINE
Payment for water service line as specified in the Design and Specification shall be made at the contract unit price for the size of line listed based on the number of linear feet installed. Compensation shall include payment for excavation, backfilling and compaction; all fittings, including locating and connecting to existing service lines, yard hydrants and/or meter; disinfection and testing; and all other necessary items for a complete and operational installation.
WATER METER ASSEMBLY WITH PRESSURE REDUCING VALVE
Payment for water meter assembly as specified in the Design and Specification shall be made at the contract unit price based on the number of water meter assemblies installed. Compensation shall include payment for excavation, backfilling and compaction; corporation stop, water meter, copper setter with specified appurtenances, angle stop, pressure reducing valve and fittings set to pressure specified by the water system owner, meter box; and all other necessary items for a complete and operational installation.