2-Technical Provisions.pdf

PDF 258 KB Posted

Attached to
Bill Parkin (MAK)
Solicitation number
75H70126Q00035
Issued by

About this file

This document comprises technical provisions for water and wastewater infrastructure construction, specifically addressing excavation, trenching, backfilling, individual septic tanks, lift stations, mound systems, and water service connections. The provisions establish detailed specifications and standards for contractor performance across multiple utility installation categories applicable to tribal, federal, and local projects.

Excavation, Trenching, and Backfilling (TP 3.0) requires open-cut methods with trench widths of 12-24 inches wider than pipe diameter, minimum 6-inch clearance on each side, and maximum 500-foot open lengths. Compaction standards vary by location, requiring 95% maximum density for roadways and 70-90% for unimproved surfaces per ASTM D1557. Pavement cutting must follow specific protocols with 6-inch setbacks for asphalt and 2-inch minimum depth for concrete. Road crossings for water and sewer service lines utilize PVC schedule 80 or Schedule 40 steel encasement pipe, with boring equipment required for roads that cannot accommodate open-cut methods.

Individual Septic Tanks (TP 11.0) specify precast reinforced concrete construction conforming to ASTM 6913 with two compartments, 2½-inch minimum wall thickness, 24-inch access risers, and required effluent filters equivalent to Zabel A1800. Individual Lift Stations (TP 12.0) require submersible effluent pumps capable of 30 gallons per minute at 16-foot head with 3/8-inch solids capacity, NEMA 4X control panels, mercury float switches, and alarm systems. Low Pressure-Dosed Mound Systems (TP 15.0) demand medium sand fill meeting ASTM C-33 gradation specifications, 10-foot by 40-foot gravel beds with 9-inch minimum depth, and track-mounted equipment only during construction to prevent soil compaction and rutting.

Water Service Connections (TP 30.0) specify polyethylene pipe (ASTM 2239, 200 psi SDR 7), compression fittings, ductile iron or brass saddles, bronze corporation stops, and cast bronze water meters reading gallons with 6-digit totalizers conforming to AWWA C-700. Installation requires minimum 2-foot cover, flushing and pressure testing prior to meter installation, and disinfection using liquid chlorine at 50 ppm minimum concentration. Where required, freezeless yard hydrants must be 3-foot bury depth with ¾-inch brass thread outlets, and existing wells require abandonment per Washington State Department of Ecology standards or Oregon equivalents. All installations must comply with OSHA trench safety regulations and applicable state and local standards.

View the file

Other files

File Type Posted
75H70126Q00035-A00001.pdf PDF
5-Aerial II.pdf PDF
1-SOW.docx DOCX document
6-Measurement and Payment.docx DOCX document
3-Drawings.pdf PDF
4-Aerial.pdf PDF
A11 Pre-Solicitation SAM Notice.pdf PDF
7-US DOL WD WA20260081 Dated 5-18-2026.pdf PDF
B01 75H70126Q00035.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1/06 Technical Provisions- TP 3.0 Excavation, Trenching, and Backfilling Page 1

TECHNICAL PROVISION 3.0

EXCAVATION, TRENCHING, AND BACKFILLING

3.01 Scope of Work

The work covered by this section includes the furnishing of all plant, labor, tools, equipment, and material, and performing all operations in connection with the excavation, trenching, and backfilling for the installation of all pipelines, structures, and accessories, all in accordance with these technical provisions and applicable drawings.

3.02 Protection of Excavation

In conformance with applicable safety regulations, the Contractor shall provide suitable shoring and sheeting to protect all excavations and provide safe working conditions for workers.

3.03 Excavation

3.03.01 General

All excavation required for the performance of this contract shall be made by open cut methods unless otherwise shown on the drawings, required by applicable encroachment permits, or approved in writing by the Project Manager.

3.03.02 Trench Excavation

The sides of all trenches for the installation of utility piping systems shall be as nearly vertical as soil conditions permit below the level of the top of the pipe. The width of the trench shall not be less than 12-inches or more than 24-inches wider than the outside diameter of the pipe barrel. Trench excavation shall be centered on pipe alignment such that a minimum clear space of 6-inches is provided on each side of the pipe. Trench width above the level of the top of the pipe may be as wide as necessary for shoring and sheeting, and for proper installation of the work.

The depth of all trenches shall be as indicated on the drawings. If not otherwise specified, the depth of all trenches shall be sufficient to provide a minimum cover of 24- inches at all locations after final backfilling.

Unless otherwise required by applicable permits to be less, the maximum length of trench that may be left open at any one time shall not exceed 500-feet. No trenches shall be left open unless otherwise permitted in writing by the Project Manager.

1/06 Technical Provisions- TP 3.0 Excavation, Trenching, and Backfilling Page 2

All trench excavation shall comply with Federal and local OSHA regulations for trench safety.

3.03.03 Pavement Cutting

Where it is necessary to remove sections of asphalt pavement, the asphalt shall be sawcut with approved equipment in a neat line 6-inches back from the outside edge of the excavation in order to provide a key when restored, or as approved by BIA roads permit or Tribal Manager.

Where it is necessary to remove sections of concrete pavement, the concrete shall be sawcut to a depth of not less than 2-inches with neat, vertical, true lines in such a manner that the adjoining surface will not be damaged.

3.04 Placement and Compaction of Pipe Embedment and Backfill Material

3.04.01 Pipe Embedment

Pipe embedment is defined as that material required to bring the trench bottom up to grade and that material placed alongside and above pipe to a level of at least 6 inches over the top of the pipe. The pipe embedment area is divided into three zones as defined below.

Bedding: Bedding is that portion of pipe embedment zone beneath the pipe. If the native soil is suitable for bedding the pipe without over- excavation, the bottom of the trench shall be accurately shaped such that one fourth of the pipe circumference is provided with uniform bearing and support for each section of the entire length of the pipe. Imported bedding material shall likewise be placed to provide uniform and adequate longitudinal support under the pipe. Bedding material shall be placed and compacted in lifts not to exceed 6-inches in loose measure.

Haunching: Haunching is that portion of the pipe embedment zone from the bottom of the pipe to the springline of pipe. Haunching material shall be placed and consolidated to provide adequate side support to the pipe while avoiding both vertical and lateral displacement of the pipe from proper alignment.

Initial Backfill: Initial backfill is that portion of the pipe embedment zone from the springline of the pipe to a minimum level of 6-inches over the top of the pipe. Initial backfill material shall be placed and compacted in lifts not to exceed 6 inches in loose measure. Compaction shall be performed in a manner to avoid damage and disturbance of the embedded pipe.

1/06 Technical Provisions- TP 3.0 Excavation, Trenching, and Backfilling Page 3

3.04.02 Compaction

Unless otherwise specified by applicable permits or roadway authority, bedding, haunching, initial backfill, final backfill, and gravel resurfacing shall be compacted to the following percent of the maximum density as determined by ASTM D1557. In-place densities of materials shall be determined by the sand-cone method, ASTM D1556 or by nuclear methods, ASTM D2922.

Percent of Maximum Density Initial Final Location Bedding Haunching Backfill Backfill Roadways and Driveways 95 95 95 95

Unimproved Surfaces, Fields, Etc. 90 90 70 70

3.05 Surface Restoration and Resurfacing

3.05.01 General

The inclusion of a bid item and estimated quantity for asphaltic, concrete, or gravel resurfacing in the Bid Schedule indicates that these items are probable. However, the exclusion of these items from the Bid Schedule does not preclude the possibility that they will be required, merely that they are not anticipated. If unanticipated resurfacing is required, unit prices will be negotiated between the Contractor and the Contracting Officer.

3.05.02 Surface Restoration

After the piping and structures have been installed and all backfilling has been completed, areas which were disturbed shall be brought to true grades. All slopes shall be trimmed and dressed, and all surfaces graded to maintain existing drainage. All streets, alleys, driveways, sidewalks, curbs, or other surfaces which have been disturbed or damaged shall be resurfaced with like materials to a condition equal to or better than the original condition.

All excess excavated material shall be properly disposed of by the Contractor.

3.05.03 Asphaltic Resurfacing

At all locations where asphaltic resurfacing is required, a compacted gravel base, 6inches in depth shall be placed prior to placement of the asphaltic wear course. This base course shall be 95 to 100 percent 3-inch minus gravel with not more than 40 percent passing a

1/06 Technical Provisions- TP 3.0 Excavation, Trenching, and Backfilling Page 4

0.0165 inch square opening (No. 40 sieve). Asphalt shall be plant mixed, with certification that the mix meets the requirements of the applicable roadway authority. Except where greater thickness is required by applicable roadway authority, the minimum thickness of the asphalt shall be the greater of 2-inches or that of the existing adjacent asphalt.

Placement of asphalt shall be in lifts not exceeding 2-inches. Compaction shall be accomplished by pneumatic-tired or steel rollers throughout the spreading operation. Final rolling shall be by steel roller. No surfacing shall be placed while the subgrade is wet, if it is raining, or if the temperature is below 40 degrees F. All edges shall be clean and tack coated prior to placement of the patch.

3.05.04 Gravel Resurfacing

All gravel resurfacing shall be done on a properly compacted subgrade. The gravel shall be spread uniformly and compacted to a minimum thickness of 3-inches. The gravel shall conform to the following gradation requirement.

Sieve Size Percent Passing

Square Opening By Weight 3/4 inch 100

0.250 inch (No. 3 sieve) 50-65

0.0029 inch (No. 200 sieve) 5 max.

3.06 Open Cut Road Crossing for Water and Sewer Service Lines

Open cut water and sewer service line crossings shall be completed at all locations shown on the site plan. The Contractor is responsible to comply with all local, county, Tribal and BIA road crossing provisions whether a permit was issued or not. PVC encasement pipe shall be the diameter shown on the drawings and shall conform to material specification ASTM D1784, Type 1, Grade 1, manufacturing specification ASTM D2241, and the pipe shall be PVC schedule 80. All PVC pipe joints shall be rubber compression ring type with rubber gaskets conforming ASTM F477, and equal to J-M Ring Tite PVC Pressure Rated Pipe, or PWPipe TwinSeal PVC.

Steel encasement pipe and fittings shall be the diameter shown on the drawings and shall be Schedule 40 and shall conform to ASTM A120. The pipe shall be joined by the use of threaded steel couplings

3.07 Bored Type Road Crossing for Water and Sewer Service Lines

1/06 Technical Provisions- TP 3.0 Excavation, Trenching, and Backfilling Page 5

Water service lines crossing roads or rights-of-way which cannot be open cut, and if noted on the site plan, the crossing shall be bored. The Contractor shall bore the crossing by using a pneumatic or hydraulic boring machine such as a Hole Hog, or or other approved boring equipment. Minimum allowable encasement pipe diameter for the crossing shall be of sufficient size to allow the water or sewer service line to be easily slid into position. Casing pipe diameter and material shall be approved by the Project Manager prior to installation.

1/06 Technical Provisions TP 11.0 Individual Septic Tank Page 1

TECHNICAL PROVISION 11.0

INDIVIDUAL SEPTIC TANK

11.01 Scope of Work

material, and performing all operations in connection with the construction of individual septic tanks, including connection to building (house) drains, solid sewer pipe, cleanouts, abandonment of existing septic tanks, fittings, effluent filters, and appurtenances in accordance with these technical provisions and applicable drawings.

11.02 Permits and Approvals

The Government shall secure the applicable site approvals and sewage disposal permits for the work specified herein.

11.03 Location of Facilities

The location of the facilities specified herein shall be as shown on the drawings and/or as staked in the field by the Project Manager. The Contractor shall not change the designated location of these facilities without the prior approval of the Project Manager.

11.04 Inspection of Installation

In addition to the applicable inspection requirements of the Tribe and/or County, the Contractor shall notify the Project Manager at least 2 working days prior to placing final backfill over the septic tank so that the Project Manager may inspect the installation.

11.05 Solid Sewer Pipe

The Contractor shall install a solid smooth pipe from the septic tank to the building (house) drain.

Solid sewer pipe and fittings shall be 4-inch PVC plastic, ASTM 3034, SDR 35, Sewer Service Lines. Installation shall be in accordance with all state and local standards.

11.06 Effluent Filter

The Contractor shall install in the outlet tee of the septic tank an effluent filter cartridge equivalent to Zabel A1800 Residential Septic Tank Effluent Filter. The outlet tee in the septic tank shall be of sufficient length to extend one (1) inch below the bottom of the filter cartridge (See detail drawing).

1/06 Technical Provisions TP 11.0 Individual Septic Tank Page 2

11.07 Septic Tank

11.07.01 Tank

The tank shall be precast, reinforced, watertight concrete as manufactured by an established firm specializing in concrete products conforming to ASTM 6913. Minimum liquid capacity below the outlet level shall be as specified on the drawing(s) and each tank shall have 2 compartments. The walls, floor & top shall have a minimum thickness of 2 ½-inches. Adequate steel reinforcement shall be provided. Each compartment shall be provided with adequate tees, elbows and baffles. The tank shall meet all state and local standards.

11.07.02 Access Riser

Each compartment of the septic tank shall be provided with a watertight access riser with a minimum dimension of 24-inches for inspection and sludge removal. The access riser on the second chamber shall be centered so as to provide access to the effluent filter. Access risers shall meet all state and local standards. Additional access ports, if required by local health codes, shall be installed by the Contractor at no additional expense to the Government. Risers shall be equal to Orenco systems lids and risers.

11.07.03 Septic Tank Installation

The septic tank shall be set in a hole excavated by the Contractor in accordance with all state and local standards.

11.08 Pump Existing Septic Tank

When required by the bid schedule (Attachment B), the Contractor shall pump existing septic tanks by pumping the liquid and solids out of the tank. The septic tank liquid and solids shall be disposed of as required by local health codes. Backfilling pumped liquid to agitate the accumulated solids in the septic tank is not allowed.

11.10 Abandon Existing Septic Tank

The Contractor shall abandon existing septic tanks by pumping out the liquid out of the tank, breaking open the cover of the tank, and backfilling the empty tank with approved borrow material.

Backfilling shall be carefully placed to eliminate voids, and shall be mounted to allow for settlement. The septic tank liquid shall be disposed of as required by local health codes.

1/06 Technical Provisions TP 11.0 Individual Septic Tank Page 3

11.11 Underground Cleanout

Where required and as shown on the plans, the Contractor shall install a two-way underground cleanout on the solid sewer line. The cleanout shall have a threaded plug and be constructed as detailed in the drawings. The cleanout shall be extended so that the square nut on the threaded plug is ½-inch below finished ground level. A concrete pad 18-inches square and 4-inches deep shall be poured around each cleanout at the ground surface. This pad shall be reinforced with welded wire mesh with a minimum 1 1/2-inch concrete cover over mesh. The wire mesh shall be ASTM approved W1.4 (1/8-inch) wire mesh on 6-inch centers.

1/06 Technical Provisions TP 12.0 Individual Lift Station Page 1

TECHNICAL PROVISION 12.0

INDIVIDUAL LIFT STATION

12.01 Scope of Work

The work covered by this section includes the furnishing of all plant, labor, tools, equipment, and materials, and performing all operations in connection with the construction of an individual lift station, including lift station basin, effluent pump, piping, force main, fittings, control panel, electrical controls and alarms, and appurtenances in accordance with these technical provisions and applicable drawings.

12.02 Lift Station

The lift station basin shall be either the second chamber of a septic tank, as shown in the drawings, or a precast, reinforced, watertight concrete basin as manufactured by an established firm specializing in concrete products, and shall conform to ASTM C. The basin shall have a minimum wall thickness of 2½-inches and the concrete shall obtain a minimum 28-day compressive strength of 3,000 psi.

The basin shall be as specified on the drawing(s), including the required minimum volume. The lift station basin shall be provided with a watertight access riser with a minimum dimension of 24-inches for inspection and maintenance. The Access riser shall meet all state and local standards.

An 18-inch square pedestal 4-inches high shall be provided as a base for the pump. The pedestal shall be located as shown on the drawing.

The installation of the lift station basin shall conform to the provisions of TP 11.0 for the installation of the septic tank and meet all state and local standards.

12.03 Effluent Pump

The sewage pump shall be as specified on the drawing(s), 115 volt, single phase submersible effluent pump. The pump shall be capable of passing 3/8-inch solids and pump at least 30 gallons per minute against a total head of 16-feet. Differing site conditions may require a similar pump with minor differences in flow/head characteristics to be provided by the Project Manager. The pump power cord shall be easily detachable from motor housing. Connector shall be sealed to motor housing with rubber O-ring. The pump details shall be as shown on the drawings or equal.

The effluent pump shall be installed within an effluent filter vault equal to ORENCO SYSTEMS Model PFEF 40 or approved equal.

12.04 Electrical Controls and Alarm

The Contractor shall furnish and install a control system compatible with the supplied pump. The controls shall include; circuit breakers for the pump and alarm system, magnetic contactor, mercury level control floats, a high liquid level alarm, running and alarm lights, and a Hand- OffAutomatic selector switch. All wiring shall be in accordance with the National Electrical

1/06 Technical Provisions TP 12.0 Individual Lift Station Page 2

Code and applicable state and local electrical codes. The installation shall be inspected and approved by the State Electrical Inspector.

Electrical service to the lift station shall be either from a new properly sized circuit breaker in the existing circuit breaker panel servicing the home, if space permits, or through a separate subpanel.

Separate circuit breakers are required for both the pump magnetic contactor and for the alarm system. In any case a fused disconnect is required if service entrance panel or subpanel is greater than 50 feet from the lift station and/or not in clear sight of the lift station and shall be located as shown on the drawings or as directed by the Project Manager.

The control panel shall be a NEMA 4X enclosure and shall house the "Hand-Off- Automatic" switch, green "pump on" indicator light, a terminal block for connecting the mercury float level controls, and the alarm system. The green "pump on" light, red alarm light and silence button shall be mounted through the enclosure door.

The magnetic contactor, alarm system, and control panel shall be mounted on outside wall of the home at a location acceptable to the homeowner. As an alternative, and with the approval of the Project Manager, the control panel or alarm panel may be located on a post near the lift station as long as the components are housed in NEMA 4X enclosure.

The pump electrical cable shall be Type UF single conductor cable sized to limit the overall voltage drop from the service entrance to the pump motor to less than 2 percent. In no case, shall wires smaller than 12 gauge be used. The electrical cable and control wires shall be buried at least 18 inches deep. House interior wiring shall be 12 gauge minimum and shall be Type NM or UF cable, while required conduit shall be EMT, PVC, or liquid tight flexible metal. All supports, nails, bolts, straps and screws shall be galvanized. The submersible power cable from the pump and the float cables shall be secured to a hook and secured such that the cables are not allowed to slip from their adjusted height.

The mercury level control switches shall be completely encapsulated in polyurethane foam and equipped with cord weights. The float switch shall be installed at the elevations indicated or as otherwise directed by the Project Manager. The electrical cable housing from the switches to the control panel shall be Type UF 14 gauge copper single conductor cable. Splices shall be made by using mechanical connectors and covering with heat-shrink tubing.

12.05 Control System Functional Requirements

12.05.01 Demand Dosing

The liquid level in the individual lift station is sensed by 3 mercury level control switches suspended at different elevations from the top of the lift station. The first (lowest) mercury level control switch shall be a redundant off switch and shall de-energize the pump should the middle dual action on-off float fail. The middle float shall be dual action and energizes and de-energizes the lift station pump. The third (highest) mercury level control switch energizes the red light and alarm bell indicating a high water level condition.

1/06 Technical Provisions TP 12.0 Individual Lift Station Page 3

During the normal mode of operation, the HAND-OFF-AUTOMATIC switch shall be in the "Automatic" position. As the liquid level in the individual lift station reaches energize level of the middle dual action mercury level control switch, an electrical signal shall be transmitted through the buried electrical cable to the control panel. The controls shall energize the lift station pump and green running light. As the liquid level in the individual lift station drops to the middle de-energize level, an electrical signal shall be transmitted to the control panel which shall de-energize the lift station pump and green running light.

This cycle shall continue to repeat itself. Should the middle dual action on-off float fail, the redundant lowest level float shall de-energize the pump and activate the alarm bell and red alarm light indicating a low level float failure.

If the liquid level in the individual lift station rises to the top mercury level control switch, the red light and alarm bell shall be energized indicating a high liquid level condition.

The alarm shall be silenced by manually pushing the "Alarm Silence" button, however, the red pilot light shall remain energized until the liquid level has fallen below the third mercury level control switch. This high liquid level light and alarm shall operate independently of the position of the pump selector switch.

When the pump selector switch is in the "Hand" position, the mercury level float switches shall be overridden and the lift station pump and green running light shall be energized independently of the liquid level in the lift station. When the pump selector switch is in the "Off" position, there shall be no power provided to the lift station pump and green running light.

12.05.02 Timed Dosing

Timed dosing may control the liquid level in the individual lift station, if specified by the Project Manager and shown on the drawings, with three mercury level control switches.

The third (highest) mercury level control switch serves as a high water level alarm and energizes the red light and alarm bell indicating a pump failure condition. When the pump is operational and dosing overload occurs, the liquid level will reach the second (mid-level) mercury level control switch and the timer shall be overridden, energizing the lift station pump and the green pump running light on the control panel. As the liquid level drops, reaching the first (lowest) mercury level, the control switch overrides the timer and de-energizes the lift station pump and the green running light.

When the liquid level in the individual lift station does rise to the third (highest) mercury level control switch, the alarm shall be silenced by manually pushing the “Alarm Silence” button. However, the red pilot light shall remain energized until the liquid level has fallen below the second mercury level control switch. This high liquid level light and alarm shall operate independently of the position of the pump selector switch.

When the pump selector switch is in the “Hand” position, the timer and mercury level float switches shall be overridden and the lift station pump and green running light shall be energized independently of the liquid level in the lift station. When the pump selector

1/06 Technical Provisions TP 12.0 Individual Lift Station Page 4 switch is in the “Off” position, there shall be no power provided to the lift station pump and green light running.

12.06 Piping

12.06.01 Lift Station Influent

The piping from the septic tank outlet to the lift station inlet shall conform to TP 11.0, solid sewer pipe. The inlet shall include a tee or baffle, as specified. The outlet discharge from the pump shall be Schedule 40 PVC 1120 pipe installed as shown in the drawings and to the approval of the Project Manager. Fittings shall be Schedule 40, ASTM 2466, except for the union, which shall be Schedule 80. The union shall be installed within easy reach from the manhole cover, hand-tight only. The male adapter that screws into the discharge port of the pump shall not be glued in place; standard plumbers’ pipe joint compound shall be used.

12.07 Force Main

The effluent force main pipe from the lift station to the shallow drainfield shall be 1 1/2-inch or 2-inch (as shown on the drawings) PVC 1120, SDR 26, conforming to ASTM 2241. All fittings for the pipe shall be 160 psi PVC with rubber compression ring joints or schedule 40 PVC with solvent welded joints.

The force main pipe shall be laid on grade in a trench at least 12-inches wide. Care shall be taken to bed the pipe in a material that is free of rocks or otherwise unsuitable material. Backfill shall be compacted by hand from the bottom of the trench to a minimum of 6-inches over the top of the pipe for the full width of the trench. A minimum of 18-inches of cover is required over the top of the pipe.

12.08 Submittals

The Contractor shall submit for approval prior to construction product/material information on the sewage lift station pump and controls.

1/06 Technical Provisions TP 12.0 Individual Lift Station Page 5

TECHNICAL PROVISION 15.0

LOW PRESSURE-DOSED MOUND SYSTEM

15.01 Scope of Work

The work covered by this section consists of furnishing all labor, tools, equipment, and materials in connection with the construction and installation of a mound soil absorption system in accordance with applicable technical provisions and drawings.

15.02 Permits and Approvals

The Government shall secure the applicable site approvals and sewage disposal permits for the work specified herein.

15.03 Piping

15.03.01 Transport and Manifold Pipe

The transport and manifold pipes shall be Schedule 40 PVC pipe, PVC 1120, conforming to ASTM 1785, 2-inches in diameter. Fittings shall be Schedule 40, conforming to ASTM 2466.

15.03.02 Distribution Laterals

The 1.25 inch diameter distribution laterals shall be Schedule 40 ASTM 1785 pipe, PVC 1120. Field perforations shall be 3/16-inch diameter spaced as shown in drawings, oriented in the 6 o'clock position, except that the last orifice on each lateral shall be oriented in the 12 o'clock position. Fittings shall be Schedule 40, ASTM 2466. The ends of the laterals shall be fitted with a male adapter and cap, screwed on hand-tight. Teflon tape shall be used.

15.03.03 Observation Pipe

Observation pipes shall be installed at locations shown in the drawings. Observation pipes shall be 4-inch diameter perforated PVC drainfield pipe fitted with a secure screw cap. All but the bottom 1-foot of the pipe shall be wrapped with filter fabric. The downslope observation pipe shall be placed with its bottom on the original ground surface. The upslope observation pipe shall have its bottom placed at the bottom of the gravel bed. Both pipes shall extend at least 6-inches above the mound surface.

15.03.04 Glue

All fittings, except as specified shall be glued in place. Glue shall meet ASTM D2564.

Laterals shall not be glued to the manifold until after the pressure test. Pipe shall be cut square and deburred inside and out. All joints shall be primed before gluing.

1/06 Technical Provisions TP 12.0 Individual Lift Station Page 6

15.04 Mound Construction

15.04.01 Materials

15.04.01.1 Medium Sand Fill

The medium sand fill shall be placed as shown in the drawings. The fill material shall meet the following particle size gradation: (Source: ASTM C-33, Specification for Fine Aggregate)

Effective % Passing

Sieve Particle Size by Weight

3/8 inch 9.50mm 100%

No. 4 4.75mm 95-100%

No. 8 2.36mm 80-100%

No. 16 1.18mm 50-80%

No. 30 0.60mm 25-60%

No. 50 0.30mm 10-30%

No. 100 0.15mm 2-10%

The sand shall be not more than 45% passing any one sieve and retained on the next consecutive sieve of those shown above.

The fineness modulus shall not be less than 2.3 nor more than 3.1. The fineness modulus is defined as the sum of the cumulative percentages retained in the sieve analysis, divided by 100, for the sieve sizes shown above. Each load of fill sand shall be approved by the Project Manager.

15.04.01.2 Gravel Bed

A 10 ft. x 40 ft. gravel bed with a minimum overall depth of 9-inches shall be provided. A minimum of 6-inches of gravel shall be placed below the distribution laterals and a minimum of 2-inches of gravel shall be placed over the laterals. The gravel shall be clean, hard, strong, non-deteriorating stone, free from coal, clay, soft fragments, or other deleterious materials, and may vary in size from ½- inch to 1½-inches, with not more than ten (10) percent fines below the ½-inch size. Gravel shall be considered clean if water poured through it remains clear. Gravel to be used must be approved by Project Manager. The gravel bed must be laid level in the bed cut into the top of the sand fill. The bottom of the bed shall be level within ± ½-inch. The top of the gravel bed shall be covered with filter fabric equal to Typar 3401.

1/06 Technical Provisions TP 12.0 Individual Lift Station Page 7

15.04.01.3 Backfill Material

Backfill material over the gravel bed may be a finer texture soil than the medium sand material. Acceptable backfill materials are medium sand, silt, loam or topsoil.

(Contractor will not be paid extra for use of high quality topsoil as backfill).

15.04.01.4 Topsoil and Seeding

The entire mound shall be covered with an 8-inch layer of topsoil. Seed and fertilizer shall be uniformly applied over the mound area with approved equipment.

Following the sowing and covering, all seeded areas shall be compacted by rolling.

The soil shall be compacted to the extent that the seed is firmly embedded. The rolling shall be done along the contour at right angles to slopes.

Seed and fertilizer mixtures shall conform to the latest guidelines of the local offices of the Soil Conservation Services or Cooperative Extension Services. Seeding shall be permitted only when soil and weather conditions permit.

The final depth of backfill and topsoil combined shall be 18 inches at the center of the bed and 12-inches at the edges of the bed.

15.04.02 Construction

Construction shall only take place when the soil moisture content is sufficiently low to avoid smearing, compacting, and puddling.

15.04.02.1 Equipment

Wheeled tractors shall not be used in the construction of the mound. Only track mounted equipment will be allowed, in order to prevent rutting, localized overloading, and compaction.

15.04.02.2 Construction Procedures

The following procedures shall be followed in the construction of the mound.

Alternate proposed methods must be approved by the Project Manager. The corners of the fill area will be staked out by the Government, together with offset stakes in case the corner stakes are lost. The Government will also provide a benchmark for elevation reference. The construction steps to be followed are listed below.

1. Determine where the pipe from the pumping chamber connects to the distribution system in the fill.

2. Trench and lay the transport pipe from the pumping chamber to the fill. Cut and cap the pipe one foot beneath the ground surface. Lay the pipe below the frost line or sloping back to the pumping chamber so that it drains after dosing. The line shall be installed at a uniform slope without sags or rises.

1/06 Technical Provisions TP 12.0 Individual Lift Station Page 8

Backfill and compact the soil around the pipe to prevent back seepage of effluent along the pipe from the mound area to the lift station. This step must be done before plowing to avoid compaction and disturbance of the surface.

3. Cut trees to ground level, remove excess vegetation by mowing. Prepare the site using a moldboard plow and plowing perpendicular to the slope.

The site should be plowed in a direction so that the plow throws the soil upslope. Use as large a plow as possible to reduce the number of drivenin furrows, which result in the compaction of the subsoil. Chisel plowing may be done if a moldboard plow is not available. Rototilling must not be done.

The important point is that a rough, unsmeared surface should be left in fine textured soils. The fill material will intermingle between the clods of soil, which should improve the infiltration rate into the natural soil by minimizing the layering which occurs.

Immediate construction after plowing is desirable. Avoid rutting the compaction of the plowed area by traffic. If its rains after the plowing is completed, wait until the soil dries out before continuing construction.

4. Reset the corner stakes, if necessary, using the offset reference stakes and locate the bed or trench areas by staking their boundaries.

5. Extend the transport pipe from the pump chamber, previously cut off below ground, to several feet above the ground surface.

6. Place the fill material which has been properly selected around the edge of the plowed area. Keep the wheels of trucks off plowed areas. Minimize traffic on the downslope side of the fill system. Work from the end and upslope sides. This will avoid compacting the soils on the downslope side, which, if compacted, would affect lateral movement of water away from the fill and possibly cause surface seepage at the toe of the fill.

7. Move the fill material into place using a small track type tractor with a blade. Do no use a tractor/backhoe having tires. Always keep a minimum of 6 inches of fill material beneath tracks to prevent compacting of the natural soil.

8. Place the fill material to the required depth, i.e., to the top of the bed. Shape sides to the desired slope.

9. With the blade of the tractor, form the bed. Hand level the bottom of the bed within ± ½-inch.

1/06 Technical Provisions TP 12.0 Individual Lift Station Page 9

10. Place the gravel in the bed to the 6-inch depth. Level the gravel.

11. Place the distribution laterals on the gravel. Connect the manifold to the transport lines from the pump chamber. Lay the laterals fairly level, removing large rises and dips.

12. Pressure test the distribution system for uniformity of flow. All clogged orifices shall be cleared; all soil and other obstructions shall be removed from the laterals.

13. Glue the laterals to the manifold. Orifices shall be oriented in the 12 o'clock position.

14. Place 2-inches of gravel over the laterals to fill the bed.

15. Install the two observation pipes.* One shall be in the downslope portion of the fill with the bottom at the original surface and the top extending above final grade where it can be capped. The other shall be located in the bed extending only from the bottom of the bed to above the final grade.

* This can be done at this point in the installation by digging the hole with an auger, or the observation pipes can be anchored in place after the original surface has been plowed, before the fill material is placed.

16. Place filter fabric over the bed, overlapping the edge of the bed by at lest 6 inches.

17. Place the backfill material over the mount and then the topsoil.

18. Seed the topsoil per 15.10.01.4. Alternatively, the Contractor may sod the mound, if he so desires.

15.05 Drainage Ditch and Culvert

If required, an open channel, trapezoidal drainage ditch shall be constructed as shown in the drawings. The channel shall have a uniform slope with a minimum channel depth of 22-inches.

The channel cross-section shall conform to the drawings and shall be seeded with grass.

If required, a 15-inch diameter, corrugated aluminum, 16-gauge, circular culvert shall be installed as shown in the drawing. The culvert shall be laid at a uniform slope and have a minimum cover of 6-inches. The open channel-culvert transition shall conform to the drawings.

1/06 Technical Provisions TP 12.0 Individual Lift Station Page 10

15.06 Curtain Drain

15.06.01 Materials

The materials required for the construction of a curtain drain (solid sewer pipe, perforated drainfield pipe, gravel, filter fabric, etc.) shall be the same as those specified for the construction of the mound.

15.06.02 Curtain Drain Installation

The Contractor shall excavate to the length, depth and in the direction specified for the curtain drain. All curtain drain trenches shall be as shown on the drawings with a minimum horizontal separation of 8-feet from the mound. The excavation shall be at least 18-inches wide. Drainfield gravel shall extend from 2-inches below the bottom of the perforated pipe to the elevation shown in the drawings for the full trench width. The perforated pipe shall be installed with the holes down. The bottom of the curtain drain trench and the perforated pipe shall be laid at a uniform slope. The top of the gravel shall be covered with a layer of filter fabric. Native soil materials shall be used for the remainder of the backfill.

Solid sewer pipe shall be used to extend the lower end of the curtain drain downslope until it daylights. The outlet shall be covered with drainfield gravel or screened to prevent entry of rodents.

1/06 Technical Provisions TP 30.0 Water Service Connections Page 1

TECHNICAL PROVISION 30.0

WATER SERVICE CONNECTIONS

30.01 Scope of Work

material, and performing all operations in connection with the construction of water service lines, including saddles, corporation stops, curb stops, water meters, coppersetters, meter boxes, fittings and appurtenances; and abandonment of existing wells; all in accordance with these technical provisions and applicable drawings.

30.02 Materials

30.02.01 Polyethylene (PE) Pipe

Polyethylene (PE) pipe shall be IPS size, 200 psi, SDR 7 in conformance with ASTM 2239.

The pipe shall be produced from high density, ultra-high molecular weight PE 3408, NSF approved resin. The pipe shall conform to the latest revision of ASTM 1248 and AWWA C-901; and shall be equal to Driscopipe 5100 Ultra-line or West Flex. The designation, PE 3408, shall be stamped on the pipe.

Fittings and connections for PE pipe shall be made with non-flare compression connections equal to Ford Pack Joint, Mueller Insta-Tite, or McDonald Mac-Pak.

30.02.02 Saddles

Saddles shall be ductile iron, brass, bronze, or stainless steel with I. P. standard tapping and shall have rigid double straps or bale-type bottom connectors with a flattened surface. The saddles shall be equal to Ford brass saddles, Mueller service clamps, or Romac style 202 saddles.

30.02.03 Corporation Stops

Corporation stops shall be bronze alloy with inlet I. P. standard thread and outlet thread compatible with the connecting piping, without the use of special adapters. They shall be equal to Ford or Mueller corporation stops.

30.02.04 Water Meters (or as amended in the Special Provisions)

Water meters shall be of cast bronze construction with inlet strainer magnetic drive and a hermetically sealed register. The meter shall read in gallons with a 6-digit totalizer, and

1/06 Technical Provisions TP 30.0 Water Service Connections Page 2 accurately record flow from 1/4 to 20 gpm and conform to AWWA C-700. The meters shall be equal to Sensus SR Series or Precision Meter PMM.

30.02.05 Coppersetter

Coppersetters shall be all copper or bronze with horizontal inlet and outlet, locking stop at meter inlet, test valve, and adequate brace bars to support the meter in a horizontal position in a rigid manner. The coppersetter shall raise the meter above the normal service line bury depth so as to place the top of the meter and angle valve no less than 6 inches nor more than 10 inches below the top surface of the finished meter box. Tandem coppersetters are required for individual pressure reducing valve installations. The coppersetter shall be sized for 1-inch IPS PE pipe and 5/8” x ¾” water meter, and shall be equal to Ford or McDonald.

30.02.06 Meter Boxes

The coppersetter, angle stop, test valve and meter idler shall be enclosed within a standard sized meter box of wire reinforced concrete or fiber reinforced plastic. All sections of boxes and lids shall be nested or otherwise interlock to prevent lateral movement. Sufficient sections shall be installed to provide a walled enclosure for a minimum depth of 18 inches below the top of the meter. Minimum cover opening dimensions shall be 10 inches x 16 inches, except for tandem coppersetter installations, which require a minimum dimension of 20 inches. Meter boxes shall be equal to Fog Tite concrete meter boxes or Brooks plastic meter boxes.

30.02.07 Individual Pressure Reducing Valves

Individual pressure reducing valves, when required, shall be installed on tandem coppersetters or in the house plumbing and shall be bronze body construction with stainless steel seat ring and strainer. They shall be equal to Watts Series 135 or Mueller Series E- 9300.

30.02.08 Water Service Line Installation

Water service lines and appurtenances shall be installed in accordance with Technical Provision 3.0, Excavation, Trenching, Backfilling, and all state and local standards.

A minimum of 2-feet of cover is required over the top of the water service lines. Actual bury depth shall be as specified by the Project Manager. Service lines shall be cut using a tool or tools specifically designed to leave a smooth, even and square end on the pipe. Cut ends shall be reamed to the full inside diameter of the pipe. Pipe ends to be connected using fittings which seal to the outside surface of the pipe shall be cleaned to a sound, smooth finish before installation. Splices shall be kept to a minimum and shall be made with compression type couplings. No splices shall be made within 10 feet of any sewer line.

1/06 Technical Provisions TP 30.0 Water Service Connections Page 3

All service connections to water mains shall be made using the specified saddles.

Particular care shall be exercised to assure that the main is not damaged by installation of the saddle. The saddle shall be aligned on the water main so that it is at a 45-degree angle above the springline of the pipe. Where required, the Contractor shall reconnect existing water service connections to new water mains using materials specified herein. The Contractor shall also connect the water service line to the existing water service line from the house or facility which is being served, if available. Otherwise this line shall be extended to with 5-feet of the proposed building (house) and the end plugged and the location marked. The Contractor shall provide approximately 10-feet of additional PE pipe and left in the trench of the service line extends only with 5-feet of the house.

Individual pressure reducing valves, where required, shall be installed on tandem coppersetters housed in a appropriately sized meter box, or in the house plumbing as shown on the drawing or as determined by the COR.

Individual double check valve assemblies, where required, shall be housed in a separate (from the water meter) appropriately sized meter box, or in the house plumbing as shown on the drawing or as determined by the COR.

30.02.09 Freezeless Yard Hydrant

Freezeless yard hydrants shall be installed only at locations specifically designated by the Project Manager.

Hydrants shall be designed for 3-foot bury, with no stuffing box, adjustable flow, ¾-inch brass hose thread on outlet. Handles shall have locking hasp. The Contractor shall provide a lock and two keys for each yard hydrant.

Install with spout 36-inches above ground surface. Place 4-cubic feet of clean coarse gravel around base of hydrant to provide for drainage. Compact around hydrant in one foot lifts to at least the density of surrounding earth. Locate as directed by the Project Manager. A separate shut-off valve is not required.

30.02.10 Individual Double Check Valve Assembly

Individual double check valve assemblies shall be bronze body construction with replaceable seats and ball valve test cocks. They shall be equal to Watts Series 709.

30.02.11 Curb Stop and Appurtenances

Curb stops shall be bronze alloy or cast brass, Minneapolis pattern with conductive compressions for IPS, PE plastic pipe. The curb boxes shall be case iron Minneapolis pattern, length as appropriate, with compatible stationary rod and lid. Two combination

1/06 Technical Provisions TP 30.0 Water Service Connections Page 4 keys and two pentagon wrenches shall be supplied and included in the bid price for the curb stops and boxes. They shall be suitable for the curb stops and boxes furnished.

30.03 Encasement Pipe for Water Service Line

30.03.01 Encasement Pipe Material

PVC encasement pipe shall be the diameter shown on the drawings and shall conform to material specification ASTM D1784, Type 1, Grade 1, manufacturing specification ASTM D2241, and the pipe shall be PVC schedule 80. All PVC pipe joints shall be rubber compression ring type with rubber gaskets conforming ASTM F477, and equal to J-M Ring Tite PVC Pressure Rated Pipe, or PWPipe TwinSeal PVC.

Steel encasement pipe and fittings shall be the diameter shown on the drawings and shall be Schedule 40 and shall conform to ASTM A120. The pipe shall be joined by the use of threaded steel couplings.

30.03.02 Encasement Installation

Where encasement pipe is required and the open cut method of installation is allowed, the Contractor shall install encasement pipe in accordance with Technical Provision 3.0, Excavation, Trenching, and Backfilling.

Water service lines crossing roads or rights-of-way which cannot be open cut shall be bored.

The Contractor shall bore the crossing by using a pneumatic or hydraulic boring machine such as a Hole Hog, or shall use water jetting equipment. Minimum allowable encasement pipe diameter for the crossing shall be of sufficient size to allow the water service line to be easily slid into position.

30.04 Flushing and Testing

Prior to installation of the meter and connection to the building or house, the entire water service line and appurtenances shall be flushed. Testing shall be accomplished by applying normal main pressure to the exposed water service line and inspecting all joints for leaks. All leaks shall be repaired. If a new water main is concurrently installed with the water service lines, then the service lines shall be tested concurrently with the main line with all joints exposed for leaks. No additional allowable leakage shall be allowed for the PE service lines.

30.05 Disinfection

Disinfection of the water service line shall be performed by the Contractor after the system is complete using liquid chlorine only with a minimum concentration of 50ppm. Use of HTH or other granular compounds will not be allowed. The chlorine solution will remain in the water service line for a minimum of ½ hour. The water service line will then flushed until chlorine

1/06 Technical Provisions TP 30.0 Water Service Connections Page 5 residual is eliminated. Care shall be taken by the Contractor to prevent any accidental water use by the homeowner during disinfecting. After the chlorine residual has been completely eliminated, the contractor shall take water samples from the house for bacteriological examination by an EPA certified laboratory. Sampling methods shall be in accordance with recommendations of the laboratory. Testing shall be done at the Contractor's expense. If unsafe bacteriological results are received, the Contractor shall re-chlorinate and flush as necessary until safe bacteriological test are obtained. Any re-chlorination and testing needed will be at the Contractor's expense.

30.06 Abandonment of Existing Cased Well

If required by price schedule (Attachment B), the Contractor shall abandon the existing well at the location shown on the drawings, by the regulations set forth in the Washington State Department of Ecology's Minimum Standards for Construction and Maintenance of Wells, Chapter 173 WAC, WAC 173-160-415, abandonment of wells, Paragraphs (1), (2), and (3). If the site is in Oregon State, the respective Oregon Standards shall apply.

Specifically, the manner in which this shall be done is as follows:

The casing shall be cut below ground level, and perforated from the bottom to within 5-feet of the land surface and pressure grouted. Perforations shall be at least four (4) equidistant cuts per row, and one (1) row per foot. Each cut shall be at least on and 1½-inches long.

Piping of sealing materials directly to the point of application or placement by means of a dump bailer is recommended. If cement grout, neat cement, or puddled clay is used as a sealing material below the static water level in a well, it shall be placed from the bottom up by methods that avoid segregation or dilution of the material. When used to place grout, the discharge end of the tremie tube shall be submerged in the grout to avoid breaking the seal while filling the annular space.

The existing water service line from the well shall be abandoned in place, and power to the pressure system shall be permanently disconnected per local and/or NEC codes.

EXCAVATION, TRENCHING, AND BACKFILLING
3.01 Scope of Work
3.02 Protection of Excavation
3.03 Excavation
3.03.02 Trench Excavation
3.03.03 Pavement Cutting
3.04 Placement and Compaction of Pipe Embedment and Backfill Material
3.04.01 Pipe Embedment
3.04.02 Compaction
Percent of Maximum Density
3.05 Surface Restoration and Resurfacing
3.05.02 Surface Restoration
3.05.03 Asphaltic Resurfacing
3.05.04 Gravel Resurfacing
3.06 Open Cut Road Crossing for Water and Sewer Service Lines
3.07 Bored Type Road Crossing for Water and Sewer Service Lines
INDIVIDUAL SEPTIC TANK
11.01 Scope of Work
11.02 Permits and Approvals
11.03 Location of Facilities
11.04 Inspection of Installation
11.05 Solid Sewer Pipe
11.06 Effluent Filter
11.07 Septic Tank
11.07.02 Access Riser
11.07.03 Septic Tank Installation
11.08 Pump Existing Septic Tank
11.10 Abandon Existing Septic Tank
11.11 Underground Cleanout
12.01 Scope of Work
12.02 Lift Station
12.03 Effluent Pump
12.04 Electrical Controls and Alarm
12.05 Control System Functional Requirements
12.05.01 Demand Dosing
12.05.02 Timed Dosing
12.06 Piping
12.06.01 Lift Station Influent
12.07 Force Main
12.08 Submittals
15.01 Scope of Work
15.02 Permits and Approvals
15.03 Piping
15.03.01 Transport and Manifold Pipe
15.03.02 Distribution Laterals
15.03.03 Observation Pipe
15.04 Mound Construction
15.04.01.1 Medium Sand Fill
15.04.01.3 Backfill Material
15.04.01.4 Topsoil and Seeding
15.04.02 Construction
15.04.02.2 Construction Procedures
15.05 Drainage Ditch and Culvert
15.06 Curtain Drain
15.06.01 Materials
15.06.02 Curtain Drain Installation
WATER SERVICE CONNECTIONS
30.01 Scope of Work
30.02 Materials
30.02.01 Polyethylene (PE) Pipe
30.02.03 Corporation Stops
30.02.05 Coppersetter
30.02.06 Meter Boxes
30.02.07 Individual Pressure Reducing Valves
30.02.08 Water Service Line Installation