6-Addendum 1 - additional scope Bingham High Video Wall 09-03-26.docx
DOCX document 15 KB Posted
- Attached to
- IFB - Video Wall for Bingham High School
- Solicitation number
- 27CA01
- Issued by
- Salt Lake County, Utah
About this file
This is an Addendum to the Invitation for Bid (IFB) for a Video Wall installation at Bingham High School issued by the Jordan School District in Utah. The addendum outlines additional scope of work that was covered during the prebid walk and clarifies the responsibilities of both the electrical contractor and video wall contractor. The electrical contractor is required to provide 1-inch painted EMT conduit with three circuits featuring dedicated neutrals of #10 wire from the AV equipment room to the new video wall location, install all necessary labor, electrical parts, and equipment to power the video wall, and supply 1-inch painted EMT conduit for fiber routing from the AV rack fiber junction box to the new video wall location. The contractor must also install 12-inch by 12-inch junction boxes at each run section exceeding 180 degrees of bend, install pull string in the conduit, and protect the gym floor with plywood under lifts. All conduits and junction boxes must match existing ceiling and wall paint.
The video wall contractor is responsible for providing and installing a video wall controller with the new system or verifying that the existing controller has the necessary outputs to operate a second video wall. The contractor must provide all connections, programming, equipment, and labor to fully integrate the new video wall with the existing system and create mirrored imaging between the new and existing video walls. Floor protection with plywood under lifts is also required for video wall installation work. The project will be awarded to the lowest responsive and responsible bidder in accordance with Utah Code Annotated Chapter 63G-6a, and the awarded contractor will receive a Purchase Order from the JSD Purchasing Department before proceeding.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Update to Additional Scope of Work Covered At Prebid walk for Bingham High Video Wall Video wall contractor to hire electrical contractor to provide the following
· Provide ¾ inch painted EMT conduit with 3 circuits with dedicated neutrals of #10 wire to new video wall location from AV equipment room. Provide and install all labor, electrical parts and equipment to provide necessary power for new video wall.
· Provide 1-inch painted EMT conduit for fiber from AV rack Fiber Junction box next to existing video wall to new video wall location. Provide a 12-inch by 12-inch junction box for each section of run that exceeds 180 degrees of bend and at the new video wall location. Install pull string in one inch conduit. Video wall contractor will pull the fiber. Daktronics will provide fiber and terminate it.
· Conduits and junction boxes will need to match existing paint on ceilings and walls.
· Contractor will need protect gym floor with plywood under lifts.
Video Wall Contractor
· Video wall contractor will need to provide and install video wall controller with new video wall or verify existing video wall controller has necessary outputs to run second video wall. Contractor will provide connection and programming necessary to mirror image between new video wall and old video wall.
· Video wall contractor will provide all terminations, programming, equipment and labor to fully intergrade new video wall with existing system.
· Contractor will need protect gym floor with plywood under lifts.