- Argonne Site Access Management Solution (SAMS)
- Solicitation number
- 5-P124-P-00107-00
- Issued by
-
Department of Energy Office of Science
About this file
This document is an Addendum No. 1 to a Request for Proposal (RFP) for Argonne National Laboratory's Site Access Management Solution (SAMS). The addendum extends the proposal due date to April 18, 2025, at 5:00 PM local time and provides detailed clarifications to vendor questions. Key requirements include developing a comprehensive site access management system to replace existing visitor management and badging systems, with specifications for processing approximately 3,000 user passes, 300 approvers, and 10 power users.
The solution must support credential issuance with 2D and 3D barcodes, ISO7816 and ISO14443A contactless cards, integration with DSX and Lenel OnGuard access control systems, and compatibility with Entrust Sigma DS3 and Datacard SD260/SD360 printers. Additional critical capabilities include PIV card authentication (primarily on Windows PCs), Active Directory SSO, custom workflow modifications, liability waiver tracking, and connection to Workday HR systems. The project has a targeted deployment timeline from June to December 2025, with the system needing to meet Department of Energy order requirements and laboratory-specific operational needs.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
John M Patton Procurement Specialist 2 Financial Management and Procurement Services Procurement Department
Argonne National Laboratory
9700 South Cass Avenue, Bldg. 201
Lemont, IL 60439
(630)252-6356 jpatton@anl.gov
April 8, 2025
TO ALL OFFERORS:
Subject:
Argonne Site Access Management Solution Request for FORMDROPDOWN No. 5-P124-P-00107-00 Addendum No. 1 Attached herewith for your information and use in preparing your proposal for the subject project is one (1) copy of Addendum No. 1.
Kindly acknowledge receipt of this Addendum by signing and returning one (1) copy of this letter.
Please email receipt to jpatton@anl.gov.
Sincerely, John M Patton Procurement Specialist 2 Procurement Department
Receipt Acknowledged:
Company:
By:
cc:
File
CF
Addendum No. 1
TO
REQUEST FOR PROPOSAL (RFP) 5-P124-P-00107-00
FOR
Argonne National Laboratory
BLDG. 201 OCF
9700 S. Cass Ave.
Lemont, IL 60439
April 8, 2025 This addendum is being issued to modify the subject RFP as follows:
I. Proposal Due Date
The proposal due date has been extended to 5:00 P.M., local prevailing time, Friday, April 18, 2025.
II. Clarifications and Vendor Questions
| # |
| RFP Document |
| Questions |
| Answers |
| 1 |
| RFP Proposal Instructions (Enclosure #1) |
PG. 3 & 4
| (Part I - Technical Proposal/Part II - Business/Management Proposal) - do either of these Parts have a page limit? |
| There is no page limit for either Part. |
| 2 |
| SOW(Enclosure 2B) |
PG 5 & 6 (Processing Site Access Visit Request)
| The SOW requires a "Stop-Order" list for denying access based on multiple criteria. Argonne previously described potential categories (Safety Violation, Termination, Threat against Person, Threat against Property). Will Argonne define stop-order threat levels, or should the system provide configurable classifications and risk scoring? |
| Argonne needs to be able to enter people to a Stop Order List. There is no other scoring or matrix that the supplier needs to be concerned. |
| 3 |
| SOW(Enclosure 2B) |
PG 7 (Deliverables)
| Can Argonne clarify the factors determining the June-December 2025 go-live timeline? Are there internal deadlines, operational dependencies, or external requirements driving this timeframe? |
| Argonne has internal needs to have SAMS operation by dates listed in RFP. |
| 4 |
| SOW(Enclosure 2B) |
PG 7 (Deliverables)
| Are there any critical system end-of-life dates, support expirations, or regulatory requirements influencing the 6 mo. deployment schedule? |
| Same as above. |
| 5 |
| SOW(Enclosure 2B) |
General
| How many Argonne employees, across all relevant user roles, will require licensed access and be active users of SAMS? |
| 3000 Users that Create/Request Passes |
300 Approvers
10 Power Users
| 6 |
| SOW(Enclosure 2B) |
PG 8 (LSSO Badging Application)
| What is the expected number and variety of credential templates needed at launch and over time across visitor types and LSSO? How detailed should these templates be to align with Argonne's operational needs? |
| Under 20. Must include (but not inclusive) picture, name, badge number, bar code, expiration date, employee type, citizenship status. |
| 7 |
| SOW —General Capabilities #1 |
| Is reading/harvesting/authenticating PIV cards expected from a browser on windows PC's, Android devices and Apple devices? (Currently there is no known solution to reading/harvesting/authenticating a PIV card on a browser without bridging software to a card reader. |
| Reading/harvesting/authenticating PIV cards is expected only from Windows PC’s. |
| 8 |
| SOW —General Capabilities #2 |
| Is AD SSO / SAML2 expected on Android and Apple devices or is AD SSO / SAML2 only expected on Windows PC's? |
| BIS question |
| 9 |
| SOW —General Capabilities #7 |
| Which parts of the solution should allow custom workflows and forms by a power user without vendor assistance? |
| The 4 other locations in this RFP that indicate they must be modifiable without vendor assistance. Please also detail other locations within your solution that will have this capability. |
| 10 |
| SOW —General Capabilities #13 |
| Is this capability expected immediately or as a possible future enhancement? If immediately what is the name of the system that contains the status of Liability Waiver completion and Safety orientation completion? |
| This capability is expected immediately. The Safety Orientation completion data is stored in CSV. Liability waivers can be completed within this system or in Workday. |
| 11 |
| SOW —General Capabilities #14 |
| What type of credentials are expected to be issued? Example PIV-I card or paper visitor pass with a 3D bar code. |
| We expect to issue credentials with 2D and 3D barcodes along with ISO7816 and ISO14443A contactless cards. |
| 12 |
| SOW —General Capabilities #14 |
| What PACS are required to have issued credentials downloaded into? DSX is referenced. Are there any others? |
| DSX and Lenel OnGuard 8.3. |
| 13 |
| SOW —General Capabilities #15 |
| Is this capability expected immediately or as a possible future enhancement? |
| This capability is expected immediately. |
| 14 |
| SOW —General Capabilities #16 |
| Should our response and price include kiosks? If so how many? |
| Kiosks can be included as an option. |
| 15 |
| SOW—Federal order compliance #2 |
| Is it acceptable to use the ISO 7816 Contact interface to get the full information off the PIV instead of the limited information available on the ISO 14443 contactless interface? |
| Yes. |
| 16 |
| SOW —Processing Site Access Visit Request #1 |
| Is this capability expected immediately or as a possible future enhancement? |
| The capability is expected immediately and must be modifiable to accommodate a forthcoming registration system. |
| 17 |
| SOW —Processing Site Access Visit Request #4 |
| Are these notification email only? |
| Notifications must be distributed by email at a minimum. As an option, SMS notifications may be considered valuable. |
| 18 |
| SOW —Processing Site Access Visit Request #9 |
| Are there existing kiosks or kiosks required as part of our response and price? |
| There are existing kiosks comprised of Dell MFF PC’s, touchscreen monitors, and Dymo label writers. Replacement kiosks can be included as an option. |
| 19 |
| SOW —Processing Site Access Visit Request #13 |
| Does "end user" refer to the visitor or an Argonne employee/contractor? |
| End user refers to an Argonne employee or contractor. The visitor themself does not need to access their own history. |
| 20 |
| SOW —Processing Site Access Visit Request #16 |
| Does the system have to connect to outside system or just have additional approver log on to the system. |
| Yes, the system must connect with an ANL-designed system (FAVOR) that is based on SQL databases. |
| 21 |
| SOW —Issuing Site Access to Visitors #1 |
| What the make and model of printers being used? |
| Entrust Sigma DS3 and Datacard SD260/SD360. |
| 22 |
| SOW —Issuing Site Access to Visitors #1 |
| Does the printer have a inline ISO 7816 encoding module? If no what has to be done to reconcile the printed data with the encoded data? |
| No, printers do not have inline ISO7816 encoding. A supplemental encoding device can be included within this project. |
| 23 |
| SOW —Issuing Site Access to Visitors #5 |
| Should our response/price include driver’s license / state id card / passport scanning hardware? If so how many? |
| Yes. We have 8 badge issuance stations, and would like that each station be able to process walk-up visitors. |
| 24 |
| SOW —Issuing Site Access to Visitors #9 |
| Can the government provide more details on the Xpress Entry Database? Manufacturer? Connection interface? |
| ExpressEntry is a software and hardware solution provided by Telaeris, Inc. It uses a SQL database. |
| 25 |
| SOW —Local Site Specific Only (LSSO) Badging Application #1 |
| Will it be the vendor's reasonability to connect to HRS/Workday? Is the solution SAS or on-prem solution and what is the version? |
| Yes, it is the vendor's responsibility to connect to HRS/Workday where needed. ANL's Workday installation is SaaS. |
| 26 |
| SOW —Local Site Specific Only (LSSO) Badging Application #1 |
| Will the vendor be responsible for upgrading the connection if Workday is updated? |
| Vendor will be responsible for upgrading connections they implement to an equivalent EOL or no longer supported software system for as long as a support agreement is active. |
U. S. Department of Energy laboratory managed by UChicago Argonne, LLC