512A5-23-311_DRAWINGSPart-4.pdf

PDF 16 MB Posted

Attached to
P400--512A5-23-311 - Demolish Building 9H
Solicitation number
36C24525B0005
Issued by

About this file

These architectural and telecommunications demolition and renovation drawings detail a comprehensive project to demolish Building 9H and relocate its telecommunications infrastructure at the Perry Point VA Medical Center. The project involves complete demolition of Building 9H, a 54,500 square foot structure built in 1924, including hazardous material abatement for asbestos, lead-based paint, PCBs, mercury, and other materials. Key technical requirements include relocating the central campus fiber-optic network distribution hub to Building 361, installing new data racks, UPS systems, electrical power supplies, and fiber-optic/ethernet patch panels, and establishing two redundant 12-strand single-mode optical fiber cable runs to multiple campus buildings.

The demolition and renovation work encompasses multiple buildings, including Buildings 9H, 344, 361, 314C, and connection corridors, with extensive telecommunications infrastructure modifications. The project requires comprehensive utility relocations, emergency power feed reassignments, and installation of new telecommunications pathways and distribution systems. The contractor must comply with VA and VA Office of Information Technology (OIT) standards, perform extensive testing and commissioning of new communication systems, and ensure minimal disruption to campus operations. The total project duration is 400 calendar days, with a planned Notice to Proceed approximately 30 days after contract award, and includes strict requirements for safety, environmental management, waste disposal, and compliance with federal, state, and local regulations.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UP

DF

DF DF DF DF DF DF DF DF DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

ex ex ex

TO DUCTBANK

exex exex

CRAW

SPACE

CRAW

SPACE

ELEVATOR

MECH RM

ELEVATOR LOBBY

ELECTRICAL RM

MECH

1 2 3

OF

D

DF

exex

82H-TD001

82H

BUILDING 82H - BASEMENT

AND FIRST FLOOR

TELECOMMUNICATIONS DEMOLITION PLANS

REWKAP/REW

20714

PHARIS

KEITH A.

L I C E N S E D

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

PERRY POINT VA

MEDICAL CENTER

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions: Date:

100% BID DOCUMENTS DEMOLISH BUILDING 9H

512A5-23-311

05-NOV-2024

VA MARYLAND HEALTHCARE SYSTEM

(502) 890-2210 * WESTPOINTENGINEERS.COM

1941 BISHOP LANE, STE. 400 * LOUISVILLE, KY 40218

PERRY POINT VAMC - PERRY POINT, MD

364H

27H 3H

2H

6H

15H

1H

13H

14H

18H

4H

5H

19H 23H366 80H

11H

9H

314C 314B

314A

17H

82H

22H

20H

CC

CC

NORTH

KEY PLAN

NOT TO SCALE

1 1/05/2024

A. COORDINATE WITH ANY CURRENT PERRY POINT EHRM PROJECT(S) TO AVOID POSSIBLE REDUNDANCIES.

B. ALL NEW FIBER WORK SHALL BE INSTALLED, TEST AND IN COMPLETE WORKING ORDER PRIOR TO THE DISCONNECTION AND/OR REMOVAL OF ANY AND ALL EXISTING FIBER AND

COPPER BACK BONE.

C. REFER TO GENERAL NOTES, SYMBOLS LEGEND, ABBREVIATIONS, ETC. ON SHEET TG001.

D. REFER TO SHEET SERIES "TSD01-", "CC-TD01-", AND SHEET TJ101 FOR ADDITIONAL INFORMATION.

E. COORDINATE ALL DEMOLITION AND RELOCATION WORK WITH EXISTING CONDITIONS, ALL TRADES AND THEIR DOCUMENTS, VA COR, VA OIT STANDARDS, VA VENDORS, AND ALL NEW

WORK. PROVIDE ALL LABOR AND MATERIAL WHERE REQUIRED.

F. ALL DEVICES ARE NOT INDICATED ON DRAWINGS, DEVICE INDICATED ON DRAWINGS ARE FOR ADDITIONAL CLARIFICATION. FIELD VERIFY WITH EXISTING CONDITIONS.

G. THE LOCATION OF ALL ELECTRICAL DISTRIBUTION EQUIPMENT, DEVICES, TELECOMMUNICATIONS EQUIPMENT, CIRCUITS, FEEDERS, CABLE MANAGEMENT SYSTEMS, CABLING, TERMINATIONS, ETC., AS INDICATED ON THIS DRAWING WERE TAKEN FROM VARIOUS SOURCES. THE INFORMATION IS DIAGRAMMATIC ONLY AND IS SUBJECT TO VARIATION FROM EXISTING CONDITIONS. IN FACT, CERTAIN EXISTING CONDITIONS MAY NOT BE INDICATED AT ALL. CONTRACTORS PROPOSING TO DO ANY PART OF THE WORK INDICATED HEREIN OR AS DEFINED IN THE SCOPE OF WORK SHALL REVIEW THE COMPLETE SET OF CONTRACT DOCUMENTS, VISIT THE SITE AND DETERMINE TO HIS/HER SATISFACTION THAT HE/SHE

WILL BE ABLE TO COMPLETE ALL WORK REQUIRED FOR THE BID AMOUNT PROPOSED.

H. PROTECT AND MAINTAIN EXISTING SYSTEMS SERVICE THAT ARE TO REMAIN AND EXISTING SERVICES BEING REMOVED UNTIL THE NEW OPTICAL FIBER SYSTEM IS FULLY OPERATIONAL AND HAS BEEN COMMISSIONED. ALL SERVICES SHALL BE KEPT OPERATIONAL AT ALL TIMES DURING ALL PHASES OF CONSTRUCTION. ALL PROTECTION MEASURES SHALL BE TAKEN TO PROTECT AND MAINTAIN THE NEW OPTICAL FIBER SYSTEM AT ALL TIMES.

I. CONDUIT ROUTES, FIBER RUNS/COUNTS/LOCATIONS ARE DIAGRAMMATIC IN NATURE. COORDINATE WILL ALL TRADES AND VERIFY EXACT LOCATION IN FIELD PRIOR TO

INSTALLATION. VERIFY IN FIELD.

J. ALL NECESSARY OUTAGES OF ANY UTILITY SERVICE OR ANY EXISTING TECHNOLOGY AND SECURITY SYSTEM SHALL BE SCHEDULED 14 DAYS IN ADVANCE WITH THE OWNER.

K. PROTECT ALL NEW AND EXISTING WORK AGAINST DAMAGE.

L. CONDUIT/INNERDUCT ENDS SHALL BE SEALED. PROVIDE FIRE PROTECTION FILL FOR ALL EMPTY AND REWORKED DUCTS ON BOTH ENDS. PROVIDE TEMPORARY FIRE PROTECTION

FILL UNTIL CABLING IS INSTALLED AND COMPLETED.

M. THE CONTRACTOR SHALL MAINTAIN THE CONTINUITY OF EXISTING CIRCUITS THAT CONTAIN DEVICES OR EQUIPMENT THAT ARE TO REMAIN. WHERE DEMOLITION/RELOCATION OF

DEVICES AND EQUIPMENT IS INDICATED, THE CONTRACTOR SHALL ENSURE THAT OTHER DEVICES OR EQUIPMENT THAT ARE CONNECTED TO THE SAME CIRCUIT, WHETHER

"UPSTREAM" OR "DOWNSTREAM", SHALL REMAIN OPERATIONAL.

N. DASHED LINES INDICATE ITEMS TO BE REMOVED, U.N.O.

O. COORDINATE WITH CAMPUS POLICE AND IT DEPARTMENT ALL WORK BEING PERFORMED ON ALL DEVICES ASSOCIATED WITH THE SECURITY SYSTEM. PROVIDE A WRITTEN NOTICE

WITHIN A MINIMUM OF TWO BUSINESS DAYS OF PRIOR OF ANY WORK BEING PERFORMED ON OR THAT EFFECTS THE SECURITY SYSTEM. CLARIFY THE WORK BEING DONE AND GET

APPROVAL FROM CAMPUS POLICE ON ACTIONS TAKEN TO SECURE ALL AREAS EFFECTED.

P. DURING THE DEMOLITION AND REMOVAL OF INFRASTRUCTURE CONNECTED TO BUILDING 9H AND OTHER SIMILARLY AGED BUILDINGS ON CAMPUS, AVOID ACCIDENTAL DISTURBANCE OF STRUCTURES WHICH MAY CONTAIN HAZARDOUS MATERIALS. ASBESTOS CONTAINING MATERIALS AND LEAD BASED PAINT ARE LOCATED THROUGHOUT THE PROJECT. REFER TO SPECIFICATIONS 02 82 13.41 ASBESTOS ABATEMENT AND 02 83 33.13 LEAD-BASED PAINT REMOVAL AND DISPOSAL FOR AREAS BEING DISTURBANCE. REFER TO “ASBESTOS CONTAINING MATERIAL NOTES”, “LEAD BASED NOTES”, AND “OTHER IDENTIFIED HAZARDOUS MATERIALS NOTES” ON “HAZARDOUS MATERIALS” DRAWINGS

“9H-HA” SERIES.

Q. CONTRACTOR SHALL TAKE GREAT CARE IN THE REMOVING AND REPLACING CEILING TILES WHERE REQUIRED DURING RENOVATION AND DEMOLITION. WHERE TILES ARE DAMAGE, CONTRACTOR SHALL REPLACE WITH NEW OR LIKE NEW TO MATCH EXISTING AREAS IN KIND.

R. COORDINATE WITH OWNER'S FIRE ALARM SYSTEM'S VENDOR, FIRE CHIEF AND VA COR TO REWORK AND RELOCATE EXISTING FIRE ALARM SYSTEM DEVICES WHERE REQUIRED PER, ALL LOCAL, STATE AND NATIONAL CODES.

1. REFER TO ENLARGE PLANS ("TN101-" SERIES) FOR NEW WORK.

2. PROTECT AND MAINTAIN EXISTING SYSTEMS SERVICE THAT ARE TO REMAIN AND EXISTING SERVICES BEING REMOVED UNTIL THE NEW OPTICAL FIBER SYSTEM IS FULLY

OPERATIONAL AND HAS BEEN COMMISSIONED. ALL SERVICES SHALL BE KEPT OPERATIONAL AT ALL TIMES DURING ALL PHASES OF CONSTRUCTION. ALL PROTECTION MEASURES SHALL BE TAKEN TO PROTECT AND MAINTAIN THE NEW OPTICAL FIBER SYSTEM AT ALL TIMES.

3. REMOVE EXISTING OPTICAL FIBER AND ASSOCIATED WIRE MANAGEMENT SYSTEMS FOR EXISTING OPTICAL FIBER SYSTEMS THAT ARE TO BE REMOVE UNDER THIS CONTRACT.

REFER TO SHEETS TG001, AND TJ101. RETAIN EXISTING MANAGEMENT SYSTEMS CONTAINING CABLING THAT IS TO REMAIN.

4. REMOVE EXISTING OPTICAL FIBER AND ASSOCIATED WIRE MANAGEMENT SYSTEMS FOR EXISTING OPTICAL FIBER SYSTEMS TO EXISTING PATCH PANEL LOCATIONS ON OTHER FLOOR(S) THAT ARE ASSOCIATED WITH THE EXISTING OPTICAL FIBER SYSTEM PASSING THRU BUILDING 9H AND ARE TO BE REMOVE UNDER THIS CONTRACT. REFER TO SHEETS TG001, AND TJ101. RETAIN EXISTING MANAGEMENT SYSTEMS CONTAINING CABLING THAT IS TO REMAIN.

5. REMOVE EXISTING COPPER CABLING CONNECTED THROUGH BUILDING "9H". WHERE REQUIRED REMOVE BACK TO NEAREST PUNCHDOWN LOCATION THAT IS TO REMAIN, COORDINATE WITH VA PROJECT COR. PROVIDE ALL LABELING, LABOR, AND MATERIALS TO TERMINATE IN A FINISHED AND WORKMANLIKE MANNER.

ALL DEVICE MAY NOT APPLY TO THIS SHEET AND SOME MAY NOT BE SHOWN: REFER TO OTHER PLANS FOR ADDITIONAL INFORMATION

SYMBOL DESCRIPTION

KEYNOTE TAG: REFER TO SCHEDULES, DETAILS, AND PLANS FOR ADDITIONAL INFORMATION

EXISTING CABLE TRAY SYSTEM.

EXISTING CONDUIT SLEEVE. FIRESTOP PER ALL CODE AND BICSI REQUIREMENTS

-EF- EXISTING FIBER TO REMAIN: ALL PROTECTION MEASURES SHALL BE TAKEN TO PROTECT ALL EXISTING OPTICAL FIBER SYSTEM AT ALL TIMES.

-DF- DEMOLITION OF EXISTING FIBER ROUTED IN BUILDINGS AND THROUGH CONNECTION CORRIDOR PATHS: REMOVE EXISTING FIBER AS INDICATED. REFER TO RENOVATION

FLOOR PLANS. UNO.

OPTICAL FIBER DISTRIBUTION WALL BOX

OPTICAL FIBER WALL BOX

ex or EX INDICATES EXISTING TO REMAIN ex

OFD

OFB

1/8" = 1'-0"

NORTH

PLAN

1/8" = 1'-0"

NORTH

PLAN

NF

NF NF NF NF NF NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

ex ex ex

IN EXISTING DUCTBANK,

REFER TO SITE PLAN,

SHEET "TSN01-A".

4 52 3

4 52 3

(2) 4" CONDUITS, EACH WITH:

(1) 12SM IN A 1" INNERDUCT.45 23

(2) 4" CONDUITS, EACH WITH:

(1) 12SM IN A 1" INNERDUCT.

OFJ

exex

NF NF NF NF NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

OF

J

OF

J

OF

J

"A SIDE"

"B SIDE"

"A SIDE"

"B SIDE" "A SIDE"

"A SIDE" "B SIDE"UP

UP exex

CRAW

SPACE

CRAW

SPACE

ELEVATOR

MECH RM

ELEVATOR LOBBY

ELECTRICAL RM

MECH

E1

TN101-A

NF

exex

82H-TN001

82H

BUILDING 82H - BASEMENT

AND FIRST FLOOR

TELECOMMUNICATIONS RENOVATION PLANS

REWKAP/REW

20714

PHARIS

KEITH A.

L I C E N S E D

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

PERRY POINT VA

MEDICAL CENTER

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions: Date:

100% BID DOCUMENTS DEMOLISH BUILDING 9H

512A5-23-311

05-NOV-2024

VA MARYLAND HEALTHCARE SYSTEM

(502) 890-2210 * WESTPOINTENGINEERS.COM

1941 BISHOP LANE, STE. 400 * LOUISVILLE, KY 40218

PERRY POINT VAMC - PERRY POINT, MD

364H

27H 3H

2H

6H

15H

1H

13H

14H

18H

4H

5H

19H 23H366 80H

11H

9H

314C 314B

314A

17H

82H

22H

20H

CC

CC

NORTH

KEY PLAN

NOT TO SCALE

1 1/05/2024

A. COORDINATE WITH ANY CURRENT PERRY POINT EHRM PROJECT(S) TO AVOID POSSIBLE REDUNDANCIES.

B. REFER TO GENERAL NOTES, SYMBOLS LEGEND, ABBREVIATIONS, ETC. ON SHEET TG001 FOR ADDITIONAL INFORMATION.

C. REFER TO SHEET SERIES "TSN01-", "CC-TN01-", "TN101-", "TJ102-", AND "TK1" FOR ADDITIONAL INFORMATION.

D. ALL DEVICES ARE NOT INDICATED ON DRAWINGS, DEVICE INDICATED ON DRAWINGS ARE FOR ADDITIONAL CLARIFICATION. FIELD VERIFY WITH EXISTING CONDITIONS.

E. THE LOCATION OF ALL ELECTRICAL DISTRIBUTION EQUIPMENT, DEVICES, TELECOMMUNICATIONS EQUIPMENT, CIRCUITS, FEEDERS, CABLE MANAGEMENT SYSTEMS, CABLING, TERMINATIONS, ETC., AS INDICATED ON THIS DRAWING WERE TAKEN FROM VARIOUS SOURCES. THE INFORMATION IS DIAGRAMMATIC ONLY AND IS SUBJECT TO VARIATION FROM EXISTING CONDITIONS. IN FACT, CERTAIN EXISTING CONDITIONS MAY NOT BE INDICATED AT ALL. CONTRACTORS PROPOSING TO DO ANY PART OF THE WORK INDICATED HEREIN OR AS DEFINED IN THE SCOPE OF WORK SHALL REVIEW THE COMPLETE SET OF CONTRACT DOCUMENTS, VISIT THE SITE AND DETERMINE TO HIS/HER SATISFACTION THAT HE/SHE WILL

BE ABLE TO COMPLETE ALL WORK REQUIRED FOR THE BID AMOUNT PROPOSED.

G. PROTECT AND MAINTAIN EXISTING SYSTEMS SERVICE THAT ARE TO REMAIN AND EXISTING SERVICES BEING REMOVED UNTIL THE NEW OPTICAL FIBER SYSTEM IS FULLY OPERATIONAL AND HAS BEEN COMMISSIONED. ALL SERVICES SHALL BE KEPT OPERATIONAL AT ALL TIMES DURING ALL PHASES OF CONSTRUCTION. ALL PROTECTION MEASURES

SHALL BE TAKEN TO PROTECT AND MAINTAIN THE NEW OPTICAL FIBER SYSTEM AT ALL TIMES

H. FOR BONDING OF RACEWAY SYSTEMS REFER TO SHEET TK102, AND REFER TO "ISTS - V4.0, JUNE 1, 2023 | INFRASTRUCTURE OPERATIONS (IO)", SECTION 4.2.8 BONDING AND

GROUNDING" FOR ADDITIONAL INFORMATION.

H. COORDINATE WITH CAMPUS POLICE AND IT DEPARTMENT ALL WORK BEING PERFORMED ON ALL DEVICES ASSOCIATED WITH THE SECURITY SYSTEM. PROVIDE A WRITTEN NOTICE WITHIN A MINIMUM OF TWO BUSINESS DAYS OF PRIOR OF ANY WORK BEING PERFORMED ON OR THAT EFFECTS THE SECURITY SYSTEM. CLARIFY THE WORK BEING DONE AND GET

APPROVAL FROM CAMPUS POLICE ON ACTIONS TAKEN TO SECURE ALL AREAS EFFECTED

I. DURING THE RENOVATION AND INSTALLATION OF NEW INFRASTRUCTURE CONNECTED TO AGED BUILDINGS ON CAMPUS, AVOID ACCIDENTAL DISTURBANCE OF STRUCTURES WHICH MAY CONTAIN HAZARDOUS MATERIALS. ASBESTOS CONTAINING MATERIALS AND LEAD BASED PAINT ARE LOCATED THROUGHOUT THE PROJECT. REFER TO SPECIFICATIONS 02 82 13.41 ASBESTOS ABATEMENT AND 02 83 33.13 LEAD-BASED PAINT REMOVAL AND DISPOSAL FOR AREAS BEING DISTURBANCE. REFER TO “ASBESTOS CONTAINING MATERIAL NOTES”, “LEAD BASED NOTES”, AND “OTHER IDENTIFIED HAZARDOUS MATERIALS NOTES” ON “HAZARDOUS MATERIALS” DRAWINGS “9H-HA” SERIES.

J. CONTRACTOR SHALL TAKE GREAT CARE IN THE REMOVING AND REPLACING CEILING TILES WHERE REQUIRED DURING RENOVATION AND DEMOLITION. WHERE TILES ARE DAMAGE, CONTRACTOR SHALL REPLACE WITH NEW OR LIKE NEW TO MATCH EXISTING AREAS IN KIND.

1. REFER TO ENLARGE PLANS; "TN101-" SERIES.

2. PROVIDE A NEW OPTICAL FIBER CABLE MANAGEMENT SYSTEM THROUGHOUT ALL CORRIDORS INDICATED AND INTO TELECOMMUNICATIONS SPACES. USE J-HOOKS IN AREAS WHERE

A CONDUIT OR CABLE TRAY SYSTEM CANNOT BE INSTALLED DUE TO EXISTING CONDITIONS. ALSO, USE CONDUIT SLEEVES TO PASS-THROUGH FIRE AND SMOKE WALLS AND IN AREAS WHERE NEITHER A NEW OPTICAL FIBER CABLE MANAGEMENT SYSTEM NOR J-HOOKS CAN BE INSTALLED DUE TO EXISTING CONDITIONS. PROVIDE A DEDICATED CABLE MANAGEMENT SYSTEM PER "ISTS - V4.0, JUNE 1, 2023 | INFRASTRUCTURE OPERATIONS (IO), APPENDIX B". PROVIDE EARTHING (GROUNDING/BONDING) PER VA OIT STANDARDS.

COORDINATE WITH VA COR FOR APPROVAL PRIOR TO INSTALLATION OF ANY J-HOOKS. WHERE J-HOOKS ARE ALLOWED, SPACING SHALL BE NO MORE THAN 3'-0" APART. J-HOOKS SHALL NOT BE USED IN OPEN CEILING AREAS. PULL BOXES SHALL BE INSTALLED PER NEC, BICSI, AND VA OIT STANDARDS.

3. SLEEVES WITH BUSHING AND FIRESTOP FOR INNERDUCT, AND OPTICAL FIBER CABLES. NUMBER AND SIZE OF SLEEVES TO BE DETERMINED TO MAINTAIN A MAXIMUM OF A 40% FILL.

PROVIDE EARTHING (GROUNDING/BONDING) PER VA OIT STANDARDS.

4. COORDINATE EXACT LOCATION(S) AND REQUIREMENTS WITH VA PROJECT COR.

5. OPTICAL FIBER ROUTING. FIELD VERIFY ROUTING AND MAKE ADJUSTMENTS PER EXISTING AND NEW WORK CONDITIONS. NUMBER OF SINGLE MOLD FIBERS AS INDICATED.

CONTRACTOR SHALL PROVIDE ALL LABOR AND MATERIALS TO CONNECT AT BOTH ENDS, SUPPORT/SECURE AND TO INSTALL COMPLETE, PER VA OIT STANDARDS.

6. ROUTE A 12SM OPTICAL FIBER OS2 CABLE IN A SEPARATE 1” PLASTIC INNERDUCT (INNERDUCT IN A DEDICATED 2" CONDUIT) TO EACH OF THE OTHER TELECOMMUNICATIONS

SPACE(S) THROUGHOUT THE SAME BUILDING, (UNO). REFER TO SHEETS TG001, "TN101-" SERIES, “TJ102-” SERIES, AND “TK1” SERIES. REUSE VA OIT STANDARD APPROVED EXISTING RACEWAY SYSTEM, WHERE IN LIKE NEW CONDITION. EXACT ROUTING TO BE FIELD VERIFIED AN APPROVED BY VA COR WHERE NOT IN A CONCEALED SPACE.

7. COORDINATE WITH EXISTING CONDITIONS AND ROUTE NEW 12SM OPTICAL FIBER OS2 CABLE IN A SEPARATE 1” PLASTIC INNERDUCT INTO EXISTING DUCTBANK. ROUTE REDUNDANT SEPARATE PATHWAYS (SIDE A AND SIDE B) IN SEPARATE CONDUITS IN DUCTBANK. PROVIDE ALL LABOR AND MATERIALS FOR A COMPLETE AND WATER-TIGHT INSTALLATION.

PROVIDE A NEW OPTICAL FIBER DISTRIBUTION JUNCTION / PULL BOX (OFJ) POSSIBLE, SIZE PER NEC "314.28 PULL AND JUNCTION BOXES AND CONDUIT BODIES."

8. ROUTE NEW CONDUIT THROUGH EXISTING FLOOR SLAB. COORDINATE EXISTING CONDITIONS BEFORE DRILLING THROUGH EXISTING FLOOR SLAB. FIELD VERIFY EXACT LOCATION AND FIRE STOP PER VA OIT STANDARDS. PROVIDE ALL LABOR AND MATERIAL TO INSTALL COMPLETE.

ALL DEVICE MAY NOT APPLY TO THIS SHEET AND SOME MAY NOT BE SHOWN: REFER TO OTHER PLANS FOR ADDITIONAL INFORMATION

SYMBOL DESCRIPTION

KEYNOTE TAG: REFER TO SCHEDULES, DETAILS, AND PLANS FOR ADDITIONAL INFORMATION

EXISTING CABLE TRAY SYSTEM.

NEW PLASTIC OPTICAL FIBER CABLE TRAY COVER: PROVIDE ALL LABOR AND MATERIALS TO INSTALL COMPLETE PER VA OIT STANDARDS, BICSI REQUIREMENTS, AND ALL

APPLICABLE CODES.

NEW OPTICAL FIBER CONDUIT PATH: PROVIDE ALL LABOR AND MATERIALS TO INSTALL COMPLETE PER VA OIT STANDARDS, BICSI REQUIREMENTS, AND ALL APPLICABLE

CODES.

NEW OPTICAL FIBER CONDUIT PATH RAN IN SPACE BELOW: PROVIDE ALL LABOR AND MATERIALS TO INSTALL COMPLETE PER VA OIT STANDARDS, BICSI REQUIREMENTS, AND ALL APPLICABLE CODES.

NEW CONDUIT SLEEVE, NUMBER AND SIZE PER BISCI REQUIREMENTS. FIRESTOP PER ALL CODE AND BICSI REQUIREMENTS

EXISTING CONDUIT SLEEVE. FIRESTOP PER ALL CODE AND BICSI REQUIREMENTS

-EF- EXISTING FIBER TO REMAIN: ALL PROTECTION MEASURES SHALL BE TAKEN TO PROTECT ALL EXISTING OPTICAL FIBER SYSTEM AT ALL TIMES.

-NF- NEW FIBER ROUTED THROUGH BUILDING FROM PATCH PANEL TO CONNECTION CORRIDOR PATHS: SEPARATE PATHWAYS (FOR REDUNDANT SIDE A AND SIDE B). ROUTED ABOVE ACCESSIBLE CEILING OR TIGHT TO STRUCTURE. REFER TO RENOVATION FLOOR PLANS. (MINIMUM 4'-0" SEPARATION). UNO.

-2NF- NEW FIBER ROUTES: INDICATES (2) REDUNDANT SEPARATE PATHWAYS (SIDE A AND SIDE B). ROUTED THROUGH BUILDING FROM PATCH PANEL TO CONNECTION CORRIDOR PATHS. ROUTED ABOVE ACCESSIBLE CEILING OR TIGHT TO STRUCTURE. REFER TO RENOVATION FLOOR PLANS. (MINIMUM 4'-0" SEPARATION). UNO.

NEW OPTICAL FIBER DISTRIBUTION JUNCTION / PULL BOX, SIZE PER NEC "314.28 PULL AND JUNCTION BOXES AND CONDUIT BODIES."

OPTICAL FIBER DISTRIBUTION WALL BOX

OPTICAL FIBER WALL BOX

ex or EX INDICATES EXISTING TO REMAIN ex

OFJ

OFD

OFB

1/8" = 1'-0"

NORTH

PLAN

1/8" = 1'-0"

DF DF

OF

B ex

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DFDFDF

DF

DF ex ex ex

ABOVE CEILING

ABOVE CEILING

OF

D

1 2 3

TR

A113

CORRIDOR

1C-A2

CORRIDOR

1C-A1

ELEVATOR

HAC

A114

314A-TD001

314A, B

BUILDING 314A AND PARTIAL BUILDING 314B

FIRST FLOOR

TELECOMMUNICATIONS DEMOLITION PLAN

REWKAP/REW

20714

PHARIS

KEITH A.

L I C E N S E D

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

PERRY POINT VA

MEDICAL CENTER

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions: Date:

100% BID DOCUMENTS DEMOLISH BUILDING 9H

512A5-23-311

05-NOV-2024

VA MARYLAND HEALTHCARE SYSTEM

(502) 890-2210 * WESTPOINTENGINEERS.COM

1941 BISHOP LANE, STE. 400 * LOUISVILLE, KY 40218

PERRY POINT VAMC - PERRY POINT, MD

364H

27H 3H

2H

6H

15H

1H

13H

14H

18H

4H

5H

19H 23H366 80H

11H

9H

314C 314B

314A

17H

82H

22H

20H

CC

CC

NORTH

KEY PLAN

NOT TO SCALE

1 1/05/2024

1/8" = 1'-0"

NORTH

PLAN

A. COORDINATE WITH ANY CURRENT PERRY POINT EHRM PROJECT(S) TO AVOID POSSIBLE REDUNDANCIES.

B. ALL NEW FIBER WORK SHALL BE INSTALLED, TEST AND IN COMPLETE WORKING ORDER PRIOR TO THE DISCONNECTION AND/OR REMOVAL OF ANY AND ALL

EXISTING FIBER AND COPPER BACK BONE.

C. REFER TO GENERAL NOTES, SYMBOLS LEGEND, ABBREVIATIONS, ETC. ON SHEET TG001.

D. REFER TO SHEET SERIES "TSD01-", "CC-TD01-", AND SHEET TJ101 FOR ADDITIONAL INFORMATION.

E. COORDINATE ALL DEMOLITION AND RELOCATION WORK WITH EXISTING CONDITIONS, ALL TRADES AND THEIR DOCUMENTS, VA COR, VA OIT STANDARDS, VA

VENDORS, AND ALL NEW WORK. PROVIDE ALL LABOR AND MATERIAL WHERE REQUIRED.

F. ALL DEVICES ARE NOT INDICATED ON DRAWINGS, DEVICE INDICATED ON DRAWINGS ARE FOR ADDITIONAL CLARIFICATION. FIELD VERIFY WITH EXISTING

CONDITIONS.

G. THE LOCATION OF ALL ELECTRICAL DISTRIBUTION EQUIPMENT, DEVICES, TELECOMMUNICATIONS EQUIPMENT, CIRCUITS, FEEDERS, CABLE MANAGEMENT

SYSTEMS, CABLING, TERMINATIONS, ETC., AS INDICATED ON THIS DRAWING WERE TAKEN FROM VARIOUS SOURCES. THE INFORMATION IS DIAGRAMMATIC ONLY AND IS SUBJECT TO VARIATION FROM EXISTING CONDITIONS. IN FACT, CERTAIN EXISTING CONDITIONS MAY NOT BE INDICATED AT ALL. CONTRACTORS PROPOSING TO DO ANY PART OF THE WORK INDICATED HEREIN OR AS DEFINED IN THE SCOPE OF WORK SHALL REVIEW THE COMPLETE SET OF CONTRACT DOCUMENTS, VISIT THE SITE AND DETERMINE TO HIS/HER SATISFACTION THAT HE/SHE WILL BE ABLE TO COMPLETE ALL WORK REQUIRED FOR THE BID

AMOUNT PROPOSED.

H. PROTECT AND MAINTAIN EXISTING SYSTEMS SERVICE THAT ARE TO REMAIN AND EXISTING SERVICES BEING REMOVED UNTIL THE NEW OPTICAL FIBER SYSTEM IS FULLY OPERATIONAL AND HAS BEEN COMMISSIONED. ALL SERVICES SHALL BE KEPT OPERATIONAL AT ALL TIMES DURING ALL PHASES OF CONSTRUCTION. ALL PROTECTION MEASURES SHALL BE TAKEN TO PROTECT AND MAINTAIN THE NEW OPTICAL FIBER SYSTEM AT ALL TIMES.

I. CONDUIT ROUTES, FIBER RUNS/COUNTS/LOCATIONS ARE DIAGRAMMATIC IN NATURE. COORDINATE WILL ALL TRADES AND VERIFY EXACT LOCATION IN FIELD

PRIOR TO INSTALLATION. VERIFY IN FIELD.

J. ALL NECESSARY OUTAGES OF ANY UTILITY SERVICE OR ANY EXISTING TECHNOLOGY AND SECURITY SYSTEM SHALL BE SCHEDULED 14 DAYS IN ADVANCE

WITH THE OWNER.

K. PROTECT ALL NEW AND EXISTING WORK AGAINST DAMAGE.

L. CONDUIT/INNERDUCT ENDS SHALL BE SEALED. PROVIDE FIRE PROTECTION FILL FOR ALL EMPTY AND REWORKED DUCTS ON BOTH ENDS. PROVIDE

TEMPORARY FIRE PROTECTION FILL UNTIL CABLING IS INSTALLED AND COMPLETED.

M. THE CONTRACTOR SHALL MAINTAIN THE CONTINUITY OF EXISTING CIRCUITS THAT CONTAIN DEVICES OR EQUIPMENT THAT ARE TO REMAIN. WHERE

DEMOLITION/RELOCATION OF DEVICES AND EQUIPMENT IS INDICATED, THE CONTRACTOR SHALL ENSURE THAT OTHER DEVICES OR EQUIPMENT THAT ARE CONNECTED TO THE SAME CIRCUIT, WHETHER "UPSTREAM" OR "DOWNSTREAM", SHALL REMAIN OPERATIONAL.

N. DASHED LINES INDICATE ITEMS TO BE REMOVED, U.N.O.

O. COORDINATE WITH CAMPUS POLICE AND IT DEPARTMENT ALL WORK BEING PERFORMED ON ALL DEVICES ASSOCIATED WITH THE SECURITY SYSTEM.

PROVIDE A WRITTEN NOTICE WITHIN A MINIMUM OF TWO BUSINESS DAYS OF PRIOR OF ANY WORK BEING PERFORMED ON OR THAT EFFECTS THE SECURITY SYSTEM. CLARIFY THE WORK BEING DONE AND GET APPROVAL FROM CAMPUS POLICE ON ACTIONS TAKEN TO SECURE ALL AREAS EFFECTED.

P. DURING THE DEMOLITION AND REMOVAL OF INFRASTRUCTURE CONNECTED TO BUILDING 9H AND OTHER SIMILARLY AGED BUILDINGS ON CAMPUS, AVOID ACCIDENTAL DISTURBANCE OF STRUCTURES WHICH MAY CONTAIN HAZARDOUS MATERIALS. ASBESTOS CONTAINING MATERIALS AND LEAD BASED PAINT ARE LOCATED THROUGHOUT THE PROJECT. REFER TO SPECIFICATIONS 02 82 13.41 ASBESTOS ABATEMENT AND 02 83 33.13 LEAD-BASED PAINT REMOVAL AND DISPOSAL FOR AREAS BEING DISTURBANCE. REFER TO “ASBESTOS CONTAINING MATERIAL NOTES”, “LEAD BASED NOTES”, AND “OTHER IDENTIFIED HAZARDOUS MATERIALS NOTES” ON “HAZARDOUS MATERIALS” DRAWINGS “9H-HA” SERIES.

Q. CONTRACTOR SHALL TAKE GREAT CARE IN THE REMOVING AND REPLACING CEILING TILES WHERE REQUIRED DURING RENOVATION AND DEMOLITION.

WHERE TILES ARE DAMAGE, CONTRACTOR SHALL REPLACE WITH NEW OR LIKE NEW TO MATCH EXISTING AREAS IN KIND.

R. COORDINATE WITH OWNER'S FIRE ALARM SYSTEM'S VENDOR, FIRE CHIEF AND VA COR TO REWORK AND RELOCATE EXISTING FIRE ALARM SYSTEM DEVICES

WHERE REQUIRED PER, ALL LOCAL, STATE AND NATIONAL CODES.

1. REFER TO ENLARGE PLANS ("TN101-" SERIES) FOR NEW WORK.

2. PROTECT AND MAINTAIN EXISTING SYSTEMS SERVICE THAT ARE TO REMAIN AND EXISTING SERVICES BEING REMOVED UNTIL THE NEW OPTICAL FIBER

SYSTEM IS FULLY OPERATIONAL AND HAS BEEN COMMISSIONED. ALL SERVICES SHALL BE KEPT OPERATIONAL AT ALL TIMES DURING ALL PHASES OF CONSTRUCTION. ALL PROTECTION MEASURES SHALL BE TAKEN TO PROTECT AND MAINTAIN THE NEW OPTICAL FIBER SYSTEM AT ALL TIMES.

3. REMOVE EXISTING OPTICAL FIBER AND ASSOCIATED WIRE MANAGEMENT SYSTEMS FOR EXISTING OPTICAL FIBER SYSTEMS THAT ARE TO BE REMOVE UNDER THIS CONTRACT. RETAIN EXISTING MANAGEMENT SYSTEMS CONTAINING CABLING THAT IS TO REMAIN.

ALL DEVICE MAY NOT APPLY TO THIS SHEET AND SOME MAY NOT BE SHOWN: REFER TO OTHER PLANS FOR ADDITIONAL INFORMATION

SYMBOL DESCRIPTION

KEYNOTE TAG: REFER TO SCHEDULES, DETAILS, AND PLANS FOR ADDITIONAL INFORMATION

EXISTING CABLE TRAY SYSTEM.

EXISTING CONDUIT SLEEVE. FIRESTOP PER ALL CODE AND BICSI REQUIREMENTS

-EF- EXISTING FIBER TO REMAIN: ALL PROTECTION MEASURES SHALL BE TAKEN TO PROTECT ALL EXISTING OPTICAL FIBER SYSTEM AT ALL TIMES.

-DF- DEMOLITION OF EXISTING FIBER ROUTED IN BUILDINGS AND THROUGH CONNECTION CORRIDOR PATHS: REMOVE EXISTING FIBER AS INDICATED.

REFER TO RENOVATION FLOOR PLANS. UNO.

OPTICAL FIBER DISTRIBUTION WALL BOX

OPTICAL FIBER WALL BOX

ex or EX INDICATES EXISTING TO REMAIN ex

OFD

OFB

DF DF DF DF DF DF DF DF DF

CO

NN

EC

TI

ON

C

OR

RI

DO

R

- A

RE

A "A

TO

B

LD

G:

4C

UP

TO

B

LD

G

9H

DF DF DF DF DF DF DF DF DF DF DF DF DF DF DF DF DF DF DF DF DF DF DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DFDF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

ex ex ex ex

4ABOVE CEILING

ABOVE CEILING

MOUNTED TO STRUCTURE

OFD

1 2 3

ELEC.

CLOSET

C-102A

CORRIDOR

C-C3

CORRIDOR

C-C1

HAC

C-102

NAVE

C-101

314C-TD001

314C, B

BUILDING 314C AND PARTIAL BUILDING 314B

FIRST FLOOR

TELECOMMUNICATIONS DEMOLITION PLAN

REWKAP/REW

20714

PHARIS

KEITH A.

L I C E N S E D

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

PERRY POINT VA

MEDICAL CENTER

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions: Date:

100% BID DOCUMENTS DEMOLISH BUILDING 9H

512A5-23-311

05-NOV-2024

VA MARYLAND HEALTHCARE SYSTEM

(502) 890-2210 * WESTPOINTENGINEERS.COM

1941 BISHOP LANE, STE. 400 * LOUISVILLE, KY 40218

PERRY POINT VAMC - PERRY POINT, MD

364H

27H 3H

2H

6H

15H

1H

13H

14H

18H

4H

5H

19H 23H366 80H

11H

9H

314C 314B

314A

17H

82H

22H

20H

CC

CC

NORTH

KEY PLAN

NOT TO SCALE

1 1/05/2024

1/8" = 1'-0"

NORTH

PLAN

A. COORDINATE WITH ANY CURRENT PERRY POINT EHRM PROJECT(S) TO AVOID POSSIBLE REDUNDANCIES.

B. ALL NEW FIBER WORK SHALL BE INSTALLED, TEST AND IN COMPLETE WORKING ORDER PRIOR TO THE DISCONNECTION AND/OR REMOVAL OF ANY AND ALL

EXISTING FIBER AND COPPER BACK BONE.

C. REFER TO GENERAL NOTES, SYMBOLS LEGEND, ABBREVIATIONS, ETC. ON SHEET TG001.

D. REFER TO SHEET SERIES "TSD01-", "CC-TD01-", AND SHEET TJ101 FOR ADDITIONAL INFORMATION.

E. COORDINATE ALL DEMOLITION AND RELOCATION WORK WITH EXISTING CONDITIONS, ALL TRADES AND THEIR DOCUMENTS, VA COR, VA OIT STANDARDS, VA

VENDORS, AND ALL NEW WORK. PROVIDE ALL LABOR AND MATERIAL WHERE REQUIRED.

F. ALL DEVICES ARE NOT INDICATED ON DRAWINGS, DEVICE INDICATED ON DRAWINGS ARE FOR ADDITIONAL CLARIFICATION. FIELD VERIFY WITH EXISTING

CONDITIONS.

G. THE LOCATION OF ALL ELECTRICAL DISTRIBUTION EQUIPMENT, DEVICES, TELECOMMUNICATIONS EQUIPMENT, CIRCUITS, FEEDERS, CABLE MANAGEMENT

SYSTEMS, CABLING, TERMINATIONS, ETC., AS INDICATED ON THIS DRAWING WERE TAKEN FROM VARIOUS SOURCES. THE INFORMATION IS DIAGRAMMATIC ONLY AND IS SUBJECT TO VARIATION FROM EXISTING CONDITIONS. IN FACT, CERTAIN EXISTING CONDITIONS MAY NOT BE INDICATED AT ALL. CONTRACTORS PROPOSING TO DO ANY PART OF THE WORK INDICATED HEREIN OR AS DEFINED IN THE SCOPE OF WORK SHALL REVIEW THE COMPLETE SET OF CONTRACT DOCUMENTS, VISIT THE SITE AND DETERMINE TO HIS/HER SATISFACTION THAT HE/SHE WILL BE ABLE TO COMPLETE ALL WORK REQUIRED FOR THE BID

AMOUNT PROPOSED.

H. PROTECT AND MAINTAIN EXISTING SYSTEMS SERVICE THAT ARE TO REMAIN AND EXISTING SERVICES BEING REMOVED UNTIL THE NEW OPTICAL FIBER SYSTEM IS FULLY OPERATIONAL AND HAS BEEN COMMISSIONED. ALL SERVICES SHALL BE KEPT OPERATIONAL AT ALL TIMES DURING ALL PHASES OF CONSTRUCTION. ALL PROTECTION MEASURES SHALL BE TAKEN TO PROTECT AND MAINTAIN THE NEW OPTICAL FIBER SYSTEM AT ALL TIMES.

I. CONDUIT ROUTES, FIBER RUNS/COUNTS/LOCATIONS ARE DIAGRAMMATIC IN NATURE. COORDINATE WILL ALL TRADES AND VERIFY EXACT LOCATION IN FIELD

PRIOR TO INSTALLATION. VERIFY IN FIELD.

J. ALL NECESSARY OUTAGES OF ANY UTILITY SERVICE OR ANY EXISTING TECHNOLOGY AND SECURITY SYSTEM SHALL BE SCHEDULED 14 DAYS IN ADVANCE

WITH THE OWNER.

K. PROTECT ALL NEW AND EXISTING WORK AGAINST DAMAGE.

L. CONDUIT/INNERDUCT ENDS SHALL BE SEALED. PROVIDE FIRE PROTECTION FILL FOR ALL EMPTY AND REWORKED DUCTS ON BOTH ENDS. PROVIDE

TEMPORARY FIRE PROTECTION FILL UNTIL CABLING IS INSTALLED AND COMPLETED.

M. THE CONTRACTOR SHALL MAINTAIN THE CONTINUITY OF EXISTING CIRCUITS THAT CONTAIN DEVICES OR EQUIPMENT THAT ARE TO REMAIN. WHERE

DEMOLITION/RELOCATION OF DEVICES AND EQUIPMENT IS INDICATED, THE CONTRACTOR SHALL ENSURE THAT OTHER DEVICES OR EQUIPMENT THAT ARE CONNECTED TO THE SAME CIRCUIT, WHETHER "UPSTREAM" OR "DOWNSTREAM", SHALL REMAIN OPERATIONAL.

N. DASHED LINES INDICATE ITEMS TO BE REMOVED, U.N.O.

O. COORDINATE WITH CAMPUS POLICE AND IT DEPARTMENT ALL WORK BEING PERFORMED ON ALL DEVICES ASSOCIATED WITH THE SECURITY SYSTEM.

PROVIDE A WRITTEN NOTICE WITHIN A MINIMUM OF TWO BUSINESS DAYS OF PRIOR OF ANY WORK BEING PERFORMED ON OR THAT EFFECTS THE SECURITY SYSTEM. CLARIFY THE WORK BEING DONE AND GET APPROVAL FROM CAMPUS POLICE ON ACTIONS TAKEN TO SECURE ALL AREAS EFFECTED.

P. DURING THE DEMOLITION AND REMOVAL OF INFRASTRUCTURE CONNECTED TO BUILDING 9H AND OTHER SIMILARLY AGED BUILDINGS ON CAMPUS, AVOID ACCIDENTAL DISTURBANCE OF STRUCTURES WHICH MAY CONTAIN HAZARDOUS MATERIALS. ASBESTOS CONTAINING MATERIALS AND LEAD BASED PAINT ARE LOCATED THROUGHOUT THE PROJECT. REFER TO SPECIFICATIONS 02 82 13.41 ASBESTOS ABATEMENT AND 02 83 33.13 LEAD-BASED PAINT REMOVAL AND DISPOSAL FOR AREAS BEING DISTURBANCE. REFER TO “ASBESTOS CONTAINING MATERIAL NOTES”, “LEAD BASED NOTES”, AND “OTHER IDENTIFIED HAZARDOUS MATERIALS NOTES” ON “HAZARDOUS MATERIALS” DRAWINGS “9H-HA” SERIES.

Q. CONTRACTOR SHALL TAKE GREAT CARE IN THE REMOVING AND REPLACING CEILING TILES WHERE REQUIRED DURING RENOVATION AND DEMOLITION.

WHERE TILES ARE DAMAGE, CONTRACTOR SHALL REPLACE WITH NEW OR LIKE NEW TO MATCH EXISTING AREAS IN KIND.

R. COORDINATE WITH OWNER'S FIRE ALARM SYSTEM'S VENDOR, FIRE CHIEF AND VA COR TO REWORK AND RELOCATE EXISTING FIRE ALARM SYSTEM DEVICES

WHERE REQUIRED PER, ALL LOCAL, STATE AND NATIONAL CODES.

1. REFER TO ENLARGE PLANS ("TN101-" SERIES) FOR NEW WORK.

2. PROTECT AND MAINTAIN EXISTING SYSTEMS SERVICE THAT ARE TO REMAIN AND EXISTING SERVICES BEING REMOVED UNTIL THE NEW OPTICAL FIBER

SYSTEM IS FULLY OPERATIONAL AND HAS BEEN COMMISSIONED. ALL SERVICES SHALL BE KEPT OPERATIONAL AT ALL TIMES DURING ALL PHASES OF CONSTRUCTION. ALL PROTECTION MEASURES SHALL BE TAKEN TO PROTECT AND MAINTAIN THE NEW OPTICAL FIBER SYSTEM AT ALL TIMES.

3. REMOVE EXISTING OPTICAL FIBER AND ASSOCIATED WIRE MANAGEMENT SYSTEMS FOR EXISTING OPTICAL FIBER SYSTEMS THAT ARE TO BE REMOVE UNDER THIS CONTRACT. RETAIN EXISTING MANAGEMENT SYSTEMS CONTAINING CABLING THAT IS TO REMAIN.

4. REMOVE EXISTING FIRE ALARM PULL BOX COMPLETE. COORDINATE ALL WORK WITH VA's VENDOR.

ALL DEVICE MAY NOT APPLY TO THIS SHEET AND SOME MAY NOT BE SHOWN: REFER TO OTHER PLANS FOR ADDITIONAL INFORMATION

SYMBOL DESCRIPTION

KEYNOTE TAG: REFER TO SCHEDULES, DETAILS, AND PLANS FOR ADDITIONAL INFORMATION

EXISTING CABLE TRAY SYSTEM.

EXISTING CONDUIT SLEEVE. FIRESTOP PER ALL CODE AND BICSI REQUIREMENTS

-EF- EXISTING FIBER TO REMAIN: ALL PROTECTION MEASURES SHALL BE TAKEN TO PROTECT ALL EXISTING OPTICAL FIBER SYSTEM AT ALL TIMES.

-DF- DEMOLITION OF EXISTING FIBER ROUTED IN BUILDINGS AND THROUGH CONNECTION CORRIDOR PATHS: REMOVE EXISTING FIBER AS INDICATED.

REFER TO RENOVATION FLOOR PLANS. UNO.

OPTICAL FIBER DISTRIBUTION WALL BOX

OPTICAL FIBER WALL BOX

ex or EX INDICATES EXISTING TO REMAIN ex

OF

B ex ex ex ex

ABOVE CEILING

ABOVE CEILING

3 25 4

3 25 4

NF

NF NF NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF NF NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

B5

TN101-A

4 52 3

(1) 4"x4" FIBER PATHWAY, EACH WITH:

(1) 12SM IN A 1" INNERDUCT.

MINIMUM 3'-0" SEPARATION.

(1) 4"x4" FIBER PATHWAY, EACH WITH:

(1) 12SM IN A 1" INNERDUCT.

MINIMUM 3'-0" SEPARATION.

TR

A113

CORRIDOR

1C-A2

CORRIDOR

1C-A1

ELEVATOR

HAC

A114

314A-TN001

314A, B

BUILDING 314A AND PARTIAL BUILDING 314B

FIRST FLOOR

TELECOMMUNICATIONS RENOVATION PLAN

REWKAP/REW

20714

PHARIS

KEITH A.

L I C E N S E D

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

PERRY POINT VA

MEDICAL CENTER

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions: Date:

100% BID DOCUMENTS DEMOLISH BUILDING 9H

512A5-23-311

05-NOV-2024

VA MARYLAND HEALTHCARE SYSTEM

(502) 890-2210 * WESTPOINTENGINEERS.COM

1941 BISHOP LANE, STE. 400 * LOUISVILLE, KY 40218

PERRY POINT VAMC - PERRY POINT, MD

364H

27H 3H

2H

6H

15H

1H

13H

14H

18H

4H

5H

19H 23H366 80H

11H

9H

314C 314B

314A

17H

82H

22H

20H

CC

CC

NORTH

KEY PLAN

NOT TO SCALE

1 1/05/2024

1/8" = 1'-0"

NORTH

PLAN

A. COORDINATE WITH ANY CURRENT PERRY POINT EHRM PROJECT(S) TO AVOID POSSIBLE REDUNDANCIES.

B. REFER TO GENERAL NOTES, SYMBOLS LEGEND, ABBREVIATIONS, ETC. ON SHEET TG001 FOR ADDITIONAL INFORMATION.

C. REFER TO SHEET SERIES "TSN01-", "CC-TN01-", "TN101-", "TJ102-", AND "TK1" FOR ADDITIONAL INFORMATION.

D. ALL DEVICES ARE NOT INDICATED ON DRAWINGS, DEVICE INDICATED ON DRAWINGS ARE FOR ADDITIONAL CLARIFICATION. FIELD VERIFY WITH EXISTING

CONDITIONS.

E. THE LOCATION OF ALL ELECTRICAL DISTRIBUTION EQUIPMENT, DEVICES, TELECOMMUNICATIONS EQUIPMENT, CIRCUITS, FEEDERS, CABLE MANAGEMENT

SYSTEMS, CABLING, TERMINATIONS, ETC., AS INDICATED ON THIS DRAWING WERE TAKEN FROM VARIOUS SOURCES. THE INFORMATION IS DIAGRAMMATIC ONLY AND IS SUBJECT TO VARIATION FROM EXISTING CONDITIONS. IN FACT, CERTAIN EXISTING CONDITIONS MAY NOT BE INDICATED AT ALL. CONTRACTORS PROPOSING TO DO ANY PART OF THE WORK INDICATED HEREIN OR AS DEFINED IN THE SCOPE OF WORK SHALL REVIEW THE COMPLETE SET OF CONTRACT DOCUMENTS, VISIT THE SITE AND DETERMINE TO HIS/HER SATISFACTION THAT HE/SHE WILL BE ABLE TO COMPLETE ALL WORK REQUIRED FOR THE BID

AMOUNT PROPOSED.

G. PROTECT AND MAINTAIN EXISTING SYSTEMS SERVICE THAT ARE TO REMAIN AND EXISTING SERVICES BEING REMOVED UNTIL THE NEW OPTICAL FIBER SYSTEM IS FULLY OPERATIONAL AND HAS BEEN COMMISSIONED. ALL SERVICES SHALL BE KEPT OPERATIONAL AT ALL TIMES DURING ALL PHASES OF CONSTRUCTION. ALL PROTECTION MEASURES SHALL BE TAKEN TO PROTECT AND MAINTAIN THE NEW OPTICAL FIBER SYSTEM AT ALL TIMES

H. FOR BONDING OF RACEWAY SYSTEMS REFER TO SHEET TK102, AND REFER TO "ISTS - V4.0, JUNE 1, 2023 | INFRASTRUCTURE OPERATIONS (IO)", SECTION 4.2.8

BONDING AND GROUNDING" FOR ADDITIONAL INFORMATION.

H. COORDINATE WITH CAMPUS POLICE AND IT DEPARTMENT ALL WORK BEING PERFORMED ON ALL DEVICES ASSOCIATED WITH THE SECURITY SYSTEM.

PROVIDE A WRITTEN NOTICE WITHIN A MINIMUM OF TWO BUSINESS DAYS OF PRIOR OF ANY WORK BEING PERFORMED ON OR THAT EFFECTS THE SECURITY SYSTEM. CLARIFY THE WORK BEING DONE AND GET APPROVAL FROM CAMPUS POLICE ON ACTIONS TAKEN TO SECURE ALL AREAS EFFECTED

I. DURING THE RENOVATION AND INSTALLATION OF NEW INFRASTRUCTURE CONNECTED TO AGED BUILDINGS ON CAMPUS, AVOID ACCIDENTAL DISTURBANCE OF STRUCTURES WHICH MAY CONTAIN HAZARDOUS MATERIALS. ASBESTOS CONTAINING MATERIALS AND LEAD BASED PAINT ARE LOCATED THROUGHOUT THE PROJECT. REFER TO SPECIFICATIONS 02 82 13.41 ASBESTOS ABATEMENT AND 02 83 33.13 LEAD-BASED PAINT REMOVAL AND DISPOSAL FOR AREAS BEING DISTURBANCE. REFER TO “ASBESTOS CONTAINING MATERIAL NOTES”, “LEAD BASED NOTES”, AND “OTHER IDENTIFIED

HAZARDOUS MATERIALS NOTES” ON “HAZARDOUS MATERIALS” DRAWINGS “9H-HA” SERIES.

J. CONTRACTOR SHALL TAKE GREAT CARE IN THE REMOVING AND REPLACING CEILING TILES WHERE REQUIRED DURING RENOVATION AND DEMOLITION. WHERE TILES ARE DAMAGE, CONTRACTOR SHALL REPLACE WITH NEW OR LIKE NEW TO MATCH EXISTING AREAS IN KIND.

1. REFER TO ENLARGE PLANS; "TN101-" SERIES.

2. PROVIDE A NEW OPTICAL FIBER CABLE MANAGEMENT SYSTEM THROUGHOUT ALL CORRIDORS INDICATED AND INTO TELECOMMUNICATIONS SPACES. USE

J-HOOKS IN AREAS WHERE A CONDUIT OR CABLE TRAY SYSTEM CANNOT BE INSTALLED DUE TO EXISTING CONDITIONS. ALSO, USE CONDUIT SLEEVES TO PASS-THROUGH FIRE AND SMOKE WALLS AND IN AREAS WHERE NEITHER A NEW OPTICAL FIBER CABLE MANAGEMENT SYSTEM NOR J-HOOKS CAN BE INSTALLED DUE TO EXISTING CONDITIONS. PROVIDE A DEDICATED CABLE MANAGEMENT SYSTEM PER "ISTS - V4.0, JUNE 1, 2023 | INFRASTRUCTURE OPERATIONS (IO), APPENDIX B". PROVIDE EARTHING (GROUNDING/BONDING) PER VA OIT STANDARDS. COORDINATE WITH VA COR FOR APPROVAL PRIOR TO INSTALLATION OF ANY J-HOOKS. WHERE J-HOOKS ARE ALLOWED, SPACING SHALL BE NO MORE THAN 3'-0" APART. J-HOOKS SHALL NOT BE USED IN OPEN CEILING AREAS. PULL BOXES SHALL BE INSTALLED PER NEC, BICSI, AND VA OIT STANDARDS.

3. SLEEVES WITH BUSHING AND FIRESTOP FOR INNERDUCT, AND OPTICAL FIBER CABLES. NUMBER AND SIZE OF SLEEVES TO BE DETERMINED TO MAINTAIN A MAXIMUM OF A 40% FILL. PROVIDE EARTHING (GROUNDING/BONDING) PER VA OIT STANDARDS.

4. COORDINATE EXACT LOCATION(S) AND REQUIREMENTS WITH VA PROJECT COR.

5. OPTICAL FIBER ROUTING. FIELD VERIFY ROUTING AND MAKE ADJUSTMENTS PER EXISTING AND NEW WORK CONDITIONS. NUMBER OF SINGLE MOLD FIBERS AS

INDICATED. CONTRACTOR SHALL PROVIDE ALL LABOR AND MATERIALS TO CONNECT AT BOTH ENDS, SUPPORT/SECURE AND TO INSTALL COMPLETE, PER VA

OIT STANDARDS.

ALL DEVICE MAY NOT APPLY TO THIS SHEET AND SOME MAY NOT BE SHOWN:

(REFER TO SCHEDULES, DETAILS, ALL GENERAL NOTES, KEYNOTES, AND PLANS FOR ADDITIONAL INFORMATION)

SYMBOL DESCRIPTION

KEYNOTE TAG: REFER TO SCHEDULES, DETAILS, AND PLANS FOR ADDITIONAL INFORMATION

EXISTING CABLE TRAY SYSTEM.

NEW PLASTIC OPTICAL FIBER CABLE TRAY COVER: PROVIDE ALL LABOR AND MATERIALS TO INSTALL COMPLETE PER VA OIT STANDARDS, BICSI

REQUIREMENTS, AND ALL APPLICABLE CODES.

NEW OPTICAL FIBER CONDUIT PATH: PROVIDE ALL LABOR AND MATERIALS TO INSTALL COMPLETE PER VA OIT STANDARDS, BICSI

REQUIREMENTS, AND ALL APPLICABLE CODES.

NEW OPTICAL FIBER CONDUIT PATH RAN IN SPACE BELOW: PROVIDE ALL LABOR AND MATERIALS TO INSTALL COMPLETE PER VA OIT

STANDARDS, BICSI REQUIREMENTS, AND ALL APPLICABLE CODES.

NEW CONDUIT SLEEVE, NUMBER AND SIZE PER BISCI REQUIREMENTS. FIRESTOP PER ALL CODE AND BICSI REQUIREMENTS

EXISTING CONDUIT SLEEVE. FIRESTOP PER ALL CODE AND BICSI REQUIREMENTS

-EF- EXISTING FIBER TO REMAIN: ALL PROTECTION MEASURES SHALL BE TAKEN TO PROTECT ALL EXISTING OPTICAL FIBER SYSTEM AT ALL TIMES.

-NF-

NEW FIBER ROUTED THROUGH BUILDING FROM PATCH PANEL TO CONNECTION CORRIDOR PATHS: SEPARATE PATHWAYS (FOR REDUNDANT SIDE A AND SIDE B). ROUTED ABOVE ACCESSIBLE CEILING OR TIGHT TO STRUCTURE. REFER TO RENOVATION FLOOR PLANS. (MINIMUM 4'-0"

SEPARATION). UNO.

-2NF-

NEW FIBER ROUTES: INDICATES (2) REDUNDANT SEPARATE PATHWAYS (SIDE A AND SIDE B). ROUTED THROUGH BUILDING FROM PATCH PANEL TO CONNECTION CORRIDOR PATHS. ROUTED ABOVE ACCESSIBLE CEILING OR TIGHT TO STRUCTURE. REFER TO RENOVATION FLOOR PLANS.

(MINIMUM 4'-0" SEPARATION). UNO.

NEW OPTICAL FIBER DISTRIBUTION JUNCTION / PULL BOX, SIZE PER NEC "314.28 PULL AND JUNCTION BOXES AND CONDUIT BODIES."

OPTICAL FIBER DISTRIBUTION WALL BOX

OPTICAL FIBER WALL BOX

ex or EX INDICATES EXISTING TO REMAIN ex

OFJ

NF NF NF NF NF

CO

NN

EC

TI

ON

C

OR

RI

DO

R

- A

RE

A "A

TO

B

LD

G:

4C

NF NF NF NF NF OF

J

OF

J

UP

NF

NF

NF NF NF NF NF NF NF NF NF NF NF NF NF

NF

ex ex ex ex

NF NF NF NF NF NF NF NF NF NF NF NF NF NF

EXTEND UP FROM DUCTBANK.

3 25 4

TO CONNECTION CORRIDOR

ABOVE CEILING

4 52 3

MOUNTED TO STRUCTURE

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

NF

F1

TN101-A

F9

TN101-B

NF

NF

NF

(1) 4"x4" FIBER PATHWAY, EACH WITH:

(1) 12SM IN A 1" INNERDUCT.

MINIMUM 3'-0" SEPARATION.

(1) 4"x4" FIBER PATHWAY, EACH WITH:

(2) 12SM IN A 1" INNERDUCT.

MINIMUM 3'-0" SEPARATION.

(1) 4"x4" FIBER PATHWAY, EACH WITH:

(1) 12SM IN A 1" INNERDUCT.

MINIMUM 3'-0" SEPARATION.

(1) 4"x4" FIBER PATHWAY, EACH WITH:

(3) 12SM IN A 1.5" INNERDUCT, AND

(2) 12SM IN A 1" INNERDUCT.

MINIMUM 3'-0" SEPARATION.

(1) 4" CONDUIT, EACH WITH:

(3) 12SM IN A 1.5" INNERDUCT, AND

(2) 12SM IN A 1" INNERDUCT.

MINIMUM 3'-0" SEPARATION. "A SIDE" (1) 4"x4" FIBER PATHWAY, EACH WITH:

(3) 12SM IN A 1.5" INNERDUCT.

"B SIDE"

ABOVE CEILING

ELEC.

CLOSET

C-102A

CORRIDOR

C-C3

CORRIDOR

C-C1

HAC

C-102

NAVE

C-101

314C-TN001

314C, B

BUILDING 314C AND PARTIAL BUILDING 314B

FIRST FLOOR

TELECOMMUNICATIONS RENOVATION PLAN

REWKAP/REW

20714

PHARIS

KEITH A.

L I C E N S E D

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

PERRY POINT VA

MEDICAL CENTER

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions: Date:

100% BID DOCUMENTS DEMOLISH BUILDING 9H

512A5-23-311

05-NOV-2024

VA MARYLAND HEALTHCARE SYSTEM

(502) 890-2210 * WESTPOINTENGINEERS.COM

1941 BISHOP LANE, STE. 400 * LOUISVILLE, KY 40218

PERRY POINT VAMC - PERRY POINT, MD

364H

27H 3H

2H

6H

15H

1H

13H

14H

18H

4H

5H

19H 23H366 80H

11H

9H

314C 314B

314A

17H

82H

22H

20H

CC

CC

NORTH

KEY PLAN

NOT TO SCALE

1 1/05/2024

1/8" = 1'-0"

NORTH

PLAN

A. COORDINATE WITH ANY CURRENT PERRY POINT EHRM PROJECT(S) TO AVOID POSSIBLE REDUNDANCIES.

B. REFER TO GENERAL NOTES, SYMBOLS LEGEND, ABBREVIATIONS, ETC. ON SHEET TG001 FOR ADDITIONAL INFORMATION.

C. REFER TO SHEET SERIES "TSN01-", "CC-TN01-", "TN101-", "TJ102-", AND "TK1" FOR ADDITIONAL INFORMATION.

D. ALL DEVICES ARE NOT INDICATED ON DRAWINGS, DEVICE INDICATED ON DRAWINGS ARE FOR ADDITIONAL CLARIFICATION. FIELD VERIFY WITH EXISTING

CONDITIONS.

E. THE LOCATION OF ALL ELECTRICAL DISTRIBUTION EQUIPMENT, DEVICES, TELECOMMUNICATIONS EQUIPMENT, CIRCUITS, FEEDERS, CABLE MANAGEMENT

SYSTEMS, CABLING, TERMINATIONS, ETC., AS INDICATED ON THIS DRAWING WERE TAKEN FROM VARIOUS SOURCES. THE INFORMATION IS DIAGRAMMATIC ONLY AND IS SUBJECT TO VARIATION FROM EXISTING CONDITIONS. IN FACT, CERTAIN EXISTING CONDITIONS MAY NOT BE INDICATED AT ALL. CONTRACTORS PROPOSING TO DO ANY PART OF THE WORK INDICATED HEREIN OR AS DEFINED IN THE SCOPE OF WORK SHALL REVIEW THE COMPLETE SET OF CONTRACT DOCUMENTS, VISIT THE SITE AND DETERMINE TO HIS/HER SATISFACTION THAT HE/SHE WILL BE ABLE TO COMPLETE ALL WORK REQUIRED FOR THE BID

AMOUNT PROPOSED.

G. PROTECT AND MAINTAIN EXISTING SYSTEMS SERVICE THAT ARE TO REMAIN AND EXISTING SERVICES BEING REMOVED UNTIL THE NEW OPTICAL FIBER SYSTEM IS FULLY OPERATIONAL AND HAS BEEN COMMISSIONED. ALL SERVICES SHALL BE KEPT OPERATIONAL AT ALL TIMES DURING ALL PHASES OF CONSTRUCTION. ALL PROTECTION MEASURES SHALL BE TAKEN TO PROTECT AND MAINTAIN THE NEW OPTICAL FIBER SYSTEM AT ALL TIMES

H. FOR BONDING OF RACEWAY SYSTEMS REFER TO SHEET TK102, AND REFER TO "ISTS - V4.0, JUNE 1, 2023 | INFRASTRUCTURE OPERATIONS (IO)", SECTION 4.2.8

BONDING AND GROUNDING" FOR ADDITIONAL INFORMATION.

H. COORDINATE WITH CAMPUS POLICE AND IT DEPARTMENT ALL WORK BEING PERFORMED ON ALL DEVICES ASSOCIATED WITH THE SECURITY SYSTEM.

PROVIDE A WRITTEN NOTICE WITHIN A MINIMUM OF TWO BUSINESS DAYS OF PRIOR OF ANY WORK BEING PERFORMED ON OR THAT EFFECTS THE SECURITY SYSTEM. CLARIFY THE WORK BEING DONE AND GET APPROVAL FROM CAMPUS POLICE ON ACTIONS TAKEN TO SECURE ALL AREAS EFFECTED

I. DURING THE RENOVATION AND INSTALLATION OF NEW INFRASTRUCTURE CONNECTED TO AGED BUILDINGS ON CAMPUS, AVOID ACCIDENTAL DISTURBANCE OF STRUCTURES WHICH MAY CONTAIN HAZARDOUS MATERIALS. ASBESTOS CONTAINING MATERIALS AND LEAD BASED PAINT ARE LOCATED THROUGHOUT THE PROJECT. REFER TO SPECIFICATIONS 02 82 13.41 ASBESTOS ABATEMENT AND 02 83 33.13 LEAD-BASED PAINT REMOVAL AND DISPOSAL FOR AREAS BEING DISTURBANCE. REFER TO “ASBESTOS CONTAINING MATERIAL NOTES”, “LEAD BASED NOTES”, AND “OTHER IDENTIFIED

HAZARDOUS MATERIALS NOTES” ON “HAZARDOUS MATERIALS” DRAWINGS “9H-HA” SERIES.

J. CONTRACTOR SHALL TAKE GREAT CARE IN THE REMOVING AND REPLACING CEILING TILES WHERE REQUIRED DURING RENOVATION AND DEMOLITION. WHERE TILES ARE DAMAGE, CONTRACTOR SHALL REPLACE WITH NEW OR LIKE NEW TO MATCH EXISTING AREAS IN KIND.

1. REFER TO ENLARGE PLANS; "TN101-" SERIES.

2. PROVIDE A NEW OPTICAL FIBER CABLE MANAGEMENT SYSTEM THROUGHOUT ALL CORRIDORS INDICATED AND INTO TELECOMMUNICATIONS SPACES. USE

J-HOOKS IN AREAS WHERE A CONDUIT OR CABLE TRAY SYSTEM CANNOT BE INSTALLED DUE TO EXISTING CONDITIONS. ALSO, USE CONDUIT SLEEVES TO PASS-THROUGH FIRE AND SMOKE WALLS AND IN AREAS WHERE NEITHER A NEW OPTICAL FIBER CABLE MANAGEMENT SYSTEM NOR J-HOOKS CAN BE INSTALLED DUE TO EXISTING CONDITIONS. PROVIDE A DEDICATED CABLE MANAGEMENT SYSTEM PER "ISTS - V4.0, JUNE 1, 2023 | INFRASTRUCTURE OPERATIONS (IO), APPENDIX B". PROVIDE EARTHING (GROUNDING/BONDING) PER VA OIT STANDARDS. COORDINATE WITH VA COR FOR APPROVAL PRIOR TO INSTALLATION OF ANY J-HOOKS. WHERE J-HOOKS ARE ALLOWED, SPACING SHALL BE NO MORE THAN 3'-0" APART. J-HOOKS SHALL NOT BE USED IN OPEN CEILING AREAS. PULL BOXES SHALL BE INSTALLED PER NEC, BICSI, AND VA OIT STANDARDS.

3. SLEEVES WITH BUSHING AND FIRESTOP FOR INNERDUCT, AND OPTICAL FIBER CABLES. NUMBER AND SIZE OF SLEEVES TO BE DETERMINED TO MAINTAIN A MAXIMUM OF A 40% FILL. PROVIDE EARTHING (GROUNDING/BONDING) PER VA OIT STANDARDS.

4. COORDINATE EXACT LOCATION(S) AND REQUIREMENTS WITH VA PROJECT COR.

5. OPTICAL FIBER ROUTING. FIELD VERIFY ROUTING AND MAKE ADJUSTMENTS PER EXISTING AND NEW WORK CONDITIONS. NUMBER OF SINGLE MOLD FIBERS AS

INDICATED. CONTRACTOR SHALL PROVIDE ALL LABOR AND MATERIALS TO CONNECT AT BOTH ENDS, SUPPORT/SECURE AND TO INSTALL COMPLETE, PER VA

OIT STANDARDS.

ALL DEVICE MAY NOT APPLY TO THIS SHEET AND SOME MAY NOT BE SHOWN:

(REFER TO SCHEDULES, DETAILS, ALL GENERAL NOTES, KEYNOTES, AND PLANS FOR ADDITIONAL INFORMATION)

SYMBOL DESCRIPTION

KEYNOTE TAG: REFER TO SCHEDULES, DETAILS, AND PLANS FOR ADDITIONAL INFORMATION

EXISTING CABLE TRAY SYSTEM.

NEW PLASTIC OPTICAL FIBER CABLE TRAY COVER: PROVIDE ALL LABOR AND MATERIALS TO INSTALL COMPLETE PER VA OIT STANDARDS, BICSI

REQUIREMENTS, AND ALL APPLICABLE CODES.

NEW OPTICAL FIBER CONDUIT PATH: PROVIDE ALL LABOR AND MATERIALS TO INSTALL COMPLETE PER VA OIT STANDARDS, BICSI

REQUIREMENTS, AND ALL APPLICABLE CODES.

NEW OPTICAL FIBER CONDUIT PATH RAN IN SPACE BELOW: PROVIDE ALL LABOR AND MATERIALS TO INSTALL COMPLETE PER VA OIT

STANDARDS, BICSI REQUIREMENTS, AND ALL APPLICABLE CODES.

NEW CONDUIT SLEEVE, NUMBER AND SIZE PER BISCI REQUIREMENTS. FIRESTOP PER ALL CODE AND BICSI REQUIREMENTS

EXISTING CONDUIT SLEEVE. FIRESTOP PER ALL CODE AND BICSI REQUIREMENTS

-EF- EXISTING FIBER TO REMAIN: ALL PROTECTION MEASURES SHALL BE TAKEN TO PROTECT ALL EXISTING OPTICAL FIBER SYSTEM AT ALL TIMES.

-NF-

NEW FIBER ROUTED THROUGH BUILDING FROM PATCH PANEL TO CONNECTION CORRIDOR PATHS: SEPARATE PATHWAYS (FOR REDUNDANT SIDE A AND SIDE B). ROUTED ABOVE ACCESSIBLE CEILING OR TIGHT TO STRUCTURE. REFER TO RENOVATION FLOOR PLANS. (MINIMUM 4'-0"

SEPARATION). UNO.

-2NF-

NEW FIBER ROUTES: INDICATES (2) REDUNDANT SEPARATE PATHWAYS (SIDE A AND SIDE B). ROUTED THROUGH BUILDING FROM PATCH PANEL TO CONNECTION CORRIDOR PATHS. ROUTED ABOVE ACCESSIBLE CEILING OR TIGHT TO STRUCTURE. REFER TO RENOVATION FLOOR PLANS.

(MINIMUM 4'-0" SEPARATION). UNO.

NEW OPTICAL FIBER DISTRIBUTION JUNCTION / PULL BOX, SIZE PER NEC "314.28 PULL AND JUNCTION BOXES AND CONDUIT BODIES."

OPTICAL FIBER DISTRIBUTION WALL BOX

OPTICAL FIBER WALL BOX

ex or EX INDICATES EXISTING TO REMAIN ex

OFJ

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

DF

ex ex ex

CONNEC

TIO

N CORRIDOR - A

REA

"A

TO

BL

DG: 3

C

1 2 3

MOUNTED TO STRUCTURE

MOUNTED TO STRUCTURE

MOUNTED TO STRUCTURE

CO

NN

EC

TIO

N

CO

RR

ID

OR

- A

RE

A

"B

CO

NN

EC

TIO

N

CO

RR

ID

OR

- A

RE

A

"A

CC-TD001-A

CC

PARTIAL CONNECTION CORRIDORS - AREA "A"

TELECOMMUNICATIONS

DEMOLITION PLAN

REWKAP/REW

20714

PHARIS

KEITH A.

L I C E N S E D

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

PERRY POINT VA

MEDICAL CENTER

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

Project Director

Revisions: Date:

100% BID DOCUMENTS DEMOLISH BUILDING 9H

512A5-23-311

05-NOV-2024

VA MARYLAND HEALTHCARE SYSTEM

(502) 890-2210 * WESTPOINTENGINEERS.COM

1941 BISHOP LANE, STE. 400 * LOUISVILLE, KY 40218

PERRY POINT VAMC - PERRY POINT, MD

364H

27H 3H

2H

6H

15H

1H

13H

14H

18H

4H

5H

19H 23H366 80H

11H

9H

314C 314B

314A

17H

82H

22H

20H

CC

CC

NORTH

KEY PLAN

NOT TO SCALE

1 1/05/2024

A. COORDINATE WITH ANY CURRENT PERRY POINT EHRM PROJECT(S) TO AVOID POSSIBLE REDUNDANCIES.

B. ALL NEW FIBER WORK SHALL BE INSTALLED, TEST AND IN COMPLETE WORKING ORDER PRIOR TO THE DISCONNECTION AND/OR REMOVAL OF ANY AND ALL

EXISTING FIBER AND COPPER BACK BONE.

C. REFER TO GENERAL NOTES, SYMBOLS LEGEND, ABBREVIATIONS, ETC. ON SHEET TG001.

D. REFER TO SHEET SERIES "TSD01-", "CC-TD01-", AND SHEET TJ101 FOR ADDITIONAL INFORMATION.

E. COORDINATE ALL DEMOLITION AND RELOCATION WORK WITH EXISTING CONDITIONS, ALL TRADES AND THEIR DOCUMENTS, VA COR, VA OIT STANDARDS, VA

VENDORS, AND ALL NEW WORK. PROVIDE ALL LABOR AND MATERIAL WHERE REQUIRED.

F. ALL DEVICES ARE NOT INDICATED ON DRAWINGS, DEVICE INDICATED ON DRAWINGS ARE FOR ADDITIONAL CLARIFICATION. FIELD VERIFY WITH EXISTING

CONDITIONS.

G. THE LOCATION OF ALL ELECTRICAL DISTRIBUTION EQUIPMENT, DEVICES, TELECOMMUNICATIONS EQUIPMENT, CIRCUITS, FEEDERS, CABLE MANAGEMENT

SYSTEMS, CABLING, TERMINATIONS, ETC., AS INDICATED ON THIS DRAWING WERE TAKEN FROM VARIOUS SOURCES. THE INFORMATION IS DIAGRAMMATIC ONLY AND IS SUBJECT TO VARIATION FROM EXISTING CONDITIONS. IN FACT, CERTAIN EXISTING CONDITIONS MAY NOT BE INDICATED AT ALL. CONTRACTORS PROPOSING TO DO ANY PART OF THE WORK INDICATED HEREIN OR AS DEFINED IN THE SCOPE OF WORK SHALL REVIEW THE COMPLETE SET OF CONTRACT DOCUMENTS, VISIT THE SITE AND DETERMINE TO HIS/HER SATISFACTION THAT HE/SHE WILL BE ABLE TO COMPLETE ALL WORK REQUIRED FOR THE BID

AMOUNT PROPOSED.

H. PROTECT AND MAINTAIN EXISTING SYSTEMS SERVICE THAT ARE TO REMAIN AND EXISTING SERVICES BEING REMOVED UNTIL THE NEW OPTICAL FIBER SYSTEM IS FULLY OPERATIONAL AND HAS BEEN COMMISSIONED. ALL SERVICES SHALL BE KEPT OPERATIONAL AT ALL TIMES DURING ALL PHASES OF CONSTRUCTION. ALL PROTECTION MEASURES SHALL BE TAKEN TO PROTECT AND MAINTAIN THE NEW OPTICAL FIBER SYSTEM AT ALL TIMES.

I. CONDUIT ROUTES, FIBER RUNS/COUNTS/LOCATIONS ARE DIAGRAMMATIC IN NATURE. COORDINATE WILL ALL TRADES AND VERIFY EXACT LOCATION IN FIELD

PRIOR TO INSTALLATION. VERIFY IN FIELD.

J. ALL NECESSARY OUTAGES OF ANY UTILITY SERVICE OR ANY EXISTING TECHNOLOGY AND SECURITY SYSTEM SHALL BE SCHEDULED 14 DAYS IN ADVANCE

WITH THE OWNER.

K. PROTECT ALL NEW AND EXISTING WORK AGAINST DAMAGE.

L. CONDUIT/INNERDUCT ENDS SHALL BE SEALED. PROVIDE FIRE PROTECTION FILL FOR ALL EMPTY AND REWORKED DUCTS ON BOTH ENDS. PROVIDE

TEMPORARY FIRE PROTECTION FILL UNTIL CABLING IS INSTALLED AND COMPLETED.

M. THE CONTRACTOR SHALL MAINTAIN THE CONTINUITY OF EXISTING CIRCUITS THAT CONTAIN DEVICES OR EQUIPMENT THAT ARE TO REMAIN. WHERE

DEMOLITION/RELOCATION OF DEVICES AND EQUIPMENT IS INDICATED, THE CONTRACTOR SHALL ENSURE THAT OTHER DEVICES OR EQUIPMENT THAT ARE CONNECTED TO THE SAME CIRCUIT, WHETHER "UPSTREAM" OR "DOWNSTREAM", SHALL REMAIN OPERATIONAL.

N. DASHED LINES INDICATE ITEMS TO BE REMOVED, U.N.O.

O. COORDINATE WITH CAMPUS POLICE AND IT DEPARTMENT ALL WORK BEING PERFORMED ON ALL DEVICES ASSOCIATED WITH THE SECURITY SYSTEM.

PROVIDE A WRITTEN NOTICE WITHIN A MINIMUM OF TWO BUSINESS DAYS OF PRIOR OF ANY WORK BEING PERFORMED ON OR THAT EFFECTS THE SECURITY SYSTEM. CLARIFY THE WORK BEING DONE AND GET APPROVAL FROM CAMPUS POLICE ON ACTIONS TAKEN TO SECURE ALL AREAS EFFECTED.

P. DURING THE DEMOLITION AND REMOVAL OF INFRASTRUCTURE CONNECTED TO BUILDING 9H AND OTHER SIMILARLY AGED BUILDINGS ON CAMPUS, AVOID ACCIDENTAL DISTURBANCE OF STRUCTURES WHICH MAY CONTAIN HAZARDOUS MATERIALS. ASBESTOS CONTAINING MATERIALS AND LEAD BASED PAINT ARE LOCATED THROUGHOUT THE PROJECT. REFER TO SPECIFICATIONS 02 82 13.41 ASBESTOS ABATEMENT AND 02 83 33.13 LEAD-BASED PAINT REMOVAL AND DISPOSAL FOR AREAS BEING DISTURBANCE. REFER TO “ASBESTOS CONTAINING MATERIAL NOTES”, “LEAD BASED NOTES”, AND “OTHER IDENTIFIED HAZARDOUS MATERIALS NOTES” ON “HAZARDOUS MATERIALS” DRAWINGS “9H-HA” SERIES.

Q. CONTRACTOR SHALL TAKE GREAT CARE IN THE REMOVING AND REPLACING CEILING TILES WHERE REQUIRED DURING RENOVATION AND DEMOLITION.

WHERE TILES ARE DAMAGE, CONTRACTOR SHALL REPLACE WITH NEW OR LIKE NEW TO MATCH EXISTING AREAS IN KIND.

R. COORDINATE WITH OWNER'S FIRE ALARM SYSTEM'S VENDOR, FIRE CHIEF AND VA COR TO REWORK AND RELOCATE EXISTING FIRE ALARM SYSTEM DEVICES

WHERE REQUIRED PER, ALL LOCAL, STATE AND NATIONAL CODES.

1. REFER TO ENLARGE PLANS ("TN101-" SERIES) FOR NEW WORK.

2. PROTECT AND MAINTAIN EXISTING SYSTEMS SERVICE THAT ARE TO REMAIN AND EXISTING SERVICES…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .