502-16-104 Fire Protection 100 pct Bid.pdf

PDF 1 MB Posted

Attached to
Z2DA--Proj. # 502-16-104 Replace HVAC System in Bldg. 2 Federal contract opportunity
Solicitation number
36C25620R0079
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--Proj. # 502-16-104 Replace HVAC System in Bldg. 2, newest first.
File Type Posted
502-16-104 Mechanical Rev. 1 Drwgs MH103 MH104 M504.pdf PDF
ADDENDUM NO. 0001.pdf PDF
EXHIBIT B PAST AND PRESENT PERFORMANCE QUESTIONNAIRE v2.docx DOCX document
502-16-104 010000 Gen Req Revision 5-18-20.docx DOCX document
Bldg 2 Asbestos Report.pdf PDF
502-16-104 Project Risk Assessment Bldg 2 HVAC 1-3-20.pdf PDF
502-16-104 Mechanical 100 pct Bid.pdf PDF
Wage Determination.txt TXT text file
EXHIBIT C SUBCONTRACTOR INFORMATION AND CONSENT v2.docx DOCX document
EXHIBIT F PROPOSAL INQUIRY FORM.docx DOCX document
502-16-104 Structural 100 pct Bid.pdf PDF
502-16-104 Electrical Rev. Drwg E-501.pdf PDF
EXHIBIT D CONTRACTOR EVALUATION FORM CONSTRUCTION SAFETY v2.docx DOCX document
36C25620R0079_3.docx DOCX document
EXHIBIT A PERFORMANCE RELEVANCY SURVEY v2.docx DOCX document
EXHIBIT E SURETY FORM.docx DOCX document
502-16-104 Combined Spec Set Replace HVAC Bldg 2.pdf PDF
502-16-04 Electrical 100 pct BID.pdf PDF
502-16-104 Final SOW.docx DOCX document
Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FIRE PROTECTION GENERAL NOTES

A. THE FIRE PROTECTION CONTRACTOR SHALL USE NFPA-13 (2019), CHAPTER 8, “PLANS AND CALCULATIONS” AS A

GUIDELINE WHEN PREPARING SUBMITTALS FOR REVIEW. DISREGARD ONLY THOSE ITEMS NOT APPLICABLE TO THE INDIVIDUAL BUILDING SYSTEM. FIRE PROTECTION MATERIALS, EQUIPMENT AND INSTALLATION SHALL BE IN ACCORDANCE WITH THE REQUIREMENTS OF NFPA-13 FOR THE INSTALLATION OF AUTOMATIC SPRINKLER SYSTEM.

B. THE FIRE PROTECTION CONTRACTOR SHALL COMPLY WITH THE 2018 INTERNATIONAL BUILDING CODE. INSTALLATION

SHALL MEET THE REQUIREMENTS OF THE AUTHORITY HAVING JURISDICTION.

C. REFER TO ARCHITECTURAL REFLECTED CEILING PLANS AND ROOM FINISH SCHEDULE WHICH INDICATE CEILING HEIGHTS. COORDINATE WITH ARCHITECT'S REFLECTED CEILING PLAN FOR PROPOSED LOCATION OF SPRINKLER HEADS IN AREAS WITH CEILINGS. LOCATE HEADS IN AREAS WITHOUT CEILINGS AS REQUIRED BY IFC, NFPA AND AUTHORITY

HAVING JURISDICTION REQUIREMENTS FOR THE APPROPRIATE HAZARD CLASSIFICATION.

D. THIS BUILDING IS A FULLY SPRINKLERED BUILDING. THE EXISTING FIRE SUPPRESSION SYSTEM IS WET PIPE TYPE SYSTEM WITH COMPLETE SPRINKLER PROTECTION UNLESS NOTED OTHERWISE. NEW HEADS AND PIPING SHALL BE AN EXTENSION OF THE EXISTING SYSTEM AND SHALL BE DESIGNED AS REQUIRED BY IFC, NFPA, AND AUTHORITY HAVING

JURISDICTION REQUIREMENTS FOR THE APPROPRIATE HAZARD CLASSIFICATION.

E. SPRINKLER HEAD LAYOUTS INDICATED ARE BASED ON OCCUPANCY HAZARD CLASSIFICATIONS OUTLINED IN NFPA-13 STANDARDS AND THE SPECIFICATIONS. EXTENDED COVERAGE DISTRIBUTION IS NOT INDICATED, BUT MAY BE UTILIZED

WHERE SPACE MEETS REQUIREMENTS SET FORTH IN NFPA-13.

F. IT IS THE CONTRACTOR'S RESPONSIBILITY TO HYDRAULICALLY CALCULATE SPRINKLER REQUIREMENTS PER THE APPROPRIATE HAZARD OCCUPANCY AND PROVIDE ACTUAL NUMBER OF HEADS, REQUIRED SPACING AND PIPE ROUTING AS REQUIRED FOR CLEARANCE WITH STRUCTURAL CONDITIONS AND OTHER TRADES TO PROVIDE A COMPLETE AND OPERABLE SYSTEM IN ACCORDANCE WITH IFC, NFPA AND AUTHORITY HAVING JURISDICTION REQUIREMENTS.

G. FIRE PROTECTION CONTRACTOR SHALL OBTAIN FLOW TEST DATA INDICATING THE WATER FLOW AND PRESSURE AVAILABLE TO THE FACILITY OR MAKE ARRANGEMENTS TO HAVE A FLOW TEST PERFORMED. FIRE PROTECTION CONTRACTOR SHALL INCLUDE IN THE BID, ALL COSTS ASSOCIATED WITH FLOW TEST. SUBMIT HYDRAULIC

CALCULATIONS AND PLANS RELATED TO A MINIMUM OF 1 REMOTE AREA FOR REVIEW.

H. PIPING IS SHOWN IN SCHEMATIC FORM TO INDICATE APPROXIMATE ARRANGEMENT OF EQUIPMENT AND PIPING.

SPRINKLER CONTRACTOR SHALL DESIGN THE SYSTEM AND ROUTE PIPING AS REQUIRED FOR CONFORMANCE WITH ACTUAL BUILDING CONDITIONS AND NFPA REQUIREMENTS. COORDINATE SPRINKLER WORK WITH ALL OTHER TRADES

TO AVOID CONFLICT.

I. REFER TO SPECIFICATION SECTIONS IN DIVISION 21 FOR ADDITIONAL INFORMATION PERTAINING TO THE FIRE

PROTECTION SYSTEM.

J. SUPPORT ALL NEW PIPING AND EQUIPMENT FROM STRUCTURE ABOVE AS REQUIRED. CONTRACTOR SHALL PROVIDE ALL SUPPLEMENTAL STEEL TO SPAN BETWEEN PRIMARY BUILDING STRUCTURAL MEMBERS. CONTRACTOR SHALL BE RESPONSIBLE FOR COMPLETE DESIGN OF SUPPLEMENTAL STEEL AND SUPPORTS INCLUDING REACTION LOADS AT

PRIMARY BUILDING STRUCTURAL MEMBERS.

K. PROVIDE SPRINKLER HEADS IN CONCEALED LOCATIONS PER NFPA REQUIREMENTS.

L. DURING CONSTRUCTION PROCEDURES, THE ENTIRE WORK AREA SHALL BE CLEAN OF ALL DUST, DIRT, AND OTHER

DEBRIS BEFORE APPLICATION OF ANY NEW MATERIALS.

M. THESE DRAWINGS INDICATE THE GENERAL EXTENT OF THE WORK AND ARE NOT INTENDED TO SHOW OR DESCRIBE ALL

WORK REQUIRED FOR THE FULL PERFORMANCE AND COMPLETION OF CONTRACT DOCUMENTS.

N. PROVIDE ALL LABOR, MATERIALS, TOOLS, EQUIPMENT, ETC. REQUIRED FOR COMPLETE AND FUNCTIONAL SYSTEM AS

SPECIFIED AND INDICATED ON THE DRAWINGS.

O. INCLUDE IN BID, ALL LICENSE, PERMIT, INSPECTION, AND OTHER FEES REQUIRED BY UTILITY COMPANIES OR AUTHORITIES HAVING JURISDICTION REQUIRED FOR COMPLETION OF WORK SO NO ADDITIONAL EXPENSES ARE

INTRODUCED TO OWNER.

P. PROMPTLY INFORM THE ENGINEER, IN WRITING, OF ANY DEVIATIONS IN THE CONTRACT DOCUMENTS FROM REQUIREMENTS OF LOCAL UTILITIES, MUNICIPALITIES, STATE OR FEDERAL LAWS AND REGULATIONS. PERFORM WORK

IN ACCORDANCE WITH SUCH REQUIREMENTS AT NO ADDITIONAL COST TO THE OWNER.

Q. FIRE PROTECTION CONTRACTOR SHALL SUBMIT ONE COMPLETE SET OF AUTOMATIC SPRINKLER SYSTEM DRAWINGS, HYDRAULIC CALCULATIONS, CURRENT WATER FLOW TEST, AND THE EQUIPMENT DATA BROCHURES PREPARED BY OR UNDER THE SUPERVISION OF, AND SEALED BY A PROFESSIONAL ENGINEER. THE SUBMITTAL SHALL BE SENT TO ALL AUTHORITIES HAVING JURISDICTION FOR REVIEW AND APPROVAL. SYSTEM SHALL ALSO BE IN COMPLIANCE WITH ALL

REQUIRED PLUMBING CODES.

R. ALL EXPENSES CARRIED BY THE ARCHITECT/ENGINEER IN TROUBLESHOOTING SYSTEM(S) PROBLEMS CAUSED BY INADEQUATE WORKMANSHIP, LACK OF TECHNICAL EXPERTISE OR OTHER FORMS OF POOR PERFORMANCE ON THE

PART OF A CONTRACTOR, SHALL BE BORN BY THAT CONTRACTOR.

S. PROVIDE FIRE STOPS / SEALANT AT ALL PIPE PENETRATIONS THROUGHOUT FIRE RATED WALLS. REVIEW ARCHITECTURAL PLANS PRIOR TO BIDDING AND INDICATE PENETRATIONS ON SPRINKLER LAYOUT SUBMITTAL.

T. PRESSURE DROP OF THE EXISTING BACKFLOW PREVENTION DEVICE SHALL INCORPORATE INTO HYDRAULIC

CALCULATIONS.

U. FIRE PROTECTION CONTRACTOR SHALL FURNISH AND INSTALL ARMOVER SUPPORTS FOR ALL END OF LINE BRANCH

LINES PER NFPA-13.

V. ALL DROPS TO SPRINKLER HEADS SHALL TEE / ELBOW OFF TOP OF BRANCH PIPE, EXCEPT WHERE STRUCTURAL, ARCHITECTURAL OR MECHANICAL EQUIPMENT CONDITIONS PRECLUDE CONVENTIONAL INSTALLATION.

W. SPRINKLER HEADS SHALL BE IN A SYMMETRICAL PATTERN, NOT NECESSARILY IN THE CENTER OF ROOMS, CORRIDORS

OR CEILING TILE.

FIRE PROTECTION CONTRACTOR

SEMI-RECESSED SPRINKLER HEAD

UPRIGHT SPRINKLER HEAD

FIRE LINE FPCFL

TAMPER SWITCH

FLOW SWITCH

CONCEALED SPRINKLER HEAD

PENDANT SPRINKLER HEAD

CHECK VALVE

GATE VALVE

EXTERIOR ALARM GONG (WATER ACTIVATED)

TEST AND DRAIN ASSEMBLY

ORDINARY HAZARD

GROUP 1 OCCUPANCY

SIDEWALL SPRINKLER HEAD

FIRE DEPARTMENT CONNECTION (FDC)

NOTE: NOT ALL SYMBOLS MAY BE USED ON THIS PROJECT

FIRE PROTECTION SYMBOLS AND ABBREVIATIONS

KEYNOTE

DETAIL OR SECTION MARK

SHOWN ON DRAWING

DETAIL MODULE NUMBER CONNECT TO EXISTING

LIMITS OF DEMOLITION

BACKFLOW PREVENTER

FIRE PROTECTION DEMOLITION GENERAL NOTES

A. LOCATIONS SHOWN FOR EXISTING FIRE PROTECTION PIPE, EQUIPMENT AND SPRINKLER HEADS ARE APPROXIMATE.

THE CONTRACTOR IS TO FIELD VERIFY THE EXACT LOCATIONS OF EXISTING FIRE PROTECTION LINES AND EQUIPMENT INCLUDING RISERS AND VALVES, AS WELL AS SPRINKLER HEADS PRIOR TO THE START OF WORK.

B. COORDINATE WITH OWNER FOR ANY SHUTDOWNS OR PLANNED INTERRUPTIONS OF THE FIRE PROTECTION SERVICE.

THE CONTRACTOR SHALL GIVE THE OWNER SEVEN (7) DAYS NOTICE PRIOR TO THE PLANNED SHUTDOWN OR

INTERRUPTION.

C. COORDINATE DEMOLITION OF FIRE PROTECTION PIPING WITH OTHER PIPING WHICH IS NOT TO BE REMOVED. PROTECT

OTHER PIPING WHICH IS NOT TO BE REMOVED FROM DAMAGE, DIRT, AND DEBRIS.

D. ALL FIRE PROTECTION RELATED EQUIPMENT AND PIPING WHICH IS REMOVED FROM THE BUILDING IS TO BE TAKEN

OFFSITE AND DISPOSED OF.

BUILDING AND OCCUPANT SAFETY -

INTERRUPTION OF FIRE PROTECTION SERVICE

A. DURING THE TIME THAT THE FIRE PROTECTION RENOVATION WORK IS BEING PERFORMED, AND THE FIRE PROTECTION SYSTEM IS DOWN AND OUT OF COMMISSION, THE FIRE PROTECTION CONTRACTOR SHALL HAVE SUFFICIENT

PERSONNEL ONSITE TO KEEP A “FIRE WATCH” ON THE FACILITY.

B. A FIRE PROTECTION WATCH IS IMPLEMENTED TO ENSURE THE FIRE SAFETY OF A BUILDING IN THE EVENT OF ANY ACT, OR SITUATION INSTIGATING AN INCREASED RISK TO PERSONS OR PROPERTY. THE TERM “FIRE WATCH” IS USED TO DESCRIBE A DEDICATED PERSON OR PERSONS WHO’S SOLE RESPONSIBILITY IS TO LOOK FOR FIRES WITHIN AN

ESTABLISHED AREA.

C. IN THE OPINION OF THE FIRE AND LIFE-SAFETY GROUP (FLS) OF FACTORY MUTUAL (FM), ANY REQUIRED FIRE PROTECTION SYSTEM THAT IS OUT OF SERVICE FOR MORE THAN 4 HOURS AND OCCUPIED IS REQUIRED TO ESTABLISH A FIRE WATCH. FOR THE PERSON OR PERSONS ASSIGNED TO THE FIRE WATCH, THIS MUST BE THEIR ONLY JOB DUTY

DURING THE TIME PERIOD OF THE FIRE PROTECTION RENOVATION WORK.

D. IN ADDITION THE BUILDING OWNER IS REQUIRED TO HAVE AN IMPAIRMENT COORDINATOR. THE OUT OF SERVICE EQUIPMENT MUST BE TAGGED “OUT OF SERVICE”. AN OUT OF SERVICE TAG MUST BE PLACED AT THE FIRE ALARM PANEL AND THE FIRE DEPARTMENT CONNECTION (REFERENCE INTERNATIONAL FIRE CODE- CHAPTER 9, SECTION 901.7).

E. FIRE WATCH PERSONNEL ARE TO KEEP WATCH FOR FIRES IN THE GENERAL AREA OF PERFORMANCE, THE PERSONS

PERFORMING THE FIRE WATCH ARE NOT PERMITTED TO PERFORM ANY OTHER DUTIES.

F. FIRE WATCH PERSONNEL ARE TO HAVE FIRE EXTINGUISHING EQUIPMENT READILY AVAILABLE AND TO BE TRAINED IN ITS

USE.

G. THE QUANTITY OF PERSONNEL INVOLVED IN THE FIRE WATCH IS TO BE ADEQUATE SUCH THAT EACH FLOOR, LEVEL, AND

ROOM OF THE FIRE AREA IS COVERED.

H. IN GENERAL, A FIRE WATCH IS TO FULFILL THE INTENT OF NFPA-72 AS FOLLOWS: 1. NOTIFY OCCUPANTS TO EVACUATE WHEN THERE IS A FIRE IN THE BUILDING; 2. NOTIFY THE CENTRAL MONITORING STATION TO INITIATE EMERGENCY PERSONNEL RESPONSE; 3. ACITVATE FIRE PROTECTION SYSTEMS IN ORDER TO RELEASE DOOR HOLDERS, CLOSE

SMOKE DAMPERS, AND SHUT DOWN FANS.

I. IF BUILDING OCCUPANTS ASSIST WITH FIRE WATCH DUTIES, THE PROCEDURES FOR CONTACTING EMERGENCY PERSONNEL AND EVACUATING THE BUILDING ARE TO BE DISTRIBUTED TO BUILDING OCCUPANTS. FOR PLANNED

OUTAGES, THE PROCEDURES ARE TO BE SENT TO THE BUILDING OWNER FOR DISTRIBUTION.

T&D

TS

FS

ORDINARY HAZARD

GROUP 2 OCCUPANCY

INFECTION CONTROL MEASURES

A. CONTRACTOR SHALL COMPLY WITH THE OWNER'S INFECTION CONTROL RISK ASSESSMENT REQUIREMENTS AND

WRITTEN DUST CONTROL PLAN.

B. EXISTING AIR QUALITY REQUIREMENTS AND OTHER UTILITY REQUIREMENTS FOR OCCUPIED AREAS SHALL BE

MAINTAINED.

C. RENOVATION AREAS SHALL BE ISOLATED FROM OCCUPIED AREAS DURING CONSTRUCTION USING AIRTIGHT BARRIERS.

PROVIDE EXHAUST AIRFLOW IN A MANNER THAT SHALL BE SUFFICIENT TO MAINTAIN NEGATIVE AIR PRESSURE IN THE CONSTRUCTION ZONE. COORDINATE TEMPORARY BARRIERS WITH INTERIM LIFE SAFETY MEASURES.

D. FIRE PROTECTION SYSTEM REVISIONS SHALL BE PROPERLY PERFORMED TO LIMIT WATERBOURNE OPPORTUNISTIC

PATHOGENS.

E. DOUBLE-BAGGING IS REQUIRED FOR CONSTRUCTION DEBRIS. COMPLY WITH OWNER'S DESIGNATED ROUTE FOR

REMOVAL.

F. CRUCIAL VENTILATION SPECIFICATIONS FOR AIR BALANCE AND FILTRATION SHALL BE VERIFIED BEFORE OWNER'S

ACCEPTANCE.

THE FIRE PROTECTION DRAWING IS DESIGNED TO BE IN CONFORMANCE WITH NFPA

13. IT IS A PERFORMANCE BASED DRAWING INDICATING THE EXTENT OF FIRE

PROTECTION WORK FOR THE AREA THAT THIS DRAWING REPRESENTS. THIS

DRAWING IS “FOR INFORMATION ONLY”, AS A REFERENCE FOR THE FIRE

PROTECTION CONTRACTOR TO BASE THE DESIGN OF THE FIRE PROTECTION

SYSTEM ON. THE CONTRACTOR SHALL VERIFY THE EXACT CONDITIONS THAT THIS

DRAWING REPRESENTS, INCLUDING ANY PERCEIVED CONCEALED SPACES, AND THE

BUILDING TYPE AND CONSTRUCTION AS OUTLINED IN THE INTERNATIONAL BUILDING

CODE, PRIOR TO THE START OF WORK. REFER TO THE INTERNATIONAL BUILDING

CODE, ESPECIALLY CHAPTERS 6 (TYPES OF CONSTRUCTION) AND CHAPTER 9 (FIRE

PROTECTION SYSTEMS), NFPA 13 (CHAPTER 8), AND THE PROJECT SPECIFICATIONS

FOR OTHER FIRE PROTECTION REQUIREMENTS.

N

RN

47721

E

ENIG

O

NA

TR

F

SEAL

RP

OO ISS OE

H RCA

IL

A N

L

E

P A

U

L L . H O L L O

W A

Y

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

FULLY SPRINKLERED

100% CONSTRUCTION

DOCUMENTS

/8

/2

:2

:2

A M

F-001

FIRE PROTECTION GENERAL

INFORMATION

01 05

TAMEKA J. TAYLOR

SM

REPLACE HVAC SYSTEM

2495 SHREVEPORT HWY. PINEVILLE,

LA 71360

1-9-2020

502-16-10417-108

PLH

DocuSign Envelope ID: B9D4F131-B263-4860-8434-0C5CADDF2C68

1/8/2020

17'-10" 12'-9" 9'-0" 12'-9" 18'-6" 18'-6" 18'-3" 10'-6" 1'-2" 14'-9" 10'-8" 18'-4" 18'-3" 18'-3" 12'-7" 9'-3" 12'-8" 17'-9"

I RQP0NMLKJI.1HGFEDCBA

3.7

7.5

3.8

6.2

4.5

2.8

3.7

7.5

3.8

6.2

4.5

2.8

102A

123A

104A

117K

117J

117H

114G

117A

117B

117C 117D

117L

117E 117F

138A

STAIRS

126A

127A

127B

126E

126B 126D

128B

128E

128A

128C

128D

128F128G

128H

122121

126C

N

RN

47721

E

ENIG

O

NA

TR

F

SEAL

RP

OO ISS OE

H RCA

IL

A N

L

E

P A

U

L L . H O L L O

W A

Y

## KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER

SHEET NOTES:

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

N

KEY PLAN

SCALE: NO SCALE

BUILDING 2

TRUE

SCOPE OF WORK

FULLY SPRINKLERED

100% CONSTRUCTION

DOCUMENTS

S S S S

/8

/2

:2

:3

A M

FD101

FIRST FLOOR FIRE PROTECTION

DEMOLITION PLAN

02 05

TAMEKA J. TAYLOR

SM

REPLACE HVAC SYSTEM

2495 SHREVEPORT HWY. PINEVILLE,

LA 71360

1-9-2020

502-16-10417-108

PLH

0 4 8 16

N O

R

TH

TRUE

Scale: 1/8" = 1'-0"

FIRST FLOOR FIRE SUPRESSION DEMOLITION PLAN

01 DEMOLISH SPRINKLER HEAD.

(TYP.)

17'-10" 12'-9" 9'-0" 12'-9" 18'-6" 18'-6" 18'-3" 10'-6" 1'-2" 14'-9" 10'-8" 18'-4" 18'-3" 18'-3" 12'-7" 9'-3" 12'-8" 17'-9"

I RQP0NMLKJI.1HGFEDCBA

3.7

7.5

3.8

6.2

4.5

2.8

3.7

7.5

3.8

6.2

4.5

2.8

01 (TYP.)

01 (TYP.)

N

RN

47721

E

ENIG

O

NA

TR

F

SEAL

RP

OO ISS OE

H RCA

IL

A N

L

E

P A

U

L L . H O L L O

W A

Y

## KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER

SHEET NOTES:

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

N

KEY PLAN

SCALE: NO SCALE

BUILDING 2

TRUE

SCOPE OF WORK

FULLY SPRINKLERED

100% CONSTRUCTION

DOCUMENTS

S S S S

/8

/2

:2

:3

A

M

FD102

ATTIC FIRE PROTECTION DEMOLITION

PLAN

03 05

TAMEKA J. TAYLOR

SM

REPLACE HVAC SYSTEM

2495 SHREVEPORT HWY. PINEVILLE,

LA 71360

1-9-2020

502-16-10417-108

PLH

Scale: 1/8" = 1'-0"

ATTIC FIRE PROTECTION DEMOLITION PLAN 0 4 8 16

N O

R

TH

TRUE

01 DEMOLISH SPRINKLER HEAD.

17'-10" 12'-9" 9'-0" 12'-9" 18'-6" 18'-6" 18'-3" 10'-6" 1'-2" 14'-9" 10'-8" 18'-4" 18'-3" 18'-3" 12'-7" 9'-3" 12'-8" 17'-9"

I RQP0NMLKJI.1HGFEDCBA

3.7

7.5

3.8

6.2

4.5

2.8

3.7

7.5

3.8

6.2

4.5

2.8

102A

123A

104A

117K

117J

117H

114G

117A

117B

117C 117D

117L

117E 117F

138A

STAIRS

126A

127A

127B

126E

126B 126D

128B

128E

128A

128C

128D

128F128G

128H

122121

126C

N

RN

47721

E

ENIG

O

NA

TR

F

SEAL

RP

OO ISS OE

H RCA

IL

A N

L

E

P A

U

L L . H O L L O

W A

Y

## KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER

SHEET NOTES:

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

N

KEY PLAN

SCALE: NO SCALE

BUILDING 2

TRUE

SCOPE OF WORK

FULLY SPRINKLERED

100% CONSTRUCTION

DOCUMENTS

S S S S

/8

/2

:2

:2

A M

F-101

FIRST FLOOR FIRE PROTECTION PLAN

04 05

TAMEKA J. TAYLOR

SM

REPLACE HVAC SYSTEM

2495 SHREVEPORT HWY. PINEVILLE,

LA 71360

1-9-2020

502-16-10417-108

PLH

Scale: 1/8" = 1'-0"

FIRST FLOOR FIRE SUPRESSION PLAN 0 4 8 16

N O

R

TH

TRUE

01 (TYP.)

01 PROVIDE SPRINKLER HEADS, BRANCH

PIPING, AND SUPPORTS.

17'-10" 12'-9" 9'-0" 12'-9" 18'-6" 18'-6" 18'-3" 10'-6" 1'-2" 14'-9" 10'-8" 18'-4" 18'-3" 18'-3" 12'-7" 9'-3" 12'-8" 17'-9"

I RQP0NMLKJI.1HGFEDCBA

3.7

7.5

3.8

6.2

4.5

2.8

3.7

7.5

3.8

6.2

4.5

2.8

01 (TYP.)

(TYP.) 01 02

03 03

04 04

04 04 04

N

RN

47721

E

ENIG

O

NA

TR

F

SEAL

RP

OO ISS OE

H RCA

IL

A N

L

E

P A

U

L L . H O L L O

W A

Y

## KEY NOTES:

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER

SHEET NOTES:

Date Checked Drawn

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

WALL RATING LEGEND

1 HR - FIRE SEPARATION

2 HR - FIRE SEPARATION

SMOKE RESISTIVE HAZARDOUS AREA

N

KEY PLAN

SCALE: NO SCALE

BUILDING 2

TRUE

SCOPE OF WORK

FULLY SPRINKLERED

100% CONSTRUCTION

DOCUMENTS

S S S S

/8

/2

:2

:3

A M

F-102

ATTIC FIRE PROTECTION PLAN

05 05

TAMEKA J. TAYLOR

SM

REPLACE HVAC SYSTEM

2495 SHREVEPORT HWY. PINEVILLE,

LA 71360

1-9-2020

502-16-10417-108

PLH

Scale: 1/8" = 1'-0"

ATTIC FIRE PROTECTION PLAN 0 4 8 16

N O

R

TH

TRUE

01 PROVIDE SPRINKLER HEADS, BRANCH

PIPING, AND SUPPORTS. HEADS SHALL BE

EXPOSED UPRIGHT PENDENT, HIGH

TEMPERATURE. HEAD SHALL REPLACE

REMOVED HEAD AND CONNECT TO EXISTING

SPRINKLER PIPING. TYPICAL.

02 CONNECT TO EXISTING SPRINKLER LINE

HIGH AT ROOF RIDGE, EXTEND DOWN TO

PROVIDE COVERAGE AT NEW AHU.

03 NEW UPRIGHT PENDANT HIGH

TEMPERATURE SPRINKLER HEAD TO

PROVIDE COVERAGE AT AHU.

04 HEAD HIGH AT UNDERSIDE OF ROOF RIDGE.

OUTLINE OF NEW AHU

Sheets
F-001 - FIRE PROTECTION GENERAL INFORMATION
FD101 - FIRST FLOOR FIRE PROTECTION DEMOLITION PLAN
FD102 - ATTIC FIRE PROTECTION DEMOLITION PLAN
F-101 - FIRST FLOOR FIRE PROTECTION PLAN
F-102 - ATTIC FIRE PROTECTION PLAN
2020-01-08T12:52:52-0800
Digitally verifiable PDF exported from www.docusign.com

File details come from the government source that posted it. Updated .