About this file

This is a Project Design document for the Supplee Farm Stream Restoration Project in Pennsylvania, developed by G. Chamberlain and completed in 2023. The project involves stream restoration work on Conowingo Creek, a Class A Warmwater Fishery (CWF), and includes multiple restoration elements such as toe logs, root wads, brush mattresses, mudsills, cross vanes, vanes, random boulder clusters, riffle rocks, and bank grading. The design incorporates two wetland sites (Wetland #1 measuring 20 feet wide by 161 feet long, and Wetland #2 measuring 18 feet wide by 28 feet long), vernal pools, staging areas, access lanes, and a temporary crossing (8 feet wide by 40 feet long). A mandatory pre-bid site showing is scheduled for 1:00 PM EST on January 20, 2026. Bids must be submitted no later than 12:00 AM EST on February 7, 2026, with bid opening at 10:00 AM EST on February 9, 2026, and bid award scheduled for 10:00 AM EST on March 10, 2026. All meetings are conducted virtually. The Pennsylvania Fish & Boat Commission has designated a trout stocking lockout period from February 15 to June 1.

Bidders are required to submit documentation online via the PennBid program, including a signed bid form and schedule, a bid bond, references, and a narrative describing experience with stream restoration in Lancaster County or Southcentral Pennsylvania, along with an overview of the firm. Signature requirements vary by entity type: individual bidders must have owner signatures, partnerships require a witnessed partner signature, and corporations must have President or Vice President signatures with corporate seal attestation. All bidding documents, including general instructions, project design, standards and sizes, aquatic resource impact tables, permit approvals, evaluation criteria, and prevailing wage determinations, are available at no cost through PennBid at https://pennbid.bonfirehub.com/. Evaluation will be conducted according to a formal Evaluation Criteria Spreadsheet, with bidders encouraged to provide detailed information to support the evaluation process.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

C o n o w in g o C re ek

C onow ingo C re e k

R o b e rt

F u lt o n H w y

C o n o w in g o C ree k

Goshen

1 1

Supplee Farm Stream Restoration Project

G. Chamberlain Design completed in 2023Conowingo Creek - CWF

Legend

Toe Log

Root Wad

Brush Mattress

Mudsill

Cross Vane

Vane

Random Boulder Cluster

Riffle

Rock Toe

Bank Grading

Bankfull Bench

Crossing

Stream

Wetland Site

Vernal Pools

Staging Area

Access Lane

Image

RGB

Red: Band_1

Green: Band_2

Blue: Band_3

PA Fish & Boat Commission Trout Stocked Lockout February 15 - June 1

0 100 200 30050 US Feet

Wetland #1 20' W x 161' L

C o n o w in go

C reek

R o b e rt

F u lto n H w y

R o b e rt

F u lto n H w y

15 16

Supplee Farm Stream Restoration Project

G. Chamberlain Design completed in 2023Conowingo Creek - CWF

Legend

Toe Log

Root Wad

Brush Mattress

Mudsill

Cross Vane

Vane

Random Boulder Cluster

Riffle

Rock Toe

Bank Grading

Bankfull Bench

Crossing

Stream

Wetland Site

Vernal Pools

Staging Area

PA Fish & Boat Commission Trout Stocked Lockout February 15 - June 1

0 100 200 300 40050 US Feet

Temporary Crossing 8' W x 40' L

Wetland #2 18' W x 28' L

ARIT Downstream1
ARIT Upstream1