2-Bid Form and Schedule - Supplee Farm.docx
DOCX document 112 KB Posted
- Attached to
- REBID - Supplee Farm Restoration Project
- Solicitation number
- Not on record
- Issued by
- Lancaster County, Pennsylvania
About this file
This is a Bid Form and Schedule document issued by the Lancaster County Conservation District for the Supplee Farm Restoration Project, a stream restoration initiative located in Fulton Township, Lancaster County, Pennsylvania. The project encompasses comprehensive natural channel stream restoration services on approximately 3,500 linear feet of Conowingo Creek, including installation of in-stream habitat structures (single rock vanes, rock cross vanes, log toe riffles, brush mattresses, root wads, mudsills, vernal pools, and random boulder clusters), riprap and bank stabilization structures with rock toe placement and geotextile materials, excavation and regrading including bankfull benches, one permanent rock-bottom agricultural crossing structure, one temporary crossing structure using marsh mats and concrete bin blocks, and final grading with seeding and stabilization. Bids must be submitted as a single lump-sum bid covering all work items and shall be submitted online through PennBid by the specified deadline. The project performance period runs from June 1, 2026 through August 31, 2027, with bidders required to specify the number of working days or calendar days needed for completion. A mandatory pre-bid site showing was scheduled for January 20, 2026 at 1:00 PM EST, with the original bid submission deadline of February 7, 2026 subsequently rebid with a new deadline of June 13, 2026 at 11:30 PM EST, public bid opening on June 15, 2026 at 10:00 AM EST, and anticipated bid award on July 14, 2026 at 10:00 AM EST.
Bids are submitted on a lump-sum basis with payment structured in up to three phases, with 90 percent of project costs reimbursed within 90 days of submittal and the final 10 percent within 160 days, contingent upon funding availability from the state agency. All bids exceeding $250,000 require a 5 percent bid guarantee, 100 percent performance bond, and 100 percent payment bond, along with worker's compensation and public liability insurance of $1,000,000. The project is funded through a Section 319 Nonpoint Source Pollution Grant administered by the Pennsylvania Department of Environmental Protection, which triggers compliance with prevailing wage requirements and Build America, Buy America mandates requiring all iron, steel, manufactured products, and construction materials to be produced in the United States. Bidders must demonstrate 5–10 years of practical experience with natural channel stream restoration work in Lancaster County or Southcentral Pennsylvania, possess capacity to manage projects of similar size and scale, and exhibit competence in stream restoration theory and construction methodologies. All required federal and state permits have been obtained, including Army Corps of Engineers authorization, Pennsylvania DEP Environmental Assessment and 401 Water Quality Certification, and erosion and sediment control plan approval.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Form Lancaster County Conservation District – Supplee Farm Restoration Project Fulton Township, Lancaster County, PA
The following bid document is for the project described as LCCD Supplee Farm Restoration Project. One lump-sum bid shall be submitted for all items as described in the project design and technical specifications documents. Bids shall be submitted on this document and submitted online through PennBid. All instructions shall be followed in the bid document provided.
The performance time specified for this project: June 1, 2026 - August 31, 2027.
Having received clarifications on all items of conflict or upon which doubt arose, the undersigned proposes to furnish all labor, materials, and equipment called for by the said documents for the entire work, in accordance with the Contract Documents, for the stipulated sum shown in the Bid Schedule.
The undersigned agrees to indemnify and hold harmless the landowner, Lancaster County Conservation District, DEP, and all other of their representatives against any and all claims for the damages to persons asserted to any person, partnership, corporation, or other organization, arising out of services performed or undertakes by said contractor, it’s agents, employees, or subcontractors, except for claims for damages directly cause by the sole fault or negligence of the parties hereto, their officers, or employees.
Submit bid to:
PennBid Attn: Grace Chamberlain Lancaster County Conservation District 1383 Arcadia Road, Room 200 Lancaster, PA 17601
Bidder’s name:
Address:
| Phone number: | Fax: | |
| Email: | EIN#: |
Bid total:
Signature Date
Supplee Farm Restoration Project
BID SCHEDULE
| Item No. |
| Description |
| Quantity |
| Unit |
| Unit Price |
| Total Price |
| 1 |
| Mobilization/Demobilization |
| 1 |
| Lump Sum |
| --- |
Erosion and Sediment Control
Construction entrance & access lane
| 2 |
| GP-1 In-Stream Habitat Structures |
| 1 |
| Lump Sum |
| --- |
Single Rock Vane
Rock Cross Vane
Log toe
Riffles
Brush Mattress
Root Wad
Mudsill
Vernal Pools
Random Boulder Clusters
| 3 |
| GP-3 Riprap and Bank Stabilization Structures |
| 1 |
| Lump Sum |
| --- |
Rock Toe
Excavation and Regrading, including bankfull benches
Geotextile
| 4 |
| GP-6 Agriculture Crossing Structures |
| 1 |
| Lump Sum |
| --- |
Rock-bottom crossing
| 5 |
| GP-8 Temporary Crossing Structures |
| 1 |
| Lump Sum |
| --- |
Marsh Mats
Concrete Bin Blocks
| 6 |
| Seeding & Stabilization |
| 1 |
| Lump Sum |
| --- |
Final Grading
Seeding
Performance Time: _____ Working Days _____ Calendar Days
Contractor’s Name Date image1.png image2.png
File details come from the government source that posted it. Updated .