Eagle Mountain City RFP Summary
This is a Request for Proposal (RFP) issued by Eagle Mountain City, Utah for construction of Cory B. Wride Memorial Park Phase 2 - South Parking Lot Improvements. The project encompasses site demolition, clearing and grubbing, removal of existing infrastructure (asphalt, concrete, curb and gutter, vegetation), stripping and replacement of topsoil, site grading, erosion control and SWPPP implementation, and construction of new parking areas with drainage and irrigation systems. The scope includes 28 line items covering work such as mobilization, concrete sidewalks (8,625 SF), asphalt pavement (60,135 SF), curb and gutter (3,355 LF), storm drain piping (605 LF across three sizes), 12 ADA ramps, catch basins, parking lot lighting, landscape improvements, and complete irrigation system installation. Proposals are due June 8, 2026 at 12:00 PM through the State of Utah's Public Procurement Portal. The RFP was issued May 19, 2026 with questions due by May 29, 2026. The anticipated contract award date is June 15, 2026. No site visits or bidders conferences are specified in the RFP document.
Pricing shall include all applicable state and federal sales taxes and any other special taxes, royalties, or patent rights. A 5% bid bond payable to Eagle Mountain City is required with proposal submission and must remain in place until contract execution and performance/payment bond posting. Upon contract award, the successful contractor must provide 100% Performance Bond and 100% Payment Bond. Insurance requirements include General Liability ($1,000,000 per occurrence/$3,000,000 aggregate), Commercial Automobile ($1,000,000 combined single limit), Architect/Engineer Professional Liability ($1,000,000 per claim/$3,000,000 aggregate), Valuable Papers Coverage, Workers Compensation, and Builder's Risk Insurance. The evaluation committee will score proposals using weighted criteria: Firm Experience (25%), Project Team Experience (25%), Functional Approach (20%), Technical Approach (17%), Cost (10%), and Introduction Letter (3%). Proposals must not exceed 15 single-sided pages in 11-12 point font and must be organized according to specified tabs addressing letter of transmittal, executive summary, detailed discussion, cost proposal, and bid forms with certificates of insurance.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Eagle Mountain City
EMC Cory Wride Phase 2 South Parking Lot
REQUEST FOR PROPOSAL (RFP) NO. EMC-FY26-16
RFP Due Date: June 8, 2026, by 12:00 P.M.
RFP Administrator: Melissa Yates, Purchasing Agent P: (801) 789-6641 E: Myates@EagleMountain.gov
Issued: May 19, 2026
Interested parties may obtain a copy of this RFP and submit responses through the State of Utah’s Public
Procurement Portal:
purchasing.utah.gov https://purchasing.utah.gov/
TABLE OF CONTENTS
OVERVIEW 3
I. INTRODUCTION 3
II. SCOPE OF SERVICES 3
III. PROPOSAL EVALUATION CRITERIA 3
IV. PROPOSAL RESPONSE OUTLINE 11
IV. INSURANCE REQUIREMENTS 12
V. TIMELINE 14
VI. ADMINISTRATIVE GUIDANCE 14
VII. ISSUING OFFICE AND RFP REFERENCE NUMBER 14
VIII. SUBMISSION OF PROPOSAL 15
IX. BID BOND 15
X. VENDOR PREQUALIFICATION 15
XI. INQUIRIES 15
XII. RESPONDENT’S RESPONSIBILITY FOR PROPOSAL COSTS 16
XIII. EVALUATION OF PROPOSALS 16
XIV. KEY COMPANY PERSONNEL 16
XV. ORAL PRESENTATION Error! Bookmark not defined.
XVI. AWARD OF THE CONTRACT 16
XVII. PROTECTED INFORMATION 17
XVIII. ADDENDUM TO RFP 17
XIX. AUTHORIZED REPRESENTATIVES 17
XX. ANTI-COLLUSION 17
XXI. RESTRICTIONS / CONFLICT OF INTEREST 18
XXII. RIGHT TO REJECT 18
XXIII. PRIVACY NOTICE 18
ATTACHMENT A 19
ATTACHMENT B-D 23
OVERVIEW
I. INTRODUCTION
Eagle Mountain City is requesting bids from responsible firms or individuals for a project called Cory B.
Wride Memorial Park Phase 2 – South Parking Lot Improvements. The project is located west of the existing pedestrian crossing in the roadway, south of the baseball fields, within the designated south parking lot area, including the retention pond.
II. SCOPE OF SERVICES
This project consists of the construction of the south parking lot improvements for Phase 2 of Cory B.
Wride Memorial Park in Eagle Mountain, Utah. The project is located west of the existing pedestrian crossing in the roadway, south of the baseball fields, and limited to the designated south parking lot area as shown on Sheet C110, including the retention pond shown on Sheet C112. Work includes site demolition, clearing and grubbing, and removal of existing asphalt, concrete, curb and gutter, vegetation, and miscellaneous site features within the limits of disturbance. The project also includes stripping, stockpiling, and reuse of topsoil, site grading and earthwork, and implementation of erosion control and SWPPP measures in accordance with City and applicable standards. All other previously constructed park improvements are existing and shall remain in place and be protected during construction.
Improvements include construction of new asphalt parking areas, aggregate base, concrete sidewalk, curb and gutter (including standard and reverse slope sections), ADA-accessible ramps, and pavement markings within the south parking lot area. Drainage improvements include installation of storm drain piping, catch basins, manholes, and associated appurtenances necessary to serve the parking lot and retention pond. Additional work includes installation of irrigation sleeves, electrical systems for parking lot lighting, and associated landscape and irrigation improvements within the project limits. All work shall include the necessary labor, materials, equipment, and incidentals required to deliver a complete and functional project. See Plans Volume 1 and 2 and project specifications for full details.
III. BID SCHEDULE
All applicable sales taxes, State, and/or Federal, and any other special taxes, patent rights, or royalties are included in the price quoted in this Proposal. Figures to be typewritten or clearly and legibly printed in ink. LS is equal to lump sum, LF is equal to linear-feet, CY is equal to cubic-yard, EA is equal to each, and SF is equal to square-feet.
Item
No.
Description Quantity Unit
Unit
Cost Total Cost
1 Mobilization 1 LS
SWPPP / Erosion Control (Including
Maintenance)
1 LS
3 Silt Fence 1,600 LF
4 Track Out Pad 1 EA
5 Clear & Grub / Vegetation Removal 157,000 SF
6 Strip, Stockpile & Replace Topsoil 157,000 SF
7 Site Grading / Cut-Fill 4,750 CY
8 Concrete Sidewalk Prep 8,625 SF
9 Concrete Sidewalk (4" Thick) 8,625 SF
10 30" Type A Curb & Gutter 1,450 LF
11 30" Reverse Slope Curb & Gutter 1,905 LF
12 Untreated Base Course (6" Thick) 2,005 TON
13 Asphalt Pavement (3" Thick) 60,135 SF
14 Seal Coat 60,135 SF
15 ADA Ramps 12 EA
Pavement Markings / Striping / ADA
Signs
1 LS
17 6" Concrete Mow Strip 90 LF
18 Irrigation Sleeves 130 LF
12" Storm Drain Pipe (Complete
Install)
290 LF
15" Storm Drain Pipe (Complete
Install)
145 LF
18" Storm Drain Pipe (Complete
Install)
170 LF
22 3' x 3' Catch Basin / Inlet Box 7 EA
23 Storm Drain Manhole with Sump 1 EA
24 Storm Drain Manhole 1 EA
25 Rip Rap / Drainage Way 1 LS
26 Electrical – Parking Lot Lighting 1 LS
27 Landscape Improvements (Complete) 1 LS
Irrigation System Improvements
(Complete)
1 LS
BID SCHEDULE TOTAL
BID SCHEDULE TOTAL (IN WORDS)
Contractor shall include all labor, materials, equipment, sleeves, piping, valves, heads, drip systems, wiring, controller modifications, topsoil placement, planting, mulch, turf restoration, testing, adjustment, warranty, and maintenance necessary to provide a complete landscape and irrigation system per the plans and specifications.
Documents and the INSTRUCTIONS FOR PREPARING PROPOSAL relating to what is to be furnished under each item of the PROPOSAL and to submittal of bid.
Bidder understands and agrees that the Owner reserves the right to reject any or all bids and to waive any informality in the bidding.
The bidder agrees that this bid shall be good and may not be withdrawn for a period of 75 calendar days after the scheduled closing time for receiving bids. Bidder acknowledges receipt of the following addenda:
The undersigned bidder shall acknowledge receipt of the following addenda, if any.
Addenda No(s).
Respectfully submitted, Bidder
(Corporate Seal)
If bid is by corporation By:
Title
Witness: if bidder is an individual Bidder’s post office address (if applicable):
Bidder's post office address:
Name and address of all members of the firm or names and titles of all officers of the corporation
Name and Title: Bidder’s address:
SEAL
Bidder’s phone number: ___________
V. MEASUREMENT AND PAYMENT
BID SCHEDULE
MOBILIZATION & DEMOBILIZATION, Bid Item 1 Measurement and Payment
Section Description a.
Measurement
Measurement shall be Lump Sum.
b. Payment
Payment shall be full compensation for all preparatory operations for the project, including but not limited to those items necessary for the project site: acquisition and payment of all permits; furnishing construction power and other utilities; furnishing, erecting, and maintenance of construction signs; construction fencing; mobilization;
demobilization; temporary facilities; temporary access; and all costs associated with the project that are not included in other bid items.
c. Payment
Payment also covers the cost of all items necessary to complete construction and restore the construction site to acceptable conditions. This includes, but is not limited to, removal of temporary construction structures, cleanup of all remaining materials on the construction site, and all other necessary clean-up measures required by the specifications and approved by the Engineer.
d. Limitation Mobilization & Demobilization cost shall not exceed 10% of the combined total Base Bid amount.
Basis of Payment
Amount Paid When Paid
25% of bid item amount With first application for payment
Remaining portion of bid item paid as percentage of the contract completed
With each subsequent application for payment
SWPPP / EROSION CONTROL, Bid Item 2
Section Description a.
Measurement
Measurement shall be Lump Sum.
b. Payment
Payment shall include all labor, materials, equipment, permits, BMPs, maintenance, inspections, and incidentals required to comply with all applicable storm water pollution prevention requirements, including dust control, sediment control, track-out prevention, inlet protection, and final stabilization within the project limits.
c. Payment Payment shall also include preparation, implementation, maintenance, and compliance with the Storm Water Pollution Prevention Plan (SWPPP) and all requirements of the State of Utah UPDES Permit.
Basis of Payment
Amount Paid When Paid
25% of bid item amount With first application for payment
Remaining portion of bid item paid as percentage of the contract completed
With each subsequent application for payment
SILT FENCE, Bid Item 3
Section Description a.
Measurement
Measurement shall be by the Linear Foot.
b. Payment Payment shall include furnishing, installation, maintenance, relocation, replacement, and removal of silt fence and all associated appurtenances as required by the plans, specifications, SWPPP, and Engineer.
Basis of Payment
Portion of bid item paid as percentage of the contract completed With each application for payment
TRACK OUT PAD, Bid Item 4
Section Description a.
Measurement
Measurement shall be per Each.
b. Payment Payment shall include furnishing, installation, maintenance, replacement, and removal of stabilized construction entrances and track out pads, including aggregate material, geotextile fabric, grading, and all associated appurtenances.
Basis of Payment
CLEAR & GRUB / VEGETATION REMOVAL, Bid Item 5
Section Description a.
Measurement
Measurement shall be by the Square Foot.
b. Payment
Payment shall include all labor, equipment, hauling, disposal, and incidentals necessary to clear and grub the site, remove vegetation, root systems, organic materials, miscellaneous debris, and other objectionable materials within the limits of disturbance.
c. Payment Payment shall also include lawful off-site disposal of all removed materials and protection of existing improvements designated to remain.
Basis of Payment
STRIP, STOCKPILE & REPLACE TOPSOIL, Bid Item 6
Section Description a.
Measurement
Measurement shall be by the Square Foot.
b. Payment Payment shall include stripping, stockpiling, protection, moisture conditioning, hauling, placement, grading, and fine grading of topsoil within the project limits as required by the plans and specifications.
c. Payment Payment shall also include all labor, equipment, and incidentals necessary to preserve stockpiled material and re-establish final landscape grades.
Basis of Payment
SITE GRADING / CUT-FILL, Bid Item 7
Section Description a.
Measurement
Measurement shall be by the Cubic Yard.
b. Payment Payment shall include excavation, embankment, moisture conditioning, placement, compaction, grading, hauling, disposal, proof rolling, and all labor, equipment, and incidentals required to achieve the proposed grades shown in the plans.
c. Payment Payment shall also include grading associated with parking lot improvements, drainage improvements, retention pond construction, and restoration within the limits of disturbance.
Basis of Payment
CONCRETE SIDEWALK PREP, Bid Item 8
Section Description a.
Measurement
Measurement shall be by the Square Foot.
b. Payment Payment shall include all excavation, subgrade preparation, compaction, fine grading, aggregate placement, and all labor, materials, equipment, and incidentals necessary to prepare the sidewalk section for concrete placement.
Basis of Payment
CONCRETE SIDEWALK (4" THICK), Bid Item 9
Section Description a.
Measurement
Measurement shall be by the Square Foot.
b. Payment Payment shall include furnishing and installation of concrete sidewalk, reinforcement where required, scoring, finishing, curing, protection, and all labor, materials, equipment, and incidentals necessary for a complete installation.
Basis of Payment
30" TYPE A CURB & GUTTER, Bid Item 10
Section Description a.
Measurement
Measurement shall be by the Linear Foot.
b. Payment Payment shall include excavation, preparation, forming, furnishing, placement, finishing, curing, and all labor, materials, equipment, and incidentals necessary for installation of curb and gutter.
Basis of Payment
30" REVERSE SLOPE CURB & GUTTER, Bid Item 11
Section Description a.
Measurement
Measurement shall be by the Linear Foot.
b. Payment Payment shall include excavation, preparation, forming, furnishing, placement, finishing, curing, and all labor, materials, equipment, and incidentals necessary for installation of reverse slope curb and gutter.
Basis of Payment
UNTREATED BASE COURSE (6" THICK), Bid Item 12
Section Description a.
Measurement
Measurement shall be by the Ton.
b. Payment
Payment shall include furnishing, hauling, placement, moisture conditioning, grading, compaction, proof rolling, and all labor, materials, equipment, and incidentals necessary for installation of untreated base course in accordance with the plans and specifications.
Basis of Payment
ASPHALT PAVEMENT (3" THICK), Bid Item 13
Section Description a.
Measurement
Measurement shall be by the Square Foot.
b. Payment Payment shall include furnishing, hauling, placement, rolling, compaction, tack coat, preparation of underlying surface, joints, transitions, and all labor, materials, equipment, and incidentals necessary for complete installation of asphalt pavement.
c. Payment Payment shall also include all work necessary to achieve the required pavement thickness, density, smoothness, and finish in accordance with the plans and specifications.
Basis of Payment
SEAL COAT, Bid Item 14
Section Description a.
Measurement
Measurement shall be by the Square Foot.
b. Payment Payment shall include furnishing and application of seal coat material, surface preparation, cleaning, traffic control, protection, and all labor, materials, equipment, and incidentals necessary for complete installation.
Basis of Payment
ADA RAMPS, Bid Item 15
Section Description a.
Measurement
Measurement shall be per Each.
b. Payment Payment shall include all excavation, grading, forming, detectable warning panels, concrete placement, finishing, curing, transitions, and all labor, materials, equipment, and incidentals necessary for installation of ADA-compliant ramps.
Basis of Payment
PAVEMENT MARKINGS / STRIPING / ADA SIGNS, Bid Item 16
Section Description a.
Measurement
Measurement shall be Lump Sum.
b. Payment Payment shall include layout, striping, pavement markings, ADA stall markings, directional arrows, signage, posts, installation hardware, traffic control, and all labor, materials, equipment, and incidentals necessary for complete installation.
Basis of Payment
6" CONCRETE MOW STRIP, Bid Item 17
Section Description a.
Measurement
Measurement shall be by the Linear Foot.
b. Payment Payment shall include excavation, preparation, forming, concrete placement, finishing, curing, and all labor, materials, equipment, and incidentals necessary for complete installation of mow strip.
Basis of Payment
IRRIGATION SLEEVES, Bid Item 18
Section Description a.
Measurement
Measurement shall be by the Linear Foot.
b. Payment
Payment shall include furnishing and installation of irrigation sleeves beneath pavement, sidewalks, and other improvements, including excavation, bedding, backfill, compaction, tracer wire where required, and all labor, materials, equipment, and incidentals necessary for complete installation.
Basis of Payment
12" STORM DRAIN PIPE (COMPLETE INSTALL), Bid Item 19
Section Description a.
Measurement
Measurement shall be by the Linear Foot.
b. Payment Payment shall include furnishing and installation of storm drain pipe, excavation, bedding, fittings, couplings, trenching, backfill, compaction, testing, disposal of excess material, and all labor, materials, equipment, and incidentals necessary for complete installation.
Basis of Payment
15" STORM DRAIN PIPE (COMPLETE INSTALL), Bid Item 20
Section Description a.
Measurement
Measurement shall be by the Linear Foot.
b. Payment
Payment shall include furnishing and installation of storm drain pipe, excavation, bedding, fittings, couplings, trenching, backfill, compaction, testing, disposal of excess material, and all labor, materials, equipment, and incidentals necessary for complete installation.
Basis of Payment
18" STORM DRAIN PIPE (COMPLETE INSTALL), Bid Item 21
Section Description a.
Measurement
Measurement shall be by the Linear Foot.
b. Payment
Payment shall include furnishing and installation of storm drain pipe, excavation, bedding, fittings, couplings, trenching, backfill, compaction, testing, disposal of excess material, and all labor, materials, equipment, and incidentals necessary for complete installation.
Basis of Payment
3' x 3' CATCH BASIN / INLET BOX, Bid Item 22
Section Description a.
Measurement
Measurement shall be per Each.
b. Payment Payment shall include excavation, bedding, base preparation, structure installation, frames and grates, connections, backfill, compaction, adjustment to grade, and all labor, materials, equipment, and incidentals necessary for complete installation.
Basis of Payment
STORM DRAIN MANHOLE WITH SUMP, Bid Item 23
Section Description a.
Measurement
Measurement shall be per Each.
b. Payment Payment shall include excavation, bedding, precast structure, sump construction, frame and cover, pipe connections, backfill, compaction, adjustment to grade, and all labor, materials, equipment, and incidentals necessary for complete installation.
Basis of Payment
STORM DRAIN MANHOLE, Bid Item 24
Section Description a.
Measurement
Measurement shall be per Each.
b. Payment Payment shall include excavation, bedding, precast structure, frame and cover, pipe connections, backfill, compaction, adjustment to grade, and all labor, materials, equipment, and incidentals necessary for complete installation.
Basis of Payment
RIP RAP / DRAINAGE WAY, Bid Item 25
Section Description a.
Measurement
Measurement shall be Lump Sum.
b. Payment Payment shall include excavation, grading, furnishing and placement of rip rap, filter fabric, drainage stabilization, erosion protection measures, and all labor, materials, equipment, and incidentals necessary for complete installation.
Basis of Payment
ELECTRICAL – PARKING LOT LIGHTING, Bid Item 26
a. Measurement shall be Lump Sum.
Measurement
b. Payment
Payment shall include furnishing and installation of conduits, wiring, pull boxes, light pole bases, poles, luminaires, electrical service connections, grounding, testing, coordination with utility providers, and all labor, materials, equipment, and incidentals necessary for complete installation of the parking lot lighting system.
Basis of Payment
LANDSCAPE IMPROVEMENTS (COMPLETE), Bid Item 27
Section Description a.
Measurement
Measurement shall be Lump Sum.
b. Payment
Payment shall include furnishing and installation of all landscape improvements shown in the plans and specifications, including planting, trees, shrubs, turf, seed, mulch, rock, topsoil, grading, staking, soil preparation, restoration, maintenance, warranty, and all labor, materials, equipment, and incidentals necessary for complete installation.
Basis of Payment
Amount Paid When Paid
Portion of bid item paid as percentage of the contract completed, with 10% held until final landscape acceptance
With each application for payment
Remaining 10% portion of bid item With final landscape acceptance by the Owner
IRRIGATION SYSTEM IMPROVEMENTS (COMPLETE), Bid Item 28
Section Description a.
Measurement
Measurement shall be Lump Sum.
b. Payment
Payment shall include furnishing and installation of all irrigation improvements shown in the plans and specifications, including piping, sleeves, valves, heads, drip systems, wiring, controllers, valve boxes, connections, testing, adjustments, restoration, and all labor, materials, equipment, and incidentals necessary for complete installation and operation of the irrigation system.
Basis of Payment
Amount Paid When Paid
Portion of bid item paid as percentage of the contract completed, with 10% held until final irrigation acceptance
With each application for payment
Remaining 10% portion of bid item With final irrigation acceptance by the Owner
VI. PROPOSAL EVALUATION CRITERIA
Proposals will be evaluated based on the response to all provisions of this RFP. Since this solicitation is an
RFP as opposed to a Bid, pricing alone will not constitute the entire selection criteria. The city may use some or all of the following criteria and corresponding percentages in its evaluation and comparison of proposals submitted. The criteria listed are not necessarily an all-inclusive list. The order in which they appear is not intended to indicate their relative importance. The City reserves the right to modify the evaluation criterion and percentage of the score as deemed appropriate prior to the commencement of evaluation.
Evaluation Process
Proposals will be reviewed by the individual committee members against certain criteria through a pre-prepared scoring matrix. The committee will submit their scores to the City
Purchasing Agent who will compile the scores and rank the submissions. The committee will meet to review the top three scoring firms and may schedule a 1-hour virtual or in-person presentation from each vendor. The presentations will not be scored, but the evaluation committee will, at the conclusion of all presentations, select a firm for award or withdraw the
RFP.
POTENTIAL PROPOSAL EVALUATION CRITERIA
Evaluation Criteria Description Percentage
Firm Experience Qualifications and experience of the firm. Demonstrated expertise and subject matter expertise in the requested Scope of Services
25%
Project Team Experience Qualifications and experience of the Firm’s Project Team, including the Firm’s Project Team’s demonstrated expertise and subject matter expertise in the requested Scope of Services
25%
Functional Approach The Firm’s project team demonstrates the ability to formulate a plan that includes the elements listed in the scope of work.
20%
Technical Approach The quality and clarity of the Firm’s proposal demonstrates the ability to formulate a plan that is concise and easily understood by stakeholders.
17%
Cost Project costs / fee schedule as compared to other firms. 10%
Introduction
Introductory Letter contains all the information requested.
3%
VII. POPOSAL RESPONSE OUTLINE
Proposals must be clear, concise, specific and, in an outline, format not exceeding 15 single side pages.
Font size must be an 11- or 12-point font. Paper size not to exceed 8.5 x 11 inches. Pertinent supplemental information should be referenced and provided as attachments but will not be considered part of the proposal. All proposals must be organized and tabbed to comply with the following sections. Tabs will not be counted toward page count as long as they do not contain proposal information.
Tab 1 - LETTER OF TRANSMITTAL. The letter of transmittal should include an introduction of the Project
Team: the name, address, telephone number, and email address of the person to be contacted along with others who are authorized to represent the company in dealing with this RFP.
Tab 2 - EXECUTIVE SUMMARY. Should include an introduction of the Firm and parent company: the name, address, telephone number, email address, nature of firm’s principal business, number of years in business, state and federal licensing certificates and Federal Tax Identification. Provide a brief statement that summarizes the unique qualifications of the Firm in relation to the unique and general requirements of this project. The respondent shall provide evidence of their firm’s capability to apply and commit staff and equipment successfully to the project and to complete the required services in a timely manner.
The respondent shall list all bankruptcy filings within the last ten years, and all current pending litigation involving the firm. Failure to provide full information may result in the proposal being deemed nonresponsive.
Tab 3 - DETAILED DISCUSSION. This section should constitute the major portion of the proposal and must contain:
1. Proposed Project Team Organization and Qualifications: Provide a chart that identifies the roles of each of the Key Individuals involved in each phase of the project. Firm should provide a listing of staff to be assigned to the project and commentary on their existing workload, and a description of the project management processes used to ensure work continues uninterrupted and communication with the city and firm is strong. Respondent shall provide, rather than a standard resume, only relevant experience and qualification of each technical person who will be involved on the project, including:
a. Educational background, academic degrees, professional association.
b. Current job title, responsibilities and type of work performed.
c. Experience on projects similar to that requested in this RFP.
Provide a matrix that indicates past project collaborations carried out by the proposed team.
2. Proposed Project Team Performance on Past Projects: Provide information for similar studies that demonstrate the Firm’s ability to accomplish this project. For each project identified, provide the following information: Owner, Description of Work, and Project Team Members’ involvement.
3. References: Provide a reference for each project listed above who may be contacted for further information regarding the performance of the Firm’s Project Team. The respondent should provide examples of similar projects through access to deliverables such as studies, reports, maps, images, video, etc.
4. Team Roles and Responsibilities: Provide a description of the roles and responsibilities of the
Firm’s Project Team members and how the Team will work together to achieve the objectives of the project. List any applicable sub-consultants.
5. Proposed Project Schedule: Provide a schedule that includes individual phases as applicable. The proposed schedule shall list important dates, times, and locations of meetings and submittals.
6. Proposed Project Approach: Outline the tasks, any special approaches, and the plan for completion. Innovation and alternatives to the scope proposed here are welcome.
7. Information addressing Project Objectives and Scope that have not been addressed.
Tab 4 - COST PROPOSAL. The Firm must submit a cost proposal allowing costs to be evaluated independently of other criteria in the proposal, both in grand total, as well as component pricing for logical subsets of service with any associated discounts listed separately. The cost proposal should include the method of determining compensation for the required services with a not-to-exceed cost estimate. It should also include the estimated cost to complete all of the Firm’s Basic Services.
Tab 5 – BID FORM (Attachment A), Certificate of Insurance AND MISCELLANEOUS additional information and attachments, including company literature and catalogs.
IV. INSURANCE REQUIREMENTS
Should the successful firm be invited to negotiate a contract for the work identified in this RFP, it shall have the capability of maintaining insurance and indemnification as follows to cover any claims incurred or arising as a result of the work. The Contractor / Consultant shall furnish Eagle
Mountain a Certificate of Insurance applying to the contract for each type of insurance required, to be approved by Eagle Mountain City. The Consultant’s insurer must be authorized to do business in Utah and must meet the specified A.M. Best rating or better at the time this contract is executed. The following insurance shall be maintained in force until all activities which are required by the Contract or as changed by contract modification are completed and accepted by Eagle Mountain:
a. General Liability insurance with a limit of not less than $1,000,000 per occurrence and not less than $3,000,000 aggregate and having an A.M. Best rating of A-class VIII or better. If this coverage is written on a claims-made basis, the Certificate of Insurance shall so indicate. Consultant represents that as long as commercially available the insurance shall remain in effect such that claims reported up to three (3) years beyond the date of substantial completion of this contract are covered.
b. Commercial Automobile insurance with a minimum combined single limit of $1,000,000 per occurrence OR $500,000 liability per person, $1,000,000 per occurrence, $250,000 Property Damage, and having an A.M. Best rate of A-class VIII or better.
c. Architect and/or Engineers Professional Liability (errors and omissions) insurance having an A.M.
Best rating of A-class VIII or better, is required at the coverage amount of $1,000,000 per claim and $3,000,000 aggregate. If this coverage is written on a claims-made basis, the Certificate of Insurance shall so indicate. Consultant represents that as long as commercially available the insurance shall remain in effect such that claims reported up to three (3) years beyond the date of substantial completion of this contract are covered (on construction contracts or modifications for construction management the insurance shall remain in effect for one (1) year after completion of the project).
d. Valuable Papers & Records Coverage and/or Electronic Data Processing (Data and Media) Coverage for the physical loss or destruction of the work product including drawings, plans, specifications and electronic data and media. Such insurance shall be of a sufficient limit to protect Consultant, its sub-consultants and Eagle Mountain from the loss of said information.
e. Workers Compensation Insurance: Consultant shall provide evidence that his employees and sub-consultant employees are covered by Workers Compensation. If they are covered by Workers Compensation Fund of Utah, then the A.M. Best rating is not required in this area.
f. Consultant shall require the insurance company that issues the Certificates of Insurance for the evidence of the required insurance coverage to endeavor to provide Eagle Mountain with 30-days written notice in the event that coverage is canceled before the policy expiration date stated in the Certificate. Consultant further agrees to provide Eagle Mountain with 30 days written notice prior to making an alternation or material change to the required insurance coverage. Insurance certificates and notice(s) should be sent to recorder@emcity.org.
g. Builders Risk Insurance. Builder’s Risk Insurance must be indicated by a checked box on the Certificate of Insurance (COI). The Contractor shall provide the City with the price for the Builder’s Risk Insurance coverage applicable to the project. Upon receipt of the Contractor’s quoted price, the City will obtain a comparable quote from the Utah Local Government Trust for the same policy limits. If the Utah Local Government Trust premium is lower than the Contractor’s quoted price, the City will procure the Builder’s Risk policy through the Trust. In such case, the Contractor shall reimburse the City for the cost of the policy, and the amount will be deducted from payments due under the contract.
h. Policies referred to in (a) and (b) above are required to be endorsed naming Eagle Mountain as Additional Insured and, on General Liability, indicate they are primary and not contributing coverage. All required policies, endorsements, insurance companies issuing same, and self-insured programs are subject to review and approval by Eagle Mountain.
V. TIMELINE
The following is a tentative schedule of this entire RFP process. While the City will attempt to apply the necessary resources to maintain this schedule, the following dates are merely projections. The City reserves the right to modify this schedule as needed to accommodate the completion of this RFP process.
TENTATIVE PROJECT SCHEDULE
RFP Published May 19, 2026
Questions from Firms Due May 29, 2026, at 5:00 pm
Questions and Answers Posted June 2, 2026
Proposals Due June 8, 2026, at 12:00 PM
Anticipated Contract Award June 15, 2026
VI. ADMINISTRATIVE GUIDANCE
The information provided herein is intended to assist Firms in the preparation of proposals necessary to properly respond to this RFP. The RFP is designed to provide interested Firms with sufficient basic information to submit proposals meeting minimum requirements but is not intended to limit a proposal's content or to exclude any relevant or essential data therefrom. Firms are at liberty and are encouraged to expand upon the specifications to give additional evidence of their ability to provide the services requested in this RFP.
VII. ISSUING OFFICE AND RFP REFERENCE NUMBER
Eagle Mountain City Engineering Department is the issuing office for this RFP and all subsequent addenda.
The reference number for this RFP is EMC-FY26-16. This number must be referenced on all proposals, correspondence, and documentation relating to this RFP. During the RFP process, the Purchasing Agent is the sole source of official information. All other communications regarding this RFP, both spoken and written, which are received by any representative of the Firm from other sources (such as any elected or appointed official of the city or any other city staff, unless said communication is required by the primary contact) shall result in the disqualification of the proposal. This refers to both formal and informal conversations and communications.
Contact: Melissa Yates, Purchasing Agent 1650 E Stagecoach Run Eagle Mountain, Utah 84005 Myates@EagleMountain.gov
(801) 789-6641
VIII. SUBMISSION OF PROPOSAL
Proposal RFP documents will be available online on May 13, 2026, at purchasing.utah.gov (select the search bar> select Current Bids > enter “EM” > select search.) Sealed proposals will then be accepted online only via purchasing.utah.gov procurement portal until June 8, 2026, at 12:00 PM. Proposals submitted after this deadline will be rejected. All proposals, upon submission to the City, shall become
City property.
Failure to provide a response to items indicated in this RFP will be interpreted by the city as an inability by the Firm to provide the requested service. All submittals shall be complete in all material respects and failure to provide a complete submittal may result in rejection of the response.
IX. BID BOND/PAYMENT BOND/PERFORMANCE BOND
A bid or proposal must be accompanied by a bid security made payable to Owner in an amount of 5% of
Bidder’s maximum bid price and in the form of a Bid bond issued by a surety. The cost of the bid bond should be entered as a line item in the RFP cost proposal.
The Bid security of the Successful Bidder will be retained until such Bidder has executed the Contract
Documents, furnished the required contract security, and met the other conditions of the Notice of
Award, whereupon the Bid security will be returned. If the Successful Bidder fails to execute and deliver the Contract Documents and furnish the required contract security within 15 days after the Notice of
Award, Owner may annul the Notice of Award and the Bid security of that Bidder will be forfeited. The
Bid security of other Bidders whom Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of seven days after the Effective Date of the Agreement or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be returned.
100% Performance Bond and 100% Payment Bond will be required upon award and signing of a contract.
X. VENDOR PREQUALIFICATION
All potential vendors are required to register with Eagle Mountain City prior to doing business. You may complete required prequalification forms by going to EagleMountain.gov/purchasing. Fill out the vendor prequalification form and submit W9.
The City may conduct such investigations as the City deems necessary to establish the responsibility, qualifications, and financial ability of Bidders, proposed Subcontractors, Suppliers, individuals, or entities to perform the Work in accordance with the contract Documents.
XI. INQUIRIES
Questions arising subsequent to the issuance of this RFP shall be submitted in writing through the State of Utah’s online procurement portal. Questions and answers will be posted online or consolidated and provided to all Firms on record of receiving this RFP on the procurement portal. All inquiries must be submitted by the close of business (5:00 PM MST) on May 29, 2026. Questions submitted after the deadline will not be addressed.
XII. RESPONDENT’S RESPONSIBILITY FOR PROPOSAL COSTS
The City is not liable for any cost incurred by Firms associated with the preparation of the proposal or the negotiation of a contract for services prior to the issuance of the contract.
XIII. EVALUATION OF PROPOSALS
The City may award a contract based on initial proposals received without discussion of such proposals with the Firm. Accordingly, each initial proposal should be submitted with the most favorable price and service available.
In evaluating proposals, the city will consider whether or not the proposals comply with the prescribed requirements, and such alternates, unit prices and other data, as may be requested in the proposal or prior to the Notice of Award. Evaluation committee members will evaluate and rank each submittal based on required information provided. Evaluation factors are based on the abilities of the proposer to efficiently perform the Scope of Services as generally outlined in the Request for Proposals. The city will be seeking to identify the submittal(s) which will best meet the needs of Eagle Mountain City as determined from the responses to the Request for Proposals.
The City will also consider the qualifications of Bidders and may consider the qualifications and experience of Subcontractors, Suppliers, and other individuals or entities proposed for those portions of the Work for which the identity of Subcontractors, Suppliers, and other individuals or entities. During the evaluation process and at the sole discretion of the City, requests for clarification of one or more proposer’s submittals may be conducted. This request for clarification may be performed by the city in a written format, or through scheduled oral interviews. Such clarification request will provide proposers with an opportunity to answer any questions the City may have on a proposer’s submittal.
XIV. KEY COMPANY PERSONNEL
In submitting a proposal package, the Respondent is representing that each person listed or referenced in the proposal package shall be available to perform the services described for the city, barring illness, accident, or other unforeseeable events of a similar nature in which case the Respondent must be able to promptly provide a qualified replacement. In the event the Respondent wishes to substitute personnel, the Respondent shall propose a person with equal or higher qualifications and each replacement person is subject to prior written city approval. In the event the requested substitute person is not satisfactory to the city and the matter cannot be resolved to the satisfaction of the city, EAGLE MOUNTAIN CITY reserves the right to cancel the contract for cause.
XV. AWARD OF THE CONTRACT
Upon completion of the evaluation process, the City may negotiate with and award the contract to the
Firm whose proposal is determined to be most advantageous and produces the best possible outcome for the city. If detailed in the proposal, factors such as additive alternate bids, discounts, transportation costs, and life cycle costs may be used to determine which bidder, if any, is offered the award. It is understood that the city is not obligated to make an award under or as a result of this RFP or to award such contract.
The parties must execute the contract prior to the commencement of performance. The contract will incorporate the provisions of this RFP (including any addenda) and other terms negotiated by the parties.
By submitting a signed proposal, the Firm agrees to the provisions of the contract described herein.
XVI. PROTECTED INFORMATION
Under the Government Records Access and Management Act, Section 63-2-101 et seq., Utah Code Ann.
(1993 and supp. 1996), as amended ("GRAMA"), the proposal submitted is open for public inspection. If the Firm desires to have information contained in its proposal protected from such disclosure, the Firm may request such treatment by providing a "written claim of business confidentiality and a concise statement of reasons supporting the claim of business confidentiality" with the proposal (GRAMA, Section
63G-2-309). All material contained in and/or submitted with the proposal becomes the Owner's property and may be returned only at the Owner's option. A business confidentiality claim form is available on the
Utah State Records Committee website:
https://eaglemountaincity.com/wp-content/uploads/2022/10/GRAMA-Claim-of-Business-
Confidentiality-Fillable.pdf
XVII. ADDENDUM TO RFP
In the event that it becomes necessary to review this RFP in whole or in part, an addendum will be provided to all Firms on record as having received this RFP through the State of Utah’s online procurement portal.
XVIII. AUTHORIZED REPRESENTATIVES
The proposal or bid must contain the signature of a duly authorized officer, or agent of the Firm’s company empowered with the right to bind the Firm for the amounts estimated and terms proposed. The Firm must also provide evidence of the authority of the officer or agent to bind the Firm. The owner shall have the option to change the Firm’s contact person if it is in the best interest of the Owner.
Include this information within the "Letter of Transmittal", which will be tabbed section "1" of a successful proposal.
XIX. ANTI-COLLUSION
The submission of a proposal constitutes agreement that the Firm has not divulged its proposal to, or conspired with, any other Firm or party to a proposal whatsoever.
This Bid is genuine and not made in the interest of or on the behalf of any undisclosed individual or entity and is not submitted in conformity with any agreement or rules of any group, association, organization, https://eaglemountaincity.com/wp-content/uploads/2022/10/GRAMA-Claim-of-Business-Confidentiality-Fillable.pdf https://eaglemountaincity.com/wp-content/uploads/2022/10/GRAMA-Claim-of-Business-Confidentiality-Fillable.pdf or corporation. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract.
XX. RESTRICTIONS / CONFLICT OF INTEREST
All proposals must clearly set forth any restrictions or provisions deemed necessary by the Firm to effectively service the proposed Contract.
If any officer, director, or agent of your organization is also an employee of Eagle Mountain City, then you shall clearly identify in your response the name of the individual(s) and the position he or she holds in your organization. Further, you shall disclose the name(s) of any City employee(s) who owns, directly or indirectly, any interest in your organization or any of its branches. This does not include stock in a publicly traded organization unless the individual holds more than a ten-percent (10%) stake.
XXI. RIGHT TO REJECT
The City reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. The City further reserves the right to reject the Bid of any Bidder whom it finds, after reasonable inquiry and evaluation, to be non-responsible. The City also reserves the right to waive all informalities or technicality in any bid or proposal in the interest of the City not involving price, time, or changes in the Work and to negotiate contract terms with the Successful
Bidder. The city has the sole discretion and reserves the right to cancel this RFP, and to waive any and all informalities and/or irregularities, or to re-advertise with either the identical or revised specifications, if it is deemed to be in the city’s best interests to do so.
XXII. PRIVACY NOTICE
Eagle Mountain City is committed to protecting your privacy. The personal data you provide for bids/proposals is collected for the purpose of processing submitted bidding documentation, permit applications, verifying identity, and contracts and will be used only for those purposes. If you choose not to provide the requested information, we may be unable to process your request or provide the service you are seeking. Your information will not be sold and is not regularly disclosed to any private or governmental entities. However, it may be shared when required by law or contract. The information collected is maintained in the Eagle Mountain Recorders office in accordance with the City's retention records schedule. Some personal data may still be subject to public disclosure as required by the Utah
Government Records Access and Management Act (GRAMA), Utah Code § 63G-2-101 et seq.”
ATTACHMENT A
Bid Form
Project Name: EMC Cory Wride Phase 2 South Parking Lot
Project Number: EMC-FY26-16
ARTICLE 1 - BID RECIPIENT
1.01 This Bid Is Submitted To: EAGLE MOUNTAIN CITY
1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with
Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in the Bid and in accordance with the other terms and conditions of the Bidding Documents.
ARTICLE 2 - BIDDER’S ACKNOWLEDGMENTS
2.01 Bidder accepts all of the terms and conditions of the Advertisement and Instructions to Bidders, including without limitations those dealing with the dispositions of Bid security. The Bid will remain subject to acceptance for 30 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.
ARTICLE 3 - BIDDER’S REPRESENTATIONS
3.01 In submitting this Bid, Bidder represents that:
A. Bidder has examined and carefully studied the Bidding Documents, the other related data identified in the Bidding Documents, and the following Addenda, receipt of which is hereby acknowledged:
Addendum No. Addendum Date
B. Bidder has visited the Site and become familiar with and is satisfied as to the general, local, and
Site conditions that may affect cost, progress, and performance of the Work.
C. Bidder is familiar with and is satisfied as to all Federal, state, and local Laws and Regulations that may affect cost, progress, and performance of the Work.
D. Bidder has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities) which have been identified in SC-4.02, and (2) reports and drawings of Hazard Environmental
Conditions, if any, at the Site that have been identified in SC-4.06 as containing reliable
“technical data.”
E. Bidder has considered the information known to Bidder; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by
Bidder, including applying the specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents; and (3) Bidder’s safety precautions and programs.
F. Based on the information and observations referred to in Paragraph 3.01.E above, Bidder does not consider that any further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance of the Work at the price(s) bid and within the times and in accordance with the other terms and conditions of the Bidding Documents.
G. Bidder is aware of the general nature of the Work to be performed by Owner and others at the
Site that relates to the Work as indicated in the Bidding Documents.
H. Bidder has given Purchasing Agent written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and the written resolution thereof by Purchasing Agent is acceptable to Bidder.
I. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work for which this Bid is submitted.
J. Bidder will submit written evidence of its authority to do business in the State or other jurisdiction where the Project is located not later than the date of its execution of the
Agreement.
ARTICLE 4 - ATTACHEMENTS TO THIS BID
4.01 The following documents are attached to and made a condition of the Bid:
A. Bid Form
B. Construction Agreement C. Bid Set plans volume 1 & 2 D. Bid Set Specifications
ARTICLE 5 - BID SUBMITTAL
5.01 This Bid is submitted by:
An Individual
Name (typed or printed): ____________________________________________________
By: _____________________________________________________________________
(Individual’s signature)
Doing business as: _______________________________________________________________
A Partnership
Partnership Name: _________________________________________________________
By: _____________________________________________________________________
(Signature of general partner -- attach evidence of authority to sign)
Name (typed or printed): __________________________________________________________
A Corporation
Corporation Name: _______________________________________________________________
State or Jurisdiction of Incorporation: ______________________________
Type (General Business, Profession, Service, Limited Liability): ___________________________
By: ___________________________________________________________________
(Signature -- attach evidence of authority to sign)
Name (typed or printed): ___________________________________________________________
Title: ____________________________________________
Attest ____________________________________________________________
SEAL,
if required by State
SEAL,
if required by State
CORPORAT
E SEAL,
if required by
State
(Signature of Corporate Secretary)
Date of Qualification to do business in ____________ [State or other jurisdiction where Project is located] is ___/___/______
A Joint Venture
Name of Joint Venture: ________________________________________________________
First Joint Venture Name:…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .