This document provides operational control procedures for construction contractors working on federal projects. It outlines requirements for stormwater discharges, solid waste management, electrical safety, fall protection, and physical hazards. Contractors must comply with permits, ordinances, and plans to control stormwater runoff and dispose of waste properly. All electrical systems must be de-energized and locked out for worker safety. Personnel must receive training on fall protection and use equipment like ladders and scaffolding appropriately. Personal protective equipment such as hard hats and steel-toed boots is required for physical hazards like sharp edges, flying debris, and heavy equipment. Inspections will be conducted by federal representatives to ensure safety compliance.

View the file

Other files for this federal contract opportunity

Other files attached to MMAC Mobile Test Bed Facility, newest first.
File Type Posted
6973GH-24-R-00011-0002.pdf PDF
15. 20-042069 MSTB Geotech.pdf PDF
13. 6973GH-24-R-00011;Questions and Answers.pdf PDF
14. FAA_MSTB_Addendum-001_231115.pdf PDF
6973GH-24-R-00011-0001.pdf PDF
2. SOW 20-042069 Mobile Systems Test Bed.pdf PDF
12. Contractor Release.pdf PDF
6973GH-24-R-00011.pdf PDF
3. 20-042069 MSTB REBID SPECIFICATIONS.pdf PDF
6. Attachment F-4 - 20-042069 Mobile Systems Test Bed.pdf PDF
7. Past Performance Experience Information Form.docx DOCX document
8. Past Performance Survey.docx DOCX document
11. SF 25A Payment Bond.pdf PDF
9. Wage Rate Decision No_OK 20230049.pdf PDF
10. SF 25 Performance Bond.pdf PDF
1. Section B - Supplies or Services-Prices.xlsx XLSX spreadsheet
4. 20-042069 MSTB REBID DRAWINGS.pdf PDF
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMP400-ENV-OC-2.4.3-CC

(Storm and Surface Water Discharges - Construction Contractors)

Document Revision Log

Status (Baseline/ Revision/

Admin Change/

Canceled)

Document Revision

Effective Date Description

Baseline 0.0 11/9/2016 Initial Release

Revision 1.0 5/15/17 Update NO CHANGE 5/15/18 RKH

NO CHANGE 5/8/19 RKH

NO CHANGE 02/09/21 KC

Kou Chang Typewritten Text

NO CHANGE 03/02/22 KC

Kou Chang Typewritten Text

NO CHANGE 04/27/23 KC

Revision: 0.0 Document Number: AMP400-ENV-OC-2.4.3-CC

UNCONTROLLED COPY WHEN DOWNLOADED

Verify That This Is The Correct Revision Before Use

Operational Control Document

1. Significant Environmental Aspect and/or Significant OSH Hazard:

Storm and Surface Water Discharges - Construction Contractors

2. Document Control Code:

AMP400-ENV-OC-2.4.3-CC

3. Source of Aspect/Hazard (activities):

Construction activities causing land disturbances/ Storage of construction material

4. Compliance Obligations (specific to activities):

MMAC-EMP-2.4.3

5. Operational Controls (such as engineering, administrative where applicable):

Comply with OPDES permit, City OF OKC ordinances and MMAC SWPP

Construction contractor training on the MMAC stormwater pollution prevention policy

Inspection of construction worksites

6. Maintenance plan(s) for the operational controls:

Review this document annually and update as necessary

7. Actions to be taken if controls fail:

AMP-400 inspectors send advisory notices if environmental protection measures are not maintained.

8. Record(s):

Advisory notices.

Construction contractor training (required for badging).

Stormwater awareness training.

9. Responsibility:

Controls (from Section 5 above) Responsible Individual

Comply with OPDES permit, City OF OKC ordinances and MMAC SWPP

Site Supervisor – Construction Contractor

Contractor awareness training Site Supervisor – Construction Contractor

Construction site inspections AMP-400 Inspectors – Contract Support

10. Competency (as evidenced by training, experience, or education.)

Title or Name Competence

Construction Contractor See signature in Section K (Clause 4560 of contract)

(Certification of Contractor Conformance to the MMAC EOSHMS)

AMP-400 Inspectors See signature in Section K (Clause 4560 of contract)

(Certification of Contractor Conformance to the MMAC EOSHMS)

Kou Chang Text Box 1.0

Revision: 0.0 Document Number: AMP400-ENV-OC-2.4.3-CC

UNCONTROLLED COPY WHEN DOWNLOADED

Verify That This Is The Correct Revision Before Use

Authorization Date

Kou Chang

AMP400-ENV-OC-2.5-CC

(Solid Waste Generation – Construction Contractor)

Document Revision Log

Status (Baseline/ Revision/

Admin Change/

Canceled)

Document Revision

Effective Date Description

Baseline 0.0 11/9/2016 Initial Release

Revision 1.0 5/15/17 Update NO CHANGE 5/15/18 RKH

NO CHANGE 5/8/19 RKH

NO CHANGE 02/09/21 KC

Kou Chang Typewritten Text

NO CHANGE 03/02/22 KC

Kou Chang

Revision: 1.0 Document Number: AMP400-ENV-OC-2.5-CC

UNCONTROLLED COPY WHEN DOWNLOADED

Verify That This Is The Correct Revision Before Use

Operational Control Document

1. Significant Environmental Aspect and/or Significant OSH Hazard:

Solid Waste Generation - Construction Contractor

2. Document Control Code:

AMP400-ENV-OC-2.5-CC

3. Source of Aspect/Hazard (activities):

Generation of construction debris

4. Compliance Obligations (specific to activities):

MMAC-EMP-2.5

5. Operational Controls (such as engineering, administrative where applicable):

Reduce the amount of construction waste where possible

Recycle construction materials where possible.

Submit monthly waste management report to AMP-100 for projects over $100,000

6. Maintenance plan(s) for the operational controls:

Review this document annually and update as necessary

7. Actions to be taken if controls fail:

Conduct after-action meetings to discuss necessary corrective actions.

8. Record(s):

Certificate of contractor conformance (AAQ record)

Monthly waste management reports

9. Responsibility:

Controls (from Section 5 above) Responsible Individual

Reduce construction waste and recycle where possible

Construction Contractor

Monthly waste management report Construction Contractor

10. Competency (as evidenced by training, experience, or education.)

Title or Name Competence

Construction Contractor See signature in Section K (Clause 4560 of contract)

(Certification of Contractor Conformance to the MMAC EOSHMS)

Authorization Date

Kou Chang

AMP400-OSH-OC-3.1-CC

(Electrical – Construction Contractor)

Document Revision Log

Status (Baseline/ Revision/

Admin Change/

Canceled)

Document Revision

Effective Date Description

Baseline 0.0 11/9/2016 Initial Release

Revision 1.0 5/15/17 Update NO CHANGE 5/15/18 RKH

NO CHANGE 5/8/19 RKH

NO CHANGE 02/19/21 KC

Kou Chang Typewritten Text

NO CHANGE 03/02/22 KC

Kou Chang

Revision: 0.0 Document Number: AMP400-OSH-OC-3.1-CC

UNCONTROLLED COPY WHEN DOWNLOADED

Verify That This Is The Correct Revision Before Use

Operational Control Document

1. Significant Environmental Aspect and/or Significant OSH Hazard:

Electrical – Construction Contractor

2. Document Control Code:

AMP400-OSH-OC-3.1-CC

3. Source of Aspect/Hazard (activities):

Removal and installation of circuits and equipment during the demolition, construction or remodeling phases. Unknown circuits may be energized during the demolition phase

4. Compliance Obligations (specific to activities):

MMAC-OSHMP-3.1

5. Operational Controls (such as engineering, administrative where applicable):

Circuits are de-energized and locked or tagged out prior to work

Electrical systems and componenets are installed by certified electricians.

Electrical plans and safety concerns are discussed during pre-construction meetings

Construction inspections

6. Maintenance plan(s) for the operational controls:

Review this document annually and update as necessary

7. Actions to be taken if controls fail:

AMP-400 inspector will initiate an advisory notice if safety hazards are observed and not immediately corrected

8. Record(s):

Construction contractor training (required for badging)

Advisory notices

9. Responsibility:

Controls (from Section 5 above) Responsible Individual

Ensure personnel are trained to appropriate levels of electrical safety

Site Supervisor - Construction Contractor

System lockout/tagout Site Supervisor - Construction Contractor

Construction site inspections AMP-400 Inspectors – Contract Support

10. Competency (as evidenced by training, experience, or education.)

Title or Name Competence

Construction Contractor

See signature in Section K (Clause 4560 of contract)

(Certification of Contractor Conformance to the MMAC EOSHMS)

Kou Chang

Revision: 0.0 Document Number: AMP400-OSH-OC-3.1-CC

UNCONTROLLED COPY WHEN DOWNLOADED

Verify That This Is The Correct Revision Before Use

AMP-400 Inspectors See signature in Section K (Clause 4560 of contract)

(Certification of Contractor Conformance to the MMAC EOSHMS)

Authorization Date

Kou Chang

AMP400-OSH-OC-5.1-CC

(Falls – Construction Contractors)

Document Revision Log

Status (Baseline/ Revision/

Admin Change/

Canceled)

Document Revision

Effective Date Description

Baseline 0.0 11/9/16 Initial Release

Revision 1.0 5/15/17 Update NO CHANGE 5/15/18 RKH

NO CHANGE 5/8/19 RKH

NO CHANGE 02/09/21 KC

Kou Chang Typewritten Text

NO CHANGE 03/02/22 KC

Kou Chang

Revision: 0.0 Document Number: AMP400-OSH-OC-5.1-CC

UNCONTROLLED COPY WHEN DOWNLOADED

Verify That This Is The Correct Revision Before Use

Operational Control Document

1. Significant Environmental Aspect and/or Significant OSH Hazard:

Falls - Construction Contractors

2. Document Control Code:

AMP400-OSH-OC-5.1-CC

3. Source of Aspect/Hazard (activities):

Work on elevated surfaces

Work on ladders and scaffolding

Use of stairs and ramps

Trip hazards from equipment, tools, cords, stairs, curbs, uneven surfaces, etc.

Slip hazards from wet floors, ice on ground, leaking equipment, etc.

4. Compliance Obligations (specific to activities):

MMAC-OSHMP-5.1

5. Operational Controls (such as engineering, administrative where applicable):

Ensure personnel are trained to levels appropriate to their exposure to fall hazards

Visual inspection of portable ladders prior to each use

Scaffolds are inspected by competent person qualified in scaffold erection prior to use and daily thereafter

Inspections of construction worksites

6. Maintenance plan(s) for the operational controls:

Review this document annually and update as necessary

7. Actions to be taken if controls fail:

AMP-400 inspector will initiate an advisory notices if safety hazards are observed and not immediately corrected.

Conduct after-action meetings to discuss necessary corrective actions.

8. Record(s):

Construction contractor training (required for badging)

Advisory notices

9. Responsibility:

Controls (from Section 5 above) Responsible Individual

Ensure personnel are trained to appropriate levels of fall protection

Site Supervisor - Construction Contractor

Visual inspection of portable ladders Site Supervisor - Construction Contractor

Scaffold inspections Site Supervisor - Construction Contractor

Construction site inspections AMP-400 Inspectors – Contract Support

Kou Chang

Revision: 0.0 Document Number: AMP400-OSH-OC-5.1-CC

UNCONTROLLED COPY WHEN DOWNLOADED

Verify That This Is The Correct Revision Before Use

Construction Contractor See signature in Section K (Clause 4560 of contract) (Certification of Contractor

Conformance to the MMAC EOSHMS)

AMP-400 Inspectors See signature in Section K (Clause 4560 of contract) (Certification of Contractor

Conformance to the MMAC EOSHMS)

Authorization Date

Kou Chang

AMP400-OSH-OC-8.1-CC

(Physical – Construction Contractor)

Document Revision Log

Status (Baseline/ Revision/

Admin Change/

Canceled)

Document Revision

Effective Date Description

Baseline 0.0 11/9/16 Initial Release

Revision 1.0 5/8/19 Changed maximum wind speeds NO CHANGE 02/09/21 KC

Kou Chang Typewritten Text

NO CHANGE 03/02/22 KC

Kou Chang

Revision: 1.0 Document Number: AMP400-OSH-OC-8.1-CC

UNCONTROLLED COPY WHEN DOWNLOADED

Verify That This Is The Correct Revision Before Use

Operational Control Document

1. Significant Environmental Aspect and/or Significant OSH Hazard:

Physical – Construction Contractor

2. Document Control Code:

AMP400-OSH-OC-8.1-CC

3. Source of Aspect/Hazard (activities):

Sharp edges are exposed during construction, demolition and remodeling on sheet metal, glass edges, broken tile, and tools

Flying debris and particles may be emitted during drilling, grinding, sawing, welding, and wind gusts

Crushing may occur from hammering activities, heavy equipment operation, falling structures and equipment, and excavation cave-in

Use of power tools, powder actuated tools, jack hammers, sledge hammers, saws, etc…

4. Compliance Obligations (specific to activities):

MMAC-OSHMP-8.1

5. Operational Controls (such as engineering, administrative where applicable):

Appropriate Personal Protective Equipment (PPE) is worn as necessary (gloves, hard hats, safety glasses, steel toed boots, etc.).

Roof work prohibited in winds of 23 MPH sustained / 35 MPH gusts or more.

Trench boxes / shoring or 1.5:1 slope of occupied trenches.

Power tools are used in accordance with manufacturer guidelines.

Machine and tool guards are used as appropriate.

Inspection of construction worksites.

6. Maintenance plan(s) for the operational controls:

Review this document annually and update as necessary

7. Actions to be taken if controls fail:

AMP-400 inspector will initiate an advisory notices if safety hazards are observed and not immediately corrected.

8. Record(s):

Construction contractor training (required for badging)

Advisory notices

9. Responsibility:

Controls (from Section 5 above) Responsible Individual

PPE is worn as necessary Site Supervisor - Construction Contractor

Construction site inspections AMP-400 Inspectors – Contract Support

Revision: 1.0 Document Number: AMP400-OSH-OC-8.1-CC

UNCONTROLLED COPY WHEN DOWNLOADED

Verify That This Is The Correct Revision Before Use

Construction Contractor See signature in Section K (Clause 4560 of contract)

(Certification of Contractor Conformance to the MMAC EOSHMS)

AMP-400 Inspectors See signature in Section K (Clause 4560 of contract)

(Certification of Contractor Conformance to the MMAC EOSHMS)

Authorization Date

AMP400-ENV-OC-2.4.3-CC (Storm and Surface Water Discharges - Construction contractors)
AMP400-ENV-OC-2.5-CC (Solid Waste Generation - Construction contractors)
AMP400-OSH-OC-3.1-CC (Electrical - Construction Contractors)
AMP400-OSH-OC-5.1-CC (Falls - Construction Contractors)
AMP400-OSH-OC-8.1-CC (Physical - Construction Contractors)
Date1_af_date: 3/22/21
Date1_af_date: 3/22/21
Date1_af_date: 3/22/21
Date2_af_date: 3/22/21
Date: 3/22/21

File details come from the government source that posted it. Updated .