This scope of work document outlines the requirements for a construction project to improve the site and construct a new Mobile Systems Test Bed training building at the Mike Monroney Aeronautical Center in Oklahoma City, Oklahoma. The project includes demolishing existing facilities, grading the site, installing utilities and infrastructure, and constructing a new 5,262 square foot pre-engineered metal building. Requirements include general site work, building construction, interior finishes, mechanical and electrical systems. The contractor must coordinate all work, obtain necessary permits, and complete the project within 365 calendar days while minimizing disruption to existing facility operations. The related federal contract opportunity is solicitation number 6973GH-24-R-00011 from the Department of Transportation Federal Aviation Administration Franchise Acquisition Services for the MMAC Mobile Test Bed Facility project.

View the file

Other files for this federal contract opportunity

Other files attached to MMAC Mobile Test Bed Facility, newest first.
File Type Posted
15. 20-042069 MSTB Geotech.pdf PDF
6973GH-24-R-00011-0002.pdf PDF
13. 6973GH-24-R-00011;Questions and Answers.pdf PDF
14. FAA_MSTB_Addendum-001_231115.pdf PDF
6973GH-24-R-00011-0001.pdf PDF
12. Contractor Release.pdf PDF
8. Past Performance Survey.docx DOCX document
11. SF 25A Payment Bond.pdf PDF
9. Wage Rate Decision No_OK 20230049.pdf PDF
10. SF 25 Performance Bond.pdf PDF
6973GH-24-R-00011.pdf PDF
3. 20-042069 MSTB REBID SPECIFICATIONS.pdf PDF
5. AMP400 OC Construction contractors combined.pdf PDF
6. Attachment F-4 - 20-042069 Mobile Systems Test Bed.pdf PDF
7. Past Performance Experience Information Form.docx DOCX document
1. Section B - Supplies or Services-Prices.xlsx XLSX spreadsheet
4. 20-042069 MSTB REBID DRAWINGS.pdf PDF
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

20-042069 Mobile Systems Test Bed

PAGE

TABLE OF CONTENTS 1

1.0 GENERAL 2

1.1 DESCRIPTION OF FACILITY/WORK 2

1.2 CONSTRUCTION DURATION 2

1.3 CONTRACTOR USE OF PREMISES 2

1.4 COORDINATION AND ON-SITE SUPERVISION 3

1.5 FIELD ENGINEERING 3

1.6 CUTTING AND PATCHING 3

1.7 SUBMITTAL REQUIREMENTS 3

1.8 SHOP DRAWINGS 4

1.9 SAMPLES 4

1.10 CONSTRUCTION PROGRESS SCHEDULE 4

1.11 QUALITY ASSURANCE-CONTROL OF INSTALLATION 4

1.12 INSPECTION AND TESTING LABORATORY SERVICES 4

1.13 TEMPORARY FACILITIES 4

1.14 BARRIERS AND FENCING 4

1.15 PROTECTION OF NEW WORK 4

1.16 PROTECTION OF EXISTING EQUIPMENT AND BUILDING 4

1.17 CONDUCT OF WORK 5

1.18 SECURITY 5

1.19 WORK HOURS 5

1.20 STARTING SYSTEMS OR EQUIPMENT 5

1.21 FINAL CLEANING 5-6

1.22 PROJECT RECORD DOCUMENT 6

1.23 CODES AND PERMITS 6

2.0 PRODUCTS AND EXECUTION 6

2.1 PROJECT DRAWINGS AND SPECIFICATIONS 6

1.0 GENERAL

1.1 DESCRIPTION OF FACILITY/WORK

A. The scope of work for the Mobile Systems Test Bed at the Mike Monroney Aeronautical Center in Oklahoma City, OK includes:

1. Improve the site and construct a new Mobile Systems Test Bed training building.

The project includes a new 5,262 gross square foot building and related site improvements. Work includes, but is not limited to: Site demolition, site grading, soil preparation, paving, utilities, concrete foundations, pre-engineered metal building structure, building envelope, doors, garage doors, windows, interior finishes, equipment, signage, fire suppression, plumbing, HVAC system, electrical power & lighting, CCTV camera system, security system, public address system, fire alarm, telecom, lightning protection system, and other items as noted on the drawings and specifications.

2. All work done must meet all the requirements indicated in the project drawings and specifications.

3. The project is located at: Mike Monroney Aeronautical Center (MMAC) 6500 S.

MacArthur Blvd., Oklahoma City, OK 73169. The construction site is located on the south side of SW 61st Street, east of Foster Drive and west of Building 232.

1.2 CONSTRUCTION DURATION

A. The contract duration for this project is 365 calendar days. The contractor will be working in an operating environment.

B. Contractor must be adequately staffed to complete all construction during contract days allotted.

1.3 CONTRACTOR USE OF PREMISES

A. The Contractor will limit their activities to the areas shown on the drawings.

B. Existing facility operations:

1. The MMAC facility is a 24-hour, 7-day per week operating facility.

2. Coordinate all construction activity with the Contracting Officer’s Representative (COR) so as not to interfere with the functions of the facility.

3. Plan and coordinate so normal facility operations may continue with minimum of disruption or interference.

1.4 COORDINATION AND ON-SITE SUPERVISION

A. The contractor must coordinate scheduling, submittals, and work of the various sections of the specifications to assure efficient and orderly sequence of installation of independent construction elements. The contractor must have a designated supervisor on site during all phases of construction activities. This person must be responsible for ensuring that the provisions of the contract are followed by all contractors.

1.5 FIELD ENGINEERING

A. Establish elevations, lines and levels and verify the elevations and location of the work conform with Contract Documents or requirements.

1.6 CUTTING AND PATCHING

A. Employ skilled and experienced installers to perform cutting and patching new work;

restore work with new products except as noted.

1.7 SUBMITTAL REQUIREMENTS

A. Submit product data for project materials to the COR for approval.

B. Submit Operation and Maintenance literature for project materials to COR for approval. Information must include any required maintenance for system operation and listing and source of replacement parts for system.

C. Submit any manufacturer’s warranty information, final system testing certificates and project as-built information after completion of the project.

D. The Contractor must provide the following information on all submittals:

1. Date

2. Name of Project

3. Specification section number and title

4. Name of Contractor or Subcontractor

5. Contractor’s stamped approval certifying he checked and coordinated the work of other trades

E. The FAA must have seven (7) working days to review the contractor submittals. Any delay as a result of submittal disapproval and required re-submittal must not be grounds for any contract adjustment. Receive submittal approval prior to starting the work. All materials installed in the work must match the approved submittals. After a submittal has been approved, no substitutions will be permitted without written approval by the COR.

1.8 SHOP DRAWINGS

See project drawings and specifications.

1.9 SAMPLES

1.10 CONSTRUCTION PROGRESS SCHEDULE

A. A waterfall type schedule for this construction project must be submitted and readjusted as required for the project.

1.11 QUALITY ASSURANCE-CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, products, services, site conditions and workmanship, to produce work of a specific quality.

B. Comply fully with manufacturer’s instructions.

C. Comply with specified standards as a minimum quality for the work except were mor stringent tolerances, codes, or specific requirements indicate higher standards or more precise workmanship.

1.12 INSPECTION AND TESTING LABORATORY SERVICES

A. The contractor is responsible for providing all testing and inspection as required in specification sections.

B. Submit name of independent laboratory.

1.13 TEMPORARY FACILITIES

1.14 BARRIERS AND FENCING

1.15 PROTECTION OF NEW WORK

The Contractor must protect new work until accepted by FAA.

1.16 PROTECTION OF EXISTING BUILDINGS AND IMPROVEMENTS

A. Provide dust control as required.

B. Provide water runoff control as indicated on the drawings and in the specifications.

1.17 CONDUCT OF WORK

Maintain area free of waste materials, debris, and rubbish. Maintain site in clean and orderly condition.

1.18 SECURITY

Provide list of contractor’s key personnel who will require badged access to COR prior to the notice-to-proceed date. Keep list current during project work.

1.19 WORK HOURS

A. Normal work hours are between 7:00 a.m. and 6:00 p.m., Monday through Friday. The contractor must coordinate work activities outside these hours with the COR.

B. Notify the COR at least 48 hours in advance if Contractor intends to work overtime and one (1) week in advance prior to weekend or holiday work.

1.20 STARTING SYSTEMS OR EQUIPMENT

A. Provide seven (7) working days notification prior to the start-up of each item.

B. Ensure that each piece of equipment or system is ready for operation.

C. Execute start-up under supervision of responsible person in accordance with manufacturers’ instructions.

D. Submit a written report that equipment or system has been properly installed and is functioning correctly.

1.21 FINAL CLEANING

A. Execute final cleaning prior to final inspection.

B. Clean interior and exterior surfaces exposed to view. Vacuum carpeted and soft surfaces.

C. Clean debris from site.

D. Remove waste and surplus materials, rubbish, and construction facilities from the MMAC property. In accordance with EO 13514, FAA is required to divert from landfill or incineration facility disposal a minimum of 50% of non-hazardous waste generated as a result of its operations. In support of meeting this requirement and to minimize the environmental impact of maintenance activities, the Contractor must divert from landfill or incineration facility disposal a minimum of 50% of non-hazardous waste and 50% of construction and demolition material and debris generated as a result of the Contractor’s work, to the maximum extent feasible. The Contractor must report non-hazardous waste diversion rates on a regular basis. The Whole Building Design Guide (http://wbdg.org) outlines recommended practices for construction waste and debris removal.

E. Restore all exteriors areas to pre-work conditions. Sod will be used, not seed.

Contractor is responsible to establish sod by watering.

1.22 PROJECT RECORD DOCUMENT

A. Maintain on site, one set of construction documents to be utilized for record drawings.

B. Record revisions to the work. Record information concurrent with construction progress.

C. Specifications: Legibly mark each item to record actual construction.

D. Record documents and shop drawings. Legibly mark each item to record actual construction.

E. Submit documents to the COR for approval prior to final inspection.

1.23 CODES AND PERMITS

A. Perform all work in accordance with the current edition of International Building Code (IBC), International Plumbing Code (IPC), International Mechanical Code (IMC), International Electric Code (IEC) and other codes referenced the project drawings and specifications.

B. Building permits will be required for this project.

2.0 PRODUCTS AND EXECUTION

2.1 PROJECT DRAWINGS AND SPECIFICATIONS

Refer to project drawings and specifications regarding products and execution.