5. 20-042069 projected const schedule with dates, REVISED 5-31-23.pdf

PDF 88 KB Posted

Attached to
6973GH-23-R-00143; 20-042069 Mobile Test Bed Facility Federal contract opportunity
Solicitation number
6973GH-23-R-00143
Issued by
Department of Transportation Federal Aviation Administration Franchise Acquisition Services

About this file

This document contains an estimated construction schedule for a federal contract to construct a Mobile Systems Test Bed Facility. The schedule outlines key project milestones and deliverables over a projected 387 calendar day performance period, including bid submission on July 7, 2023, contract award by July 18, 2023, a notice to proceed by August 2, 2023 and estimated completion by August 22, 2024. Major tasks addressed in the schedule include site work from September through October 2023, prefabricated building erection from December 2023 through January 2024, various interior mechanical, electrical and plumbing rough-ins from February through March 2024, long-lead equipment deliveries and associated delays, interior finishes from June through August 2024, and commissioning and closeout through the end of August 2024. The related federal contract opportunity is solicitation number 6973GH-23-R-00143 being procured by the Department of Transportation Federal Aviation Administration Franchise Acquisition Services for construction of the Mobile Test Bed Facility.

View the file

Other files for this federal contract opportunity

Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

20-042069 MOBILE SYSTEMS TEST BID

ESTIMATED CONSTRUCTION SCHEDULE, Updated 5/31/23

TASK NAME

DURATION

(DAYS) OVERLAP

NET

SCHEDULE

DAYS START DATE

COMPLETE

DATE COMMENTS

BIDS DUE 0 0 to 07/07/23 BID EVALUATION 7 0 7 07/07/23 to 07/14/23 PROJECT AWARD 4 0 4 07/14/23 to 07/18/23 CONTRACTING 14 0 14 07/18/23 to 08/01/23 NOTICE TO PROCEED 1 0 1 08/01/23 to 08/02/23 Projected Date, actual may vary CONTRACTOR MOBILIZATION 10 0 10 08/02/23 to 08/12/23 SUBMITTALS 28 0 28 08/12/23 to 09/09/23 PEMB FABRICATION (12 week lead) 84 09/09/23 to 12/02/23 Long lead item per A/E, 5/18/23 ELECTRICAL PANEL (40 week lead) 280 09/09/23 to 06/15/24 Long lead item per A/E, 5/18/23 SITEWORK 28 7 21 09/02/23 to 09/30/23 UNDERGROUND MEP/UTILITIES 21 0 21 09/30/23 to 10/21/23 FLOOR SLAB 35 7 28 10/14/23 to 11/18/23 PEMB DELIVERY DELAY 14 0 14 11/18/23 to 12/02/23 14 CALENDAR DAY DELAY ERECT PEMB 21 0 21 12/02/23 to 12/23/23 PEMB ROOF PANELS 14 0 14 12/23/23 to 01/06/24 PEMB WALL PANELS 21 0 21 01/06/24 to 01/27/24 EXTERIOR DOORS & WINDOWS 14 0 14 01/27/24 to 02/10/24 ELECTRICAL ROUGH-IN 21 7 14 02/03/24 to 02/24/24 PLUMBING ROUGH-IN 14 7 7 02/17/24 to 03/02/24 MECHANICAL ROUGH-IN 14 0 14 03/02/24 to 03/16/24 FIRE SUPPRESSION ROUGH-IN 14 7 7 03/09/24 to 03/23/24 BUILDING INSULATION 7 0 7 03/23/24 to 03/30/24 ELEC. PANEL DELIVERY DELAY 77 77 03/30/24 to 06/15/24 77 CALENDAR DAY DELAY INTERIOR FINISHES 14 0 14 06/15/24 to 06/29/24 FINISH OUT ELECTRICAL 14 0 14 06/29/24 to 07/13/24 INSTALL EQUIPMENT / CRANES 14 7 7 07/06/24 to 07/20/24 FINISH OUT PLUMBING 14 0 14 07/20/24 to 08/03/24 FINISH OUT MECHANICAL 14 7 7 07/27/24 to 08/10/24 COMMISIONING 7 0 7 08/10/24 to 08/17/24 PUNCH LIST 3 0 3 08/17/24 to 08/20/24 CERTIFICATE OF OCCUPANCY 2 0 2 08/20/24 to 08/22/24

ESTIMATED CONSTRUCTION DURATION 387 CALENDAR DAYS

LEGEND

BIDDING & CONTRACTING

CONSTRUCTION PHASE

SCHEDULE DELAY

Sheet1

File details come from the government source that posted it. Updated .