5. 20-042069 projected const schedule with dates, REVISED 5-31-23.pdf
PDF 88 KB Posted
- Attached to
- 6973GH-23-R-00143; 20-042069 Mobile Test Bed Facility Federal contract opportunity
- Solicitation number
- 6973GH-23-R-00143
About this file
This document contains an estimated construction schedule for a federal contract to construct a Mobile Systems Test Bed Facility. The schedule outlines key project milestones and deliverables over a projected 387 calendar day performance period, including bid submission on July 7, 2023, contract award by July 18, 2023, a notice to proceed by August 2, 2023 and estimated completion by August 22, 2024. Major tasks addressed in the schedule include site work from September through October 2023, prefabricated building erection from December 2023 through January 2024, various interior mechanical, electrical and plumbing rough-ins from February through March 2024, long-lead equipment deliveries and associated delays, interior finishes from June through August 2024, and commissioning and closeout through the end of August 2024. The related federal contract opportunity is solicitation number 6973GH-23-R-00143 being procured by the Department of Transportation Federal Aviation Administration Franchise Acquisition Services for construction of the Mobile Test Bed Facility.
View the file
Other files for this federal contract opportunity
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
20-042069 MOBILE SYSTEMS TEST BID
ESTIMATED CONSTRUCTION SCHEDULE, Updated 5/31/23
TASK NAME
DURATION
(DAYS) OVERLAP
NET
SCHEDULE
DAYS START DATE
COMPLETE
DATE COMMENTS
BIDS DUE 0 0 to 07/07/23 BID EVALUATION 7 0 7 07/07/23 to 07/14/23 PROJECT AWARD 4 0 4 07/14/23 to 07/18/23 CONTRACTING 14 0 14 07/18/23 to 08/01/23 NOTICE TO PROCEED 1 0 1 08/01/23 to 08/02/23 Projected Date, actual may vary CONTRACTOR MOBILIZATION 10 0 10 08/02/23 to 08/12/23 SUBMITTALS 28 0 28 08/12/23 to 09/09/23 PEMB FABRICATION (12 week lead) 84 09/09/23 to 12/02/23 Long lead item per A/E, 5/18/23 ELECTRICAL PANEL (40 week lead) 280 09/09/23 to 06/15/24 Long lead item per A/E, 5/18/23 SITEWORK 28 7 21 09/02/23 to 09/30/23 UNDERGROUND MEP/UTILITIES 21 0 21 09/30/23 to 10/21/23 FLOOR SLAB 35 7 28 10/14/23 to 11/18/23 PEMB DELIVERY DELAY 14 0 14 11/18/23 to 12/02/23 14 CALENDAR DAY DELAY ERECT PEMB 21 0 21 12/02/23 to 12/23/23 PEMB ROOF PANELS 14 0 14 12/23/23 to 01/06/24 PEMB WALL PANELS 21 0 21 01/06/24 to 01/27/24 EXTERIOR DOORS & WINDOWS 14 0 14 01/27/24 to 02/10/24 ELECTRICAL ROUGH-IN 21 7 14 02/03/24 to 02/24/24 PLUMBING ROUGH-IN 14 7 7 02/17/24 to 03/02/24 MECHANICAL ROUGH-IN 14 0 14 03/02/24 to 03/16/24 FIRE SUPPRESSION ROUGH-IN 14 7 7 03/09/24 to 03/23/24 BUILDING INSULATION 7 0 7 03/23/24 to 03/30/24 ELEC. PANEL DELIVERY DELAY 77 77 03/30/24 to 06/15/24 77 CALENDAR DAY DELAY INTERIOR FINISHES 14 0 14 06/15/24 to 06/29/24 FINISH OUT ELECTRICAL 14 0 14 06/29/24 to 07/13/24 INSTALL EQUIPMENT / CRANES 14 7 7 07/06/24 to 07/20/24 FINISH OUT PLUMBING 14 0 14 07/20/24 to 08/03/24 FINISH OUT MECHANICAL 14 7 7 07/27/24 to 08/10/24 COMMISIONING 7 0 7 08/10/24 to 08/17/24 PUNCH LIST 3 0 3 08/17/24 to 08/20/24 CERTIFICATE OF OCCUPANCY 2 0 2 08/20/24 to 08/22/24
ESTIMATED CONSTRUCTION DURATION 387 CALENDAR DAYS
LEGEND
BIDDING & CONTRACTING
CONSTRUCTION PHASE
SCHEDULE DELAY
Sheet1