UDOT Bike Lane Striping and Signage Project - Scope of Work Summary
This Scope of Work document is issued by the Utah Department of Transportation (UDOT) for a bike lane striping and signage project located at the intersection of Wasatch Boulevard (SR-210) and Big Cottonwood Canyon Road (SR-190) in Cottonwood Heights, Utah. The project encompasses SR-190 from Mile Posts 1.7 to 2.0 and SR-210 from Mile Posts 0.0 to 0.2. Services requested include removal of existing turn lane curbing, repaving of roadway sections as necessary, removal and replacement of plowable end sections, removal and relocation of sign posts, sign bases, and signs, removal and reinstallation of striping and sharrows, installation of new green bike lane striping, and striping of the turning radius from westbound SR-190 to southbound SR-210. The mandatory virtual pre-bid meeting is scheduled for Thursday, March 26, 2026, at 1:00 PM Mountain Time via Google Meet. The bid submission deadline is April 6, 2026, at 2:00 PM, with work to commence on or after May 1, 2026, and be fully completed by May 21, 2026. The project is supervised by Shawn Wright, Station Supervisor, and Erikson Betts, Maintenance Engineer, at UDOT Maintenance Station 233.
All products and materials must be submitted to Erikson Betts at ebetts@utah.gov for acceptance prior to use on the project. Traffic control plans must be submitted and approved at least one week before work begins and should also be directed to ebetts@utah.gov. Contractors must contact Shawn Wright prior to the start of any work shift and coordinate with the Traffic Operations Center before implementing traffic control measures. The project will be executed in accordance with the 2026 UDOT Standard Specifications and Drawings. Electronic bid submission is required through the U3P (Bonfire) platform. The contract will be awarded to the lowest responsive and responsible bidder under Solicitation #UDOT260199CN, with the UDOT Procurement Services Division serving as the issuing unit and Region 2 as the conducting unit.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Utah Department of Transportation Request for Sign and Striping Bid
The Utah Department of Transportation (UDOT) is requesting your company to submit a detailed quote for the Big Cottonwood Canyon & Wasatch Blvd. Signing and Striping project as described below.
PROJECT
| Project Location (Route & Mile Posts) |
| SR-190 (MP 1.7 to 2.0) & SR-210 (MP 0.0 to 0.2) |
| UDOT Maintenance Station & Contact |
| Station 233 Supervisor Shawn Wright |
Maintenance Engineer Erikson Betts
INSTRUCTIONS
| Date of Request |
| 3/19/26 |
| Submission Deadline |
| 4/62026 @2:00 PM |
| Date of Mandatory Site Visit with UDOT Maintenance Representative |
| 3/26/2026 @1:00 PM – Virtual |
Bike Lane Striping and Signage Virtual Mandatory pre bid Meeting Thursday, March 26 · 1:00 – 2:00pm Time zone: America/Denver Google Meet joining info Video call link: https://meet.google.com/ryi-opvn-cub Or dial:
More phone numbers: https://tel.meet/ryi-opvn-cub?pin=7580018489031
| Start Date and Anticipated Completion Date for Scope of Work |
| Start on or after 5/1/2026 |
All work completed by 5/21/2026
| Submittal Instructions |
| Electronic submittal is required through U3P (Bonfire) |
SCOPE OF WORK
In Cottonwood Heights at the intersection of Wasatch Blvd (SR-210) and Big Cottonwood Canyon Rd. (SR-190), the northbound bike lane striping and other associated intersection changes as shown in the planset are to be updated in order to relocate the bike lane into the right turn only lane and have bicycles share the lane with the vehicles traveling east up Big Cottonwood Canyon. This project includes removal of existing turn lane curbing, repaving if necessary the roadway section underneath the curbing, removal and replacement of a plowable end section, removal of existing sign posts, sign bases, and signs, installation or relocation of new sign bases, sign posts and signs, removing and reinstalling striping and sharrows and installation of new green bike lane striping. The turning radius from WB SR-190 to SB SR-210 will also need to be striped.
2026 UDOT Standard Specifications and Drawings are to be used for this project. At the applicable time during the project, it will be necessary for UDOT to evaluate the asphalt underneath the removed curbing to see if it will need to be replaced or not. Contact Erikson Betts at to coordinate this inspection. All products to be used on the project will need to be submitted to Erikson Betts at ebetts@utah.gov for acceptance. All traffic control plans must be submitted and accepted for use a minimum of 1 week prior to work beginning. Send all Traffic Control Plans to ebetts@utah.gov. Contact Shawn Wright prior to the start of any shift where work is to be performed. Contact the Traffic Operations Center to update them prior to any traffic control being set up at .
Traffic limitations for this project will be: