About this file
This is a cost sheet submittal form for a Utah Department of Transportation (UDOT) Invitation for Bid (IFB) Solicitation #UDOT260199CN, which involves bike lane striping and signage work on Wasatch Boulevard and Big Cottonwood Canyon. The project scope includes installation of a northbound SR-210 and westbound SR-190 bike lane by moving the existing NB Wasatch Boulevard bike lane from the #2 lane to the Right Turn Only lane, updating intersections with applicable signs and striping, removing concrete curbing, and removing and replacing a plowable end section. The project must be completed before May 21, 2026. A mandatory virtual pre-bid meeting is scheduled for Thursday, March 26, 2026, at 1:00 p.m. via Google Meet. The cost sheet includes 34 pay items spanning mobilization, traffic control, maintenance of traffic, earthwork, asphalt paving, pavement markings, and signage work. Estimated quantities include 12 cubic yards of granular borrow, 70 feet of concrete curb removal, 14 tons of HMA asphalt, 1,012 square feet of green MMA, 13 preformed thermoplastic pavement messages, and various sign installation and removal items.
The cost sheet format requires contractors to submit bid values only in designated blue fields, with all items currently showing zero dollar amounts pending contractor submission. Award will be made to the contractor submitting the lowest responsive and responsible bid based on the total project cost. The form notes that quantities listed are for estimation purposes only, with actual quantities to be determined in the field and payment based on actual quantities delivered and installed. The conducting procurement unit is UDOT Region 2, and contractors must reference Solicitation #UDOT260199CN on all bid submissions.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Original Bid
| Cost submittal-Wasatch Blvd. and Big Cottonwood Canyon Signing and Striping Project | Enter Bid Values in Blue Fields Only | ||
| Table 1: Locations of Installation, Upgade, or Repair | |||
| Location | Type (Installation, upgade. Or Repair) | General Scope | |
| NB SR-210 and WB SR-190 | Installation | Move the NB Wasatch Blvd. bike lane from the # 2 lane to the Right Turn Only lane and update intersection with applicable signs and striping, remove concrete curbing, and remove and replace a plowable end section. |
| Table 2: Items not included | ||||||
| No. | Pay Item Number | Item Description | UoM | Estimated Quantity | Submited Cost per UoM | Cost |
| 1 | 1501701 | Mobilization | Lump | 1 | $ - 0 | |
| 2 | 15547005 | Traffic Control | Lump | 1 | $ - 0 | |
| 3 | 1557701 | Maintenance of Traffic | Lump | 1 | $ - 0 | |
| 4 | 20567015 | Granular Borrow (Plan Quantity) | CY | 12 | $ - 0 | |
| 5 | 020757010 | Separation Geotextiles | SQ YD | 35 | $ - 0 | |
| 6 | 022217120 | Remove Concrete Curb | FT | 70 | $ - 0 | |
| 7 | 022217121 | Remove Flexible Delineation | Each | 1 | $ - 0 | |
| 8 | 022217151 | Remove Plowable End Section | Each | 1 | $ - 0 | |
| 9 | 02221719 | Remove Asphalt Pavement | SQ YD | 35 | $ - 0 | |
| 10 | 023167020 | Roadway Excavation (Plan Quantity) | CY | 19 | $ - 0 | |
| 11 | 027217020 | Untreated Base Course (Plan Quantity) | CY | 6 | $ - 0 | |
| 12 | 027417050 | HMA - 1/2 Inch | Ton | 14 | $ - 0 | |
| 13 | 027487010 | Liquid Asphalt MC-70 or MC-250 | Ton | 1 | $ - 0 | |
| 14 | 027487060 | Emulsified Asphalt CSS-1H | Ton | 1 | $ - 0 | |
| 15 | 027767017 | Concrete Curb Type B5 | FT | 5 | $ - 0 | |
| 16 | 027767100 | Plowable End Section | Each | 1 | $ - 0 | |
| 17 | 027687105 | Pavement Message (Preformed Thermoplastic) | Each | 13 | $ - 0 | |
| 18 | 027687115 | Pavement Message (Preformed Thermoplastic Stop Line, Crosswalks - 12 Inch) | FT | 38 | $ - 0 | |
| 19 | 027657030 | Remove Pavement Marking | FT | 880 | $ - 0 | |
| 20 | 027657040 | Remove Pavement Message | Each | 14 | $ - 0 | |
| 21 | 027657050 | Pavement Marking Paint | Gal | 10 | $ - 0 | |
| 22 | 027687100 | Green MMA | SF | 1012 | $ - 0 | |
| 23 | 028917050 | Sign Type A-2, 24 INCH X 30 INCH | Each | 1 | $ - 0 | |
| 24 | 028917066 | Sign Type A-1, 36 INCH X 30 INCH | Each | 1 | $ - 0 | |
| 25 | 028917028 | Sign Type A-2, 12 INCH X 36 INCH | Each | 1 | $ - 0 | |
| 26 | 028917266 | Remove Sign Face | Each | 2 | $ - 0 | |
| 27 | 028917270 | Remove Sign Less Than 20 Square Feet | Each | 1 | $ - 0 | |
| 28 | 028917285 | Relocate Sign Less than 20 Square Feet | Each | 1 | $ - 0 | |
| 29 | 028917300 | Small Sign Tubular Steel Post Base (B1) | Each | 3 | $ - 0 | |
| 30 | 028917360 | Sign Post P2 | Each | 3 | $ - 0 | |
| 31 | 029837010 | Grinding for Grooved-In Pavement Markings | FT | 496 | $ - 0 | |
| 32 | 029837020 | Grinding for Continuous Grooved-In Pavement Marking Lines | FT | 476 | $ - 0 | |
| 33 | 029837030 | Griding for Grooved-In Pavement Messages | Each | 13 | $ - 0 | |
| 34 | 029837035 | Griding for Grooved-In Pavement Messages | FT | 38 | $ - 0 | |
| Table 2 cost | $ - 0 | |||||
| Total Project Cost Summary Table | Total | |||||
| Base Bid (Items 1-34) | $ - 0 | |||||
| Fields in this table will automatically populate based on bids. |
| Basis of Award |
| Award will be given to contractor with the overall lowest cost from the total project costs summary table. Quantities listed are for estimate purposes only, actual quantities may be more or less and will be determined in the field. Contractor will be paid based on actual quantities |
File details come from the government source that posted it. Updated .