This file is a 100% final submittal of runway electrical design drawings for Selfridge Air National Guard Base in Michigan, prepared by Mead & Hunt, Inc. for the State of Michigan Department of Technology, Management, and Budget. The project, titled "Runway Encroachment Solution - Project #2," addresses airfield improvements and Task 1 - MCC to mitigate runway encroachment at Runway 01-19. The drawings are part of a comprehensive electrical plan (EA129-EA150) covering proposed electrical infrastructure including runway lighting systems (in-pavement and elevated lights), approach lighting systems (ALS-1N, ALS-2N, ALS-3N, and ALS-1S, ALS-2S, ALS-3S), Precision Approach Path Indicator (PAPI) systems, runway end/threshold lights, taxiway lighting, and lighting control systems. The project encompasses runway centerline stationing from approximately station 78+00 to 226+65, with multiple electrical circuits, junction cans, conduit systems, and communication infrastructure. Additional work includes relocation of existing Runway 01 and Runway 19 glide slope equipment shelters, standby generators, antenna systems, and weather station equipment to new locations outside the runway's critical areas, along with extension of primary power, fiber optic cables, and communication systems to these relocated facilities.
The electrical design specifies installation of multiple 5 kV cable circuits (#6 and #2 conductor sizes) in Schedule 40 PVC conduit, both direct-buried and concrete-encased, with connections to the existing airfield electrical vault serving dual 4800V primary supplies. The project includes new SFL-19 master control systems, emergency backup power systems, and comprehensive fiber optic communication networks for system monitoring and control. Temporary PAPI systems are designed to maintain approach lighting functionality during the permanent system relocation. Ground systems utilize #6 solid copper counterpoise conductors installed between runway edges and light lines, with all ground rod connections via exothermic welds. The design accommodates future aircraft arresting systems through installation of inset runway in-pavement lights. The drawings reference detailed installation specifications on related sheets (EA121, EA304, EA502, EA505, EA510, EA519-EA527) and are designated as Type B-3 final submittal documents dated June 5, 2026, with sheets 4 of 467 in the complete contract documentation package.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
E E E E E E E E E
E E
E E
E E
E E
E E
EEEEEEEEEEEEE
E E E
E E E
E E
E E
E E E E E E E E E E
E E E E E E E E E E E E E E E E E E E
EEEEEEEEE
E E E E E E E E E E E E E E EE E E E E E E E
E E
E E
E E
E E
E E
E
E
E
E
E
E
E
E
E
E
E E
FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
V
D
D D
D
D D
C B
C B
C B
FR
FRFR
UD
C B
144+00 145+00 146+00 147+00 148+00 149+00 150+00 151+00 152+00
W W W W W W W W
W WW WW WW W
RDR
RDR
CP
CP
R
R
R
R19
R19
R19
R19
R19
R19
R19
R19
R19
R19
CP
CP
CP
CP
CP
CP
CP
C P
C P
C P
CP
CP
CP
CP
CP
CP
CP
R1
R1
STA: 144+97.30
85.01' L
EL: 579.50
STA: 146+94.12
84.99' L
EL: 579.58
STA: 148+91.07
85.00' L
EL: 579.50
STA: 150+88.04
85.00' L
EL: 579.44
STA: 150+88.04
85.00' R
EL: 579.48
STA: 148+91.07
85.00' R
EL: 579.54
STA: 146+94.10
85.00' R
EL: 579.51
STA: 144+97.13
85.00' R
EL: 579.45
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A
B
C
D
E
F
G
H
J
K
L
M
N
P
SU
BM
IT
TE
D B
Y:
C H
EC
KE
D B
Y:
D R
AW
N
B Y:
D
ES
IG
N
ED
B
Y:
C O
N
TR
AC
T
N O
SO
LI
C
IT
AT
IO
N N
O
IS
SU
E D
AT
E:
SI
ZE
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E
SHEET ID
SHEET OF 467
MI ANGB
ST
AT
E O
F M
IC
H
IG
AN
D
EP
AR
TM
EN
T
O F
TE
C
H N
O
LO
G Y, ST
AT
E
FA
C
IL
IT
IE
S
AD
M
IN
IS
TR
AT
IO
N D
ES
IG
N A
N D
C O
N
ST
R U
C
TI
O N
D
IV
IS
IO
N
LA
N C
IN
G
, M
IC
H
IG
AN
M
AN
AG
EM
EN
T, A N
D B
U D
G
ET
JU
N E
5, AN
SI
D
M
EA
D
H U
N T, IN
C
D
EM
IN
G W
AY
M
ID
D
LE
TO
N , W
I
SE
LF
R
ID
G E
AI
R
N
AT
IO
N
AL
G
U
AR
D B
AS
E, M
IC
H
IG
AN
R
U N
W
AY
E N
C R
O
AC
H M
EN
T
SO
LU
TI
O
N
PR
O
JE
C
T #2
AI
R
FI
EL
D
IM
PR
O
VE
M
EN
TS
TA
SK
M C
C A
M
IT
IG
AT
E R
U N
W
AY
E N
C R
O
AC
H M
EN
T
Y
TY
PE
B -3
0% F
IN
AL
S U
BM
IT
TA
L
M
JR
D
LU
PA
B
D R
P
PR
O
PO
SE
D
E
LE
C
TR
IC
AL
P
LA
N
EA129
KEY MAP
M
AT
C H
L
IN
E
- P
R
EV
IO
U
S
SH
EE
T
M
AT
C H
L
IN
E
- N
EX
T
SH
EE
T
RUNWAY 01-19
TAXIW
AY M
TRUE N
PLAN
NORTH
00 30 60
TR
U
E N
PLAN
NORTH
1-2" SCH. 40 PVC WITH:1-1/C #6,
5kV, L-824C CABLE (RWY R1. CKT.)
#6 SOLID COPPER. COUNTERPOISE
INSTALLED HALF WAY BETWEEN
EDGE OR RWY AND LIGHT LINE.
ALL CONNECTION TO GROUND
RODS MUST BE DONE USING
EXOTHERMIC WELDS (TYP.)
1-2" SCH. 40 PVC WITH:1-1/C #6, 5kV, L-824C CABLE (RWY R19. CKT.)
1-1/C #6, 5kV, L-824C CABLE
IN EX. DUCT (RWY R19. CKT.)
1-1/C #6, 5kV, L-824C CABLE
IN EX. DUCT (RWY R1 CKT.)
INSTALL:
2-1/C #6, 5kV, L-824C CABLE (ALS 1 N CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 2 N CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 3 N CKT.)
2-1/C #6, 5kV, L-824C CABLE (RWY R19. CKT.)
2-1/C #6, 5kV, L-824C CABLE (RWY PAPI 19. CKT.)
1-1/C #6, 5kV, L-824C CABLE (RDR CKT.)
2-1/C #2, 5kV, 133% EPR INSULATION (SFL 19 POWER)
1-#2 INSULATED GROUND, 600V
2-1/C #6, 5kV, L-824C CABLE (THRSLD N. CKT.)
IN EXISTING DUCT BANK AND STRUCTURES TO
AIRFIELD ELECTRICALVAULT
INSTALL: 1-1/C #6, 5kV, L-824C CABLE (RWY R1 CKT.)
1-1/C #6, 5kV, L-824C CABLE (RWY R19 CKT.)
IN EX. DUCT BANK
INSTALL: 1-1/C #6, 5kV, L-824C
CABLE (RDR CKT.) IN EX. DUCT
SYSTEM
NOTE: SEE GENERAL CONSTRUCTION
NOTES ON SHEET EA121.
INSTALL NEW L-862(L)
ELEVATED HIRL ON NEW
L867 BASES, COLORS AS
SHOWN (TYP.)
1-2" SCH. 40 PVC CONCRETE ENCASED
1/C #6, 5KV, L-824C CABLE
RWY R1 CKT.) (ABI 001) 1-2" SCH. 40 PVC CONCRETE ENCASED
1/C #6, 5KV, L-824C CABLE
RWY R19 CKT.) (ABI 001)
1-1/C #6, 5kV, L-824C CABLE
IN EX. DUCT (RWY R19. CKT.)
EXISTING RDR SIGN
REMOVED, BASE CAN AND
FOUNDATION REMAIN
1-1/C #6, 5kV, L-824C CABLE
IN EX. DUCT (RWY R19. CKT.)
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text N00°26'17"E
AutoCAD SHX Text 14000.00'
EEEEEEEEEEEEEEEEEEEEEEEE
E E E E E E
EEEEEE
E E E
E
E E
E E E E E E
E E E E E
E E E E E E
E E E E E
E
E
E E E E E
E
E
E
EEEEEEE
E E E E E E E E E E E E E E E E E E E E E E E
E
E
E
E
E
E
E
E
E
E
EE
E
FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS
D
D
C B
C B
C B
C B
FR
UD
FRFR
153+00 154+00 155+00 156+00 157+00 158+00 159+00 160+00 161+00
W WW W W W W W W W
W WW WW WW WW W
RDR
RDR
CP
CP
JC
-6
P P
P P
TE
M
P
PA
PIC
P
C P
CP CP
TEMP PAPI
STA 153+36.98
R 149.51
STA 153+44.98
L -145.00
STA 153+45.03
R 145.00
STA: 152+85.01
85.00' L
EL: 579.50
STA: 152+85.01
85.00' R
EL: 579.32
STA: 154+81.98
85.00' L
EL: 579.37
STA: 154+81.98
85.00' R
EL: 579.38
STA: 156+78.95
85.00' L
EL: 579.49
STA: 156+78.95
85.00' R
EL: 579.32
STA: 158+75.92
85.00' R
EL: 579.49
STA: 158+75.92
85.00' L
EL: 579.48
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A
B
C
D
E
F
G
H
J
K
L
M
N
P
SU
BM
IT
TE
D B
Y:
C H
EC
KE
D B
Y:
D R
AW
N
B Y:
D
ES
IG
N
ED
B
Y:
C O
N
TR
AC
T
N O
SO
LI
C
IT
AT
IO
N N
O
IS
SU
E D
AT
E:
SI
ZE
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E
SHEET ID
SHEET OF 467
MI ANGB
ST
AT
E O
F M
IC
H
IG
AN
D
EP
AR
TM
EN
T
O F
TE
C
H N
O
LO
G Y, ST
AT
E
FA
C
IL
IT
IE
S
AD
M
IN
IS
TR
AT
IO
N D
ES
IG
N A
N D
C O
N
ST
R U
C
TI
O N
D
IV
IS
IO
N
LA
N C
IN
G
, M
IC
H
IG
AN
M
AN
AG
EM
EN
T, A N
D B
U D
E
5, AN
SI
D
M
EA
D
H U
N T, IN
C
D
EM
IN
G W
AY
M
ID
D
LE
TO
N , W
I
SE
LF
R
ID
G E
AI
R
N
AT
IO
N
AL
G
U
AR
D B
AS
E, M
IC
H
IG
AN
R
U N
W
AY
E N
C R
O
AC
H M
EN
T
SO
LU
TI
O
N
PR
O
JE
C
T #2
AI
R
FI
EL
D
IM
PR
O
VE
M
EN
TS
TA
SK
M C
C A
M
IT
IG
AT
E R
U N
W
AY
E N
C R
O
AC
H M
EN
T
Y
TY
PE
B -3
0% F
IN
AL
S U
BM
IT
TA
L
M
JR
D
LU
PA
B
D R
P
PR
O
PO
SE
D
E
LE
C
TR
IC
AL
P
LA
N
EA130
KEY MAP
M
AT
C H
L
IN
E
- P
R
EV
IO
U
S
SH
EE
T
M
AT
C H
L
IN
E
- N
EX
T
SH
EE
T
RUNWAY 01-19
TA
XI
W
AY
J
TA
XI
W
AY
L
NEW RDR SIGN
NEW RDR SIGN
NEW 2" ELECTRICAL
CONDUIT, TYP.
TRUE N
PLAN
NORTH
00 30 60
TR
U
E N
PLAN
NORTH
#6 SOLID COPPER. COUNTERPOISE
INSTALLED HALF WAY BETWEEN
EDGE OR RWY AND LIGHT LINE.
ALL CONNECTION TO GROUND
RODS MUST BE DONE USING
EXOTHERMIC WELDS (TYP.)
1-1/C #6, 5kV, L-824C CABLE
IN EX. DUCT (RWY R19. CKT.)
INSTALL:
2-1/C #6, 5kV, L-824C CABLE (ALS 1 N CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 2 N CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 3 N CKT.)
2-1/C #6, 5kV, L-824C CABLE (RWY PAPI 19. CKT.)
1-1/C #6, 5kV, L-824C CABLE (RDR CKT.)
2-1/C #2, 5kV, 133% EPR INSULATION (SFL 19 POWER)
1-#2 INSULATED GROUND, 600V
2-1/C #6, 5kV, L-824C CABLE (THRSLD N. CKT.)
IN EXISTING DUCT BANK AND STRUCTURES TO
AIRFIELD ELECTRICALVAULT
1-2" SCH. 40 PVC WITH:2-1/C #6,
5kV, L-824C CABLE (RDR CKT.)
1-1/C #6, 5kV, L-824C CABLE
IN EX. DUCT (RWY R19. CKT.)
INSTALL: 1-1/C #6, 5kV, L-824C
CABLE (RDR CKT.) IN EX. DUCT
SYSTEM
NOTE: SEE GENERAL CONSTRUCTION
NOTES ON SHEET EA121.
INSTALL NEW L-862(L)
ELEVATED HIRL ON NEW
L867 BASES, COLORS AS
SHOWN (TYP.)
INTERCEPT EX. CONDUIT
AND INSTALL AN L-867
JUNCTION CAN WITH 3/8"
BLANK COVER (TYP.)
THRESHOLD CROSSING
CRITICAL OBJECT
CRITICAL OBJECT
ELEVATION
STATION
PAPI APERTURE
ELEVATION
CRITICAL OBJECT
RUNWAY REFERENCE
PAPI LOCATION
HEIGHT
STATION
RUNWAY REFERENCE
POINT ELEVATION
POINT STATION
RUNWAY THRESHOLD
RUNWAY THRESHOLD
ELEVATION
STATION
UNIT 3
UNIT 4
N/A
N/A
N/A
NOTE: UNIT 1
UNIT 1
TO THE RWY.
IS CLOSEST
UNIT 2
RWY END
19 TEMP
EDGE
ABOVE GRD.
APPROX.HT
ANGLE
AIMING
RWY END
ELEVATION
GROUND
19 TEMP
581.40'
52'
160+49
160+49
580.60'
580.44'
170+37.86
3°30'
3°10'
PAPI DESIGN
LOCATION DATA
2°50'
2°30'
578.55'
578.86'
577.89
577.53'
2.85'
3.54'
3.51'
3.87'
PAPI SITING AND AIMING CHART
AutoCAD SHX Text N00°26'17"E
EEEEEEEEEEEEEEEEEEEEEEE
E E E E E E E E E E E E E E E E E E E
E E E E E E E E E E E E E E E E E E E E E E
E E E
E
EEEEEEEEEEEEEEEEEEE
E E E E
E E E E E E E E E E E E E E E E E E E E E E
FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILSD
D
D
D
UD
UD
161+00 162+00 163+00 164+00 165+00 166+00 167+00 168+00 169+00
W W W W W W W W
W WW WW WW W
R D
R C
P
JC
-7
CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CPTEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI
STA 163+44.85
R 145.00
STA 163+44.98
L -145.00
STA 163+36.68
R 145.00
STA: 162+69.86
85.00' L
EL: 579.68
STA: 162+69.86
85.00' R
EL: 579.42
STA: 164+66.83
85.00' L
EL: 579.58
STA: 164+66.83
85.00' R
EL: 579.29
STA: 166+63.81
85.00' L
EL: 579.55
STA: 166+63.80
85.00' R
EL: 579.48
STA: 168+60.75
85.00' R
EL: 579.51
STA: 168+60.77
85.00' L
EL: 579.57
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A
B
C
D
E
F
G
H
J
K
L
M
N
P
SU
BM
IT
TE
D B
Y:
C H
EC
KE
D B
Y:
D R
AW
N
B Y:
D
ES
IG
N
ED
B
Y:
C O
N
TR
AC
T
N O
SO
LI
C
IT
AT
IO
N N
O
IS
SU
E D
AT
E:
SI
ZE
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E
SHEET ID
SHEET OF 467
MI ANGB
ST
AT
E O
F M
IC
H
IG
AN
D
EP
AR
TM
EN
T
O F
TE
C
H N
O
LO
G Y, ST
AT
E
FA
C
IL
IT
IE
S
AD
M
IN
IS
TR
AT
IO
N D
ES
IG
N A
N D
C O
N
ST
R U
C
TI
O N
D
IV
IS
IO
N
LA
N C
IN
G
, M
IC
H
IG
AN
M
AN
AG
EM
EN
T, A N
D B
U D
E
5, AN
SI
D
M
EA
D
H U
N T, IN
C
D
EM
IN
G W
AY
M
ID
D
LE
TO
N , W
I
SE
LF
R
ID
G E
AI
R
N
AT
IO
N
AL
G
U
AR
D B
AS
E, M
IC
H
IG
AN
R
U N
W
AY
E N
C R
O
AC
H M
EN
T
SO
LU
TI
O
N
PR
O
JE
C
T #2
AI
R
FI
EL
D
IM
PR
O
VE
M
EN
TS
TA
SK
M C
C A
M
IT
IG
AT
E R
U N
W
AY
E N
C R
O
AC
H M
EN
T
Y
TY
PE
B -3
0% F
IN
AL
S U
BM
IT
TA
L
M
JR
D
LU
PA
B
D R
P
PR
O
PO
SE
D
E
LE
C
TR
IC
AL
P
LA
N
EA131
KEY MAP
M
AT
C H
L
IN
E
- P
R
EV
IO
U
S
SH
EE
T
M
AT
C H
L
IN
E
- N
EX
T
SH
EE
T
RUNWAY 01-19
NEW RDR SIGN
NEW RDR SIGN
TRUE N
PLAN
NORTH
00 30 60
TR
U
E N
PLAN
NORTH
#6 SOLID COPPER. COUNTERPOISE
INSTALLED HALF WAY BETWEEN
EDGE OR RWY AND LIGHT LINE.
ALL CONNECTION TO GROUND
RODS MUST BE DONE USING
EXOTHERMIC WELDS (TYP.)
1-1/C #6, 5kV, L-824C CABLE
IN EX. DUCT (RWY R19. CKT.)
INSTALL:
2-1/C #6, 5kV, L-824C CABLE (ALS 1 N CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 2 N CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 3 N CKT.)
2-1/C #6, 5kV, L-824C CABLE (RWY PAPI 19. CKT.)
1-1/C #6, 5kV, L-824C CABLE (RDR CKT.)
2-1/C #2, 5kV, 133% EPR INSULATION (SFL 19 POWER)
1-#2 INSULATED GROUND, 600V
2-1/C #6, 5kV, L-824C CABLE (THRSLD N. CKT.)
IN EXISTING DUCT BANK AND STRUCTURES TO
AIRFIELD ELECTRICALVAULT
NEW 2" ELECTRICAL
CONDUIT, TYP.
1-2" SCH. 40 PVC WITH:2-1/C #6,
5kV, L-824C CABLE (RDR CKT.)
NOTE: SEE GENERAL CONSTRUCTION
NOTES ON SHEET EA121.
INSTALL NEW L-862(L)
ELEVATED HIRL ON NEW
L867 BASES, COLORS AS
SHOWN (TYP.)
INTERCEPT EX. CONDUIT
AND INSTALL AN L-867
JUNCTION CAN WITH 3/8"
BLANK COVER (TYP.)
INSTALL 2-1/C #6, 5KV,
L-824, DIRECT BURIED.
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text N00°26'17"E
E E E E E E E E E E E E E E E
E
E E
E E
E E
E
EEEEEE
E
E
E
E
E
E E E
E E E
E E E E E E E E E E E E E E E E
E E E E E E E E E E E E E E E
E E E E E E E E E E E E E E E EEEE
E E E E
E E E E E E E E E E E E E E E E E E E E E E E
EEEEEE
E
E
E E
E
FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS
FO
C-ILS
D
FR
FR
UD
C
BC
B
FR
170+00 171+00 172+00 173+00 174+00 175+00 176+00 177+00 178+00
W W W W W W
W W
W W
W WW WW W
R D
R C
P
JC
-8
CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CPTEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI
STA 173+36.47
R 145.00
STA 173+44.98
L -145.00
STA 173+44.63
R 145.00
STA: 170+57.74
85.00' L
EL: 579.56
STA: 170+57.74
85.00' R
EL: 579.61
STA: 172+54.71
85.00' L
EL: 579.66
STA: 172+54.71
85.00' R
EL: 579.72
STA: 174+51.68
85.00' L
EL: 579.71
STA: 174+51.68
85.00' R
EL: 579.71
STA: 176+48.65
85.00' L
EL: 579.77
STA: 176+48.65
85.00' R
EL: 579.80
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A
B
C
D
E
F
G
H
J
K
L
M
N
P
SU
BM
IT
TE
D B
Y:
C H
EC
KE
D B
Y:
D R
AW
N
B Y:
D
ES
IG
N
ED
B
Y:
C O
N
TR
AC
T
N O
SO
LI
C
IT
AT
IO
N N
O
IS
SU
E D
AT
E:
SI
ZE
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E
SHEET ID
SHEET OF 467
MI ANGB
ST
AT
E O
F M
IC
H
IG
AN
D
EP
AR
TM
EN
T
O F
TE
C
H N
O
LO
G Y, ST
AT
E
FA
C
IL
IT
IE
S
AD
M
IN
IS
TR
AT
IO
N D
ES
IG
N A
N D
C O
N
ST
R U
C
TI
O N
D
IV
IS
IO
N
LA
N C
IN
G
, M
IC
H
IG
AN
M
AN
AG
EM
EN
T, A N
D B
U D
E
5, AN
SI
D
M
EA
D
H U
N T, IN
C
D
EM
IN
G W
AY
M
ID
D
LE
TO
N , W
I
SE
LF
R
ID
G E
AI
R
N
AT
IO
N
AL
G
U
AR
D B
AS
E, M
IC
H
IG
AN
R
U N
W
AY
E N
C R
O
AC
H M
EN
T
SO
LU
TI
O
N
PR
O
JE
C
T #2
AI
R
FI
EL
D
IM
PR
O
VE
M
EN
TS
TA
SK
M C
C A
M
IT
IG
AT
E R
U N
W
AY
E N
C R
O
AC
H M
EN
T
Y
TY
PE
B -3
0% F
IN
AL
S U
BM
IT
TA
L
M
JR
D
LU
PA
B
D R
P
PR
O
PO
SE
D
E
LE
C
TR
IC
AL
P
LA
N
EA132
KEY MAP
M
AT
C H
L
IN
E
- P
R
EV
IO
U
S
SH
EE
T
M
AT
C H
L
IN
E
- N
EX
T
SH
EE
T
RUNWAY 01-19
NEW RDR SIGN
NEW RDR SIGN
TRUE N
PLAN
NORTH
00 30 60
TR
U
E N
PLAN
NORTH
NEW 2" ELECTRICAL
CONDUIT, TYP.
#6 SOLID COPPER. COUNTERPOISE
INSTALLED HALF WAY BETWEEN
EDGE OR RWY AND LIGHT LINE.
ALL CONNECTION TO GROUND
RODS MUST BE DONE USING
EXOTHERMIC WELDS (TYP.)
1-1/C #6, 5kV, L-824C CABLE
IN EX. DUCT (RWY R19. CKT.)
INSTALL:
2-1/C #6, 5kV, L-824C CABLE (ALS 1N CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 2 N CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 3 N CKT.)
2-1/C #6, 5kV, L-824C CABLE (RWY PAPI 19. CKT.)
1-1/C #6, 5kV, L-824C CABLE (RDR CKT.)
2-1/C #2, 5kV, 133% EPR INSULATION (SFL 19 POWER)
1-#2 INSULATED GROUND, 600V
2-1/C #6, 5kV, L-824C CABLE (THRSLD N. CKT.)
IN EXISTING DUCT BANK AND STRUCTURES TO
AIRFIELD ELECTRICALVAULT
1-2" SCH. 40 PVC WITH:2-1/C #6,
5kV, L-824C CABLE (RDR CKT.)
INSTALL: 1-1/C #6, 5kV, L-824C
CABLE (RDR CKT.) IN EX. DUCT
SYSTEM
NOTE: SEE GENERAL CONSTRUCTION
NOTES ON SHEET EA121.
INSTALL NEW L-862(L)
ELEVATED HIRL ON NEW
L867 BASES, COLORS AS
SHOWN (TYP.)
INTERCEPT EX. CONDUIT
AND INSTALL AN L-867
JUNCTION CAN WITH 3/8"
BLANK COVER (TYP.)
INSTALL 2-1/C #6, 5KV,
L-824, DIRECT BURIED.
EXISTING RDR SIGN
REMOVED, BASE CAN AND
FOUNDATION REMAIN
AutoCAD SHX Text E
AutoCAD SHX Text N00°26'17"E
E E E E
E E
E E
E E
E E
E E
E E
E E
E
E E
E E
E E
E E
E
EEEEE E E
E
E E
E E E
E
E
EE
E E
E
E
E
E
E
E
E E
E E E E E E E E E E E E E
E E
E E
E E
E
E E E E E E E E E
E E
EEEEEEEEEE
E E E E
E E
E E E E E E E
E
E
E
E
E
E
E E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS
FOC-ILS
FR
C B
178+00 179+00 180+00 181+00 182+00 183+00
Y W
Y W Y W Y W
Y WY W
JC
-9
R D
R R
D R
R D
R R
D R
C P
C P
C P
C P
DUCT-C
E
DUCT-C
E
R D
R C
P
CP CP CP CP CP CP
TEMP PAPI TEMP PAPI TEMP PAPI TEMP PAPI
TEM
P PAPI
D
SDSDSDSDSDSD
STA: 178+45.62
85.00' L
EL: 579.83
STA: 178+45.62
85.00' R
EL: 579.84 STA: 180+42.59
85.00' R
EL: 579.73
STA: 182+39.56
85.00' L
EL: 579.63
STA: 180+42.59
85.00' L
EL: 579.71
STA: 182+39.56
85.00' R
EL: 579.79
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A
B
C
D
E
F
G
H
J
K
L
M
N
P
SU
BM
IT
TE
D B
Y:
C H
EC
KE
D B
Y:
D R
AW
N
B Y:
D
ES
IG
N
ED
B
Y:
C O
N
TR
AC
T
N O
SO
LI
C
IT
AT
IO
N N
O
IS
SU
E D
AT
E:
SI
ZE
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E
SHEET ID
SHEET OF 467
MI ANGB
ST
AT
E O
F M
IC
H
IG
AN
D
EP
AR
TM
EN
T
O F
TE
C
H N
O
LO
G Y, ST
AT
E
FA
C
IL
IT
IE
S
AD
M
IN
IS
TR
AT
IO
N D
ES
IG
N A
N D
C O
N
ST
R U
C
TI
O N
D
IV
IS
IO
N
LA
N C
IN
G
, M
IC
H
IG
AN
M
AN
AG
EM
EN
T, A N
D B
U D
E
5, AN
SI
D
M
EA
D
H U
N T, IN
C
D
EM
IN
G W
AY
M
ID
D
LE
TO
N , W
I
SE
LF
R
ID
G E
AI
R
N
AT
IO
N
AL
G
U
AR
D B
AS
E, M
IC
H
IG
AN
R
U N
W
AY
E N
C R
O
AC
H M
EN
T
SO
LU
TI
O
N
PR
O
JE
C
T #2
AI
R
FI
EL
D
IM
PR
O
VE
M
EN
TS
TA
SK
M C
C A
M
IT
IG
AT
E R
U N
W
AY
E N
C R
O
AC
H M
EN
T
Y
TY
PE
B -3
0% F
IN
AL
S U
BM
IT
TA
L
M
JR
D
LU
PA
B
D R
P
PR
O
PO
SE
D
E
LE
C
TR
IC
AL
P
LA
N
EA133
KEY MAP
M
AT
C H
L
IN
E
- P
R
EV
IO
U
S
SH
EE
T
M
AT
C H
L
IN
E
- N
EX
T
SH
EE
T
RUNWAY 01-19
TA
XI
W
AY
A
NOTES:
1. SEE NOTES ON EA121.
TRUE N
PLAN
NORTH
00 30 60
TR
U
E N
PLAN
NORTH
#6 SOLID COPPER. COUNTERPOISE
INSTALLED HALF WAY BETWEEN
EDGE OR RWY AND LIGHT LINE.
ALL CONNECTION TO GROUND
RODS MUST BE DONE USING
EXOTHERMIC WELDS (TYP.)
1-1/C #6, 5kV, L-824C CABLE
IN EX. DUCT (RWY R19. CKT.)
INSTALL:
2-1/C #6, 5kV, L-824C CABLE (ALS 1 N. CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 2 N. CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 3 N. CKT.)
2-1/C #6, 5kV, L-824C CABLE (RWY PAPI 19. CKT.)
1-1/C #6, 5kV, L-824C CABLE (RDR CKT.)
2-1/C #2, 5kV, 133% EPR INSULATION (SFL 19 POWER)
1-#2 INSULATED GROUND, 600V
2-1/C #6, 5kV, L-824C CABLE (THRSLD N. CKT.)
IN EXISTING DUCT BANK AND STRUCTURES TO
AIRFIELD ELECTRICALVAULT
TIE NEW DUCT TO
EX. CONDUITTERMINATE CP ON A 3 4" X 10'
COPPER CLAD GROUND ROD
(TYP. FOR BOTH SIDES OF
TWY A INTERSECTION)
1-1/C #6, 5kV, L-824C CABLE
IN EX. DUCT (RWY R19. CKT.)
1-2" SCH. 40 PVC WITH:2-1/C #6,
5kV, L-824C CABLE (RDR CKT.)
MATCH LINE - SEE EA145
INSTALL:1-1/C #6, 5kV, L-824C
CABLE (RDR CKT.) IN EX. DUCT
NOTE: SEE GENERAL CONSTRUCTION
NOTES ON SHEET EA121.
INSTALL NEW L-862(L)
ELEVATED HIRL ON NEW
L867 BASES, COLORS AS
SHOWN (TYP.)
INTERCEPT EX. CONDUIT
AND INSTALL AN L-867
JUNCTION CAN WITH 3/8"
BLANK COVER (TYP.)
INSTALL 2-1/C #6, 5KV,
L-824, DIRECT BURIED.
SPLICE TEMPORARY PAPI POWER CABLES
TO EX. PAPI CIRCUIT USING L-823
CONNECTORSINSTALL: 1-1/C #6, 5kV, L-824C
CABLE (RDR CKT.) IN EX. DUCT
SYSTEM
INSTALL NEW INSET HIRL ON NEW
L868 BASES, COLORS AS SHOWN
TO ACCOMMODATE FUTURE
AIRCRAFT ARRESTING SYSTEM
INSTALL NEW INSET HIRL ON NEW
L868 BASES, COLORS AS SHOWN
TO ACCOMMODATE FUTURE
AIRCRAFT ARRESTING SYSTEM
INSTALL NEW INSET HIRL ON NEW
L868 BASES, COLORS AS SHOWN
TO ACCOMMODATE FUTURE
AIRCRAFT ARRESTING SYSTEM
INSTALL NEW INSET HIRL ON NEW
L868 BASES, COLORS AS SHOWN
TO ACCOMMODATE FUTURE
AIRCRAFT ARRESTING SYSTEM
INSTALL NEW INSET HIRL ON NEW
L868 BASES, COLORS AS SHOWN
TO ACCOMMODATE FUTURE
AIRCRAFT ARRESTING SYSTEM
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text N00°26'17"E
E
E
E
E
E
E E E E E E E E E E E E E E E E E E E E E E E E E E E E E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
EEEEEE
E E
E E
E E
E E
E E
E
E E E
E E E E E E E E E E E E
E E
E E
EEEEEEEEEE
E E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E E E E E
E
EEEEEE
E
E
E
E
FOC-ILS
FOC-ILS
FOC-ILS
FOC-ILS
FOC-ILS
FOC-ILS
FOC-ILS
FOC-ILS
D
D
FR
UD
UD
183+00 184+00 185+00 186+00 187+00 188+00 189+00
P P
P P
PAPI 19 PAPI 19 PAPI 19 PAPI 19 PAPI 19 PAPI 19 PAPI 19 PAPI 19 PAPI 19
PA
PI
CPCPCPCPCPCPCPCPCPCPCPCP
C P
C P
R
R
C P
C P
C P
Y W
Y WY WY W
Y W Y W
R D
R C
P R
D R
C P
DUCT-C
E
DUCT-CE DUCT-CE DUCT-CE DUCT-CE DUCT-CE DUCT-CE
DUCT-CE DUCT-CE DUCT-CE DUCT-CE DUCT-CE DUCT-CE
STA 185+46.00
R 215.00
STA 183+44.79
R 145.00
STA 183+44.98
L -145.00
DD
D
SDSDSDSDSDSDSDSDSDSDSDSD
SD
STA: 188+30.47
85.00' L
EL: 579.79
STA: 186+33.50
85.00' L
EL: 579.75
STA: 188+30.47
85.00' R
EL: 579.67
STA: 186+33.50
85.00' R
EL: 579.71STA: 184+36.53
85.00' R
EL: 579.69
STA: 184+36.53
85.00' L
EL: 579.69
FR
UD
UD
UD
UD
UD
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A
B
C
D
E
F
G
H
J
K
L
M
N
P
SU
BM
IT
TE
D B
Y:
C H
EC
KE
D B
Y:
D R
AW
N
B Y:
D
ES
IG
N
ED
B
Y:
C O
N
TR
AC
T
N O
SO
LI
C
IT
AT
IO
N N
O
IS
SU
E D
AT
E:
SI
ZE
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E
SHEET ID
SHEET OF 467
MI ANGB
ST
AT
E O
F M
IC
H
IG
AN
D
EP
AR
TM
EN
T
O F
TE
C
H N
O
LO
G Y, ST
AT
E
FA
C
IL
IT
IE
S
AD
M
IN
IS
TR
AT
IO
N D
ES
IG
N A
N D
C O
N
ST
R U
C
TI
O N
D
IV
IS
IO
N
LA
N C
IN
G
, M
IC
H
IG
AN
M
AN
AG
EM
EN
T, A N
D B
U D
E
5, AN
SI
D
M
EA
D
H U
N T, IN
C
D
EM
IN
G W
AY
M
ID
D
LE
TO
N , W
I
SE
LF
R
ID
G E
AI
R
N
AT
IO
N
AL
G
U
AR
D B
AS
E, M
IC
H
IG
AN
R
U N
W
AY
E N
C R
O
AC
H M
EN
T
SO
LU
TI
O
N
PR
O
JE
C
T #2
AI
R
FI
EL
D
IM
PR
O
VE
M
EN
TS
TA
SK
M C
C A
M
IT
IG
AT
E R
U N
W
AY
E N
C R
O
AC
H M
EN
T
Y
TY
PE
B -3
0% F
IN
AL
S U
BM
IT
TA
L
M
JR
D
LU
PA
B
D R
P
PR
O
PO
SE
D
E
LE
C
TR
IC
AL
P
LA
N
EA134
RUNWAY 01-19
KEY MAP
M
AT
C H
L
IN
E
- N
EX
T
SH
EE
T
NEW RDR SIGN
M
AT
C H
L
IN
E
- P
R
EV
IO
U
S
SH
EE
T
MATCH LINE - SHEET EA145
SEE SHEET EA145 FOR NEW GLIDE SLOPE
LOCATION
NEW RDR SIGN
EX. ELECTRICAL
MANHOLE
TRUE N
PLAN
NORTH
00 30 60
TR
U
E N
PLAN
NORTH
#6 SOLID COPPER. COUNTERPOISE
INSTALLED HALF WAY BETWEEN
EDGE OR RWY AND LIGHT LINE.
ALL CONNECTION TO GROUND
RODS MUST BE DONE USING
EXOTHERMIC WELDS (TYP.)
INSTALL:
2-1/C #6, 5kV, L-824C CABLE (ALS 1 N. CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 2 N. CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 3 N. CKT.)
2-1/C #6, 5kV, L-824C CABLE (RWY PAPI 19. CKT.)
1-1/C #6, 5kV, L-824C CABLE (RDR CKT.)
2-1/C #2, 5kV, 133% EPR INSULATION (SFL 19 POWER)
1-#2 INSULATED GROUND, 600V
2-1/C #6, 5kV, L-824C CABLE (THRSLD N. CKT.)
IN EXISTING DUCT BANK AND STRUCTURES TO
AIRFIELD ELECTRICALVAULT
1-2" SCH. 40 PVC WITH:2-1/C #6,
5kV, L-824C CABLE (RDR CKT.)
.0
50.0'
1-2" SCH. 40 PVC WITH:2-1/C #6,
5kV, L-824C CABLE (PAPI 19 CKT.)
1-2" SCH. 40 PVC WITH:2-1/C #6,
5kV, L-824C CABLE (RDR CKT.)
EX. 2W-4" COMM
DUCT BANK W:
1-12 STRAND,
SINGLE MODE F/O
CABLE
EX. 4W-4"-INSTALL:
2-1/C #6, 5kV, L-824C CABLE (ALS 1 N. CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 2 N. CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 3 N. CKT.)
2-1/C #6, 5kV, L-824C CABLE (RWY PAPI 19. CKT.)
1-1/C #6, 5kV, L-824C CABLE (RDR CKT.)
2-1/C #2, 5kV, 133% EPR INSULATION (SFL 19 POWER)
1-#2 INSULATED GROUND, 600V
2-1/C #6, 5kV, L-824C CABLE (THRSLD N. CKT.)
IN EXISTING DUCT BANK AND STRUCTURES
L-880 (L) PAPI
SYSTEM (TYP.)
NOTE: SEE GENERAL CONSTRUCTION
NOTES ON SHEET EA121.
INSTALL NEW L-862(L)
ELEVATED HIRL ON NEW
L867 BASES, COLORS AS
SHOWN (TYP.)
THRESHOLD CROSSING
CRITICAL OBJECT
CRITICAL OBJECT
ELEVATION
STATION
PAPI APERTURE
ELEVATION
CRITICAL OBJECT
RUNWAY REFERENCE
PAPI LOCATION
HEIGHT
STATION
RUNWAY REFERENCE
POINT ELEVATION
POINT STATION
RUNWAY THRESHOLD
RUNWAY THRESHOLD
ELEVATION
STATION
UNIT 3
UNIT 4
N/A
N/A
N/A
NOTE: UNIT 1
UNIT 1
TO THE RWY.
IS CLOSEST
UNIT 2
RWY END
EDGE
ABOVE GRD.
APPROX.HT
ANGLE
AIMING
RWY END
ELEVATION
GROUND
581.70'
60.00'
185+46
185+46
580.79'
580.74'
196+90
3°30'
3°10'
PAPI DESIGN
LOCATION DATA
2°50'
2°30'
579.02'
578.54'
578.08
577.59'
2.68'
3.16'
3.62'
4.11'
PAPI SITING AND AIMING CHART
INSTALL: 2-1/C #6, 5kV, L-824C
CABLE (RDR CKT.) IN EX. DUCT
SYSTEM
1-1/C #6, 5kV, L-824C CABLE
IN EX. DUCT (RWY R19. CKT.)
1-1/C #6, 5kV, L-824C CABLE IN EX. 2"
DUCT (RWY R19. CKT.)
CONNECT EX. DUCT TO
LIGHT BASE
1-2" SCH. 40 PVC WITH: 1-1/C #6, 5KV,
L-824C CABLE (RWY R19. CKT.)
INSTALL NEW INSET HIRL ON NEW
L868 BASES, COLORS AS SHOWN
TO ACCOMMODATE FUTURE
AIRCRAFT ARRESTING SYSTEM
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text N00°26'17"E
E
E E
E E
E E
E E E E E E
E E
EE E
E
E E
E E
E E
E E
E E
E E E E E E E E E
E
E
E
E
E
E
E E E E E E E E E E E E E
E E E E E E E E E E E E E E E
E
E
E E E E E E E E E E E E E E
FOC-ILS
FOC-ILS
FOC-ILS
FOC-ILS
FOC-ILS
FOC-ILS
FOC-ILS
FOC-ILS
FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS
D
D
D
D
D
FR
FR
UD
FRUD
190+00 191+00 192+00 193+00 194+00 195+00 196+00 197+00 198+00
CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP
CP
PA
PI
PA
PI
PA
PI
PA
PI
PA
PI
PA
PI
PA
PI
PAPI 1
PAPI 1
CP
CP
C P
C P
C P
C P
C P
C P
C P
C P
C P
JC
-10
ALS-1N
ALS-1N
E E
E E
E E
E E
E
THLD-N
THLD-N
THLD-N
CP
CP
CP
CP
O G
O G
O G
O G
Y G
O G
O G
Y G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
O G
R R
R RY W
Y W
Y W
Y W
RDR
RDR RDR RDR RDR RDR
CP
CP CP CP CP CP
RDR RDR RDR RDR RDR
CP CP CP CP CP CP
R19
FO
C-ILS
FOC-ILS
FO
C
-ILS
FO
C
-ILS
FO
C
-ILS
FO
C
-ILS
FO
C
-ILS
FO
C
-ILS
FO
C
-ILS
FO
C
-ILS
DUCT-CE DUCT-CE
DUCT-CE DUCT-CE DUCT-CE
C P
C P
Y W
Y W
Y W
YW
R19R19R19R19
R19
STA 193+44.98
R 145.00
STA 193+44.98
L -145.00
STA 196+91.50
L -131.65
FR
FR
UD
UD
C B
C B
D
SD SD SD SD SD SD SD SDSDSDSDSDSDSDSD
SD
SD
SD
SD
STA: 192+24.41
85.00' L
EL: 579.63
STA: 194+21.38
85.00' L
EL: 579.62
STA: 194+21.38
85.00' R
EL: 579.72
STA: 192+24.41
85.00' R
EL: 579.68
STA: 190+27.44
85.00' R
EL: 579.70
STA 196+91.48
L -150.00
STA 196+91.48
R 150.00
STA: 190+27.44
85.00' L
EL: 579.72
STA: 196+18.35
85.00' L
EL: 579.64
STA: 196+18.35
85.00' R
EL: 579.72
STA: 198+15.32
85.00' L
EL: 579.63
STA: 198+15.32
85.00' R
EL: 579.67
STA 196+91.50
L 0.00
STA: 197+89.98
0.00'
EL: 580.71
STA: 198+89.98
FRFR
U D
UD
UD
UD
UD
UD
UD
UD
U D
U D
U D
U D
U D
U D
U D
U D
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A
B
C
D
E
F
G
H
J
K
L
M
N
P
SU
BM
IT
TE
D B
Y:
C H
EC
KE
D B
Y:
D R
AW
N
B Y:
D
ES
IG
N
ED
B
Y:
C O
N
TR
AC
T
N O
SO
LI
C
IT
AT
IO
N N
O
IS
SU
E D
AT
E:
SI
ZE
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E
SHEET ID
SHEET OF 467
MI ANGB
ST
AT
E O
F M
IC
H
IG
AN
D
EP
AR
TM
EN
T
O F
TE
C
H N
O
LO
G Y, ST
AT
E
FA
C
IL
IT
IE
S
AD
M
IN
IS
TR
AT
IO
N D
ES
IG
N A
N D
C O
N
ST
R U
C
TI
O N
D
IV
IS
IO
N
LA
N C
IN
G
, M
IC
H
IG
AN
M
AN
AG
EM
EN
T, A N
D B
U D
E
5, AN
SI
D
M
EA
D
H U
N T, IN
C
D
EM
IN
G W
AY
M
ID
D
LE
TO
N , W
I
SE
LF
R
ID
G E
AI
R
N
AT
IO
N
AL
G
U
AR
D B
AS
E, M
IC
H
IG
AN
R
U N
W
AY
E N
C R
O
AC
H M
EN
T
SO
LU
TI
O
N
PR
O
JE
C
T #2
AI
R
FI
EL
D
IM
PR
O
VE
M
EN
TS
TA
SK
M C
C A
M
IT
IG
AT
E R
U N
W
AY
E N
C R
O
AC
H M
EN
T
Y
TY
PE
B -3
0% F
IN
AL
S U
BM
IT
TA
L
M
JR
D
LU
PA
B
D R
P
PR
O
PO
SE
D
E
LE
C
TR
IC
AL
P
LA
N
EA135
RUNWAY 01-19
KEY MAP
M
AT
C H
L
IN
E
- N
EX
T
SH
EE
T
TA
XI
W
AY
K
REMOVED LIGHT BAR
ASPHALT PAVEMENT REPAIR,
SEE DETAIL 1/ CP304, TYP.
REMOVED LIGHT BAR
PCC PAVEMENT REPAIR,
SEE DETAIL 2/ CP304, TYP.
NEW FULL DEPTH PCC
REPAIR FOR APPROACH
LIGHT BAR DUCT BANK
SEE DETAIL 3/ CP502, TYP.
M
AT
C H
L
IN
E
- P
R
EV
IO
U
S
SH
EE
T
NEW RDR SIGN
NEW RDR SIGN
ELECTRICAL MANHOLE
TRUE N
PLAN
NORTH
00 30 60
TR
U
E N
PLAN
NORTH
1-2" SCH. 40 PVC WITH:2-1/C #6,
5kV, L-824C CABLE (RDR CKT.)
2-1/C #6, 5kV, L-824C CABLE IN EX.
DUCT SYSTEM (RDR CKT.)
INSTALL:
2-1/C #6, 5kV, L-824C CABLE (ALS 1 N. CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 2 N. CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 3 N. CKT.)
2-1/C #6, 5kV, L-824C CABLE (TWY B CKT.)
2-1/C #2, 5kV, 133% EPR INSULATION (SFL 19 POWER)
1-#2 INSULATED GROUND, 600V
2-1/C #6, 5kV, L-824C CABLE (THRSLD N. CKT.)
IN EXISTING DUCT BANK AND STRUCTURES TO
AIRFIELD ELECTRICALVAULT
INSTALL 5-IN-PAVEMENT
RWY END/THRESHOLD
LIGHTS ON NEW BASES,
COMPLETE WITH ALL
COMPONENTS AND
WIRING (RWY R19 CKT.)
SEE SHEET EA510 FOR
THRESHOLD BAR DETAIL.
INSTALL 5-IN-PAVEMENT RWY
END/THRESHOLD LIGHTS ON
NEW BASES, COMPLETE WITH
ALL COMPONENTS AND
WIRING (RWY R19 CKT.) SEE
SHEET EA510 FOR
THRESHOLD BAR DETAIL.
1-2" SCH. 40 PVC WITH:2-1/C #6,
5kV, L-824C CABLE (RDR CKT.)
INSTALL NEW IN-PAVEMENT
APPROACH LIGHTS (5 EACH),
COMPLETE WITH ALL
COMPONENTS AND WIRING
ON NEW LIGHT BASES AND
CONCRETE FOUNDATIONS
(TYP. FOR STATIONS 90-114)
1-2" SCH. 40
PVC WITH: 2-1/C
#6, 5kV, L-824C
CABLE (ALS 1 N.
CKT.)
INSTALL NEW IN-PAVEMENT
APPROACH LIGHTS (5 EACH),
COMPLETE WITH ALL
COMPONENTS AND WIRING
ON NEW LIGHT BASES AND
CONCRETE FOUNDATIONS
(TYP. FOR STATIONS 90-114)
1-2" SCH 40 PVC-PCC ENCASED WITH:
1-24 STRAND, SINGLE MODE FIBER
OPTIC CABLE TO NEW GLIDE SLOPE
LOCATION
1-4" PVC, PCC ENCASED WITH:
2-#2, 5 kV, 133% EPR INSULATION
1-#8, 600V GROUND TO
RELOCATED GLIDE SLOPESITE
1-2" SCH. 40 PVC PCC ENCASED WITH"
2-1/C, #6, 5kV, L-824C (PAPI 19 CKT.)
INSTALL NEW
REIL (SLAVE).
CONNECT TO
RWY R19 CKT.
INSTALL NEW IN-PAVEMENT THRESHOLD
BAR LIGHTS (41 EACH) ON NEW BASE CANS,
COMPLETE WITH ALL COMPONENTS AND
WIRING (THRSHLD S CKT.). SEE SHEET
EA510 FOR INSTALLATION DETAIL
NEW REIL (MASTER).
L-849, STYLE E, 20/6.6A
SERIES CONNECTION.
(RWY R1 CKT.) INSTALL
INTERCONNECT SHIELDED
WIRE IN SEPARATE
CONDUIT
INSTALL REIL
INERCONNECT WIRING IN
SEPARATE 2" SCH. 40 PCC
ENCASED CONDUIT
1-2" SCH. 40 PVC
WITH: 2-1/C #6,
5kV, L-824C CABLE
(THLD N CKT.)
NOTE: SEE GENERAL CONSTRUCTION
NOTES ON SHEET EA121.
INSTALL NEW L-862(L)
ELEVATED HIRL ON NEW
L867 BASES, COLORS AS
SHOWN (TYP.)
CONNECT EX. 2"
DUCT TO LIGHT
BASE
CONNECT EX. 2" DUCT TO
LIGHT BASE
1-1/C #6, 5kV, L-824C CABLE
IN EX. DUCT (RWY R19. CKT.)
1-1/C #6, 5kV, L-824C CABLE IN EX. 2"
DUCT (RWY R19. CKT.)
CONNECT EX. 2"
DUCT TO LIGHT BASE
CONNECT EX. 2"
DUCT TO LIGHT BASE
SPLICE PROPOSED HAMMERHEAD
(FUTURE TAXIWAY B) CIRCUIT TO
EXISTING TAXIWAY K CIRCUIT IN
EXISTING STRUCTURE
SPLICE TO EXISTING TAXIWAY K
CIRCUIT IN EXISTING STRUCTURE
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text N00°26'17"E
E E E E
E E E
FOC-ILS FOC-ILS FOC-ILS
D
FR
UD
199+00 200+00 201+00 202+00 203+00 204+00 205+00 206+00
CP CP CP CP CP CP CP CP CP CP CP CP CP
CP
CP
CP
CP
CP
CP
CP
CP CP CP
CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP
R RB
B B B
ALS-1N
ALS-1N
ALS-1N
ALS-1N
ALS-1N
ALS-1N
ALS-1N
ALS-2N
ALS-2N
ALS-2N
ALS-2N
ALS-2N
ALS-2N
ALS-2N
ALS-2N
ALS-2N
ALS-2N
ALS-2N
ALS-2N
ALS-2N
ALS-2N
E
ALS-1N
ALS-1N
B
B
R R
R RR R
R R R R
R R R R R19 R19 R19 R19 R19 R19 R19 R19 R19 R19 R19 R19 R19 R19 R19 R19 R19 R19 R19 R19
R19 R19 R19 R19 R19 R19 R19
PLZ
PLZ
PLZ
PLZ
PLZ
PLZ
ALS-2N ALS-2N
ALS-2N
ALS-2N
ALS-1N
ALS-1N
ALS-1N
ALS-3N ALS-3N
ALS-3N
ALS-3N
LOC01 LOC01
LO
C
LO
C
SFL-5kV SFL-5kV
SFL-5kV SFL-5kV
FOC-SFL FOC-SFL
FO
C
-SFL
ALS-1N
ALS-2N
ALS-3N
LOC01
SFL-5kV
FOC-SFL
ALS-2N
ALS
-2N
ALS
-2N
ALS
-2N
ALS
-2N
ALS
-2N
ALS
-2N
ALS-2N
ALS-3N
ALS
-3N
ALS
-3N
ALS
-3N
ALS
-3N
ALS
-3N
ALS
-3N
ALS-3N
SFL-5
kV
SFL-5
kV
SFL-5
kV
SFL-5
kV
SFL-5
kV
SFL-5
kV
SFL-5kV
FOC-S
FL
FOC-S
FL
FOC-S
FL
FOC-S
FL
FOC-S
FL
FOC-SFL
ALS-3N
TWY B TWY B
TW
Y B
TW
Y B
TW
Y B
CP
C P
C P
C P
CP CP CP CP CP CP CP
CP
CP
CP
CP
CP
CP
CP
CP CP CP
TWY B TWY B TWY B
TW
Y B
TWY B
TWY B
TWY B
TWY B
TWY B
TWY B
TWY B
TWY B
TWY B
TWY B TWY B TWY B
ALS-1N
ALS-2N
ALS-3N
SFL-5kV
FOC-SFL
TWY B TWY B
ALS-2N
ICC-C
ICC-E
R19R19R19R19R19R19R19R19R19R19R19R19
U D
U D
U D
U D
U D
UD UD UDUDUDUDUDUDUDUDUDUDUDUD UDUDUDUDUDUD
U D
U D
U D
U D
U D
U D
U D
U D
UDUDUDUDUDUDUDUDUDUDUDUDUDUDUDUDUDUDUDUD
UDUDUD
UD
UD
UD
UD
UD
UD
UD
UD
UD
UD
UD
UD
UD
UD
UD
U D
U D
U D
U D
C B
C B
SD
SD
SD
SD
SD
SD SD SD SD SD SD SD SD SD
STA: 200+12.29
85.00' R
EL: 579.63
STA: 200+12.29
85.00' L
EL: 579.63
STA: 202+09.26
85.00' L
EL: 579.70
STA: 202+09.26
85.00' R
EL: 579.70
STA: 204+06.23
85.00' R
EL: 580.13
STA: 206+03.17
85.00' R
EL: 580.95
STA: 206+03.20
85.00' L
EL: 581.02
STA: 204+06.23
85.00' L
EL: 580.21
STA 205+89.64
L -340.00
STA: 205+38.33
291.25' L
EL: 578.03
STA: 204+35.21
188.13' L
EL: 578.91
STA: 203+32.08
85.00' L
EL: 579.94
STA: 198+15.32
STA: 198+89.98
0.00'
EL: 580.77
STA: 199+89.98
0.00'
EL: 580.77
STA: 200+89.98
0.00'
EL: 580.77
STA: 201+89.98
0.00'
EL: 580.82
STA: 202+89.98
0.00'
EL: 580.97
STA: 203+89.98
0.00'
EL: 581.22
STA: 204+89.98
0.00'
EL: 581.57
STA: 205+89.98
0.00'
EL: 582.02
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A
B
C
D
E
F
G
H
J
K
L
M
N
P
SU
BM
IT
TE
D B
Y:
C H
EC
KE
D B
Y:
D R
AW
N
B Y:
D
ES
IG
N
ED
B
Y:
C O
N
TR
AC
T
N O
SO
LI
C
IT
AT
IO
N N
O
IS
SU
E D
AT
E:
SI
ZE
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E
SHEET ID
SHEET OF 467
MI ANGB
ST
AT
E O
F M
IC
H
IG
AN
D
EP
AR
TM
EN
T
O F
TE
C
H N
O
LO
G Y, ST
AT
E
FA
C
IL
IT
IE
S
AD
M
IN
IS
TR
AT
IO
N D
ES
IG
N A
N D
C O
N
ST
R U
C
TI
O N
D
IV
IS
IO
N
LA
N C
IN
G
, M
IC
H
IG
AN
M
AN
AG
EM
EN
T, A N
D B
U D
E
5, AN
SI
D
M
EA
D
H U
N T, IN
C
D
EM
IN
G W
AY
M
ID
D
LE
TO
N , W
I
SE
LF
R
ID
G E
AI
R
N
AT
IO
N
AL
G
U
AR
D B
AS
E, M
IC
H
IG
AN
R
U N
W
AY
E N
C R
O
AC
H M
EN
T
SO
LU
TI
O
N
PR
O
JE
C
T #2
AI
R
FI
EL
D
IM
PR
O
VE
M
EN
TS
TA
SK
M C
C A
M
IT
IG
AT
E R
U N
W
AY
E N
C R
O
AC
H M
EN
T
Y
TY
PE
B -3
0% F
IN
AL
S U
BM
IT
TA
L
M
JR
D
LU
PA
B
D R
P
PR
O
PO
SE
D
E
LE
C
TR
IC
AL
P
LA
N
EA136
RUNWAY 01-19
KEY MAP
M
AT
C H
L
IN
E
- N
EX
T
SH
EE
T
PROPOSED TAXIWAY
EDGE LIGHTS, TYP. SEE
NOTES 13 AND 14 ON
SHEET EA121
PROPOSED
RUNWAY IN-PAVEMENT
EDGE LIGHT, L-850C, R/R (TYP.)
SEE NOTES 13 AND 14 ON
SHEET EA121
INSTALL TAXIWAY EDGE
LIGHT BASE CANS WITH 3/8"
BLANK COVERS UNDER
TASK 1 FOR FUTURE TASK 3
(BASE BID)
INSTALL L-867 BASE CANS WITH
3/8" BLANK COVERS UNDER
THIS CONTRACT FOR FUTURE
TAXIWAY A (TASK 2) WORK
PROVIDE 5' OF SCH. 40 PVC AND CAP
OUTSIDE PAVEMENTLIMITS FOR
FUTURE TAXIWAY A (TASK 2) WORK
TRUE N
PLAN
NORTH
00 30 60
TR
U
E N
PLAN
NORTH
INSTALL 2-1/C #6, 5000V, L-824C,
IN EXISTING CONDUIT AND
ELECTRICAL STRUCTURES, TO
AIRFIELD ELECTRICAL VAULT,
TYP. (ALS-1 N CKT.)
1-2" SCH. 40 PVC, PCC ENCASED
WITH: 2-1/C #6, 5kV, L-824C, (ALS-1N CKT.)
INSTALL NEW IN-PAVEMENT
APPROACH LIGHTS (5 EACH),
COMPLETE WITH ALL
COMPONENTS AND WIRING
ON NEW LIGHT BASES AND
CONCRETE FOUNDATIONS
(TYP. FOR STATIONS198-206)
INSTALL NEW IN-PAVEMENT
APPROACH LIGHTS (3 EACH),
COMPLETE WITH ALL
COMPONENTS AND WIRING
ON NEW LIGHT BASES AND
CONCRETE FOUNDATIONS
1-2" SCH. 40 PVC WITH: 1-1/C #6,
5kV, L-824C CABLE (RWY R19 CKT, BASE BID)
INSTALL NEW IN-PAVEMENT
APPROACH LIGHTS (5 EACH),
COMPLETE WITH ALL
COMPONENTS AND WIRING
ON NEW LIGHT BASES AND
CONCRETE FOUNDATIONS
(TYP. FOR STATIONS198-206)
INSTALL NEW IN-PAVEMENT
APPROACH LIGHTS (3 EACH),
COMPLETE WITH ALL
COMPONENTS AND WIRING
ON NEW LIGHT BASES AND
CONCRETE FOUNDATIONS
1-2" SCH. 40 PVC WITH:
1-1/C #6, 5kV, L-824C
CABLE (RWY R19 CKT.,
BASE BID)
#6 SOLID COPPER. COUNTERPOISE
INSTALLED HALF WAY BETWEEN
EDGE OR RWY AND LIGHT LINE. ALL
CONNECTION TO GROUND RODS
MUST BE DONE USING EXOTHERMIC
WELDS, TYP. (BASE BID)
INSTALL NEW IN-PAVEMENT
APPROACH LIGHTS (5 EACH),
COMPLETE WITH ALL
COMPONENTS AND WIRING
ON NEW LIGHT BASES AND
CONCRETE FOUNDATIONS
(TYP. FOR STATIONS198-206)
1-2" SCH. 40 PVC, PCC ENCASED
WITH: 2-1/C #6, 5kV, L-824C, (ALS-1N CKT.)
1-2" SCH. 40 PVC, PCC ENCASED
WITH: 2-1/C #6, 5kV, L-824C, (ALS-2N CKT.)
#6 SOLID COPPER. COUNTERPOISE
INSTALLED HALF WAY BETWEEN
EDGE OR RWY AND LIGHT LINE.
ALL CONNECTION TO GROUND
RODS MUST BE DONE USING
EXOTHERMIC WELDS (TYP.)
INSTALL NEW SFL-19 MASTER
CONTROL RACK, ADB 400VDC.
SYSTEM. SEE INSTALLATION
DETAILS ON SHEET EA505
2" SCH 40 PVC WITH:
1- 12-STRAND, SINGLE MODE
OUTDOOR FIBER CABLE, OS2, FROM
SFL MASTER CONTROL CABINET TO
AIRFIELD ELECTRICAL VAULT, FOR
CONTROL AND MONITORING OF THE
SFL SYSTEM.
4" SCH 40 PVC WITH:
2- #2, 5kV, 133% EPR INSULATION 1-#6, 600v GND
1-2" SCH. 40 PVC WITH:
2-1/C #6, 5kV, L-824C
CABLE (TWY B CKT.,
BASE BID)
INSTALL:
2-1/C #6, 5kV, L-824C CABLE (ALS 1 N. CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 2 N. CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 3 N. CKT.)
2-1/C #6, 5kV, L-824C CABLE (TWY K CKT.)
EACH IN 2" SCH. 40 PVC
ALS-1N ALS-2N
NOTE: SEE GENERAL CONSTRUCTION
NOTES ON SHEET EA121.
INSTALL NEW L-862
ELEVATED HIRL ON NEW
L867 BASES, COLORS AS
SHOWN. SEE NOTE 13
ON SHEET EA121 (TYP.)
(BASE BID)
(BASE BID)
(BASE BID)
(BASE BID)
(BASE BID) (BASE BID)(BASE BID)
(BASE BID)
(BASE BID)
(BASE BID)(BASE BID)
(BASE BID)
INSTALL 1-4" SCH. 40 PVC WITH
2-#2, 15 kV, 133% EPR CABLES
1-#2, 600V GROUND
SEE SHEET EA524
FOR LOCALIZER
MARKER DETAILS
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text N00°26'17"E
207+00 208+00 209+00 210+00 211+00 212+00 213+00 214+00 215+00
CP CP CP CP
C P
C P
C P
C P
C P
C P
C P
C P
C P
CP CP CP CP
TW
Y B
TW
Y B
TW
Y B
TW
Y B
B E
E
E E
B
B B B
R R
R R
R R
R R
R R
R R
R R
R R
R R
R R
R19 R19 R19
R19 R19 R19 R19
R
R
R
PLZ
PLZ
CP
TWY B TWY B TWY B TWY B TWY B
SFL-N
SFL-N
SFL-N
SFL-N
SFL-N
SFL-N
ALS-2N
ALS-2N
ALS-2N
ALS-2N
ALS-2N
PLZ
ALS-2N
ALS-2N
PLZ
ALS-2N
ALS-2N
ALS-2N
ALS-2N
ALS-3N
ALS-3N
ALS-3N
ALS-3N
SFL-N
SFL-N
ALS-2N
ALS-2N
IC
C
-E
IC
C -E
IC
C
-E
IC
C -C
IC
C
-C
IC
C -C
SFL-N
SFL-N
ALS-2N
ALS-3N
ALS-2N
ALS-2N
PLZ
SFL-N
SFL-N
ALS-2N
ALS-3N
ICC-C ICC-C ICC-C
ICC-E ICC-E ICC-E
PLZ
PLZ
PLZ
PLZ
ALS-3N
ALS-3N
ALS-3N ALS-3N ALS-3N
ALS-3N ALS-3N ALS-3N ALS-3N
AL
S-
3N
AL
S- 3N
AL
S-
3N
ALS-3N ALS-3N
ALS-3N
ALS-3N
ALS-3N
ICC-C
ICC-C
ICC-C
ICC-C ICC-C ICC-C ICC-C ICC-C ICC-C
ICC-E
ICC-E
ICC-E
ICC-E ICC-E ICC-E ICC-E ICC-E ICC-E
PLZ
SF
L-
N
ALS-2NALS-2NALS-2N
ALS
-2N
ALS
-2N
IC
C
-E
IC
C -E
ICC-E ICC-E
IC
C
-E
IC
C -E
IC
C
-E
IC
C
-C
IC
C -C
ICC-C ICC-C
IC
C
-C
IC
C -C
IC
C
-C
CP CP CP
C P
C P
C P
C P
C P
CP CP CP CP CP
CP
CP
C P
CP CP CP CP CP CP CP CP
C P
C P
C P
CP CP
C P
C P
C P
C P
E
C P
C P
C P
C P
CP CP CP CP
CP
CP
CP
CP CP CP CP CP CP CP CP
C P
CP
CP CP CP
LO
C
LO
C01
LO
C01
LO
C01
LO
C
01C
LO
C01C
LO
C01C
LO
C01C
DUCT-CE DUCT-CE DUCT-CE
FO
FO
FO
FO
FO
FO
FO
FO
FO
FO
FO
FO
FO
FO
FO
FO
W W
W W
W W
W W
W W
W W
W W
W W
W W
W W
W W
W
FR
FR
U D
FR
UDUDUD
UDUDUD
UD
U D
U D
U D
U D
U D
SD
SD
D
D
D
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
STA: 207+99.98
85.00' R
EL: 582.06
STA: 207+99.98
75.00' R
EL: 582.25
STA: 207+99.98
65.00' R
EL: 582.43
STA: 207+99.98
55.00' R
EL: 582.60
STA: 207+99.98
45.00' R
EL: 582.73
STA: 207+99.98
85.00' L
EL: 582.10
STA: 207+99.98
75.00' L
EL: 582.26
STA: 207+99.98
65.00' L
EL: 582.43
STA: 207+99.98
55.00' L
EL: 582.60
STA: 207+99.98
45.00' L
EL: 582.73
STA: 208+00.57
162.50' L
EL: 581.54
STA: 207+99.97
226.88' L
EL: 581.44
STA: 207+99.98
291.25' L
EL: 581.35
STA: 206+69.16
291.25' L
EL: 579.57
STA: 207+99.98
95.00' R
EL: 581.86
STA 206+74.61
L -339.88
STA 208+36.25
L -137.49
STA 208+89.24
L -137.49 STA 209+89.68
L -137.49
STA 210+84.71
L -47.75
STA 211+89.71
L -47.75
STA 213+84.52
L -47.56
STA 214+73.74
R 10.27
STA 212+89.71
L -47.75
STA: 206+89.98
0.00'
EL: 582.57
STA: 207+91.48
0.00'
EL: 583.23
SD
SD
SD
SD
SD
SD
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A
B
C
D
E
F
G
H
J
K
L
M
N
P
SU
BM
IT
TE
D B
Y:
C H
EC
KE
D B
Y:
D R
AW
N
B Y:
D
ES
IG
N
ED
B
Y:
C O
N
TR
AC
T
N O
SO
LI
C
IT
AT
IO
N N
O
IS
SU
E D
AT
E:
SI
ZE
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E
SHEET ID
SHEET OF 467
MI ANGB
ST
AT
E O
F M
IC
H
IG
AN
D
EP
AR
TM
EN
T
O F
TE
C
H N
O
LO
G Y, ST
AT
E
FA
C
IL
IT
IE
S
AD
M
IN
IS
TR
AT
IO
N D
ES
IG
N A
N D
C O
N
ST
R U
C
TI
O N
D
IV
IS
IO
N
LA
N C
IN
G
, M
IC
H
IG
AN
M
AN
AG
EM
EN
T, A N
D B
U D
E
5, AN
SI
D
M
EA
D
H U
N T, IN
C
D
EM
IN
G W
AY
M
ID
D
LE
TO
N , W
I
SE
LF
R
ID
G E
AI
R
N
AT
IO
N
AL
G
U
AR
D B
AS
E, M
IC
H
IG
AN
R
U N
W
AY
E N
C R
O
AC
H M
EN
T
SO
LU
TI
O
N
PR
O
JE
C
T #2
AI
R
FI
EL
D
IM
PR
O
VE
M
EN
TS
TA
SK
M C
C A
M
IT
IG
AT
E R
U N
W
AY
E N
C R
O
AC
H M
EN
T
Y
TY
PE
B -3
0% F
IN
AL
S U
BM
IT
TA
L
M
JR
D
LU
PA
B
D R
P
PR
O
PO
SE
D
E
LE
C
TR
IC
AL
P
LA
N
EA137
RUNWAY 01-19
KEY MAP
M
AT
C H
L
IN
E
- P
R
EV
IO
U
S
SH
EE
T
MATCH LINE - SHEET EA146
PROPOSED TAXIWAY
EDGE LIGHTS, SEE NOTES
13 AND 14 ON SHEET
EA121, TYP. (BASE BID)
INSTALL 1-2" SCH.40 PVC FOR
TAXIWAY A (TASK 2) FUTURE
WORK (BASE BID)
INSTALL L-867 BASE CA WITH 3/8"
BLANK COVERS UNDER THIS
CONTRACT FOR FUTURE TAXIWAY
A (TASK 2)WORK (BASE BID)
INSTALL NEW IN-PAVEMENT
APPROACH LIGHTS (5 EACH),
AND (1 EACH) IN-PAVEMENT
FLASHER, COMPLETE WITH ALL
COMPONENTS AND WIRING ON
NEW LIGHT BASES AND
CONCRETE FOUNDATIONS M
AT
C
H L
IN
E
- N
EX
T
SH
EE
T
(S) LOC CHECKPOINT
TRUE N
PLAN
NORTH
00 30 60
TR
U
E N
PLAN
NORTH
6W-2" PPC ENCASED DUCT BANK
1-2" SCH. 40 PVC WITH:
2-1/C #6, 5kV, L-824C
CABLE (RWY R19 CKT.)
1-2" SCH. 40 PVC, PCC ENCASED
WITH: 2-1/C #6, 5kV, L-824C, (ALS-2N CKT.)
INSTALL NEW IN-PAVEMENT
APPROACH LIGHTS (8 EACH),
COMPLETE WITH ALL
COMPONENTS AND WIRING ON
NEW LIGHT BASES AND
CONCRETE FOUNDATIONS
INSTALL NEW IN-PAVEMENT
APPROACH LIGHTS (8 EACH),
COMPLETE WITH ALL
COMPONENTS AND WIRING ON
NEW LIGHT BASES AND
CONCRETE FOUNDATIONS
INSTALL 1-2" SCH. 40 PVC
FOR FUTURE TAXIWAY B
(TASK 3) WORK
INSTALL ELEVATED RUNWAY END
(THRESHOLD) LIGHTS ON NEW L-867
BASES, COMPLETE WITH ISOLATION
TRANSFORMERS AND 360 RED LENSES.
SEE NOTES 13 AND 14 ON SHEET EA121
(BASE BID)
INSTALL ELEVATED RUNWAY END
(THRESHOLD) LIGHTS ON NEW L-867
BASES, COMPLETE WITH ISOLATION
TRANSFORMERS AND 360 RED
LENSES. SEE NOTES 13 AND 14 ON
SHEET EA121, TYP. (BASE BID)
INSTALL 1 -2" SCH. 40 PVC FOR POWER WITH:
3-1/C #8 THWN-2
1-#8 GREEN EQUIP. GROUND
FROM MAIN SFL CONTROL PANEL TO JUNCTION
BOX AT EACH FLASHER STATION. POWER WIRES
ARE CONNECTED IN PARALLEL FROM STATION TO
STATION (TYP.).
INSTALL 1- 2" SCH. 40 PVC FROM MAIN SFL CONTROL
PANEL TO EACH FLASHER STATION WITH:
1-MANHATTAN WIRE M8628010, #18 AWG , TRIAD
SHIELDED, 600V CABLE FOR COMMUNICATION BUS.
DAISY CHAIN FROM MASTER P1 TO FIRST ICC P1 AND
FROM ICC P3 TO NEXT ICC P1 (TYP.). SEE
CONNECTION DIAGRAM ON SHEET EA520
2" SCH. 40 PVC WITH:
2-1/C #6, 5kV, L-824C (ALS-2N CKT.)
2-1/C #6, 5kV, L-824C (ALS-3N CKT.)
INSTALL NEW ELEVATED
APPROACH LIGHTS (5 EACH),
AND (1 EACH) ELEVATED
FLASHER, COMPLETE WITH ALL
COMPONENTS AND WIRING ON
NEW LIGHT BASES AND
CONCRETE FOUNDATIONS (TYP.
FROM STA. 208+90 TO STA.
226+65). SEE ALSF STATIONING
ON SHEET EA152
JET BLAST FEN
C
E
ALS-2N ALS-3N
INSTALL NEW ELEVATED
APPROACH LIGHTS (5 EACH),
AND (1 EACH) ELEVATED
FLASHER, COMPLETE WITH ALL
COMPONENTS AND WIRING ON
NEW LIGHT BASES AND
CONCRETE FOUNDATIONS (TYP.
STA. 208+90 TO STA. 226+65).
SEE ALSF STATIONING ON
SHEET EA152
1-2" SCH. 40 PVC CONDUIT
FROM ICC CABINET TO LIGHT
BAR WITH:
1- MANUFACTURER-SUPPLIED 5
CONDUCTOR, SHIELDED CABLE
(TYP.) SEE SHEET EA520 FOR
CONNECTION DIAGRAM (TYP.)
NOTE: SEE GENERAL CONSTRUCTION
NOTES ON SHEET EA121.
(BASE BID) (BASE BID)
(BASE BID)
(BASE BID)
1-2" SH. 40 PVC CONCRETE
ENCASED 24-STRAND
SINGLE-MOD FIBER OPTIC CABLE.
INSTALL 1-4" SCH. 40 PVC WITH
2-#2, 15 kV, 133% EPR CABLES
1-#2, 600V GROUND
MATCH LINE - SHEET EA149
AutoCAD SHX Text N00°26'17"E
C O
M M
COMM
COMM
COMM
COMM
C O
M M
C O
M M
C O
M M
C /E
C /E
C /E
C /E
C /E
C /E
C /E
C /E
C /E
C /E
C /E
C /E
C /E
C /E
C /E
C /E
C /E D
D
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
215+00 216+00 217+00 218+00 219+00 220+00 221+00 222+00
PLZ
IC
C
-E
IC
C -C
IC
C
-C
IC
C -C
PLZALS-3N
ICC-C
ICC-E
PLZDUCT-CE DUCT-CE
PLZ
PLZ
PLZ
PLZ
PLZ
PLZALS-3N ALS-3N ALS-3N ALS-3N ALS-3N
ICC-C ICC-C
CP CP CP CP CP CP CP CP CP CP CP CP
ICC-E ICC-E
ICC-C ICC-C
ICC-E ICC-E
ICC-C ICC-C
ICC-E ICC-E
ICC-C ICC-C
ICC-E ICC-E
ICC-C ICC-C
ICC-E ICC-E
CP CP CP CP CP CP CP CP CP CP CP CP CP CP CP
C P
C P
C P
C P
CP CP
DUCT-CE
BH
#05
BH
#06
STA 215+84.71
R 10.35
STA 216+55.00
R 10.01 STA 217+68.67
R 10.01
STA 218+68.67
R 10.01
STA 219+68.67
R 10.01 STA 220+68.67
R 10.01
STA 221+68.67
R 10.01
STA 222+68.67
R 10.01
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A
B
C
D
E
F
G
H
J
K
L
M
N
P
SU
BM
IT
TE
D B
Y:
C H
EC
KE
D B
Y:
D R
AW
N
B Y:
D
ES
IG
N
ED
B
Y:
C O
N
TR
AC
T
N O
SO
LI
C
IT
AT
IO
N N
O
IS
SU
E D
AT
E:
SI
ZE
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E
SHEET ID
SHEET OF 467
MI ANGB
ST
AT
E O
F M
IC
H
IG
AN
D
EP
AR
TM
EN
T
O F
TE
C
H N
O
LO
G Y, ST
AT
E
FA
C
IL
IT
IE
S
AD
M
IN
IS
TR
AT
IO
N D
ES
IG
N A
N D
C O
N
ST
R U
C
TI
O N
D
IV
IS
IO
N
LA
N C
IN
G
, M
IC
H
IG
AN
M
AN
AG
EM
EN
T, A N
D B
U D
E
5, AN
SI
D
M
EA
D
H U
N T, IN
C
D
EM
IN
G W
AY
M
ID
D
LE
TO
N , W
I
SE
LF
R
ID
G E
AI
R
N
AT
IO
N
AL
G
U
AR
D B
AS
E, M
IC
H
IG
AN
R
U N
W
AY
E N
C R
O
AC
H M
EN
T
SO
LU
TI
O
N
PR
O
JE
C
T #2
AI
R
FI
EL
D
IM
PR
O
VE
M
EN
TS
TA
SK
M C
C A
M
IT
IG
AT
E R
U N
W
AY
E N
C R
O
AC
H M
EN
T
Y
TY
PE
B -3
0% F
IN
AL
S U
BM
IT
TA
L
M
JR
D
LU
PA
B
D R
P
PR
O
PO
SE
D
E
LE
C
TR
IC
AL
P
LA
N
EA138
KEY MAP
M
AT
C H
L
IN
E
- P
R
EV
IO
U
S
SH
EE
T
M
AT
C H
L
IN
E
- N
EX
T
SH
EE
T
INSTALL NEW ASPHALT
MILLING/AGGREGATE SURFACED
MAINTENANCE ROAD, TYP.
TRUE N
PLAN
NORTH
00 30 60
TR
U E N
PLAN
NORTH
4W-2" PCC ENCASED
DUCT BANK (BY OTHERS)
1-2" SCH. 40 PVC, WITH: 2-1/C #6,
5kV, L-824C, (ALS-3N CKT.)
INSTALL 1 -2" SCH. 40 PVC FOR POWER WITH:
3-1/C #8 THWN-2
1-#8 GREEN EQUIP. GROUND
FROM MAIN SFL CONTROL PANEL TO JUNCTION
BOX AT EACH FLASHER STATION. POWER WIRES
ARE CONNECTED IN PARALLEL FROM STATION TO
STATION (TYP.).
INSTALL 1- 2" SCH. 40 PVC FROM MAIN SFL CONTROL
PANEL TO EACH FLASHER STATION WITH:
1-MANHATTAN WIRE M8628010, #18 AWG , TRIAD
SHIELDED, 600V CABLE FOR COMMUNICATION BUS.
DAISY CHAIN FROM MASTER P1 TO FIRST ICC P1 AND
FROM ICC P3 TO NEXT ICC P1 (TYP.). SEE
CONNECTION DIAGRAM ON SHEET EA520
INSTALL NEW ELEVATED
APPROACH LIGHTS (5 EACH),
AND (1 EACH) ELEVATED
FLASHER, COMPLETE WITH ALL
COMPONENTS AND WIRING ON
NEW LIGHT BASES AND
CONCRETE FOUNDATIONS (TYP.
STA. 208+90 TO STA. 226+65).
SEE ALSF STATIONING ON
SHEET EA152
4-4" SCH. 40 PVC, PCC ENCASED
WITH: (ALS-3N CKT.)
(ICC-C)
(ICC-E)
(SPARE)
1-2" SCH. 40 PVC CONDUIT
FROM ICC CABINET TO LIGHT
BAR WITH:
1- MANUFACTURER-SUPPLIED 5
CONDUCTOR, SHIELDED CABLE
(TYP.) SEE SHEET EA520 FOR
CONNECTION DIAGRAM (TYP.)
NOTE: SEE GENERAL CONSTRUCTION
NOTES ON SHEET EA121.
AutoCAD SHX Text N00°26'17"E
XXXXXX
X X
X X
X X
X X
X X
X X
X X
X X
X X X X X X X
C /E
C /E
C /E
C /E
C /E
C /E
C /E
C /E
C /E
C /E
C /E
C /E
C /E
C /E
C /E
C /E
C /E
223+00 224+00 225+00 226+00 227+00 228+00 229+00 230+00 231+00
PLZ
PLZ
PLZ
PLZALS-3N ALS-3N ALS-3N ALS-3N
CP CP CP CP CP CP CP CP CP CP
ICC-C ICC-C
ICC-E ICC-E
ICC-C ICC-C
ICC-E ICC-E
ICC-C ICC-C
ICC-E ICC-E
ICC-C ICC-C
ICC-E ICC-E
CP CP CP CP CP CP CP CP CP CP
STA 223+68.67
R 10.01
STA 224+68.67
R 10.01
STA 225+68.67
R 10.01
STA 226+68.67
R 10.01
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A
B
C
D
E
F
G
H
J
K
L
M
N
P
SU
BM
IT
TE
D B
Y:
C H
EC
KE
D B
Y:
D R
AW
N
B Y:
D
ES
IG
N
ED
B
Y:
C O
N
TR
AC
T
N O
SO
LI
C
IT
AT
IO
N N
O
IS
SU
E D
AT
E:
SI
ZE
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E
SHEET ID
SHEET OF 467
MI ANGB
ST
AT
E O
F M
IC
H
IG
AN
D
EP
AR
TM
EN
T
O F
TE
C
H N
O
LO
G Y, ST
AT
E
FA
C
IL
IT
IE
S
AD
M
IN
IS
TR
AT
IO
N D
ES
IG
N A
N D
C O
N
ST
R U
C
TI
O N
D
IV
IS
IO
N
LA
N C
IN
G
, M
IC
H
IG
AN
M
AN
AG
EM
EN
T, A N
D B
U D
E
5, AN
SI
D
M
EA
D
H U
N T, IN
C
D
EM
IN
G W
AY
M
ID
D
LE
TO
N , W
I
SE
LF
R
ID
G E
AI
R
N
AT
IO
N
AL
G
U
AR
D B
AS
E, M
IC
H
IG
AN
R
U N
W
AY
E N
C R
O
AC
H M
EN
T
SO
LU
TI
O
N
PR
O
JE
C
T #2
AI
R
FI
EL
D
IM
PR
O
VE
M
EN
TS
TA
SK
M C
C A
M
IT
IG
AT
E R
U N
W
AY
E N
C R
O
AC
H M
EN
T
Y
TY
PE
B -3
0% F
IN
AL
S U
BM
IT
TA
L
M
JR
D
LU
PA
B
D R
P
PR
O
PO
SE
D
E
LE
C
TR
IC
AL
P
LA
N
EA139
KEY MAP
M
AT
C H
L
IN
E
- P
R
EV
IO
U
S
SH
EE
T
BASE PROPERTY LINE
TRUE N
PLAN
NORTH
00 30 60
TR
U E N
PLAN
NORTH
INSTALL NEW ASPHALT
MILLING/AGGREGATE SURFACED
MAINTENANCE ROAD, TYP.
1-2" SCH. 40 PVC, PCC ENCASED
WITH: 2-1/C #6, 5kV, L-824C, (ALS-3N CKT.)
INSTALL 1 -2" SCH. 40 PVC FOR POWER WITH:
3-1/C #8 THWN-2
1-#8 GREEN EQUIP. GROUND
FROM MAIN SFL CONTROL PANEL TO JUNCTION
BOX AT EACH FLASHER STATION. POWER WIRES
ARE CONNECTED IN PARALLEL FROM STATION TO
STATION (TYP.).
INSTALL 1- 2" SCH. 40 PVC FROM MAIN SFL CONTROL
PANEL TO EACH FLASHER STATION WITH:
1-MANHATTAN WIRE M8628010, #18 AWG , TRIAD
SHIELDED, 600V CABLE FOR COMMUNICATION BUS.
DAISY CHAIN FROM MASTER P1 TO FIRST ICC P1 AND
FROM ICC P3 TO NEXT ICC P1 (TYP.). SEE
CONNECTION DIAGRAM ON SHEET EA520
INSTALL NEW ELEVATED
APPROACH LIGHTS (5 EACH),
AND (1 EACH) ELEVATED
FLASHER, COMPLETE WITH ALL
COMPONENTS AND WIRING ON
NEW LIGHT BASES AND
CONCRETE FOUNDATIONS (TYP.
FROM STA. 208+90 TO STA.
226+65). SEE ALSF STATIONING
ON SHEET EA152
1-2" SCH. 40 PVC CONDUIT
FROM ICC CABINET TO LIGHT
BAR WITH:
1- MANUFACTURER-SUPPLIED 5
CONDUCTOR, SHIELDED CABLE
(TYP.) SEE SHEET EA520 FOR
CONNECTION DIAGRAM (TYP.)
NOTE: SEE GENERAL CONSTRUCTION
NOTES ON SHEET EA121.
AutoCAD SHX Text N00°26'17"E
E E E E E E E E E E E E E E E E
E
E
E
E
E
E
E
E
E
E
E
EEE
EE
FOC
FOC
FOC
FO
C
FO
C
COMM
COMM
COMM
COMM
COMM COMM
COMM
COMM
COMM
COMM
COMM
E
C O
M M
C O
M M
FO
C
FO
C
E E
M H
M H
FOC-ILS
FOC-ILS
FOC-ILS
FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS
FO
C
-IL
S
FO
C
-IL
S
FO
C
-IL
S
FOC-ILS FOC-ILS FOC-ILS FOC-ILS
FO
C
-IL
S
FOC
FOC
FOC
FOC
FOC
FOC
FOC
FOC FOC FOC FOC FOC FOC FOC FOC FOC FOC FOC FOC FOC FOC FOC FOC FOC
FOC
FOC
FOC
FOC
FOC
COMM COMM COMM COMM COMM COMM COMM COMM COMM COMM COMM COMM COMM COMM COMM COMM COMM COMM
FOC FOC FOC FOC
COMM COMM COMM COMM COMM COMM COMM
COMM COMM COMM COMM COMM COMM COMM T
T
FO
C
FO
C
C O
M M
C O
M M
T
FOC
FOC
FOC
COMM
COMM
COMM
FOC FOC FOC FOC FOC
FOC FOC FOC FOC FOC FOC
FO
C
FO
C
FO
C
FO
C
FO
C
FO
C
C O
M M
C O
M M
C O
M M
C O
M M
C O
M M
CO
M
M
X X
X X
X X
X X
X X
X X
XXXXXXXXXXXXXXXXXXXXX
X X
X X
X X
X X
X X
X X
X X
W W
W W
W W
W W
W W
W
W W W W W W W
W
W
W
W
CB
CB
CB
CB
CB
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A
B
C
D
E
F
G
H
J
K
L
M
N
P
SU
BM
IT
TE
D B
Y:
C H
EC
KE
D B
Y:
D R
AW
N
B Y:
D
ES
IG
N
ED
B
Y:
C O
N
TR
AC
T
N O
SO
LI
C
IT
AT
IO
N N
O
IS
SU
E D
AT
E:
SI
ZE
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E
SHEET ID
SHEET OF 467
MI ANGB
ST
AT
E O
F M
IC
H
IG
AN
D
EP
AR
TM
EN
T
O F
TE
C
H N
O
LO
G Y, ST
AT
E
FA
C
IL
IT
IE
S
AD
M
IN
IS
TR
AT
IO
N D
ES
IG
N A
N D
C O
N
ST
R U
C
TI
O N
D
IV
IS
IO
N
LA
N C
IN
G
, M
IC
H
IG
AN
M
AN
AG
EM
EN
T, A N
D B
U D
E
5, AN
SI
D
M
EA
D
H U
N T, IN
C
D
EM
IN
G W
AY
M
ID
D
LE
TO
N , W
I
SE
LF
R
ID
G E
AI
R
N
AT
IO
N
AL
G
U
AR
D B
AS
E, M
IC
H
IG
AN
R
U N
W
AY
E N
C R
O
AC
H M
EN
T
SO
LU
TI
O
N
PR
O
JE
C
T #2
AI
R
FI
EL
D
IM
PR
O
VE
M
EN
TS
TA
SK
M C
C A
M
IT
IG
AT
E R
U N
W
AY
E N
C R
O
AC
H M
EN
T
Y
TY
PE
B -3
0% F
IN
AL
S U
BM
IT
TA
L
M
JR
D
LU
PA
B
D R
P
PR
O
PO
SE
D
E
LE
C
TR
IC
AL
P
LA
N
EA140
KEY MAP
TR
U
E N
PLAN
NORTH
00 50 100
TAXIW
AY M
(E
XISTIN
G ASPHALT
MIDFIELD ACCESS ROAD
(EXISTING ASPHALT)
EXISTING ELECTRICAL VAULT BUILDING.
SEE SHEETS ES101 AND ES102 FOR
DETAILED VAULT UPGRADES
EXISTING 12W-4"
ELECTRICAL DUCT
BANK (HOMERUN), TYP.
PMH(1)
14W-4" DB
HH(1C)
4W-4" CONCRETE ENCASED
ELEC DUCTBANK
TRANSFORMERS
2W-4" CONCRETE ENCASED
COMM DUCTBANK
GENERATOR
COMM MH (64C)
ELEC MH (E3)
2W-4" CONCRETE
ENCASED COMM DUCTBANK
500KVA TRANSFORMER
ELEC MH (E2)
COMM MH (64B)
2W-4" CONCRETE
ENCASED COMM DUCTBANK
12W-4" DB
PMH(2)
2W-4" DB2W-4" DB
HH(2C)
INSTALL:
2-1/C #6, 5kV, L-824C CABLE (ALS 1 N CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 2 N CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 3 N CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 1 S CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 2 S CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 3 S CKT.)
2-1/C #6, 5kV, L-824C CABLE (RWY 19 CKT.)
2-1/C #6, 5kV, L-824C CABLE (RWY 1 CKT.)
2-1/C #6, 5kV, L-824C CABLE (RWY PAPI 19 CKT.)
2-1/C #6, 5kV, L-824C CABLE (RWY PAPI 1 CKT.)
2-1/C #6, 5kV, L-824C CABLE (RDR CKT.)
2-1/C #6, 5kV, L-824C CABLE (THRSLD N. CKT.)
2-1/C #6, 5kV, L-824C CABLE (THRSLD S. CKT.)
2-1/C #2, 5kV, 133% EPR INSULATION (SFL 19 POWER) 2-1/C #2, 5kV, 133% EPR INSULATION (SFL 1 POWER)
2-#2 INSULATED GROUND, 600V
IN EXISTING DUCT BANK AND STRUCTURES
INSTALL:
2- 12-STRAND, SINGLE MODE OUTDOOR
FIBER CABLE, OS2, TO SFL-N AND SFL-S
MASTER CONTROL CABINETS IN EXISTING
COMMUNICATION DUCT SYSTEM. SEE
SHEET EA505 AND EA520 FOR DETAILS
NOTE: SEE GENERAL CONSTRUCTION
NOTES ON SHEET EA121.
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text N00°26'17"E
E E
E
E E E
E
E
E E E
E E
E E
E E
E E
E
E
E
E E
E
E E E E
E E
E E
E E
E E
E E
E
E E
E E
E E
E
EE
E E
EE
E
EEEEEE
EE
E E E E
EEE
E E
E
E
E
E
E
E E E E E E E E E E E E E E E
E E
E E
E E
E E
E E
E E
E E
E
E E
E E
E E
E E
E E
E
E
E E
E E
E E
E E
E E
E E
E
E
E E
E E
E E
E
E
E E E E E E E E E
E E E E E E E E E E
E
E
E
E
E
E E E E E E E E E E
E
E
E E
E E
E E
E
COMM COMM COMM
E E E E E E E E E E E E E E
E
E
E
E
E E E
EEE
E E
E
E
E E
E E
E E
E
EEEEEEEEEEEEEEE
EEEEEEE
E E
E
EEEEEEEEEEE
EEEEEEEEEEEEEEEEE
EEEEEEEEE
COMM
COMM
COMM
COMM
COMM
COMM
COMM
COMM
COMM
COMM
COMM
COMM
COMM
COMM
COMM
COMM
E
E E
E
E E
FOC FOC FOC
FOC FOC FOC
FOC
FOC
FOC
FOC
FOC
FOC
FOC
FOC
FOC FOC
FOC
FOC
FOC
FOC
FOC
FOC
FOC
FOC
FOC
FOC
FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS
FOC-ILS
FOC-ILS
FOC-ILS
FOC
FOC
FOC
FOC
FOC
FOC
FOC
FOC
FO
C
-IL
S
FO
C
-IL
S
FO
C
-IL
S
FO
C
-IL
S
FO
C
-IL
S
FO
C
-IL
S
FO
C
-IL
S
FO
C
-IL
S
FO
C
-IL
S
FO
C
-IL
S
FO
C
-IL
S
E E
E E
E E
E E
E
D
D
D
D
D
D
D
CB
CB
CB
U D
U D
U D
U D
FR
FR
D
CBCB
FR
W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W
W W W W W W WWWW
W W W W W W W W W WW W W W W W W W W W W
CB
CB
CB
CB
CB
CB
CB
CB
CB
2+
3+
4+
5+
6+
7+
8+
9+
0+
1+
2+
C P
C P
C P
C P
C P
PPPP PAPI 1CP
R
R
R
R
R
R1
R1
R1
CP
CP
CP
W W
W W
W W
W W
W W
RD
R
RD
R
CP
CP
STA 123+45.00
L -145.00
STA 126+50.00
L -215.00
UD
FR
U D
U D
U D
U D
D SDSD
STA: 131+18.34
85.00' R
EL: 579.67
STA: 131+18.34
85.00' L
EL: 579.73
STA: 129+21.37
85.00' L
EL: 579.67
STA: 125+27.43
85.00' L
EL: 579.60
STA: 123+30.46
85.00' L
EL: 579.75
STA 124+99.98
L -400.00
STA: 127+24.40
85.00' L
EL: 579.72
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A
B
C
D
E
F
G
H
J
K
L
M
N
P
SU
BM
IT
TE
D B
Y:
C H
EC
KE
D B
Y:
D R
AW
N
B Y:
D
ES
IG
N
ED
B
Y:
C O
N
TR
AC
T
N O
SO
LI
C
IT
AT
IO
N N
O
IS
SU
E D
AT
E:
SI
ZE
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E
SHEET ID
SHEET OF 467
MI ANGB
ST
AT
E O
F M
IC
H
IG
AN
D
EP
AR
TM
EN
T
O F
TE
C
H N
O
LO
G Y, ST
AT
E
FA
C
IL
IT
IE
S
AD
M
IN
IS
TR
AT
IO
N D
ES
IG
N A
N D
C O
N
ST
R U
C
TI
O N
D
IV
IS
IO
N
LA
N C
IN
G
, M
IC
H
IG
AN
M
AN
AG
EM
EN
T, A N
D B
U D
E
5, AN
SI
D
M
EA
D
H U
N T, IN
C
D
EM
IN
G W
AY
M
ID
D
LE
TO
N , W
I
SE
LF
R
ID
G E
AI
R
N
AT
IO
N
AL
G
U
AR
D B
AS
E, M
IC
H
IG
AN
R
U N
W
AY
E N
C R
O
AC
H M
EN
T
SO
LU
TI
O
N
PR
O
JE
C
T #2
AI
R
FI
EL
D
IM
PR
O
VE
M
EN
TS
TA
SK
M C
C A
M
IT
IG
AT
E R
U N
W
AY
E N
C R
O
AC
H M
EN
T
Y
TY
PE
B -3
0% F
IN
AL
S U
BM
IT
TA
L
M
JR
D
LU
PA
B
D R
P
PR
O
PO
SE
D
E
LE
C
TR
IC
AL
P
LA
N
EA141
KEY MAP
TR
U
E N
PLAN
NORTH
00 50 100
INSTALL:
2-1/C #6, 5kV, L-824C CABLE (ALS 1 N CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 2 N CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 3 N CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 1 S CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 2 S CKT.)
2-1/C #6, 5kV, L-824C CABLE (ALS 3 S CKT.)
2-1/C #6, 5kV, L-824C CABLE (RWY 19 CKT.)
2-1/C #6, 5kV, L-824C CABLE (RWY 1 CKT.)
2-1/C #6, 5kV, L-824C CABLE (RWY PAPI 19 CKT.)
2-1/C #6, 5kV, L-824C CABLE (RWY PAPI 1 CKT.)
2-1/C #6, 5kV, L-824C CABLE (RDR CKT.)
2-1/C #6, 5kV, L-824C CABLE (THRSLD N. CKT.)
2-1/C #6, 5kV, L-824C CABLE (THRSLD S. CKT.)
2-1/C #2, 5kV, 133% EPR INSULATION (SFL 19 POWER) 2-1/C #2, 5kV, 133% EPR INSULATION (SFL 1 POWER)
2-#2 INSULATED GROUND, 600V
IN EXISTING DUCT BANK AND STRUCTURES
INSTALL:
2- 12-STRAND, SINGLE MODE OUTDOOR
FIBER CABLE, OS2, TO SFL-N AND SFL-S
MASTER CONTROL CABINETS IN EXISTING
COMMUNICATION DUCT SYSTEM. SEE
SHEET EA505 AND EA520 FOR DETAILS
INSTALL NEW L-806(L) SUPPLEMENTAL
WIND CONE WITH L-810 OBSTRUCTION
LIGHT WITH IR EMITTER . CONNECT TO R1
RUNWAY CIRCUIT. USE 20/6.6 A INLINE
TRANSFORMER AS REQUIRED BY
MANUFACTURER
L-880 (L) PAPI
SYSTEM (TYP.)
NOTE: SEE GENERAL CONSTRUCTION
NOTES ON SHEET EA121.
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text C
AutoCAD SHX Text C
AutoCAD SHX Text N00°26'17"E
EEEEEEEEEEEEEEEE
E
E
E E
E E
E E
E E
E E E E E E E E
E E E E E E E E
E E E
E E
E E
E E
E E
E E E E E E E E E E E E E E E
EEEEEEEEEEEE
E E E E E E E E E E
EEEEEE
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
EE
E
E
E
E
E
E
E
E
E
4800V
4800V
4800V
4800V
4800V
4800V
4800V
4800V
4800V
4800V
C O
M M
C O
M M
C O
M M
C O
M M
C O
M M
COMM
COMM
COMM
COMM
E
E
E
E
E
E
E
E
E E
E E
E E
E
E
E
E
E
E
E
E
E
E
FO
C
-ILS
FO
C
-ILS
FO
C
-ILS
FO
C
-ILS
FO
C
-ILS
T
50 kVA
E E E E E E E E E E E
D
D
C
BC
BC
B
C B
UD UD UD UD UD UD UD UD UD UD UD UD UD
UD UD UD UD UD UD UD UD UD
FR
FR
UD
FR
C B
C B
106+00 107+00 108+00 109+00 110+00 111+00 112+00 113+00 114+00 115+00 116+00 117+00 118+00 119+00 120+00 121+00
CP CP CP CP CP CP CP CP CP CP
CP CP CP CP CP CP CP CP
ALS-2S
ALS-2S
ALS-1S
ALS-1S
ALS-1S
ALS-1S
ALS-1S
E E
E E
E E
R1 R1 R1 R1 R1 R1 R1
G O
G O
G O
G Y
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G O
G Y
G O
G O
G O
G O
G O
G O
G O
R Y W Y
W Y
W Y
W Y
R YR YR Y
R Y R Y R Y R Y
JC
-2
R1 R1 R1 R1 R1 R1 R1 R1 R1
W Y
W Y
GS1C
G S1C
G S1C
G S1C
G S1C
G S1C
G S1C
G S1C
CP
C P
C P
C P
C P
C P
C P
C P
C P
C
STA 113+45.10
R 145.03STA 113+36.92
R 145.00
FR
FR
U D
U D
UD UD UD UD UD UD UD UD UD
UD UD UDUD UD UD UD UD UD
SD
SD
STA: 121+33.49
85.00' L
EL: 579.82
STA: 121+33.49
85.00' R
EL: 579.82
EL: 579.96
STA 120+34.44
R 953.52
EL: 580.02
STA: 119+36.52
85.00' L
EL: 579.89
STA: 119+36.52
85.00' R
EL: 579.89
STA 120+28.84
R 406.59
4800V
4800V
COMM
COMM
COMM
COMM
COMM
COMM
COMM
COMM
E
E
E
E
E
E
E
E
E
E E
E E
E E
E E
E
FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS FOC-ILS
COMMCOMMCOMMT
COMM
COMM
COMM
COMMC
G
S1C G
S1C G
S1C C
P C
P C
P C
P
STA 120+37.09
R 1500.01
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A
B
C
D
E
F
G
H
J
K
L
M
N
P
SU
BM
IT
TE
D B
Y:
C H
EC
KE
D B
Y:
D R
AW
N
B Y:
D
ES
IG
N
ED
B
Y:
C O
N
TR
AC
T
N O
SO
LI
C
IT
AT
IO
N N
O
IS
SU
E D
AT
E:
SI
ZE
M
AR
K
D
ES
C R
IP
TI
O N
D
AT
E
SHEET ID
SHEET OF 467
MI ANGB
ST
AT
E O
F M
IC
H
IG
AN
D
EP
AR
TM
EN
T
O F
TE
C
H N
O
LO
G Y, ST
AT
E
FA
C
IL
IT
IE
S
AD
M
IN
IS
TR
AT
IO
N D
ES
IG
N A
N D
C O
N
ST
R U
C
TI
O N
D
IV
IS
IO
N
LA
N C
IN
G
, M
IC
H
IG
AN
M
AN
AG
EM
EN
T, A N
D B
U D
E
5, AN
SI
D
M
EA
D
H U
N T, IN
C
D
EM
IN
G W
AY
M
ID
D
LE
TO
N , W
I
SE
LF
R
ID
G E
AI
R
N
AT
IO
N
AL
G
U
AR
D B
AS
E, M
IC
H
IG
AN
R
U N
W
AY
E N
C R
O
AC
H M
EN
T
SO
LU
TI
O
N
PR
O
JE
C
T #2
AI
R
FI
EL
D
IM
PR
O
VE
M
EN
TS
TA
SK
M C
C A
M
IT
IG
AT
E R
U N
W
AY
E N
C R
O
AC
H M
EN
T
Y
TY
PE
B -3
0% F
IN
AL
S U
BM
IT
TA
L
M
JR
D
LU
PA
B
D R
P
PR
O
PO
SE
D
E
LE
C
TR
IC
AL
P
LA
N
EA142
KEY MAP
TRUE N
PLAN
NORTH
00 50 100
TR
U
E N
PLAN
NORTH
M
AT
C H
L
IN
E
- S H
EE
T
EA
EXISTING 19 GLIDE SLOPE EQUIPMENT
SHELTER AND STANDBY GENERATOR
TO BE RELOCATED. SEE SHEET EA142
FOR PROPOSED NEW LOCATION
RWY 1 AND RWY19 GLIDE SLOPE RELOCATION NOTES :
1. THE CONTRACTOR IS RESPONSIBLE FOR VISITING THE SITE TO BECOME
FAMILIAR WITH EXISTING INSTALLATION PRIOR TO BIDDING.
2. THE CONTRACTOR IS RESPONSIBLE FOR COORDINATING WITH HQ
AFFSA/XME (WHO OWNS THE ILS EQUIPMENT) AND LOCAL WORK CENTER
(WHO MAINTAINS THE WEATHER EQUIPMENT) PRIOR TO DISCONNECTING
AND RECONNECTING EXISTING EQUIPMENT.
3. ITEMS TO BE RELOCATED INCLUDE BUT NOT LIMITED TO:
a) GLIDE SLOPE EQUIPMENT SHELTER
b) GLIDE SLOPE STANDBY GENERATOR
c) SERVICE TRANSFORMER
d) GLIDE SLOPE ANTENNA MAST AND ANTENNA ELEMENTS
e) WEATHER TOWER, WIND TOWER, AND VARIOUS WEATHER INSTRUMENTS
f) MISCELLANEOUS EQUIPMENT NEEDED TO COMPLETE THE RELOCATION
3 RELOCATION SHALL INCLUDE BUT NOT BE LIMITED TO:
a) DE-ENERGIZING AND DISCONNECTING SERVICE EQUIPMENT.
b) DISCONNECTING TRANSMITTING EQUIPMENT FROM ANTENNAS.
c) DISCONNECTING POWER TO ANTENNA MAST.
d) NEW FOUNDATIONS AT NEW SITE FOR EQUIPMENT BEING RELOCATED.
e) EXTENDING 4800V PRIMARY TO NEW LOCATION.
f) PLACE AND INSTALL TRANSFORMER ON NEW CONCRETE PAD AT THE NEW
LOCATION.
g) EXTENDING 24 STRAND, SINGLE MODE FIBER OPTIC CABLE AND
TERMINATING AT THE NEW LOCATION.
h) EXTENDING 25 PR, #19 COMMUNICATION CABLE AND TERMINATING AT
NEW LOCATION.
i) RE-ENERGIZING ELECTRICAL SERVICE AT THE NEW LOCATION.
j) RECONNECTING COMMUNICATION EQUIPMENT AT THE NEW LOCATION.
k) PLACING GLIDE SLOPE ANTENNA MAST…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .