Q&A 1
| O&M and VTE Maintenance Services Fresno, CA Solicitation Number: 47PK0219R0013 | ||
| Reference | Question | GSA Reply |
| page 2/182, para 2 | Can the government provide the current value of the incumbent contract? | The current contract annual cost = $1.237 MIL |
| page 3/182, para 3 | Can the government provide a copy of the attendance roster for the pre-proposal conference and site visit? | Yes. See attached sign-in Sheet. |
| C.1.r | Can the government clarify the scheduled and unscheduled maintenance requirements for fitness equipment? | Fitness center equipment shall be maintained IAW the manufacturer's recommended maintenance procedures. |
| C.8.5 | Can the government provide historic data on the number of service request received per year? | The number of service calls has varied widely year over year |
| Can the government provide historic data on the number of service request received for work not under the scope of this Contract per year? | average of 3-4 per year | |
| C.8.8.b | Has Energy Performance goals been identified by the government for Robert E Cole Federal Building and US Courthouse? | Yes |
| C.20 | Is labeling of the electrical circuits currently up to date? | Yes |
| C.24.5 | Can the government provide manufacture data for the UV lighting systems, to include manufacture, model, size, and quantities? | The UV lights are not listed in the equipment inventory because they are not stand alone equipment, they are part of the air handling equipment which is listed on the equipment inventory. |
| C.34.5 | Can the government provide manufacture data for the Air distribution terminal boxes, to include manufacture, model, size, and quantities? | 262 VAV's, 93 MIT's and 80 MFT's |
| C.45.20 | Can the government provide manufacture data for the Roof Anchorage Points, to include manufacture, model, and quantities? | 20 of them. |
| Exhibit J.5 | Can the government verify that shared liability for cost exceeding the nonreimbursable threshold of $2500.00 does not apply to any vertical transportation repair? | Confirmed; Vertical transportation equipment is full service and all repairs are to be included. No threshold exists for repairs to VTE equipment. |
| L.3.1.2(2)(b) | Can the government provide chiller sizes to include manufacture make, model, and serial number? | 1 ea York Unit Model YTG3A2B2-CGJ |
2 ea York Unit Model YTJ3C2E2-CRJ
L.3.1.2(2)(b) Can the government provide boiler sizes to include manufacture make, model, and serial number? 2 ea Cleaver Brooks model FLX-700-300-160HW 2 ea Lochinvar model CFN501PM
| L.3.1.2(3) | Question 1: Is the government requiring a complete QCP or a summary? | ||
| Question 2: If a complete QCP is required, will the government consider excluding the QCP from page count? | Contract shall develop and submit a summary QCP including the submission requirement stated in the SOW and submit a complete “Quality Control Plan” (QCP) 5 days before the contract start date. | ||
| C.44 | Will shared-liability apply to all larger repairs or only one per month | Shared liability is not limited to one per month | |
| Will the Government be providing office space for the contractor in the building? | Yes, the contractor will occupy the office space that is currently occupied by the incumbent |
Q&A 2
| O&M and VTE Maintenance Services Fresno, CA Solicitation Number: 47PK0219R0013 | |||
| Reference | Page # | Questions | GSA Reply |
| C.1 (C.) & C46.1 | 18, 65 | Café equipment, deep fat fryer has a ansual system. Will the O&M maintain the ansul system? | Yes |
| C.8.2 | 31 | Communications-will GSA provide 2-way radios for contract use? | Yes |
| C.36.1 | 47 | Controls/HVAC Training-will this position be a FTE for the BAS technician? | It is not required for this to be an FTE. This is up to the Contractor. |
| C.1 (j.) | 18 | Window cleaning system equipment (wall glider, tracks, davits, pedestals and associated equipment) will the equipment be required for annual inspections only? | Window washing is currently only required once yearly. Inspections on the equipement are once yearly and within 30 days before use. If coordinated properly, this can be a once yearly inspection. |
| C.1 | 18 | Will all major equipment inspections be required in the Base year of the contract? Eddy Current, Dry Pipe, Obstructions Inspections? | No, these inspections will continue on their normal cycle. |
| C.1 (r.) | 18 | Fitness center equipment (GSA-owned equipment only) Is there a list of GSA owned fitness equipment? Is this a repair and/or replace type of equipment? | There is not currently a list of this equipment. Yes, it is repair and/or replace equipment. |
| C.1.2 (i.) | 19 | Landscaping systems-is the irrigation systems excluded as well? | sprinkler heads and controls are excluded. Underground piping, valves and pumps are included in this contract |
| Exhibit J.6 | 136 | BIS-Will the CO/COR provide a copy of drawings, and blueprints to the contractor? | Yes |
| C.35.1 | 46 | it was mentioned during the conference that a complete air balance of the building is required, can you provide the reference # of the contract that states this is required? | Air balancing isn't specifically required by name, however the 6-step procedure outlined in http://retuningtraining.labworks.org/training/lms/) is, which involces analyzing and tuning the HVAC system |
| C.1 (h.) | 18 | Does the PA System on the Fire Alarm Panel suffice? | Existing systems |
| C.1 (o.) | 18 | Keycard systems, and control systems. Will the contractor be responsible for the USMS, and Judges access systems? Typically this is maintained by an outside vendor not O&M | No, the O&M will not be responsible for those key card access systems |
| C.1 (p.) | 18 | Are the wheelchair lifts ASME certified? | No |
| C.2 (f.) | 19 | Kitchen equipment excluded-is this for all freezers, coolers, and cooking equipment? | Amended SOW C.1t, Kitchen equipment will now be included in this contract |
| C.38.1 | 50 | Vertical trans-states 51 elevator test per year, is that correct? | Yes |
| C.42.4 | 56 | Painting-if the mechanical rooms are not currently painted, will they still be required to be painted? | Painting required by ANSI or OSHA is required. Codes do not require an entire room to be painted. |
Q&A 3
| O&M and VTE Maintenance Services Fresno, CA Solicitation Number: 47PK0219R0013 | ||
| Reference | Question | GSA Reply |
| 1. How many $2,500 deductible events per year for the last 3 years? | It is varied year over year. | |
| 2. What is the dollar value of the current contract for each of the last five years? | The current contract annual cost = $1.237 MIL | |
| 3. Is the offeror to submit no more than three projects as PPQ? Would GSA disregard the 4th and 5th contract/project if five projects are submitted? | Offeror should submit no more than three projects with relevant experience. | |
| 4. The Instructions to Offerors (pages 176 and 177) indicates information regarding Teaming Arrangements and Joint ventures should be included in “Volume I: General Company Information.” Does the Government want offerors to include the “General Company Information” in the Experience section or the Management Plan of Volume I? | Information regarding Teaming Arrangements and Joint ventures can be submitted separately. | |
| 5. If included in the Management Plan, can the number of pages required to describe the Teaming Arrangement or the Joint Venture be excluded from the 80 page Management Plan requirement? | See answer #4. | |
| 6. | Reference page 175, submission of Past Performance Questionnaires. RFP states: “For each project submitted under Factor L.3.1.1 Prior Experience, the offeror is requested to submit by the closing date for receipt of proposals a completed questionnaire Attachment D: Past Performance Questionnaire (PPQ). It is incumbent on the Offeror to ensure this information is current and accurate. Completed questionnaires should be sent directly from the reference to the Contracting Officer utilizing the instructions set forth in Attachment D of this RFP.” |
Does the government intend for BOTH offerors and the references to submit completed Past Performance Questionnaires or only the references are required to directly email the PPQs?
| The Past Performance Questionnaires (PPQ) should be emailed directly to the Contracting Officer from your references (not offerors). | ||
| 7. Paragraph C.5.1 on page 29 of the RFP states “The Contractor shall provide no more than thirty (60) days of transition startup services prior to the Contract start date…” Is the transition plan period 30 days or 60 days? | This is a typo error. The transition plan period is no more than thirty (30) days. | |
| 8. Reference page 176 of the RFP states “If applicable, include a copy of the Teaming Arrangement in Volume I: General Company Information of the proposal package.” Volume 1 includes 1. Experience, 2. Management Plan and 3. Past Performance. Shall Offerors place the TA in number 4 spot? | Yes, Teaming Arrangement can be submitted separately. | |
| 9. Reference page 1 of the RFP, Offer Receipt Date/Time of Friday, January 3, 2019@4:00 pm Pacific Time. With the holidays, many PPQ recipients are unavailable. Would the government consider allowing an extension for the receipts of the PPQs? | The due date for submission of quotes/proposals and the PPQ has been extended to January 14, 2020 @04:00 pm Pacific Time. | |
| 10. Paragraph 35.1, page 46, indicates the Preventive Maintenance Plan is submitted to the government within 30 days of contract start date; however the Submittals Chart / Deliverables from Paragraph C.48, page 71, indicates the Preventive Maintenance system should be delivered within 5 days of contract start. Please advise the date the offeror should submit the Preventive Maintenance Plan to the government. | Preventive Maintenance Plan should be delivered within 5 days of contract start. |
Q&A 4
| O&M and VTE Maintenance Services Fresno, CA Solicitation Number: 47PK0219R0013 | ||
| Reference | Question | GSA Reply |
| 1. Page 1 of the Request for Proposal (RFP) solicitation and also L.2.1, page 167 appear to have typographical errors, as they state the proposal due date is January 3, 2019. Please clarify. | Quotation/Proposal packages shall be submitted electronically no later than Tuesday January 14, 2020, 04:00 pm Pacific Time (email time stamp of arrival will be used for timely submission documentation) by email to Contract Specialist (CS) Jasmine Dare at jasmine.dare@gsa,gov and Contracting Officer (CO) Mei Chan at mei.chan@gsa.gov. | |
| 2. On page 22 of the RFP, under Federal Holidays, it states “…Thanksgiving is always the 3rd Thursday of November.” Thanksgiving in the U.S. is on the 4th Thursday of November. Please clarify. | Thanksgiving in the U.S. is on the 4th Thursday of November. | |
| 3. On page 29 of the RFP, C.5.1 states “The Contractor shall provide no more than thirty (60) days of transition startup services…” What is the length of the transition phase startup: 30 days or 60 days? Please clarify. | The Contractor shall provide no more than thirty (30) days of transition startup services. | |
| 4. On page 30 of the RFP, C.6.f refers to “TDL inspections.” No definition for TDL is provided in the RFP. Does TDL stand for “Terminal Deficiency List”? Please clarify. | TDL stands for “Terminal Deficiency List”. | |
| 5. On page 36 of the RFP, C.10.2.h states “Vertical Transportation, if applicable, escalators, elevators, dumb waiters or note Contractor information.” Please clarify what is being required for the Building Operating plan by this statement. | See amended SOW | |
| 6. C.23.3, on page 43, states “The Contractor shall respond promptly to routine work requests (i.e. plumbing & lighting issues) and complete the required work within twenty-four (24) hours of notification.” Is the work required to be completed within 24 hours of normal workdays (Monday through Friday, excluding holidays)? For example, if a routine work request were initiated at 3:45PM on a Friday, would completion by 3:45PM the following Monday (provided Monday is not a holiday) be considered timely? Please clarify. | Weekends are not considered to be part of the 24-hour response time for routine calls | |
| 7. C.28, page 44 states “In many cases, the AMS will be connected to the BAS.” Is the AMS connected to the BAS in the Coyle Federal Building and Courthouse? Please clarify. | No, See amended SOW C.36 | |
| 8. C.35.4, on page 47 of the RFP, states “The Contractor shall conduct the six step Re-Tuning procedure described in the Pacific Northwest National Laboratory (PNNL) (http://retuningtraining.labworks.org/training/lms/) Building commissioning training website. The initial frequency of the Re-Tuning is semi-annually.” Has any Re-Tuning been conducted under the current contract, and if so, when has it been performed? | No, See amended SOW C.35.4. Ongoing Commissioning / Re-Tuning: RESERVED |
| 9. On page 88 of the RFP, H.7 has a statement that seems to either be missing words or have additional words: “The Contractor shall accumulate GSA Form 139 (Record of Time of Arrival and Departure from Building) or other designated form for use in recording presence each calendar week, certify in writing on each form that the information shown is true and correct and, and within thirty (30) calendar days of week’s end, and shall be submitted with monthly submittal to the CO or designee.” Additionally, the intent of “within thirty (30) calendar days of week’s end” is unclear. Please clarify. | GSA Form 139 (Record of Time of Arrival and Departure from Building) shall be submitted with the monthly submittals to the CO or designee. Thirty (30) calendar days of week’s end meant the end of the month. |
| 10. L.1, page 167 has two paragraph (j)s. The second (j) repeats the initial statement/title of the first (j). Please clarify the duplication. | This is not duplication. The 2nd (j) is applicable to the following: Class Deviation 2018-O0018—Micro-Purchase Threshold, Simplified Acquisition Threshold, and Special Emergency Procurement Authority. Effective August 31, 2018. This deviation remains in effect until it is incorporated into the FAR or DFARS, or otherwise rescinded |
(j) Unique entity identifier. (Applies to all offers exceeding the micro-purchase threshold and offers at any dollar value if the solicitation requires the Contractor to be registered in the System for Award Management (SAM) database.) * * *
| 11. L.2.1, page 169 states “Offerors shall submit their RFP in Portable Document Format (PDF) with a total file size of less than 10MB.” Is each individual volume restricted to being below 10MB, or is it that the two volumes combined must be less than 10MB? Please clarify. | The two volumes combined must be less than 10MB. |
| 12. Section L goes from L.4 on pages 176 and 177 to L.6 on page 177. Is L.5 missing? Please clarify. | L.5 is reserved. |
| 13. The List of Documents on page 3 of the summary indicates that Exhibit J7a contains WD 2015-5641. Page 137 of the RFP also states that it is to be WD 2015-5641. However, the Exhibit actually contains WD 2015-5609. Please clarify which wage determination is intended. | WD 2015-5641 was incorrect and it should be WD 2015-5609. |
| 14. PWS L.2.1 at the bottom pf page 168 states “The use of hyperlinks in quotes is prohibited.” Please clarify what is meant by “quotes” in this context. Some hyperlinks are contained within a typical Word document, such as subject headings used to build tables of contents, and captions with figure and table numbers from which are used to build lists of figures and tables. Are these not permissible? Please clarify. | Hyperlinks - a short cut link to the other location is prohibited when submitting the quotes/proposals. |
| 15. PWS L.3.2.1.a states in the first paragraph (on page 175) “The offeror shall complete Attachment B (Price Schedule) of this solicitation.” However, the third paragraph (on page 176) states “The offeror shall also submit and (sic) Excel format proposal using the template provided by the Government with this solicitation – Attachment B, Price Schedule.” Is the same thing being requested twice, or is the second version to somehow be different? Please clarify. | Offeror shall submit Attachment B – Price Schedule (Excel Format) - provided by the Government with this solicitation. |
| 16. PWS page 169, in the table at the top of the page, lists the SF 1449 as being before Attachment B in the offeror’s Price Proposal. However, L.3.2.1, on pages 175-176, lists the SF 1449 as being after Attachment B in the Price Proposal. Which is it? Please clarify. | Offeror shall submit both Attachment A – SF-1449 and Attachment B – Price Schedule (Excel Format) for the Volume II – Price Proposal. |
| 17. PWS L.6 on page 177 states, with underscoring, “If applicable, include a copy of the Joint Venture documentation in Volume I: General Company Information of the proposal package, 4 Page Max.” What is meant by JV “documentation”? If it refers to the JV agreement, please realize that an 8(a) Joint Venture Agreement must be approved by the Small Business Administration, and the information the SBA requires in a JVA typically runs to well over four pages. Please clarify. | In addition to the 8(a) Joint Venture Agreement approved by the Small Business. |
JVs/Partnerships shall provide the following information:
• Written certification to the Contracting Officer signed by all parties in the JV/Partnership stating that the parties have entered into a JV/Partnership that complies fully with the requirements under 13 CFR125.8(b). Please contact the SBA for guidance or instructions on the content.
• The letter shall contain the statement that the parties shall perform the contract in compliance with the JV/Partnership agreement and with the performance of work requirements set forth in 13 CFR 125.8(c).
• The JV must be registered in the System for Award Management (SAM).
18. Can the On-site Supervisor (PWS C.8.1) be the same person as the Chief Engineer under the CBA?
| Depends on the CBA; the SOW does not required two separate persons. | ||
| 19. PWS page 15 and Attachment B both state “The Standard Coefficient is the markup (percent of cost) to be applied to the total cost of the O&M services in the base and option years of the contract,” and “The standard coefficient is not to be applied to work being classified as a repair.” However, this is contradicted by the facts that 1) there is no formula in Attachment B to multiply the O&M amount by the Standard Coefficient; and 2) the O&M line item has to include the cost of repairs for which the contractor is liable, for the simple reason that there is nowhere else to put those costs. In addition, PWS C.41.1, Repairs, General, states “No mark up or coefficient shall be applied to any labor costs, parts, materials, or supplies.” The Government seems to be saying that contractors cannot charge G&A and profit on all repairs, and possibly on “any labor costs, parts, materials, or supplies.” Please clarify what mark-ups are permitted where, and what is subject to the Standard Coefficient and what its purpose is. | There is no contradiction; the standard coefficient can be applied to the overall cost of the contract and be used for additional services orders, but not repairs, per GSA policy. | |
| 20. The section of Attachment B labeled ENGINEER/TECHNICIAN HOURLY RATES for O&M and ADDITIONAL SERVICES HOURLY RATES, O&M, list four different job titles: Engineer, Stationary; Engineer, Utility; HVAC Technician; and General Mechanic. Only the first of these is listed on the CBA. While the second job title is sometimes listed in IUOE contracts, it is not listed in this one. How does the Government expect offerors to have a basis for this hourly rate? Please clarify. | The job titles may be SCA or CBA titles; the Contractor can use the rates for the titles they will use for the contract. | |
| 21. The section of Attachment B labeled ENGINEER/TECHNICIAN HOURLY RATES for O&M and ADDITIONAL SERVICES HOURLY RATES, O&M, list four different job titles: Engineer, Stationary; Engineer, Utility; HVAC Technician; and General Mechanic. The last two job titles are SCA job titles that would likely be in conflict with the CBA, so that they would have to be subcontracted on an occasional basis, and would likely have higher rates than in-house employees. Is this the Government’s understanding? Please clarify job titles for hourly rates. | The job titles may be SCA or CBA titles; the Contractor can use the rates for the titles they will use for the contract. | |
| 22. Solicitation L.1(j), page 167, requires a contractor to list its "Unique Entity Identifier," with its Electronic Funds Transfer (EFT) indicator being a suffix to the Unique Entity Identifier. SAM.gov does not provide a way to request a Unique Entity Identifier. Is it the DUNS number? Please clarify Unique Entity Identifier and EFT indicator and how they may be obtained. | No action is required at this time if you have already registered the DUNS in SAM. GSA is currently working on the transition from DUNS to Unique Entity Identifier (UEI). | |
| 23. Will the Government be providing office space for the contractor in the building? | Yes, the contractor will occupy the office space that is currently occupied by the incumbent | |
| 24. Please provide a copy of the site visit sign-in sheet. | Yes. See attached sign-in Sheet. |
Q&A 5
| O&M and VTE Maintenance Services Fresno, CA Solicitation Number: 47PK0219R0013 | ||
| Reference | Question | GSA Reply |
| When was the last damper testing done and on how many dampers. On commercial buildings it should be done every 4 years but your bid states 2 years? Please confirm? | On 10/18/19 out 95 Fire Dampers were tested. It should be pointed out that this addresses Fire Dampers only as that was what the question asked, so this is exclusionary of Fire/Smoke Dampers. | |
| How many fire alarm panels are there in the entire building? If there are many in the building, do they all speak back to a main panel? This is important to know as you also mentioned you desire monitoring on this contract. How many monitor contracts are currently set up and with what company? If a certain set of devices speaks to 1 panel and they don’t point back to a main panel, then it would require its own monitor agreement etc. just need to clarify this very important factor? | There is 1 Main Panel one the ground floor and a panel on the third floor. There is also one secondary on the 5th floor that the smokes feed into that does talk to the control panels. | |
| Do you utilize land lines for the monitoring or do you have cellular dialers. If so, how many? | We utilize 2 land lines. The system also has 2 cellular dialers included, but they are not used due to unreliability of cellular signal in this building. | |
| Is a “lift required” to do any of the fire device inspections? If so, what size and type lift? Can a lift fit thru the door if required? | no, we have no fire devices that cannot be inspected without a lift, so no lift is required. That is not to say that a lift cannot be used for any of them. If a lift were to be used, I certainly wouldn't take it upon GSA to dictate the size and type of lift which would be the determining factor on whether or not it could fit through a door. | |
| When were the last 6 and 12 year tear downs conducted on the extinguishers? | Our fire extinguishers were replaced with new throughout the building in 2017 |