New_SOW_9-20-18.rtf
RTF text file 455 KB Posted
- Solicitation number
- 47PH1118R0009
About this file
Revised Scope of work replacing all previous versions
Text of this file
V.2 (091918) file_0.jpg file_1.wmf
GSA Public Buildings Service Greater Southwest Region
SCOPE OF WORK
Replacement of Cooling Tower & Pumps Laredo Federal Building/CH 1300 Victoria Laredo, TX 78040
Date: September 19th, 2018
Prepared by: Dana Ulanoff Project Manager: Sha’Mar Nolen
SCOPE OF WORK
The contractor shall provide all materials, supplies, labor, equipment and supervision, necessary to complete the demolition and replacement of cooling tower, pumps and VFD cooling tower fan motor controls. Upon completion of the project, this cooling tower shall be connected to the common building condenser water piping and DDC BAS (Building Automation System).
New cooling tower requirements:
Minimum 400 tons LWT/EWT (F) 94.1/84.1 78degf Wet Bulb GPM- 1200 (3 GPM/ton) Two fans @ 10 HP each Motor Davit with OSHA approved platform/Ladder & safety cage Service Platform/vibration switch/Electric sump heaters Fan Motors-Shaft Grounding Rings 316 stainless upper and lower sections *Cooling tower submittals shall be submitted with the proposal*
General Construction Requirements Keep work areas clean on a daily basis.
| Remove debris from site on a daily basis. |
| Protect all existing walls and furniture from damage. |
| Contractor is responsible for all damages to government property caused by him/her and their subcontractors. |
| Contractor is responsible for all dimensions and quantities. |
| Contractor shall field verify all existing conditions prior to submitting a proposal. |
Demolition
Remove existing cooling tower, CHW/CW pumps.
| Disconnect all electrical, direct digital controls, piping and associated equipment to tower. Remove all unused conduit/wiring back to panel boards and provide knock- out plugs at all unused openings. |
| Remove and properly dispose of cooling towers. |
| Tower replacement shall occur over a weekend. Contractor shall have the building’s O & M mechanic onsite during the tower replacement and include these labor costs in their proposal. Contractor shall also include chemical costs in their cost proposal that the contractor shall pay directly to the O&M contractor for the chemicals required during the refilling of the chilled water & condenser water system. |
ALTERATIONS
Cooling Tower
Provide and install 316 stainless steel two fan cooling tower. (upper and lower section 316 SS) Equal to or better than Evapco Model Number USS 29-3121 (See cooling tower Exhibit) New Cooling Tower to include the following:
316 stainless steel upper and lower section Premium efficiency inverter duty motors Reinforced basin for alternate steel support Ladder/safety cage/work platform Motor davit and base, vibration switch Two (2) each electric sump heaters 7KW each
| Proposal documents shall include new tower spec sheet. |
| All new piping shall be primed and painted white and labeled. |
| Install a butterfly isolation valve on the inlet, outlet and equalizer line of each tower cell. This isolation valve(s) are used to isolate each cell for one cell operation for maintenance and repairs. |
| Install yellow grating equal to or better than Corvex material with grit surface. 1.5 inch deep & 1.5 inch square mess around cooling tower perimeter that is sitting on elevated platform. Since the new tower dimensions may be less than the tower being removed, only the area around the tower that sits on the elevated platform that has 3 feet or more of space on the existing elevated tower support structure will require this grating material with a rail. |
| Install rail around this platform for fall protection. Rail to be made of rust free material. |
| Apply Metalclad "CeramAlloy CL+AC coating to the condenser tube sheets, division bar and end plate for two each 200 ton capacity chillers. Prepare surfaces prior to coating in accordance to the manufactures’ recommendation. Only one chiller can be inoperative at a time. 5 Year Labor and Material Warranty |
| Install new 4” cooling tower sump drain & tower over flow piping from sanitary sewer lift station in the chiller mechanical room to cooling towers. Approximately 95’ (feet) run. |
| Cover air intake louver with sheet metal from the inside of chiller mechanical room and install 2” inch duct board. Fasten material appropriately. Approximately 115” x 95”. |
The Tower Support Structure Tower support structure shall be in accordance to the tower manufacture’s installation requirement.
Tower Bypass Valve Condenser water piping: New piping shall be primed and painted white.
New piping shall be labeled with directional arrows and description (Example: condenser water supply, condenser water return). Reuse existing tower bypass valves.
Cooling Tower Electrical Provide and install all necessary and properly sized electrical conduit and electrical wiring for new tower.
| Contractor will be responsible to verify existing electrical power and/or circuit breakers will handle new tower’s electrical voltage and amperage. |
| Provide and install properly sized transformers, electrical panel(s) and circuit breakers for new tower as needed. |
| Provide new panel schedules reflecting work accomplished. |
Makeup Water Line and Meters Insulate tower makeup water line.
| Cover insulation with metal/aluminum jacketing. |
| Install new Onicon F-3500 (or equal) electromagnetic gross building water meter per manufacturer’s pipe diameter and linear recommendations. Map demand and consumption points’ to the nearest unitary BAS controller. |
| Install new makeup water meter and blow down water meter per manufacturer’s pipe diameter and linear recommendations. Map demand and consumption points’ to the nearest unitary BAS controller. |
| Map demand and consumption water meter points from unitary controller to the Niagara AX JACE and develop graphical representation on the meter page and cooling tower graphic page and site metering page as described in item 6. |
| Program 15-minute pulse interval as an ever increasing historical value on a 730-Day FIFO history hyperlink on both graphic pages and incorporate into the JACE history utility trend tool. |
Map 15-minute interval history as a long term history on the Niagara Advanced Metering System Regional Niagara AX Enterprise Web supervisor for long term archive (GSA will provide tutorial aid upon request).
New Condenser Water /Chilled Water Pumps Install two (2) each new vertical inline condenser water (600 GPM/40FT and (2) two each chilled water pumps (480 GPM/65FT with inlet suction guide/strainer and triple duty valves. (flow control/check valve/shut off valve) Pumps shall be split coupling type. See Pump Exhibit Fan Coil & Mini Split
Install two each 4 ton chilled water fan coil units in the chiller mechanical room. Not to exceed 1600 CFM each. Installation shall include connecting to the supply and return chilled water main line. Insulate new piping, installing a new modulating valve, thermostat, strainer, flow control valve (9.6 GPM each), two new manual full port ball valves per unit, 7 day/24hr time clock, Merv 8 (2 inch) filter, electrical disconnect and labeling of the lines. Install copper condensate line and route to nearest drain. Insulate condensate line. Install a minimum 4 foot long supply air metal duct with supply air grills. Insulate supply air duct. Location in mechanical chiller room shall be approved by the COR.
Install a minimum 12,000 BTU ductless mini split for the
Gauges elevator equipment room located in the chiller room with wired thermostat and surge protector. Remove the window A/C unit and install stainless steel cover over window unit opening on both sides. Install insulation between the two covers minimum 3 inches in thickness. Minimum 24 SEER required for the ductless mini split. Install appropriate size condensate pump and route line to drain. Unit to be mounted on exterior wall next to chiller plant using the manufactures wall mounting kit.
Install new liquid filled gauges with gauge shut off ball valves in a manifold configuration.
One gauge per pump (Refer to Gauge exhibit) One gauge per condenser (Refer to Gauge exhibit) One gauge per evaporator (Refer to Gauge exhibit)
Condenser/Chilled Water Pump & Cooling Tower Fans VFD’s Install new appropriate sized frequency drives (VFD) and connect to new cooling tower fan motors, new condenser/chilled water pumps. The VFD for the cooling tower fans shall be located in the chiller mechanical room. Install new electrical disconnects for the cooling tower fan motors.
| Install a pressure differential control across the condenser and evaporator for each chiller and integrate to the BAS and new sequence of operation. Total 4 each. |
| Integrate drive to BAS. |
| Drive speed in HZ shall be reflected in the BAS graphics. |
| Replace/install electrical service to new VFD’s, tower sump heaters, vibration switches and fan motors. |
| The vibration switch(s) shall be connected to the BAS and send out an email notification in the event the vibration switch is tripped. The vibration switch(s) shall shut down the cooling tower fan(s) when tripped. |
Lighting
Replace (20) existing two lamp pendant mount fixtures in chiller plant to new LED pendant mount fixtures. Performance shall be equal or better to Lighting Exhibit 1.
| Replace (38) existing four lamp recessed 2x4 lay-in fixtures in parking garage. Performance shall be equal or better to Lighting Exhibit 2. |
| Add lighting controls to garage lights. Performance and specification shall be equal or better than Lighting Exhibit 3A and 3B. |
| Contractor shall provide a minimum of one hour training to GSA property management and O&M contractor on the maintenance and configuration of the sensors. At the conclusion of the lighting installation, the contractor shall turn over the wireless configuration tool to the O&M contractor for this building. |
| If required, the contractor shall include battery back-up with all new fixtures. |
| Fixtures shall have Energy Star Ratings and Design Light Consortium (DLC). |
Building Automation System and Integration The entire chill water plant, cooling tower(s), heating water plant and the sequence of operation shall be programed on a nonproprietary BAS with the use of Niagara programmable MS/TP unitary plant controllers (or equal-Buy America Act compliant) DDC that are 100% programmable from the Niagara engineering workbench engineering tool. MS/TP controllers shall be available from multiple vendor neutral warehouse distribution channels and shall be vetted through the GSA during the submittal process. MS/TP controllers shall not require 3rd party programming or configuration engineering software. Refer to the SOO Exhibit and BAS 1 and 2 Specifications Exhibits.
| Removal of existing plant programming, point mapping, and cleanup efforts shall occur on the TAC ASD programming by a TAC Invensys I/A certified technician to ensure that Niagara and TAC Invensys programming does not interfere and is cleaned up to prevent future troubleshooting efforts at the building by outside contractors. |
| Provide Niagara AX fully configurable and programmable MS/TP unitary plant controller to control all plant operations. |
| The plant shall operate off of the Niagara configurable logic on the MS/TP plant controller in a stand-alone “last- known/received command” status when communication fails to the Niagara JACE supervisory controller hosting the BAS graphical user interface, histories, user profiles, and schedules. When MS/TP unitary device(s) loose status (heartbeat continuity) with the JACE during unoccupied hours, the plant MS/TP sequence of operations shall be programmed to fail to an “occupied status” to ensure tenant comfort. |
Install MS/TP compatible water treatment loop controller Ex: Advantage Controls Megatron SS BACnet Controller (or equal) to replace existing controller to totalize, trend, and log water treatment system conductivity/fill/bleed on the local BAS JACE.
| Install conduit and (approx. 50 linear ft.) low voltage sensor wire from the sensor to the water treatment controller. |
| Terminate wire on both ends (field device and at controller) |
| Map Input/Output (I/O) points at the BACnet unitary controller |
| Map 15-minute interval of eleven (11) BACnet point histories (listed below) for long term archive to existing Advanced Metering System Enterprise Niagara Web Supervisor Server located on the GSA Framework network. |
| System- CoC (Cycles of Concentration) |
| System- pH |
| System- Conductivity |
| System- M. Conductivity |
| System- ORP |
System- S. Temp
| System- M. Temp |
| System- Conductivity Setpoint |
System- Calibration
| Water Meter- Total Value |
| Flow Meter- Flow Rate (per MIN) |
e.) Integrate new controllers’ I/O points to existing JACE GUI and re-establish controller/meter point status on GSA Niagara AX Advanced Metering Vykon Energy Suite web supervisor server. Existing graphical pages will be updated with new IO point mapping. Create new history trends for new IO points.
f.) Develop Niagara Graphical representation mirroring that of other GSA JACE sites by reutilizing existing graphic “.px” file that has been developed of the water treatment system.
g.) Set up 14-day FIFO in the JACE history utility and as hyperlinks on the water treatment graphical representation page.
h.) Add condenser water temperature conductivity alarm programming to send a critical plant alarm via GSA BAS and SMTP server(s) if the condenser water conductivity rises over 1100ppm (adjustable) for more than ten (10) minutes (adjustable).
i.) Modify the PVC water treatment manifold in the proper locations and add one (1) pH electrode sensor, one (1) ORP electrode sensor, and one (1) Conductivity electrode sensor.
j.) Hot tap and install one (1) Makeup Conductivity sensor in the make-up water line.
Refer to Exhibits BAS for additional details and mapping requirements.
The new cooling tower’s control system shall communicate with existing Niagara building automated system.
| Replacement cooling tower shall be wired to and communicate to the Building's Niagara JACE Controller serving as the BAS front end graphical user interface. |
| The cooling tower shall not be linked through a propriety building system controller. |
| Contractor will be responsible to verify the existing BAS and provide all necessary wiring, controls to integrate cooling tower’s controls to BAS. |
| The BAS Integration contractor shall include any mapping and linking changes of the cooling tower. |
| On the graphics page of the building’s BAS including new piping, for the cooling tower. |
| The Contractor shall program the existing and any new feedback points using MS/TP protocol integrated into the existing Niagara BAS front end graphical user interface. |
| Contractor will be responsible to verify the existing BAS and provide all necessary wiring, controls, and/or MS/TP cards (if required) to integrate tower’s controls to the Niagara BAS. |
| Automated valves shall provide reporting feedback on current status, history screens, and valve icons shall be visible on the BAS central plant page. |
| All analog histories of new tower points shall be recorded in 15-minute intervals and stored in the building JACE controller for 14 days. |
All discrete heating/chill/condenser water point histories shall be recorded both as 15-minute interval, 14-day FIFO history logs but also as COV histories storing 100 intervals within the
JACE.
| All new cooling tower point histories shall be exported daily from the JACE to the GSA AMS Enterprise Niagara AX Web Supervisor for long term archival storage. |
| Provide the necessary BACnet equipment controllers, interface cards, and/ or expansion boards to incorporate sequence of operation along with new equipment into the BAS. |
| The contractor shall use a site specific GSA IT government provided GSA laptop for the programming of the BAS. Company laptops are not permitted. |
| Provide Niagara workbench license if not already installed. Hand receipt BAS laptop from GSA property manager on a GSA Form 525. HSPD-12 Security clearance required, GSA GAC Smart Card, and GSA network access required for the BAS technician providing programming and integration work. Technicians without security clearance will not be permitted. |
| Provide detailed IT/DDC Controls Riser diagram as Microsoft Visio file for approval by GSA prior to ordering hardware or beginning site work. Provide as built DDC controls shop drawings at the project completion. |
| Provide 100% of program files backed up to GSA IT PC, backup disk(s) and contract completion file. |
| Utilize GSA point naming and tagging standard |
BAS Exhibit.
Utilyze and model graphics pages from the graphics design guide BAS Exhibit.
BAS Security Requirements:
Contractor personnel, and precisely the BAS DDC Controls integration technician performing installation and work on the BAS under this contract must possess HSPD-12 Clearance (must receive final fit determination) and GAC Cards in order to access GSA secured networks and sites.
| Badge will be required if working inside the building, (PIV HSPD-12) |
| Supervisor/lead person with a PIV HSPD12 may Escort for those working outside the building only. |
| HSPD-12 Security clearance required, GSA GAC Smart Card, and GSA network access required for the BAS technician providing programming and integration work. Technicians without security clearance will not be permitted. |
| Contractor shall ensure that DDC controls have 20% spare capacity at the end of the contract warranty period by ensuring proper amount of existing and memory resources for future cyber-security updates in accordance with BAS Exhibit. |
Integration Technician:
Integration technician performing installation shall be certified on the Niagara AX JACE and TAC I/A series DDC controls for both installation and maintenance of the system. The integration technician performing installation shall have a proven minimum of 3 years Niagara experience 5 years total DDC controls experience performing the required tasks. The Contractor shall provide with their offer the integration technician’s resume and certification documentation.
Specifications and Requirements Valves connections, accessories and operators
| Provide threaded ends for valves 2.5 inches and smaller |
| Provide flanged or grooved ends for valves 3 inch and larger |
| For butterfly valves (isolation valves) provide lever handle, infinitely adjustable with lock nut and memory stop. Provide hot dipped galvanized extension stems, valve handles and gear actuators outdoors. Provide weatherproof galvanized cast iron gear operators for valves mounted outdoors. |
Condenser water piping
| New piping shall be primed and painted white. |
| New piping shall be labeled with directional arrows and description (Example: condenser water supply, condenser water return). |
Automatic isolation valves:
| Type of end fitting: pattern to mate with ANSI 125 flange. |
| Cast iron GG25 with stainless steel stem and ball. |
| Pipe insulation- Match existing size/type/color scheme and labeling. |
| Steel pipe and fittings: |
| Steel pipe, DN 50 (NPS 2) and smaller: ASTM A 53, type S (seamless) or type F (furnace butt welded), grade B, schedule 40, black steel, plain ends. |
| Steel Pipe, DN 65 through DN 300 (NPS 2-1/2 through NPS 12): ASTM A 53, type E (electric- resistance welded), Grade B, Schedule 40, black steel, plain ends. |
| Steel Pipe Nipples: ASTM A 733, made of ASTM A 53, Schedule 40, black steel; electric-resistance welded for DN 65 (NPS 2-1/2) and larger. |
| Cast-Iron Threaded Fittings: ASME B16.4; Classes 125 and 250. Malleable-Iron Threaded Fittings: ASME B16.3, Classes 150 and 300. |
MATERIAL TECHNICAL SPECIFICATIONS
Where a particular manufacturer's product is specified, it is not intended to discriminate against other manufacturer's which are equal in quality of material, workmanship, appearance and function to those specified. Rather, it is intended to establish and indicate the desired standard of quality. If any tests are required to determine the equality of any substitutes, such tests shall be made by an independent authority as approved by the government. All expenses related to proposed substitutions shall to be paid by the Contractor. Proposed items are to be submitted with the proposal and shall be a basis for the award of the contract.
All materials and equipment shall bear evidence of the Underwriter's Laboratories Inc. Label (UL) or approval of other nationally recognized independent testing organizations adequately equipped and competent to perform such services when these standards are required and such product listing is available.
PRODUCT DATA AND SAMPLES
Product Data: Contractor shall submit one electronic set of tower product data including any valves, piping, insulation, BAS hardware, refrigerant monitoring system, catalog sheets, brochures, performance charts or other standard descriptive data provided by any Subcontractor, supplier or distributor. Product Data must be certified by the Contractor stating that it was reviewed and approved. Product to be used must be highlighted on the data sheet by the Contractor. Product Data used for construction must bear GSA’s stamp certifying final review and approval. No product shall be used that does not bear such stamp. Submittals shall be identified on a submittal register provided by the Contractor and transmitted using a transmittal letter.
Samples: Contractor shall submit physical samples establishing standards by which completed work is judged. Samples shall indicate color range, functional characteristics and shall represent exact material to be used on the project.
SPECIAL INSTRUCTIONS
Contractors shall submit proposal with a detailed cost breakdown. Cost Breakdown shall be submitted in CSI Master Format 2010. Proposal shall include make and model of all proposed equipment. Cooling tower selection shall include dimensions, operating weight and performance rating within submitted proposal. Cooling tower selection shall be submitted with the proposal. Cooling tower selection submitted with the proposal shall not be equal to or better than the cooling tower specifications in Cooling Tower Exhibit.
Contractor is responsible to comply with the “Buy American Act”. Buy American Act provides domestic construction material be used in performing this contract.
| Contractor will be responsible to request and furnish all required overhead and/or road blocking permits from the City and or electrical/utility providers when using a crane at this location if the city street requires a blockage when off-loading the tower. |
| Install yellow grating equal to or better than Corvex material with grit surface. 1.5 inch deep & 1.5 inch square mess around cooling tower perimeter that is sitting on elevated platform. Install rail around this platform for fall protection. Rail to be made of rust free material. |
PERFORMANCE REQUIREMENT
The Contractor shall field verify existing conditions prior to any demolition.
| The Contractor shall be responsible for coordinating all activities of subcontractors. This responsibility includes coordination of; preparation of shop drawings preparation of shop drawings produced by different subcontractors where their work interfaces or may potentially conflict or interfere and the installation of such work; scheduling of work by subcontractors and use of the Project site for staging and logistics. |
| The contractor shall reinstall existing access panels; etc., back to their original location and condition after all work is completed. |
| Safety Plan: Contractor shall submit a site specific plan including hazardous communication plan list of the flow of communication in case of emergency, lock-out / tag-out with narrative that explains lock-out |
/ tag out procedures, AHA / JHA’s for major activities, crane safety plan (if applicable) for crane erection and use. Include preferred location for crane set up, operator certification credentials, and crane inspection/certification documentation within thirty (30) of Partial Notice to Proceed.
| Contractor to provide a work plan within thirty (30) days of Partial Notice to Proceed (PNTP) identifying equipment access plan, CHWP / CWP piping tie-in and electrical tie-in for review and acceptance prior to installation. |
| Contractor to provide schedule of values within thirty (30) days of Partial Notice of Proceed (PNTP). The Contractor shall prepare and submit for approval a detail cost breakdown of the Contract price, to be referred to as the Schedule of Valves, assigning values to each component of the Work. |
| Values must include all direct and indirect cost, although a separate value for bond cost may be established. |
| The Schedule of Valves must contain sufficient detail to enable the Project Manager to evaluate applications for payment. |
| Before submitting a request for payment, the Contractor shall schedule a pencil copy review with the Project Manager for review and acceptance. |
| Once the tower is fully operational the Contractor shall be responsible to provide a report to GSA Project Manager for the following: Re-balance water flow, Manufacturer’s Start-up Check-list and Commissioning (all adjustments and balancing to the system shall be in accordance with manufacturer requirements) |
SECURITY CLEARANCE REQUIREMENT
All Contractor personnel performing working on premises at GSA owned and operated buildings are required to pass a security background check conducted by the Department of Homeland Security/Federal Protective Service. No Contractor employee will be allowed to perform work on the building premises until employee has been determined to be suitable for hire by the Department of Homeland Security/Federal Protective Service. Badge will be required if working inside the building, (PIV HSPD-12).
In addition to the GSA security check, on all Customs and Border Protection facilities, an additional security check of all individuals entering the facility will be performed by Customs and Border Protection. The information required is Full Name, Date of Birth and Last 4 Digits of their Social Security Number. This information must be submitted to the Project Manager a minimum of 72 hours prior to entering the secured areas of the facilities for any reason. This includes all pre-bid and pre-construction meeting as well as all employees of the Contractor awarded the project.
Contractor personnel, and precisely the BAS DDC Controls integration technician performing installation and work on the BAS under this contract must possess HSPD-12 Clearance (must receive final fit determination) and GAC Cards in order to access GSA secured networks and sites.
WORKING HOURS
Work not impacting normal building occupancy shall be performed during normal business hours Monday through Friday 6:00 am to 6:00 pm. Any work affecting normal building occupancy needs to be scheduled after normal business hours/weekends and approved by GSA building manager.
Tower replacement shall occur over a weekend and be operational by the next business day. Contractor shall have the building’s O & M mechanic onsite during the tower replacement and include these labor costs in the proposal.
O & M is available for hire to escort/assist in locating any mechanical valve or other component that needs to be shut down to replace tower.
PERIOD OF PERFORMANCE
All work shall be completed within 45 calendar days after cooling tower delivery. It is estimated that it will take 6-10 weeks to manufacture the tower. A partial PNTP will be issued to place the order on the equipment upon approved submittals.
The Period of Performance shall be two hundred forty (240) calendar days after the Partial Notice of to Proceed has been issued.
| Partial Notice to Proceed (PNTP): |
| A PNTP will be issued after bonds and insurance are accepted to authorize the contractor to order the equipment upon approved submittals. |
| The contractor shall provide a proof of purchase document within fourteen (14) calendar days after the acceptance of the Cooling tower Submittal to the GSA Project Manager |
| The Contractor shall hold biweekly progress meetings during PNTP. |
| The contractor shall prepare and distribute meeting minutes within 3 calendar days after the meeting. |
| Full Notice to Proceed (FNTP): |
| The Full Notice to Proceed will be issued once the cooling tower has been delivered to the site. |
| The Contractor shall complete all SOW activities within thirty (45) calendar days after the FNTP is issued. |
| The contractor shall remove the existing cooling tower within six (6) calendar days from the FNTP. |
| The new cooling tower shall be fully operational within ten (10) calendar days after the removal of the existing cooling tower. |
| The Contractor shall hold weekly progress meetings during FNTP. |
| The contractor shall prepare and distribute meeting minutes within 3 calendar days after the meeting. |
LIQUIDATED DAMAGES
If substantial completion is not achieved, the Contracting Officer may assess liquidated damages at a rate of $158.37 per calendar day.
PROJECT SCHEDULE
Contractor shall submit to the GSA Project Manager a project schedule within thirty (30) days of P a r t ia l Notice of Proceed. The project schedule shall include a written narrative describing the major work activities, activities critical path and major constraints underlying the sequence and logic, all tasks to be performed under this project, duration of each task and tentative date/s each task will be performed. Project schedule must be approved by the GSA Project Manager prior to performing any work under this project. The project schedule shall incorporate milestone events specifics in the Contract, including as applicable PNTP, Substantial Completion and milestones related to specific work phases and site restrictions. The project schedule shall also include Contractor- defined milestones to identify target dates for critical events, based upon the Contractor’s chosen sequence of work. Microsoft Project or other similar format can be used for this schedule.
Progress Meetings The Contractor shall meet with the Government for the purpose of jointly reviewing the actual progress of the project as compared to the as planned progress and to review the planned/upcoming activities. The progress meeting will address the status of progress to date, potential delays, Changes, and Submittals. The contractor shall prepare and distribute meeting minutes within 3 days following each meeting. Progress meetings during PNTP shall be held biweekly. Progress meetings during FPNTP shall be held weekly.
CONSTRUCTION WASTE MANAGEMENT PLAN SPECIFICS (AFTER CONTRACT AWARD)
Fourteen days (14) from Partial Notice to proceed, the Contractor shall submit to the Project Manager, a draft Waste Management Plan for mixed debris recycling to GSA approval. The plan shall include (but not be limited to) the following: List of the materials to be reused or recycled.
The Contractor will record and track the type and quantity, by weight or each material salvaged, reused, recycled or disposed throughout the project. The Contractor shall provide a Construction Management Waste Management Report upon request of Substantial Completion.
FINAL PREPARATIONS
Contractor shall provide both classroom and hands-on training at a minimum four (4) hours to training to GSA maintenance personnel. This training will be conducted by the Tower Manufacture’s authorized service technician and the BAS integration technician. Training shall be on all new components such as meters, pumps, fan coil unit, ductless mini split, Nexus electric meter and chemical controller. The completed training sign in sheets shall be a deliverable for the closeout documentation.
Contactor shall provide two (2) sets of as-built drawings on compact disk (CD). As-built drawings shall be in Auto CAD format and shall illustrate all alterations performed under this contract. Final payment will not be authorized until all as-built drawings are provided.
Contractor shall provide three (3) copies (3 hard and 3 electronic) of owner’s (O&M) manuals for the tower, makeup water meter, pumps, blowdown meter, smart meter, fan coil unit , ductless mini split electric meter, chemical controller and VFD.
Contractor shall return all GSA Badges issued for this project. Final payment will not be authorized until all O&M manuals and badges are provided and returned.
SUSTAINABILITY
Green Purchasing: The contractor shall refer to the “Green Procurement Compilation” for all products being installed in federal facilities. The Green Procurement Compilation can be found at https://sftool.gov/greenprocurement.The standards found in this compilation shall guide all product purchasing decisions as they relate to federal facilities.
WARRANTY
All workmanship and materials shall be warranted for a period of not less than three hundred sixty five (365) days from date of acceptance by the Government (Standard Warranty) plus extended compressor parts and labor warranty (4 years).
| The Contractor shall provide a copy of warranty of items procured. Warranty shall be in writing and shall include any conditions which may invalidate the warranty. |
| Warranty shall include procedures on how to exercise warranty rights. Provide points of contact in order to get services required. |
| Standard warranty shall be all inclusive of parts, labor and materials, related coverage and additional costs, if any. |
| Contractor shall provide all applicable manufacturers’ warranties at time of completion. |
END OF SCOPE OF WORK
Other files
| File | Type | Posted |
|---|---|---|
| PUMP_EXHIBIT_20180919_(1).pdf | ||
| SOO_Exhibit_Laredo_(1).docx | DOCX document | |
| 09_Pre-Proposal_Record.pdf | ||
| Laredo_RFI_(1).pdf | ||
| SOW_10-17-18.doc | DOC document | |
| C101_The_Agreement.pdf | ||
| C301_GC_Reps_&_Certs.pdf | ||
| Exhibit_I._SOO_Exhibit.pdf | ||
| Exhibit_D.pdf | ||
| Exhibit_F._Gauge_Exhibit.pdf | ||
| Exhibit_B.pdf | ||
| TX235_01-05-18.pdf | ||
| Exhibit_H._PUMP_EXHIBIT.pdf | ||
| Exhibit_A.pdf | ||
| Exhibit_C.pdf | ||
| Exhibit_G._Lighting_Exhibit.pdf | ||
| 47PH1118R0009__Form.pdf | ||
| Exhibit_E.__Cooling_Tower.pdf | ||
| GSA527-15b.pdf | ||
| TX0311__SOW_08-09-2018.pdf |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it.