5_hypothetical_project__Attachment_-_A_20190529.pdf

PDF 932 KB Posted

Attached to
SPD F&O Design-Build/Construction MA IDIQ Federal contract opportunity
Solicitation number
47PH0119R0001
Issued by
General Services Administration Public Buildings Service Region 7

About this file

This document provides specifications for a design-build construction project. The General Services Administration seeks proposals by July 31, 2019 for an indefinite-delivery/indefinite-quantity contract to design and construct miscellaneous federal facilities in Region 7. Offerors must have experience designing and building similar structures. The selected contractor will work collaboratively with GSA and other stakeholders to finalize construction documents, obtain necessary approvals, and complete projects on an as-needed basis. Submittals will be reviewed within specified timeframes. The contractor must coordinate work with other involved parties and ensure compliance with all applicable standards and regulations.

A

View the file

Other files for this federal contract opportunity

Other files attached to SPD F&O Design-Build/Construction MA IDIQ, newest first.
File Type Posted
Solicitation_Amendment_47PH0119R0001_0007.pdf PDF
47PH0119R0001__Form_1442_rev_20190729.pdf PDF
Solicitation_Amendment_47PH0119R0001_0006.pdf PDF
Questions_and_Answers__3_20190718.pdf PDF
47PH0119R0001_Solicitation_Amendment_SF_30_0005.pdf PDF
47PH0119R0001__Form_1442_rev_20190717.pdf PDF
47PH0119R0001_hypothetical_project__Attachment_-_C_revised_20190711.pdf PDF
47PH0119R0001_SPD_F&O_DB_IDIQ_-_Agreement_20190717.pdf PDF
47PH0119R0001_hypothetical_project_Attachment_-_E_revised_20190711.pdf PDF
47PH0119R0001_Project_Data_Sheet_20190716_unlocked.pdf PDF
47PH0119R0001_hypothetical_project_Attachment_-_F_revised_20190711.pdf PDF
47PH0119R0001_hypothetical_project_Attachment_-_D_revised_20190711.pdf PDF
47PH0119R0001_-_Revised_Solicitation__20190717.pdf PDF
20190710_meeting_attendees_update_for_submission_after_Amendment_0002.pdf PDF
47PH0119R0001Questions_and_Answers__2_20190717.pdf PDF
47PH0119R0001_SF_30_Solicitation_Amendment_0004.pdf PDF
3_47PH0119R0001__Form_1442_rev_20190716.pdf PDF
Solicitation_Amendment_47PH0119R0001_0003_20190716.pdf PDF
09_agenda-meeting_minutes,_Pre-Proposal_Conference,_Design-Build_Construction_IDIQ_20190703.pdf PDF
SPD_IDIQ_Presentation_-_Preproposal_Conference_-_20190702_-_Ft_Worth,_TX.pdf PDF
meeting_attendees.pdf PDF
Solicitation_Amendment_47PH0119R0001_0002.pdf PDF
1_SPD_F&O_DB_IDIQ_-_Revised_Solicitation__20190626.pdf PDF
hypothetical_SOW_-_Nationwide_LED_Signage_revised_20190626.pdf PDF
Solicitation_Amendment_47PH0119R0001_0001_(1).pdf PDF
Amendment_0001_questions_through_20190626.pdf PDF
Hypothetical_Price_Proposal_Sheet_revised_20190626.xlsx XLSX spreadsheet
https://forms.gle/qxfJLfYYPZvLPkTZ6 —
5_hypothetical_project_Attachment_-_G_20190529.pdf PDF
1_SPD_F&O_DB_IDIQ_-_Solicitation__20190621.pdf PDF
2_C301_GC_Reps_&_Certs_20190516.docx DOCX document
5_hypothetical_project__Attachment_-_C.pdf PDF
3_47PH0119R0001__Form_1442.pdf PDF
4_SPD_F&O_DB_IDIQ_-_Agreement_20190621.pdf PDF
8_Project_Data_Sheet_form_20190516.pdf PDF
9_SPD_F&O_DB_IDIQ_-_Small_Business_Socioeconomic_Category_Certification_Form.pdf PDF
5_hypothetical_project_SOW_-_Nationwide_LED_Signage_20190603.pdf PDF
5_hypothetical_project__Attachment_-_B.pdf PDF
5_hypothetical_project_Attachment_-_D.pdf PDF
7_PBS_Past_Performance_Form_Rev_6_12_15.docx DOCX document
5_hypothetical_project_Attachment_-_F.pdf PDF
5_hypothetical_project_Attachment_-_E.pdf PDF
6_Hypothetical_Price_Proposal_Sheet.xlsx XLSX spreadsheet
Show all 43

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROPERTY OF THE UNITED STATES GOVERNMENT

COPYING, DISSEMINATION, OR DISTRIBUTION OF THESE

DRAWINGS, PLANS, OR SPECIFICATIONS TO

UNAUTHORIZED PERSONS IS PROHIBITED

Do not remove this notice Properly destroy documents when no longer needed

11.13.15LAND BORDER INTEGRATION

LED SIGNAGE PHASE III – BID PACKAGE 3 TASK

ORDER:

100% DESIGN BRIDGING DOCUMENTS

Attachment - A

Nationwide LED Signage

DIVISION ONE SPECIFICATIONS

TOC-1 11/13/15

SENSITIVE BUT UNCLASSIFIED (SBU) PROPERTY OF THE UNITED STATES GOVERNMENT. FOR OFFICIAL USE ONLY.

Do not remove this notice. Properly destroy documents when no longer needed.

DIVISION ONE TABLE OF CONTENTS

011000 SUMMARY

011400 WORK RESTRICTIONS

013100 PROJECT MANAGEMENT AND COORDINATION

013120 CRITICAL PATH METHOD SCHEDULING

013220 PHOTOGRAPHIC DOCUMENTATION

013300 SUBMITTAL AND SUBSTITUTION PROCEDURES

014000 QUALITY ASSURANCE AND CONTROL

014200 REFERENCES

015000 TEMPORARY FACILITIES AND CONTROLS

015930 SECURITY PROCEDURES

015950 SAFETY AND HEALTH

017000 EXECUTION REQUIREMENTS

017310 CUTTING AND PATCHING

017320 SELECTIVE DEMOLITION

017350 FIRE PROTECTION FOR HOT WORK

017700 CLOSEOUT PROCEDURES

017810 PROJECT RECORD DOCUMENTS

017822 OPERATION AND MAINTENANCE DOCUMENTATION

018200 DEMONSTRATION AND TRAINING

UNIFORMAT SECTIONS

PROJECT DESCRIPTION

1010 PROJECT SUMMARY:

CONSTRUCTION SYSTEMS AND ASSEMBLIES

A. SUBSTRUCTURE:

A10 FOUNDATION SYSTEMS

A1020 Special Foundation Systems

B. SHELL:

B10 SUPERSTRUCTURE

B1030 Support Framing B20 EXTERIOR ENCLOSURE – Not Used

C. INTERIORS - Not Used

D. SERVICES:

D20 PLUMBING – Not Used

D30 HVAC – Not Used

D40 FIRE PROTECTION – Not Used

D50 ELECTRICAL

E. EQUIPMENT & FURNISHINGS – Not Used

F. SPECIAL CONSTRUCTION AND DEMOLITION:

F10 SPECIAL CONSTRUCTION

F1030 Special Construction Systems

F20 SELECTIVE BUILDING DEMOLITION

DIVISION ONE SPECIFICATIONS

TOC-1 11/13/15

SENSITIVE BUT UNCLASSIFIED (SBU) PROPERTY OF THE UNITED STATES GOVERNMENT. FOR OFFICIAL USE ONLY.

Do not remove this notice. Properly destroy documents when no longer needed.

F2010 Building Elements Demolition

G. BUILDING SITEWORK

G2010 Pavement Markings

Z. GENERAL

Z10 GENERAL REQUIREMENTS

Z1020 Procedural General Requirements

Z20 BIDDING REQUIREMENTS

Z2022 Request for Proposal (RFP) Requirements

274210 DYNAMIC SIGNAGE SYSTEM

END OF TABLE OF CONTENTS

SECTION 011000 – SUMMARY

011000-1 11/13/15 SENSITIVE BUT UNCLASSIFIED (SBU) PROPERTY OF THE UNITED STATES GOVERNMENT. FOR OFFICIAL USE ONLY.

Do not remove this notice. Properly destroy documents when no longer needed.

PART 1 - GENERAL

1.1 PROJECT INFORMATION

1.2 DESIGN BUILD CONTRACTOR RESPONSIBILITIES

A. Bridging Design Development Documents: The documents developed by the Bridging Document

Architect’s team are not construction documents. The documents describe the general materials and quality level requirements for the Project. The Design-Builder shall include all costs and services to complete the design, submit and obtain approvals, and then finalize and obtain approval of shop drawings, and product submittals and construct the Project in accordance with the specified requirements

B. Finalization of Construction Documents:

1. The Design Builder shall be required to advance the design plans and specifications to the 65%

Midpoint Design Submittal level and submit to GSA for review and comment. Refer to Division 1 Submittal Procedures.

2. 95% Pre-Final Design Submittal shall be 100% complete, coordinated, and checked drawings and specifications.

3. The Design Builder shall finalize the documents and submit 100% complete signed and sealed drawings, specifications, and design calculations.

4. The Design Builder will be retaining an A/E to complete 100% design. These submittals will go to GSA for review.

1.3 WORK BY OTHER CONTRACTORS

A. The Design Build Contractor shall cooperate with other contractors performing related work, including providing labor, materials and other costs necessary to satisfactorily

A. Houlton, ME

B. Higate Springs, VT

C. Rainbow Bridge, NY

D. Eastport, ME

E. Orville, WA

SECTION 011000 – SUMMARY

011000-2 11/13/15 SENSITIVE BUT UNCLASSIFIED (SBU) PROPERTY OF THE UNITED STATES GOVERNMENT. FOR OFFICIAL USE ONLY.

Do not remove this notice. Properly destroy documents when no longer needed.

coordinate the Contract work with work performed under other contracts.

1.4 SCHEDULE OF GOVERNMENT-FURNISHED PROPERTY

A. The project includes a standalone computer loaded with Windows 7 operating system to be installed by the Design-Build Contractor. The Design-Build Contractor shall advise GSA at least 30 days in advance of when the property should be delivered.

1.5 DESIGN-BUILD CONTRACTOR’S USE OF SITE

A. Refer to Section 011400 Work Restrictions for port operation hours.

B. Alterations to Existing Conditions: Existing conditions shall be cut, drilled, removed, temporarily removed, or removed and replaced, as necessary for performance of Work under the Contract. Work out of alignment where exposed by removal of existing work shall be called to the attention of GSA. Necessary corrective work shall be as directed.

1. Replacements of existing conditions that are removed shall match similar existing conditions.

2. Unless otherwise indicated, existing structural members shall not be cut or altered without authorization by the Contracting Officer.

3. Conditions remaining in place, which are damaged or defaced during the Work, shall be restored to the condition existing at time of award of Contract.

4. Discolored or unfinished surfaces exposed by removal of existing conditions, that are indicated to be final exposed surfaces, shall be refinished or replaced as necessary to produce uniform and harmonious contiguous surfaces.

C. Existing structures will remain in place.

D. Existing utility services with related meters and equipment will remain in place.

E. Removed items indicated to remain the property of the Government shall be stored on site where directed by the GSA Construction Manager as coordinated with Port Personnel.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION (Not Applicable)

END OF SECTION 011000

SECTION 011400 – WORK RESTRICTIONS

011400-1 11/13/15 SENSITIVE BUT UNCLASSIFIED (SBU) PROPERTY OF THE UNITED STATES GOVERNMENT. FOR OFFICIAL USE ONLY.

Do not remove this notice. Properly destroy documents when no longer needed.

PART 1 - GENERAL

1.1 DESIGN-BUILD CONTRACTOR USE OF PREMISES

A. The Design-Build Contractor shall limit use of the premises to the work in areas indicated as coordinated with the Port’s Representative and GSA’s Construction Manager, and to allow for Government occupancy and public use.

1. Confine operations at the site to areas indicated. Do not disturb portions of the site beyond the areas in which Work is indicated.

2. Keep driveways and entrances serving the premises clear and available at all times to the Government, Government employees and to visitors. Do not use these areas for parking or storage of materials.

3. Schedule deliveries to minimize space and time requirements for storage of material and equipment on site.

4. Repair damage caused by construction operations to the satisfaction of the government. Take precautions to protect the building, its occupants and the public during the construction period.

A representative of the Design-Build Contractor shall be available to arrive on site within one

(1) hour of notice should an emergency occur.

5. Keep public areas, such as hallways, stairs, lobbies and toilet rooms, free from accumulation of waste material, rubbish, construction debris and construction materials.

6. Space on the premises will be made available for the Design-Build Contractor's staging of materials and related activities, provided that its use will not interfere with operations of the Government. Parking is limited and space may or may not be available. Design-Build

Contractor to coordinate use of site with ports through GSA’s Construction Manager and include this information in a Site Utilization plan to be submitted for approval at the pre-construction meeting.

7. Existing materials and equipment that are removed as part of the construction operations, and that are not reused or designated to be salvaged as Government property, shall become the property of the Design-Build Contractor and shall be removed from the site. Pollution producing equipment shall not be located near air intakes where airborne smoke or fumes could be drawn into the building. When not required for powering unloading

8. No apparatus with an open flame is allowed to be used within the facility without the prior receipt of a burn permit. Design-Build Contractor to coordinate with GSA’s Construction

Manager to obtain burn permits. Burn permits are required for each separate occurrence.

9. The work shall be sequenced to minimize disruption to building occupants, visitors, and maintenance activities. All work schedules must be coordinate with the ports.

10. Coordinate with GSA’s Construction Manager for site access.

11. Coordinate with the GSA‘s Construction Manager for correct response procedures for any building system alarms occurring during or resulting from the construction process.

12. All building systems outside the immediate construction area shall be kept fully operational during normal working hours.

1.2 PORT OCCUPANCY

A. The Government will occupy the site and buildings during the entire period of construction.

Cooperate with GSA’s Construction Manager and Port’s Representative during construction operations to minimize conflicts, mitigate noise, and facilitate Government usage. Perform the

Work in a manner that does not interfere with the Government's operations.

1.3 WORKING HOURS

A. Government Occupancy Hours: Government personnel are scheduled to occupy the site during the following hours:

1. Hours: 6 AM to 10 PM daily.

SECTION 011400 – WORK RESTRICTIONS

011400-2 11/13/15 SENSITIVE BUT UNCLASSIFIED (SBU) PROPERTY OF THE UNITED STATES GOVERNMENT. FOR OFFICIAL USE ONLY.

Do not remove this notice. Properly destroy documents when no longer needed.

2. Hours: 6 AM to 10 PM daily.

B. Work accomplished during Government Unoccupied Hours shall be performed at no additional cost to the Government. Design-Build Contractor shall submit a proposed schedule and make accommodation as necessary to gain approval through GSA’s Construction Manager from the Port’s representatives.

1.4 WORK RESTRICTIONS BY PORT

PART 2 - PRODUCTS (Not Applicable)

END OF SECTION 011400

SECTION 013100 – PROJECT MANAGEMENT AND COORDINATION

013100-1 11/13/15 SENSITIVE BUT UNCLASSIFIED (SBU) PROPERTY OF THE UNITED STATES GOVERNMENT. FOR OFFICIAL USE ONLY.

Do not remove this notice. Properly destroy documents when no longer needed.

PART 1 - GENERAL

1.1 SUMMARY

A. This section includes certain administrative provisions for managing and coordinating construction operations, including but not limited to the following:

1. General project coordination.

2. Administrative and supervisory personnel.

3. Conferences and meetings.

4. Electronic Project Management (ePM) System.

5. Requests for Information (RFI).

6. Utility service interruptions.

7. General Coordination Provisions.

1.2 GENERAL PROJECT COORDINATION

A. Coordination of Trades: Coordinate construction operations included in the various sections of the Specifications to provide an efficient and orderly installation of each part of the Work.

Coordinate construction operations included under different sections of the Specifications that depend on each other for proper installation, connection or operation. Keep, conduit, and the like as close as possible to ceiling slab, walls, and columns to take up a minimum amount of space. Assure all controls can be reached and operated.

1. Schedule construction operations in the sequence required to obtain the best results where the installation of one part of the Work depends on installation of other components before or after that part.

2. Coordinate installation of different components to provide maximum accessibility for required maintenance, service, testing and repair.

1.3 CONFERENCES AND MEETINGS

A. Preconstruction Conference: The Design-Build Contractor shall schedule a preconstruction conference before starting construction at a time and place convenient to the GSA. The purpose of the conference is to review responsibilities and personnel assignments.

1. Attendees: Participants at the conference shall be familiar with the project, shall be authorized to conclude matters relating to the Work, and shall minimally include.

a. GSA.

b. Design-Build Contractor’s Architect.

c. Design-Build Contractor.

d. Major subcontractors.

e. Major suppliers.

f. Other concerned parties.

2. Agenda: Subjects for discussion shall include items of significance that could affect progress, including but not limited to the following:

a. Tentative construction schedule.

b. Critical work sequencing.

c. Designation of responsible personnel.

d. Procedures for processing field decisions and Change Orders.

e. Procedures for processing Applications for Payment.

f. Distribution of Contract Documents.

g. Submittal of Shop Drawings, Product Data, and Samples.

h. Preparation of Record Documents.

i. Use of the premises.

013100-2 11/13/15 SENSITIVE BUT UNCLASSIFIED (SBU) PROPERTY OF THE UNITED STATES GOVERNMENT. FOR OFFICIAL USE ONLY.

Do not remove this notice. Properly destroy documents when no longer needed.

j. Parking availability.

k. Office, work, and storage areas.

l. Equipment deliveries and priorities.

m. Safety procedures.

n. First aid.

o. Security.

p. Housekeeping and progress cleaning.

q. Working hours.

r. Energy and resource efficiency / sustainability

s. Waste management

t. Training

B. Progress Meetings: The Contactor shall conduct weekly progress meetings at the Project Site and through conference calls. Dates of meetings shall be coordinated with preparation of the payment request.

1. Attendees: In addition to the Design-Build Contractor's and GSA's representatives, each subcontractor, supplier, or other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. All participants at the conference shall be familiar with the Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of the previous progress meeting.

Review other items of significance that could affect progress. Include topics for discussion as appropriate to the status of the Project.

a. Design-Build Contractor's Construction Schedule and the three week rolling bar chart: Review progress since the last meeting. Determine where each activity is in relation to the Design-Build Contractor's Construction Schedule, whether on time or ahead or behind schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time. Coordinate with Port Representative work for the upcoming two weeks.

b. Review the present and future needs of each entity present, including but not limited to the following:

1) Interface requirements.

2) Time.

3) Sequences of operations.

4) Status of submittals.

5) Deliveries.

6) Off-site fabrication.

7) Access.

8) Site utilization.

9) Temporary facilities and controls.

10) Hours of work.

11) Hazards and risks.

12) Housekeeping and progress cleaning.

13) Quality and work standards.

14) Change Orders.

15) Documentation of information for payment requests.

16) Updating of Record Documents.

3. Schedule Updating: The Design-Build Contractor shall revise the Design-Build

013100-3 11/13/15 SENSITIVE BUT UNCLASSIFIED (SBU) PROPERTY OF THE UNITED STATES GOVERNMENT. FOR OFFICIAL USE ONLY.

Do not remove this notice. Properly destroy documents when no longer needed.

Contractor's Construction Schedule and three week rolling bar chart after each progress meeting where revisions to the schedule have been made or recognized. The revised schedules shall be issued concurrently with the report of each meeting.

C. Final Inspection Meeting: GSA will schedule and conduct a final inspection meeting on site, at a time convenient to Contractor and Architect within30 calendar days of Substantial Completion.

Attendees: Authorized representatives of GSA; Design-Build Contractor and its superintendent;

major subcontractors as required; suppliers as required; and other concerned parties shall attend the meeting. Participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

1. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following:

a. Preparation of record documents.

b. Submittal of written warranties.

c. Review of prepared Volumes I and II. Refer to Section017822 Operations and

Maintenance Documentation.

d. Review of material samples, attic stock, and spare parts.

e. Review of completed demonstrations and training.

f. Preparation of Design-Build Contractor's punch list.

g. Procedures for processing Applications for Payment at Substantial Completion and for final payment.

h. Responsibility for removing temporary facilities and controls.

i. Site demobilization and clean up.

2. Minutes: GSA’s Construction Manager will record and distribute meeting minutes.

1.4 ELECTRONIC PROJECT MANAGEMENT (ePM) SYSTEM

A. A secure, web-based, electronic project management (ePM) system will be provided by GSA to accommodate information exchange needs of the Project. The ePM system will be maintained continuously through completion of the Construction Stage. All communications between the GSA, Design-Build Contractor, and other entities involved in the execution of the Project shall be captured and recorded in the ePM system. User licenses and training will be provided for GSA and Design-Build Contractor members of the Project Delivery Team who will require access to the ePM system.

B. Design-Build Contractor shall use ePM system for communications with GSA and other entities involved in Project. Electronic storage and transmission of information via the ePM system shall comply with GSA's Document Security Requirements.

1.5 REQUESTS FOR INFORMATION (RFI)

A. General: The RFI process shall be the Contractor’s formal method to request Project information. RFIs shall only be used by the Contractor when:

1. Contractor discovers a constructability issue.

2. Contractor has a question about information in the Contract Documents

3. Contractor requires information not found in the Contract Documents, B. Contractor shall make a reasonable attempt to answer Subcontractor questions without putting them in RFI format and passing them on to GSA.

013100-4 11/13/15 SENSITIVE BUT UNCLASSIFIED (SBU) PROPERTY OF THE UNITED STATES GOVERNMENT. FOR OFFICIAL USE ONLY.

Do not remove this notice. Properly destroy documents when no longer needed.

C. Immediately upon discovery of the need for additional information or interpretation of Contract Documents, Contractor shall prepare and submit an RFI to GSA.

1. Contractor shall coordinate and submit RFIs in a prompt manner so as to avoid delays in

Contractor's work or work of subcontractors.

2. Submit RFI electronically to GSA using the ePM system.

D. Content of the RFI: Include a detailed, legible description of item requiring information or interpretation and the following:

1. Project name and LPOE name.

2. Date.

3. Name of Contractor.

4. RFI number, numbered sequentially.

5. RFI subject.

6. Specification Section number and title and related paragraphs, as appropriate.

7. Drawing number and detail references, as appropriate.

8. Field dimensions and conditions, as appropriate.

9. Contractor's suggested resolution. If Contractor's suggested resolution impacts the

Contract Schedule or the Contract Sum, Contractor shall state such impact in the RFI.

a. Contractor to provide the requested time period for response, but must allow a minimum of

7 calendar days for GSA response.

E. Attachments: Include sketches, descriptions, measurements, photos, Product Data sheets, Shop Drawings, coordination drawings, and other information necessary to fully describe items requiring interpretation.

1. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on sketches.

F. RFI Format: Attachments shall be electronic files in Adobe Acrobat PDF format.

G. GSA Action: GSA will review each RFI, determine action required, and respond. Allow 7 calendar days for GSA's response to each RFI.

H. The following Contractor-generated RFIs will be returned without action:

1. Requests for approval of submittals.

2. Requests for approval of substitutions.

3. Requests for approval of Contractor's means and methods.

4. Requests for coordination information already indicated in the Contract Documents.

5. Requests for adjustments in the Contract Time or the Contract Sum.

6. Requests for interpretation of GSA’s actions on submittals.

7. Incomplete RFIs or inaccurately prepared RFIs.

I. GSA action may include a request for additional information, in which case GSA time for response will date from time of receipt of additional information.

J. RFI Register: Prepare and maintain a tabular log of RFIs organized by the RFI number.

K. RFI Recordkeeping: Maintain one complete set of RFIs at project site.

L. On receipt of GSA response, update RFI log and distribute RFI response to affected parties.

1.6 UTILITY SERVICE INTERRUPTIONS

A. Design-Build Contractor shall coordinate all utility service interruptions with the Port through GSA’s Construction Manager.. Design-Build Contractor shall submit proposed dates and times of each scheduled interruption, with estimated period of outage, list of existing equipment that

013100-5 11/13/15 SENSITIVE BUT UNCLASSIFIED (SBU) PROPERTY OF THE UNITED STATES GOVERNMENT. FOR OFFICIAL USE ONLY.

Do not remove this notice. Properly destroy documents when no longer needed.

will be affected by the interruption, proposed sequence of equipment shut-down and start-up, and responsible personnel no less than 72 hours prior to interruption..

B. Coordination of Interruptions: Sufficiently in advance of each scheduled utility interruption, the Design-Build Contractor shall issue a notice to all affected parties, confirming each provision of the interruption, or canceling and rescheduling. Coordinate with GSA’s Construction Manager to confirm that the responsible personnel are prepared to execute the shut-down and start-up of affected existing equipment, prior to each interruption.

PART 2 - PRODUCTS (Not applicable)

PART 3 - EXECUTION

3.1 GENERAL COORDINATION PROVISIONS

A. Inspection of Conditions: Prior to installations, require the installer of each major component to inspect both the substrate and conditions under which work is to be performed.

1. Do not proceed until unsatisfactory conditions have been corrected in an acceptable manner.

2. Coordinate temporary enclosures with required inspections and tests to minimize the necessity of uncovering completed construction for that purpose.

B. Construction in Progress: Keep construction in progress, and adjoining materials in place, clean during handling and installation. Apply protective coverings where required for protection from damage or deterioration.

C. Completed Construction: Clean completed construction, and provide maintenance, as frequently as necessary to prevent damage or soiling or other deterioration through the remainder of the construction period. Adjust and lubricate operable components as necessary to assure operability without damage.

D. Limiting Exposures: Supervise construction operations to prevent exposure of any part of construction, completed or in progress, to harmful, dangerous, damaging or otherwise deleterious conditions during the construction period.

END OF SECTION 013100

SECTION 013120 – CRITICAL PATH METHOD SCHEDULING

013120-1 11/13/15 SENSITIVE BUT UNCLASSIFIED (SBU) PROPERTY OF THE UNITED STATES GOVERNMENT. FOR OFFICIAL USE ONLY.

Do not remove this notice. Properly destroy documents when no longer needed.

PART 1 - GENERAL

1.1 SUMMARY

A. Develop a detailed Network Plan using the most current version of preferred electronic scheduling software, demonstrating complete fulfillment of all Work shown in the contract documents. Regularly update the Network Plan in accordance with the requirements of this Section, and use it in planning, coordinating, and performing all the Work under this contract. Schedule activities shall accurately depict the entire scope of work to be performed to complete the project including, but not limited to, all activities of subcontractors, consultants, equipment vendors and suppliers, GSA, and others, as required.

B. The purpose of the Project Schedule shall be to:

1. Ensure adequate planning, staffing, scheduling and reporting during execution of the Work by the Design-Build Contractor;

2. Ensure coordination of the Work among all affected parties;

3. Assist the Design-Build Contractor and GSA in the preparation and evaluation of the Design-Build

Contractor’s monthly progress payments; and

4. Assist the Design-Build Contractor and GSA in monitoring the progress of the work, and evaluating proposed changes to the Contract and/or requests for additional time to Project Completion.

1.2 DEFINITIONS

A. Definitions applicable to this Section include the following:

1. Activity - An element of the Work or task performed during the course of the project. Each schedule activity shall be a clearly defined and manageable task depicting an expected duration, an expected cost, and expected resource requirements.

2. Baseline Schedule - The original work plan approved by GSA as the Project Schedule.

3. Constraint - A scheduling restriction imposed on the start or finish of an activity. Only contractual/owner-designated constraints are allowed.

4. Critical Path - The Project primary critical path is defined as the path with the least amount of total float which constitutes the longest, continuous path of interrelated activities depicting project work from notice to proceed to project completion. All reports and graphics indicating the Critical Path shall depict the longest path of interrelated activities. Unless otherwise approved by GSA, the Baseline Schedule Critical Path shall use all allotted Contract time.

5. Critical Path Method (CPM) - A scheduling technique using activities, durations, and interrelationships/dependencies (logic), such that all activities are interrelated with logic ties from the beginning of the project to the completion of the project.

6. Data Date - The data date of each schedule update shall be the first calendar day of each month and represent all work performed through the last calendar day of the preceding month.

7. Float – is the difference between the planned early dates and the planned late dates; the amount of time an activity can be delayed without affecting the Substantial Completion Date. Float is considered a project commodity jointly shared between GSA and the Design-Build Contractor and shall be used in the best interest of completing the Project on time.

8. Float Suppression - utilization of zero free float constraints which allows an activity to start as late as possible by using all its' available free float. This technique allows activities to appear more critical than if the activity's total float was based on early dates. Assigning zero free float prevents true sharing of total float between GSA and the Design-Build Contractor.

9. Fragnet - A subset group of interrelated activities representing only a portion of the CPM schedule.

10. Network Plan - The Network Plan is the entire database of activities, logic, durations, and all items relating to any activity input into the scheduling software and is the complete representation of the

Project Schedule prepared using the Critical Path Method and graphically shown in a time-scaled form. The network shows the sequence and interdependence of the activities, and planned and actual progress by activity, required for complete performance of the Work.

11. Project Schedule - The Project Schedule includes the Preliminary Schedule (submitted with offer or as determined by the CO), the approved Baseline Schedule (developed based on the Preliminary

Schedule), and all subsequent Schedule Updates, Schedule Revisions, Recovery Schedules, and As-Built Schedule.

013120-2 11/13/15 SENSITIVE BUT UNCLASSIFIED (SBU) PROPERTY OF THE UNITED STATES GOVERNMENT. FOR OFFICIAL USE ONLY.

Do not remove this notice. Properly destroy documents when no longer needed.

12. Recovery Schedule – A schedule depicting the Design-Build Contractor's plan for recovery of time lost on the project, though no fault of the Government.

13. Schedule Revision - A schedule in which the plan for the work is revised. A Schedule Revision is required when the current schedule no longer represents the actual or planned prosecution of the Work

14. Schedule Update - A schedule in which only progress is updated from the prior data date to the current data date. No revisions to logic ties will be permitted in a Schedule Update.

15. Time Impact Analysis - A technique to demonstrate the comparison of the time impact for each schedule revision or proposed revision against the current approved Project Schedule.

16. Total Float - The amount of time an activity (or chain of activities) can be delayed without affecting the Project Substantial Completion Date.

17. Working Day - A Working Day is a calendar day scheduled for active prosecution of the work.

1.3 CRITICAL PATH METHOD SCHEDULE

A. Provide a detailed, time-scaled computer generated Project Schedule with activities representing each portion of the Work for the entire Contract Performance Period. The Project Schedule shall use the Critical Path Method (CPM) for the planning, scheduling and reporting of the work to be performed under the contract. and shall be produced using the most current version of the preferred software system, or fully transferable to a project planner software (refer to SCHEDULING SOFTWARE). The type of schedule shall be Precedence Diagramming Method (PDM).

B. No unspecified milestones, Design-Build Contractor-designated Constraints, Float suppression techniques, or use of Activity durations, logic ties and/or sequences deemed unreasonable by GSA shall be used in the Project Schedule.

C. As defined by the Contract, the entire project performance period shall establish the Project Completion Date which shall be used in the planning and presentation of the Design-Build Contractor’s Project

Schedule. If the Design-Build Contractor forecasts a planned early Substantial Completion Date in the Baseline Project Schedule, the Design-Build Contractor shall be required to resource-load all schedule activities including procurement (fabrication and delivery)/ construction /close-out/commissioning activities depicted in the Baseline Project Schedule. Approval of a planned early completion date is solely at the discretion of GSA. GSA reserves the right not to approve any schedule deemed to have an unrealistic forecasted Substantial Completion Date. Government approval of an early completion Project Schedule shall not modify the Contract directed Substantial Completion Date or Project Completion

Date. The time difference between the Design-Build Contractor’s planned Substantial Completion Date and the Contract directed Substantial Completion Date shall be considered Project Float, jointly owned and for the mutual use of both the Design-Build Contractor and GSA.

D. The Design-Build Contractor shall provide the computer processing of the CPM schedule, graphics, cost and resource reports required under this Section and/or as requested by GSA both electronically and in hardcopy at no additional cost to GSA throughout the entire project performance period until Project completion is achieved.

1.4 SUBMITTALS AND MEETINGS

A. Preliminary Schedule:

1. The Request for Proposal contains a conceptual schedule for Design-Build Contractor consideration of the major milestones anticipated for completion of design, procurement, construction and installation of the project components. In response to the Request for Proposals the Design-Build Contractor shall submit a Preliminary Schedule as supporting documentation to their technical approach to the project that generally aligns with the conceptual schedule, or addresses equivalent milestones and major activities required to substantially complete the within the period of performance anticipated.

2. The Preliminary Schedule shall detail planned work/operations for the entire duration of the Project with summary level activities representing major components of work included in the Contract for the balance of the Project performance period through to the Substantial Completion Date.. The

Preliminary Schedule shall include a written narrative describing the major design and construction activities and any activities that will be accomplished concurrently at more than one port.

013120-3 11/13/15 SENSITIVE BUT UNCLASSIFIED (SBU) PROPERTY OF THE UNITED STATES GOVERNMENT. FOR OFFICIAL USE ONLY.

Do not remove this notice. Properly destroy documents when no longer needed.

B. Project Schedule Requirements Meeting:

1. The Design-Build Contractor shall meet with GSA within five work days after Notice to Proceed to conduct a joint review of the Project Schedule requirements in this Section.

C. Baseline Project Schedule

1. The Design-Build Contractor shall submit the Baseline Project Schedule within twenty calendar days after Notice to Proceed. The Baseline Schedule shall be the Design-Build Contractor's detailed plan for ALL work from NTP to the Substantial Completion Date, as established in the

Contract. All punch list work shall be completed on, or prior to, the Contract Completion Date. Cost and resource loading of the schedule activities shall not be required.

2. Unless otherwise approved by the GSA, the Project Schedule shall include, but is not limited to, the following items:

a. Activities necessary to depict, to the extent applicable, ALL procurement, design, construction, close-out, start-up, testing and balancing, commissioning, training, and turnover, and work by separate contractors.

b. Activities necessary to depict the procurement and submittal process including shop drawings and sample submittals, and the fabrication and delivery of key and long-lead procurement elements. The Project Schedule shall indicate intended submittal dates, and depict the review period as defined in the Contract or Supplementary Provisions for A/E/GSA review.

Procurement/submittal activities shall be assigned codes that will allow these activities to sorted and printed separately from the construction/close-out/commissioning work activities.

Procurement, submittal and review activities may be included in a separate Project Group but shall include all interrelationships to applicable construction/close-out/commissioning activities shown in the Project Schedule.

c. The Baseline Schedule shall have a Data Date no later than NTP, and no activities shall be progressed to show work completed to date.

d. Activity descriptions of the work shall include area designators sufficient to identify where the Work will occur, and if applicable, that match the Key Plans shown on the 100% Construction

Drawings. The work related to each Activity shall be limited to one work trade and one area.

e. Interrelationships (logic) and sequencing for ALL activities. Each activity shall have at least one predecessor (except for the first activity) and one successor (except for the last activity) relationship to form a logically connected Network Plan from NTP to the Contract Completion

Date.

f. Activity durations shall be in units of whole work days. Except submittal and procurement activities, durations shall not exceed fifteen work days unless approved by the GSA. Durations for Government submittal reviews shall meet the requirements set forth in the Contract

Documents.

g. Contractual milestone events as defined in the Contract Documents including, but not limited to, phased work, work restrictions/access/shift work, and work being performed by separate contractors. The Design-Build Contractor is prohibited from assigning milestones that are NOT consistent with key dates shown by GSA in the Contract Documents.

h. ALL activities shall at a minimum be coded by AREA, RESPONSIBILITY (trade/ subcontractor), and PHASE. Additional codes are allowed to sufficiently identify where work will occur. Codes shall be a maximum of six (6) characters and abbreviations shall be fully described in the Project Schedule. The Design-Build Contractor’s self-performed work shall be clearly identifiable.

D. Baseline Schedule Review Process and Submittal Requirements

1. The GSA will review the Baseline Schedule and provide comments to the Design-Build Contractor within ten work days of receipt of submittal and, if needed, will arrange for a Baseline Schedule Review Meeting with the Design-Build Contractor for discussion of the schedule. The Baseline

Schedule, when approved, shall become the basis for the next monthly Schedule Update submitted by the Design-Build Contractor.

a. Baseline Schedule Review Meeting. The Design-Build Contractor shall present the Baseline

Schedule to GSA at the review meeting, and describe the Design-Build Contractor's means and methods for accomplishing the Work.

b. In the event that GSA provides comments or the Baseline Schedule does NOT meet the

013120-4 11/13/15 SENSITIVE BUT UNCLASSIFIED (SBU) PROPERTY OF THE UNITED STATES GOVERNMENT. FOR OFFICIAL USE ONLY.

Do not remove this notice. Properly destroy documents when no longer needed.

requirements of this specification, the Design-Build Contractor shall, within five (5) work days, revise the Project Schedule to bring it into compliance with these requirements, and Design-

Build Contractor shall make a full Baseline Schedule submission for GSA’s review and approval.

c. GSA's approval of the Baseline Project Schedule does not relieve the Design-Build Contractor of responsibility whatsoever for the accuracy or feasibility of the Project Schedule, or of the Design-Build Contractor’s ability to meet the Substantial Completion Date. Such acceptance does not create a warranty, expressed or implied, or acknowledge or admit the reasonableness of the activities, logic, durations, manpower, cost or equipment loading of the Design-Build Contractor’s Project Schedule.

d. If the Design-Build Contractor fails to timely submit the Baseline Schedule, the GSA may withhold approval of progress payments until the Design-Build Contractor submits the required

Project Schedule.

2. The Baseline Schedule submission shall be comprised of the following, unless otherwise requested by the GSA:

a. One (1) electronic copy of the entire Project Schedule shall be uploaded into ePM and copied to a CD-ROM. The electronic copy shall be in a compressed format. The electronic filename shall have a unique identifier. Hard copy prints and reports shall be generated from the same version of the Project Schedule that is provided in electronic form.

b. Two (2) full-color prints of the Network Plan (in time-scaled form), unless otherwise designated by the Contacting Officer. Prints shall be 11”x17” standard size sheets. The following information shall be shown on the prints: Activity ID, Activity Description, Calendar ID, Original

Duration, Remaining Duration, Percent Complete, Area Code, Responsibility Code, Early Start, Early Finish, Total Float, Budgeted Cost, and Budgeted Quantity (i.e., labor, materials, equipment, etc.). The prints shall include legends, dates and titles to sufficiently identify the Project Schedule.

c. A narrative providing additional clarification/explanation of items such that GSA is informed of the approach used to plan and sequence the work, coordinate with other separate Design- Build Contractors to the extent applicable, and resource and cost load the Project Schedule.

E. Schedule Updates:

1. The Design-Build Contractor shall submit a monthly Schedule Update that indicates the progress achieved since approval of the prior monthly Project Schedule update. The Schedule Update shall be approved by GSA prior to submittal of a Schedule Revision.

2. The Project Schedule shall be updated on a monthly basis throughout the entire Project performance period until Project completion is achieved.

3. The Design-Build Contractor shall meet with GSA each month at a Schedule Update Meeting to review the Design-Build Contractor’s requested percent complete for actual progress achieved through the Data Date of the Schedule Update, and actual date information for activities that were started and/or completed during the reporting period.

4. The Schedule Update submission shall be comprised of the following:

a. One (1) electronic copy of the entire Project Schedule shall be uploaded into ePM and copied to a CD-ROM. The electronic copy shall be in a compressed format. The electronic filename shall have a unique identifier and shall include a sequential number for each monthly update.

Hard copy prints and reports shall be generated from the same version of the Project Schedule that is provided in electronic form.

b. Two (2) full color time-scaled network prints. Prints shall be 11”x17” standard size sheets. The following information shall be shown on the prints: Activity ID, Activity Description, Calendar ID, Original Duration, Remaining Duration, Percent Complete, Area Code, Responsibility

Code, Early Start, Early Finish, Late Start, Late Finish, and Total Float. The prints shall include legends, dates and titles to sufficiently identify the Project Schedule.

c. Monthly narrative shall address the following:

1) Description of Work performed during the reporting period

2) Description of the primary, secondary and tertiary Critical Paths

3) Description of Work anticipated to be performed during the next reporting period

4) Number of days ahead/behind the Substantial Completion Date

5) Discussion of changes to the primary Critical Path since the prior month’s update

013120-5 11/13/15 SENSITIVE BUT UNCLASSIFIED (SBU) PROPERTY OF THE UNITED STATES GOVERNMENT. FOR OFFICIAL USE ONLY.

Do not remove this notice. Properly destroy documents when no longer needed.

6) Description of problem areas and anticipated problem areas

7) Current and anticipated delays including cause of delay, corrective actions taken, and impact of the delay on other activities, milestones, and completion dates

8) Pending items (Change Orders, requests for time-extensions, etc.), and status thereof

5. GSA will review and provide comments on the Schedule Update within ten work days of receipt of the Design-Build Contractor’s submission.

6. If the Design-Build Contractor fails to timely submit the Schedule Update, the GSA may withhold approval of progress payments until the Design-Build Contractor submits the required Project Schedule Update.

7. In the event of change modifications:

a. As determined by CPM schedule analysis, only delays determined to be solely caused by

GSA that affect the Substantial Completion Date will be considered for a time extension.

b. When change modifications are proposed, potential delays are anticipated, or delays are experienced, the Design-Build Contractor shall submit to GSA a written Time Impact Analysis describing the effect of each modification, potential delay, delay, or Design-Build Contractor request on the Substantial Completion Date. This analysis shall be developed and submitted at the earliest time the Design-Build Contractor becomes aware of a delay or potential delay, or as requested by the GSA. The preparation of Time Impact Analyses is considered part of the construction process and will be performed at no additional cost to the Government.

c. Failure of the Design-Build Contractor to timely submit a Time Impact Analysis shall mean that it is mutually agreed that the particular modification, delay, or Design-Build Contractor request does not require an extension of the contract time.

d. Approval or rejection of each Time Impact Analysis by the GSA shall be made within fifteen work days after receipt of each Time Impact Analysis, unless subsequent meetings and negotiations are necessary. Upon approval, a copy of the Time Impact Analysis signed by the GSA shall be returned to the Design-Build Contractor and incorporated into the Project Schedule at the next Schedule Revision which will be become the current approved Project

Schedule.

e. The Design-Build Contractor shall submit a Time Impact Analysis as follows:

1) Within five (5) work days after receipt of a written change modification.

2) Within five (5) work days after receipt of a written notice by the GSA.

3) Within five (5) work days from the beginning of a delay caused by unforeseeable circumstances.

f. The Time Impact Analysis shall meet the requirements for submittal of a Schedule Revision including a Fragnet (see Section 1.05.F.3.c) with sufficient supporting documentation to enable the GSA to make a determination on the Design-Build Contractor’s request for time extension.

1.5 RESPONSIBILITY FOR COMPLETION

A. If, in the opinion of the GSA, the Design-Build Contractor falls behind the planned progress as noted by negative float shown on the current monthly Schedule Update, the Design-Build Contractor shall take any and all steps necessary to improve its progress at no additional cost to the Government. This shall not be construed as prohibiting the Design-Build Contractor from increasing the number of working hours, shifts per day, working days per week, or the amount of construction equipment, or any combination of the foregoing, to eliminate the delay in the scheduled progress.

B. Failure of the Design-Build Contractor to comply with the requirements of the GSA under Paragraph 1.06.A shall be grounds for determination by the GSA that the Design-Build Contractor is not prosecuting the work with such diligence as will ensure completion within the contract time. Upon such determination, the GSA may terminate the Design-Build Contractor's right to proceed with the work, or any separable part thereof, in accordance with the applicable provisions of the GSA Form 3506.

1.6 PAYMENTS TO DESIGN-BUILD CONTRACTOR

A. The GSA shall review the Design-Build Contractor's monthly request for payment upon receipt and shall process the request for payment based upon the current approved Schedule Update. The GSA will consider the Design-Build Contractor's overall progress toward Project Completion along with the progress for discrete activities to determine the amount to be approved for the monthly payment request.

013120-6 11/13/15 SENSITIVE BUT UNCLASSIFIED (SBU) PROPERTY OF THE UNITED STATES GOVERNMENT. FOR OFFICIAL USE ONLY.

Do not remove this notice. Properly destroy documents when no longer needed.

1.7 PERFORMANCE MONITORING

A. The GSA may elect throughout, or at any time during, the Project to record the number of workers and construction equipment working on each construction schedule activity in each area of the Project. The GSA's request for this information will be without additional cost to the Government and shall be provided within five (5) work days of receipt of the GSA's written request. This information will be used by the GSA to evaluate the adequacy of the Design-Build Contractor’s performance and project manpower staffing, as well as any Design-Build Contractor claims.

B. The Design-Build Contractor is required to host weekly construction coordination meetings. As such, the Design-Build Contractor shall prepare a three week rolling bar chart showing one week behind the date of the meeting depicting work completed, and two weeks look-ahead. The bar chart should be sorted by

Area by Total Float. Information to be shown on the bar chart includes: Activity ID, Activity Description, Original Duration, Remaining Duration, Percent Complete, Area Code, Responsibility Code, Early

Start/Actual Start, Early Finish, and Total Float.

1.8 SCHEDULER REQUIREMENTS/QUALIFICATIONS

A. Within five (5) work days after the date of Notice to Proceed, the Design-Build Contractor shall designate in writing an authorized scheduler or scheduling representative in the Design-Build Contractor’s organization who shall be responsible for coordinating with GSA during the preparation and maintenance of the Project Schedule. Design-Build Contractor's scheduler shall possess demonstrated proficiency in CPM schedule methodology and utilization of the current version of the preferred scheduling software.

B. The Design-Build Contractor’s project superintendent, and the scheduling representative and, to the extent applicable, the personnel responsible for developing and inputting information into the Project Schedule shall attend schedule related meetings and monthly update meetings throughout the duration of the Project.

1.9 CPM SCHEDULING SOFTWARE

A. The scheduling software used by the Design-Build Contractor shall be the most current version.

END OF SECTION 013120

SECTION 013220 – PHOTOGRAPHIC DOCUMENTATION

013220-1 11/13/15 SENSITIVE BUT UNCLASSIFIED (SBU) PROPERTY OF THE UNITED STATES GOVERNMENT. FOR OFFICIAL USE ONLY.

Do not remove this notice. Properly destroy documents when no longer needed.

PART 1 - GENERAL

1.1 SUMMARY

A. This section includes requirements for the Design-build Contractor to submit and maintain photographic records of the construction process.

1.2 QUALITY CONTROL

A. Photographer's Qualifications: Photographer shall have experience with construction progress photography.

1.3 MINIMUM NUMBER OF PHOTOGRAPHS

A. The minimum number of construction photographs on average of 20 photographs per 5 working days over the duration of Work plus additional photographs as required to document major components of the construction and installation process.

1.4 SUBMITTALS

A. Construction Photographs. Photographer shall submit and/or upload to ePM electronic files of each view to the GSA within 7 calendar days after taking photographs.

1. Minimum [3200 by 2400] pixels, in unaltered original files, with same aspect ratio as the sensor, uncropped, date and time stamped, in folder named by date the photographs are…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .