This federal contract opportunity notice seeks a contractor to replace the emergency generator and fire pump at the Walter H. Rice Federal Building and U.S. Courthouse in Dayton, Ohio. The scope of work includes replacing the existing diesel generator with a new 500 kW natural gas generator and replacing the existing fire pump. The construction cost estimate ranges from $1 million to $3.375 million. The performance period is 275 calendar days from the on-site notice to proceed. The NAICS code is 236220 with a small business size standard of $39.5 million. A pre-proposal conference will be held on August 29, 2022. Proposals are due by September 30, 2022. The soliciting agency is the General Services Administration Public Buildings Service Region 5.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 05.pdf | ||
| Amendment 04.pdf | ||
| Amendment 02.pdf | ||
| 2022 08 29 Pre-Poposal Sign-In Sheet.pdf | ||
| Updates Description for Bid Adddendum 1.pdf | ||
| Bid Addendum 1 - Revised Specs.pdf | ||
| Amendment 01.pdf | ||
| 47PF0022R0090_Rice GEN and FP.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is required to sign this document and return copies to the issuing office.Contractor is not
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NUMBER 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
R10A. MODIFICATION OF CONTRACT/ORDER NUMBE
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
is not extended.The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
PAGE OF PAGES
CODE6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
R5 AMD Southern Construction Contracting Team 230 S. Dearborn St.
Room 3500 Chicago, IL 60604 USA
R5 AMD Southern Construction Contracting Team 230 S. Dearborn St.
Room 3500 Chicago, IL 60604 USA
47PF0022R0090
1 1
09/21/2022
08/18/2022
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Amendment 03, Solicitation 47PF0022R0090 Emergency Generator and Fire Pump Replacement Walter H. Rice Federal Building and U.S. Courthouse, 200 West 2nd Street, Dayton, Ohio 45402
Amendment 03 is hereby issued to 1) address all RFI's to date, 2) revise the SF1442 and incorporate a pricing breakdown form, 3) issue bid addendum #2 with drawing updates, 4) incorporate Section 012000 - Allowances, and 5) extend the due date/time to 4:00 PM CDT on 9/30/2022. You must acknowledge receipt of this and all amendments.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
Responses to All RFI’s
RFP 47PF0022R0090
Emergency Generator and Fire Pump Replacement
Walter H. Rice Federal Building and U.S. Courthouse 200 West 2nd Street, Dayton, Ohio
1) Is the project funded?
Response: Yes; The project is funded.
2) Who is the GSA’s elevator maintenance vendor and contact info? At the pre-bid it was mentioned the vendor listed in the solicitation is not the current vendor.
Response:
The Murphy Elevator Company 800-752-6075 | service@murphyelevator.com
3) Please provide a roof insulation and membrane specification.
Response: The scope of work only entails the existing shed and not the main building roof.
4) Please provide a detail of the existing roof construction.
Response: The scope of work only entails the existing shed and not the main building roof.
5) E-1-2
Note #14 calls for supplying a 150A disconnect switch while the single line diagram (E-2-3 Note #14) calls for supplying a 150A disconnect switch.
Response: The contractor is to supply and install all disconnect switches.
6) E-2-3 Single Line Diagram There are multiple transformer feeds calling for a 4-wire feed. Can the feeds to the transformers be 3-wire?
Response: Yes, the feeds to the transformers can be 3-wire.
Cable schedule calls for #8 conductors for a 100A feed. Should these be #3 conductors?
Response: Yes, use #3 AWG conductors.
Single Line Diagram calls for a 400A feed to ATS-RSB which is rated at 200A.
Response: Revise ATS from 200A to 400A.
7) E-2-4 (Single Line)
Note #2 calls for transformer T-P-PNL to be a 75KVA. Sheet E-1-3 calls for a 45KVA.
Response: New panel P-PNL is a 100A panel. 45KVA transformer is sufficient.
8) The drawings identify 200-square feet of Spray-on Fire Proofing in Room B10 on the north wall near air handling units. The pipe end sealant on insulated piping, pipe wrap on insulated piping throughout;
white sealant on insulated duct work throughout and finish top coat in Jury Room 910C are called out.
In regards to throughout, are all the materials identified to be abated? A quantity for the fire proofing was provided, but nothing else. Is there other ACM to be abated besides the fire proofing?
Response:
Abatement is not required if areas identified in the hazardous materials report as hazardous are not disturbed or affected during construction. Please review the hazardous materials report for a list of these areas.
9) Drawing A-1-01 Partial Demolition Plan First Floor Level, MD-1-1 Generator Demolition Plan –
Basement; FP-0-1 – Hazardous Material Report; and FPD-1-1 and FPD-2-1 Basement Fire Protection Plan all possibly include areas where the fire proofing, pipe insulation and/or end cap materials may need addressed. But nothing is specifically called out. Can you please clarify the scope of the abatement?
Response:
Abatement is not required if areas identified in the hazardous materials report as hazardous are not disturbed or affected during construction. Please review the hazardous materials report for a list of these areas.
10) Drawings E-1-2 and E-2-9 have missing information. On E-1-2 there are arrows with no notes and E-
2-9 has coded notes in which the tail ends of the sentences are cut off. Can you please forward corrected drawings?
Response:
Will adjust columns in coded note list, sheet E-2-9 & replot. Sheet E-1-2, Please verify you are referencing the latest drawing revision: “100% REVISED CONSTRUCTION DOCUMENTS” issued 07/15/2022. All leaders on drawing E-1-2 have accompanying annotations.
11) 3.4 – The alternator shall support 1020 sKVA with a maximum voltage dip of 30% - Could you please bump this value up to 1,720 minimum sKAVA value at 30%?
Response:
The specifications will be revised with a future bid amendment. Please refer to the revised specifications once issued.
Updated Note: There are no changes to the specification section.
12) 3.6 - The alternator shall meet temperature rise standards of UL2200 (120 degrees C). The insulation system material shall be class "H" capable of withstanding 150 degrees C temperature rise. – With a temp rise so high, the generator life will be decreased and run VERY HOT – CAT NG generator will be 105 degrees which will lengthen the life of the generator and run cooler.
Response:
The specifications will be revised with a future bid amendment. Please refer to the revised
13) 5.1 - The UL2200 approved generator package shall incorporate four (4) factory installed circuit breakers. Three of the breaker shall be 80% rated LSI electronic (600, 400 and 200 amp). The fourth breaker will be 800amp thermal magnetic for load banking purposes. The 400amp breaker is for future use. Distributor or field installed breakers are not acceptable. All line side connections are to be factory installed. Output lugs shall be provided for load side connections. – We can’t provide or have space for four breakers inside of the generator. Could we supply the three way breaker provided by Trystar in the attachment? This will suffice the breakers as well as the loadbank and generator docking station as per the intent of the spec.
Response:
The specifications will be revised with a future bid amendment. Please refer to the revised
14) 7.3A – Supplier of the Genset and associated items shall have permanent service facilities in this trade area. These facilities shall comprise a permanent force of factory trained service personnel on 24 hour call, experienced in servicing this type of equipment, providing warranty and routine maintenance service to afford the owner maximum protection. Delegation of this service responsibility for any of the equipment listed herein will not be considered fulfillment of these specifications. Service contracts shall also be available. – Suggestion to have the service company be located less than 25 miles from the Dayton RICE building for immediate response and have a 24x7X365 call availability.
Response:
The specifications will be revised with a future bid amendment. Please refer to the revised
15) 7.4A - The standby electric generating system components, complete genset and instrumentation panel shall be warranted by the manufacturer against defective materials and factory workmanship for a period of ten (10) years. Such defective parts shall be repaired or replaced at the manufacturer's option, free of charge for parts, labor and travel. – Suggestion to detail the coverage to have the “as shipped consist” as well as rental units available if the issue or parts can’t be located to repair the generator – Similar to the Platinum and Platinum Plus warranty which is attached.
Response:
The specifications will be revised with a future bid amendment. Please refer to the revised
16) Who is the fire protection contractor that performed the most recent upgrades to the fire alarm system?
Response:
Madison Services, Inc.
2833 Lincoln Street, Suite #02. Highland, IN 46322
17) General Note 1 on Sheet M-1-2 directs the contractor to receive pricing from Center Point Energy Company for removal of existing meter and installation of new meter. Center Point Energy Company has indicated that only the account holder may request this information. Please provide direction or an allowance value that can be incorporated into pricing submitted.
Response:
Provide a $45,000 allowance.
18) Note 20 on Sheet MD-1-1 directs the contractor to remove existing energy monitoring device and store for re-installation as shown in plans. This device is scheduled for re-installation per note 9 on sheet M- 1-2. Note 10 on Sheet M-1-2 also calls for a new matching energy monitoring device to be installed on new piping. Please provide make/model information on existing device to be reinstalled.
Response: See following photos.
19) Summary 011000 1.5 K notes “Contractor shall coordinate and contract and pay for all O&M personnel to be on-site for training and shutdowns as required to comply with GSA, local fire department, etc.
requirements.” Given the extent of services required is unknown, and hourly rates as well as O&M protocol for providing said services is unavailable, please provide an allowance value for all bidders to carry.
Response:
Refer to the new specification section 012100 Allowances.
20) Section 011400 Work Restrictions section 1.2.C states work in the basement shall occur during Government occupied hours. Section 1.2.D.2 implies that work shall occur during Government unoccupied hours while U.S. Courts are in session. Please reconfirm 1.2.C general working hours;
work in the basement shall occur during Government occupied hours and that other work inside the building but not in the basement shall occur during Government unoccupied hours.
Response:
All work that is noisy shall be done after building occupied hours. All work in the basement may be performed during normal building occupied hours. All work not in the basement shall be done after normal building occupied hours.
21) Please confirm non disruptive work in mechanical areas of the facility, to include the basement, as well as mechanical/electrical closets on various floors, and at the roof/Penthouse level can occur during Government occupied hours.
Response:
All work that is noisy shall be done after building occupied hours. All work in the basement may be performed during normal building occupied hours. All work not in the basement shall be done after normal building occupied hours.
22) Section 013525 Fire Prevention & Protection in Construction, Alteration, and Demolition Projects item 3.1.E 1 notes “Contractor is responsible for costs of shutdowns including assistance by the building O&M service contractor.” Given the extent of services required is unknown, and hourly rates as well as O&M protocol for providing said services is unavailable, please provide an allowance value for all bidders to carry.
Response:
Refer to the new specification section 012100 Allowances.
23) RFI Clarification:
The intent of the work on the shed is to shorten it so that the new generator and pad can fit in front of it with the required clearances and not impact the parking lot. The work involves removing the existing wall/door and a portion of the shed roof via saw cutting. Then, construct a new wall/door to create a shorter storage building under the existing roof.
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
d. Offers providing less than
STANDARD FORM 1442 (REV. 8/2014)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED PAGE OF PAGES
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and copies to perform the work required are due at the place specified in Item 8 by (hour) Central time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
b. An offer guarantee is, is not required.
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE.
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 8/2014) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
27. PAYMENT WILL BE MADE BY
10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
CLINS DESCRIPTION PRICE
BASE $
ALLOWANCE 01 $
ALLOWANCE 02 $
TOTAL CONTRACT PRICE (Sum of CLINS 0001, 0002 & 0003) $
Company Name:
Authorized Signature:
Date:
PRICE BREAKDOWN - EMERGENCY GENERATOR AND FIRE PUMP REPLACEMENT
The Contractor, having examined the scope of work, plans, specifications and site conditions of the proposed work, hereby proposes to furnish all materials, labor, supplies and supervision to complete the proposed project per contract documents for the total sum stated.
CONTRACTOR INFORMATION
EMERGENCY GENERATOR AND FIRE PUMP REPLACEMENT PCNEPM52751
WALTER H RICE FEDERAL BUILDING, DAYTON OH BID ADDENDUM #2
ALLOWANCES 012100 - 1
PROPERTY OF THE UNITED STATES GOVERNMENT – FOR OFFICIAL USE ONLY
Do not remove this notice – Properly destroy documents when no longer needed
SECTION 012100 - ALLOWANCES
PART 1 - GENERAL
RELATED DOCUMENTS
A. The Government is providing the references included in this sub-section for information purposes only and is not intended to provide a comprehensive, all-inclusive list of any and all potentially relevant portions of the Contract Documents. Drawings and general provisions of the Contract, including Federal Acquisition Regulations (FAR) and General Services Administration Acquisition Regulations (GSAR) contract clauses, and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements governing allowances.
1. Certain items are described in the Contract Documents as allowance items. The purpose of allowance items is to defer selection of actual products and systems to a later date when direction will be provided to the Contractor. The Contracting Officer will issue Modifications to incorporate allowance items in the Work after actual products and systems have been determined.
B. Types of allowance items may include the following :
1. Lump-sum allowance items.
2. Unit-price allowance items.
3. Quantity allowance items.
1.3 SELECTION AND PURCHASE
A. At the earliest practical date after award of the Contract, advise the contracting officer of the date when final selection and purchase of each product or system described by an allowance item must be completed to avoid delaying the Work. Allowances must be included in all schedule submissions
1.4 ACTION SUBMITTALS
A. Submit proposals for products or systems described by allowance items in the form specified for Change Orders.
1.5 INFORMATIONAL SUBMITTALS
A. Submit copies of invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each unit-price and quantity allowance item.
ALLOWANCES 012100 - 2
Do not remove this notice – Properly destroy documents when no longer needed
B. Coordinate and process submittals for allowance items in same manner as for other portions of the Work.
1.6 COORDINATION
A. Coordinate allowance items with other portions of the Work. Furnish templates as required to coordinate installation.
B. Modifications based on an allowance item shall include cost to Contractor of specific products and systems selected by the contracting officer under allowance and shall include taxes, freight, delivery to Project site, Contractor's costs for receiving and handling at Project site, labor, installation, overhead, and profit.
1. If requested by the contracting officer, purchase additional quantities under unit-price or quantity allowances and prepare unused material for storage by Contracting officer. Deliver unused material to Contracting officer's storage space as directed.
1.7 ADJUSTMENT OF ALLOWANCE ITEMS
A. Modifications to an allowance item shall comply with the changes clauses and any other contract modifications procedures found in the Contract Documents.
B. Contracting officer reserves the right to establish the quantity of work-in-place by independent quantity survey, measure, or count.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine products covered by an allowance item promptly on delivery for damage or defects. Return damaged or defective products to manufacturer for replacement.
3.2 PREPARATION
A. Coordinate materials and their installation for each allowance item with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.
ALLOWANCES 012100 - 3
Do not remove this notice – Properly destroy documents when no longer needed
3.3 SCHEDULE OF ALLOWANCE ITEMS
A. Allowance Item No. 01: General Note 1 on Sheet M-1-2 directs the contractor to receive pricing from Center Point Energy Company for removal of existing meter and installation of new meter. Lump Sum Allowance (not to exceed): $45,000.00.
B. Allowance Item No. 02: Summary 011000 1.5 K notes “Contractor shall coordinate and contract and pay for all O&M personnel to be on-site for training and shutdowns as required to comply with GSA, local fire department, etc. requirements.” Section 013525 Fire Prevention & Protection in Construction, Alteration, and Demolition Projects item 3.1.E 1 notes “Contractor is responsible for costs of shutdowns including assistance by the building O&M service contractor.” Lump Sum Allowance (not to exceed):
$10,000.00.
END OF SECTION 012100
GSA EMERGENCY GENERATOR AND FIRE PUMP REPLACEMENT
WALTER H RICE FEDERAL BUILDING, DAYTON OH
PCNEPM52751
BID ADDENDUM #2
Updates to documents for BID ADDENDUM #2 submission. 1
Do not remove this notice – Properly destroy documents when no longer needed
UPDATES TO DOCUMENTS FOR BID ADDENDUM #2
September 16, 2022
The following sheets have been updated.
MECHANICAL
1. Drawing MD-1-1
a. Coded notes updated.
2. Drawing M-1-1
a. Coded noted updated.
3. Drawing M-2-1
a. Unchanged
ELECTRICAL
4. Drawing E-0-1
a. Unchanged
5. Drawing ED-1-1
a. Update to basement fire protection demolition plan callouts
b. Update demo note
6. Drawing E-1-1
a. Add note to generator footprint detail
7. Drawing E-1-2
a. Revised coded note 14
8. Drawing E-2-3
a. Revised new transformers to show 3-wire primary
9. Drawing E-2-4
a. Revised new transformers to show 3-wire primary
b. Revised transformer to 45kVA
10. Drawing E-2-9
a. Revised RSB ATS switch from 200A to 400A
FIRE PROTECTION
11. Drawing FP-0-1
a. Unchanged
12. Drawing FPD-1-1
a. Update to basement fire protection demolition plan callouts
b. Update to cross connection detail
i. Update demo plan to reflect removal of inaccurate pipes
ii. Update detail callouts
GSA EMERGENCY GENERATOR AND FIRE PUMP REPLACEMENT
WALTER H RICE FEDERAL BUILDING, DAYTON OH
PCNEPM52751
BID ADDENDUM #2
Updates to documents for BID ADDENDUM #2 submission. 2
Do not remove this notice – Properly destroy documents when no longer needed
13. Drawing FPD-2-1
a. New detail added to sheet
i. Include new pipe demo schematic
ii. Modify basement fire protection demolition plan to reflect demo schematic
b. Update to basement fire protection demolition plan callouts
c. Update to coded notes
14. Drawing FP-1-1
a. Update to basement fire protection plan callouts
b. Add cross connection detail
i. Update demo plan to reflect removal of inaccurate pipes
ii. Update detail callouts
15. Drawing FP-2-1
a. New detail added to sheet
i. Include new pipe demo schematic
ii. Modify basement fire protection plan to reflect demo schematic
b. Update to basement fire protection plan callouts
c. Update to coded notes
16. Drawing FP-3-1
a. Update to fire protection schematic
17. Added specification section 012100 Allowances.
END OF SECTION
MECH.
B13
DN
STORAGE
SHED
MECH.
B11
R M
G 3PSI
G
H
P
EX 3"
EX 2"
EX 2"
V
V
V
G HP
CODED NOTES
1. REMOVE DIESEL FUEL STORAGE TANK AND CONCRETE PAD LOCATED AT
GROUND LEVEL IN PARKING LOT.
2. REMOVE 1" DIESEL FUEL PIPING FROM STORAGE TANK TO DAY TANK LOCATED
IN BASEMENT.
3. REMOVE DIESEL FUEL DAY TANK
4. REMOVE 1" DIESEL FUEL PIPING FROM DAY TANK TO GENERATOR
5. REMOVE DOMESTIC WATER BACKFLOW PREVENTER
6. REMOVE DOMESTIC WATER PIPING FROM SUPPLY PIPING IN CORRIDOR AND
FROM BACKFLOW PREVENTER TO GENERATOR HEAT EXCHANGER.
7. CAP REMAINING DOMESTIC WATER SUPPLY PIPING IN CORRIDOR
8. REMOVE GENERATOR EXHAUST PIPE MUFFLER
9. REMOVE 8" GENERATOR EXHAUST PIPING
10. CAP REMAINING EXHAUST PIPING AT STAIRWELL WALL AND ABOVE ROOF.
ABANDON PIPING INSIDE STORAGE BUILDING CHASE IN PLACE.
11. EXISTING GAS PRESSURE REGULATOR VENT PIPING TO REMAIN
12. EXISTING 3PSI GAS PIPING TO BUILDING TO REMAIN
13. EXISTING GAS METER TO BE REMOVED BY GAS COMPANY
14. EXISTING GAS REGULATOR TO BE REMOVED BY GAS COMPANY
15. EXISTING HIGH PRESSURE GAS SERVICE PIPING TO BE REMOVED BY GAS
COMPANY
16. EXISTING 3 PSI GAS PIPING TO BE REMOVED BY CONTRACTOR
17. EXISTING REGULATOR VENT PIPING TO BE REMOVED BY CONTRACTOR
18. EXISTING RELIEF VENT PIPING TO BE REMOVED BY CONTRACTOR
19. REMOVE EXISTING VENT PIPING EXTENDING ABOVE GRADE.
20. REMOVE EXISTING ENERGY MONITORING DEVICE AND STORE FOR
RE-INSTALLATION AS SHOWN IN PLANS. (INTECK MODEL #100G DLS
DATALOGGING ERT MODULE)
HARDLINES DESIGN
METRO CD ENGINEERING
24 X 36
45402-1443OHDAYTON
200 W SECOND STREET
RICE FEDERAL BUILDING
A. ADEJOBI
GENERATOR AND FIRE PUMP REPLACEMENT
ISSUED FOR
BID ADDENDUM 2
09/16/2022
CDN
M
MECHANICAL DEMOLITION PLANS
MD-1-1
SCALE: 1/8" = 1'-0"
GENERATOR DEMOLITION PLAN-BASEMENT (WEST)
M1
N
SYMBOL LEGEND
* ALL SYMBOLS MAY NOT BE USED
PIPE UP
PIPE DOWN
OBJECTS TO BE REMOVED
EXISTING OBJECTS TO REMAIN
PIPE TEE BRANCH UP
PIPE TEE BRANCH DOWN
SHUTOFF VALVE
OS&Y VALVE
NATURAL GAS REGULATOR
NEW WORK TO BE PROVIDED
NATURAL GAS PIPING, HIGH PRESSURE
NATURAL GAS PIPING, PRESSURE INDICATED
NATURAL GAS VENT PIPING
CONNECT TO EXISTING
SCALE: NONE
EXISTING NATURAL GAS METER ASSEMBLY
M2
EXISTING OWNER DEVICE
TO BE REMOVED
REGULATOR
METER
VENT PIPING
SCALE: 1/8" = 1'-0"
GAS METER DEMOLITION PLAN-BASEMENT (EAST)
M1
N
G HP
G 3PSI
V
GENERAL NOTES
1. THE CONTRACTOR SHALL INCLUDE IN HIS BID THE COST FOR CENTER POINT
ENERGY COMPANY TO REMOVE THE EXISTING NATURAL GAS METER AND
ASSOCIATED PIPING; AND TO PROVIDE AND INSTALL THE REPLACEMENT DUAL
NATURAL GAS METER MANIFOLD.
2. THE CONTRACTOR SHALL COORDINATE PHASING OF DEMOLITION AND
CONSTRUCTION WORK WITH THE GSA AND CENTER POINT ENERGY COMPANY
TO MINIMIZE DISRUPTION OF NATURAL GAS SERVICE TO THE BUILDING AND
OPERATIONAL READINESS OF THE EMERGENCY GENERATOR
HIGH PRESSURE
SERVICE PIPING
3PSI BUILDING
SUPPLY PIPING
MICHAEL
CHOW
E-64993
S
T
A
T
E
OF
O
H
I
O
R
E
G
I
S T
E
R
E
D
P
R
O
F
E
S
S
I
O
N
AL
E
N
G
I
N
E
E
R
AutoCAD SHX Text L
AutoCAD SHX Text K
AutoCAD SHX Text M
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text D
AutoCAD SHX Text C
AutoCAD SHX Text B
AutoCAD SHX Text A
AutoCAD SHX Text
FOR OFFICIAL USE ONLY
AutoCAD SHX Text
UNITED STATES GOVERNMENT
AutoCAD SHX Text
PROPERTY OF THE
AutoCAD SHX Text
GREAT LAKES REGION 5
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
OF
AutoCAD SHX Text
DISCIPLINE
AutoCAD SHX Text
DRAWING NO.
AutoCAD SHX Text
DRAWN BY
AutoCAD SHX Text
DATE
AutoCAD SHX Text
PCN NO.
AutoCAD SHX Text
GSA PM
AutoCAD SHX Text
PROJ. DESC.
AutoCAD SHX Text
BLDG NO.
AutoCAD SHX Text
CITY/ST./ZIP
AutoCAD SHX Text
STREET
AutoCAD SHX Text
BLDG NAME
AutoCAD SHX Text
MARK
AutoCAD SHX Text
FLOOR NO.
AutoCAD SHX Text
DATE
AutoCAD SHX Text
DESCRIPTION
AutoCAD SHX Text
REVISION
AutoCAD SHX Text
TITLE
AutoCAD SHX Text
GENERAL SERVICES ADMINISTRATION
AutoCAD SHX Text
SHEET DESIGNATOR
AutoCAD SHX Text SENSITIVE BUT UNCLASSIFIED (SBU) - PROPERTY OF THE UNITED STATES GOVERNMENT. COPYING, DISSEMINATION, OR DISTRIBUTION OF THESE DRAWINGS, PLANS, OR SPECIFICATIONS TO UNAUTHORIZED PERSONS IS PROHIBITED. Do not remove this notice. Properly destroy documents when no longer needed.
AutoCAD SHX Text
SHEET SIZE
AutoCAD SHX Text
SUB A/E
AutoCAD SHX Text
PRIME A/E
AutoCAD SHX Text
CONS. CONTR.
AutoCAD SHX Text
A/E CON. NO.
AutoCAD SHX Text
CONTRACTORS
AutoCAD SHX Text
CONSTR. CON.
AutoCAD SHX Text
A/E TASK NO.
AutoCAD SHX Text
CONS. WORK
AutoCAD SHX Text
CONTRACTOR INFO
AutoCAD SHX Text
GENERAL SERVICES ADMINISTRATION
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
230 S. DEARBORN, CHICAGO IL
AutoCAD SHX Text
OH0195ZZ
AutoCAD SHX Text
EPM52751
AutoCAD SHX Text
AutoCAD SHX Text
BSMT
AutoCAD SHX Text 09/16/2022
AutoCAD SHX Text
AutoCAD SHX Text
REVISION
AutoCAD SHX Text 09/16/2022
AutoCAD SHX Text
LIMITED OFFICIAL USE ONLY
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 8'
AutoCAD SHX Text 16'
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 8'
AutoCAD SHX Text 16'
AutoCAD SHX Text
B12
MECH.
B34
MECH.
B13
STAIR
ST4-B1
MECH.
B11
LOCKERS
B18A
ELEC.
B14
2 3
2"
EX 3"
G
P S
I
G
P S
I
SEE SHEET M1-2
FOR CONTINUATION
STAIR
EXISTING
SHED
EX. MAN
HOLE
EXISTING
GUARD
BOOTH
EXISTING
BUILDING
EXISTING
PARKING LOT
PARKING
#34
GENERATOR
G
2"
3"
HARDLINES DESIGN
METRO CD ENGINEERING
24 X 36
45402-1443OHDAYTON
200 W SECOND STREET
RICE FEDERAL BUILDING
A. ADEJOBI
GENERATOR AND FIRE PUMP REPLACEMENT
ISSUED FOR
BID ADDENDUM 2
09/16/2022
CDN
M
MECHANICAL PLANS WEST
M-1-1
Scale: 1/8" = 1'-0"
BASEMENT MECHANICAL PLAN WEST
M-1-1
N
CODED NOTES
1. NEW NATURAL GAS PIPING THRU WALL ABOVE DOOR AT APPROX. ELEVATION
OF 9'-0 A.F.F.
2. EXISTING PROPELLER WALL FAN TO REMAIN
3. EXISTING DE-ACTIVATED VENTILATION AIR INLET SHUTTER TO REMAIN
4. EXISTING VENTILATION TUNNELS BELOW GRADE TO AREA WELL
5. EXISTING EXHAUST HOOD TO REMAIN
6. NEW NATURAL GAS PIPING UP TO GENERATOR AT GROUND LEVEL.
7. NATURAL GAS PIPING UP FROM AREA WELL AT BASEMENT LEVEL. ROUTE
THRU STORAGE SHED WALL AT APPROX. 7'-0" A.F.F.
8. SUPPORT NATURAL GAS PIPING FROM CONCRETE PARKING LOT WALL.
9. PROVIDE PIPE SUPPORT STAND FOR NATURAL GAS PIPING AT ELBOW WHERE
PIPING TURNS HORIZONTAL.
10. PROVIDE PRESSURE REGULATOR: 6000 CFH, 2 PSIG INLET, 10 IN. WC. OUTLET.
INCREASE PIPE SIZE TO 3" DOWNSTREAM OF REGULATOR.
11. EXISTING 3" NATURAL GAS PIPING TO HEATING AND WATER HEATING
EQUIPMENT
GENERAL NOTES
1. THE CONTRACTOR SHALL INCLUDE IN HIS BID THE COST FOR CENTER POINT
ENERGY COMPANY TO REMOVE THE EXISTING NATURAL GAS METER AND
ASSOCIATED PIPING; AND TO PROVIDE AND INSTALL THE REPLACEMENT DUAL
NATURAL GAS METER MANIFOLD.
2. THE CONTRACTOR SHALL COORDINATE PHASING OF DEMOLITION AND
CONSTRUCTION WORK WITH THE GSA AND CENTER POINT ENERGY COMPANY
TO MINIMIZE DISRUPTION OF NATURAL GAS SERVICE TO THE BUILDING AND
OPERATIONAL READINESS OF THE EMERGENCY GENERATOR
SYMBOL LEGEND
* ALL SYMBOLS MAY NOT BE USED
PIPE UP
PIPE DOWN
OBJECTS TO BE REMOVED
EXISTING OBJECTS TO REMAIN
PIPE TEE BRANCH UP
PIPE TEE BRANCH DOWN
SHUTOFF VALVE
OS&Y VALVE
NATURAL GAS REGULATOR
NEW WORK TO BE PROVIDED
NATURAL GAS PIPING, HIGH PRESSURE
NATURAL GAS PIPING, PRESSURE INDICATED
NATURAL GAS VENT PIPING
CONNECT TO EXISTING
G HP
G 3PSI
V
Scale: 1/8" = 1'-0"
GRADE LEVEL MECHANICAL PLAN WEST
M-1-1
N
MICHAEL
CHOW
E-64993
S
T
A
T
E
OF
O
H
I
O
R
E
G
I
S T
E
R
E
D
P
R
O
F
E
S
S
I
O
N
AL
E
N
G
I
N
E
E
R
AutoCAD SHX Text
UP
AutoCAD SHX Text
UNEXCAVATED
AutoCAD SHX Text L
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
FOR OFFICIAL USE ONLY
AutoCAD SHX Text
UNITED STATES GOVERNMENT
AutoCAD SHX Text
PROPERTY OF THE
AutoCAD SHX Text
GREAT LAKES REGION 5
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
OF
AutoCAD SHX Text
DISCIPLINE
AutoCAD SHX Text
DRAWING NO.
AutoCAD SHX Text
DRAWN BY
AutoCAD SHX Text
DATE
AutoCAD SHX Text
PCN NO.
AutoCAD SHX Text
GSA PM
AutoCAD SHX Text
PROJ. DESC.
AutoCAD SHX Text
BLDG NO.
AutoCAD SHX Text
CITY/ST./ZIP
AutoCAD SHX Text
STREET
AutoCAD SHX Text
BLDG NAME
AutoCAD SHX Text
MARK
AutoCAD SHX Text
FLOOR NO.
AutoCAD SHX Text
DATE
AutoCAD SHX Text
DESCRIPTION
AutoCAD SHX Text
REVISION
AutoCAD SHX Text
TITLE
AutoCAD SHX Text
GENERAL SERVICES ADMINISTRATION
AutoCAD SHX Text
SHEET DESIGNATOR
AutoCAD SHX Text SENSITIVE BUT UNCLASSIFIED (SBU) - PROPERTY OF THE UNITED STATES GOVERNMENT. COPYING, DISSEMINATION, OR DISTRIBUTION OF THESE DRAWINGS, PLANS, OR SPECIFICATIONS TO UNAUTHORIZED PERSONS IS PROHIBITED. Do not remove this notice. Properly destroy documents when no longer needed.
AutoCAD SHX Text
SHEET SIZE
AutoCAD SHX Text
SUB A/E
AutoCAD SHX Text
PRIME A/E
AutoCAD SHX Text
CONS. CONTR.
AutoCAD SHX Text
A/E CON. NO.
AutoCAD SHX Text
CONTRACTORS
AutoCAD SHX Text
CONSTR. CON.
AutoCAD SHX Text
A/E TASK NO.
AutoCAD SHX Text
CONS. WORK
AutoCAD SHX Text
CONTRACTOR INFO
AutoCAD SHX Text
GENERAL SERVICES ADMINISTRATION
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
230 S. DEARBORN, CHICAGO IL
AutoCAD SHX Text
OH0195ZZ
AutoCAD SHX Text
EPM52751
AutoCAD SHX Text
AutoCAD SHX Text
BSMT
AutoCAD SHX Text 09/16/2022
AutoCAD SHX Text
AutoCAD SHX Text
REVISION
AutoCAD SHX Text 09/16/2022
AutoCAD SHX Text
LIMITED OFFICIAL USE ONLY
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 8'
AutoCAD SHX Text 16'
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 8'
16'
TELE.
B09
MECH.
BMA
VERT. PEN.
VP1-B1
STORAGE
B4
EX 3"
G
P
S I
G
P
S I
2"
3"
SEE SHEET M1-1
FOR CONTINUATION
SIDEWALK
GRAVEL AREA
AREA WELL
WILKINSON ST.
G 3PSI
G 3PSI
2"
3"
PARKING LOT
HARDLINES DESIGN
METRO CD ENGINEERING
24 X 36
45402-1443OHDAYTON
200 W SECOND STREET
RICE FEDERAL BUILDING
A. ADEJOBI
GENERATOR AND FIRE PUMP REPLACEMENT
ISSUED FOR
BID ADDENDUM 2
09/16/2022
Scale: 1/8" = 1'-0"
BASEMENT MECHANICAL PLAN EAST
M-1-2
N
CDN
M
MECHANICAL PLANS EAST
M-1-2
CODED NOTES
1. EXISTING NATURAL GAS PIPING TO BUILDING TO REMAIN
2. NEW NATURAL GAS PIPING ROUTED THRU BASEMENT TO NEW GENERATOR
3. NEW GAS PIPING FROM GAS METER ALONG EXISTING WALL, DROPS DOWN
UNDERGROUND INTO BUILDING THROUGH BASEMENT WALL.
4. NATURAL GAS REGULATOR BY GAS COMPANY
5. BUILDING GAS METER BY GAS COMPANY
6. GENERATOR GAS METER BY GAS COMPANY
7. CONNECT NEW 3" GAS PIPE INTO EXISTING PIPE.
8. NEW NATURAL GAS PIPING THRU WALL ABOVE DOOR AT APPROX. ELEVATION
OF 9'-0 A.F.F.
9. RE-INSTALL ENERGY MONITORING DEVICE REMOVED DURING DEMOLITION.
SEE SHEET MD-1-1 (INTECK MODEL #100G DLS DATALOGGING ERT MODULE)
10. INSTALL NEW ENERGY MONITORING DEVICE, MATCH EXISTING, MAKE ALL
FINAL CONNECTIONS. (INTECK MODEL #100G DLS DATALOGGING ERT
MODULE)
11.
12. NEW FENCE, SEE ARCHITECTURAL PLANS FOR DETAILS.
13. NEW BOLLARDS, SEE ARCHITECTURAL PLANS FOR DETAILS.
GENERAL NOTES
1. THE CONTRACTOR SHALL INCLUDE IN HIS BID THE COST FOR CENTER POINT
ENERGY COMPANY TO REMOVE THE EXISTING NATURAL GAS METER AND
ASSOCIATED PIPING; AND TO PROVIDE AND INSTALL THE REPLACEMENT DUAL
NATURAL GAS METER MANIFOLD.
2. THE CONTRACTOR SHALL COORDINATE PHASING OF DEMOLITION AND
CONSTRUCTION WORK WITH THE GSA AND CENTER POINT ENERGY COMPANY
TO MINIMIZE DISRUPTION OF NATURAL GAS SERVICE TO THE BUILDING AND
OPERATIONAL READINESS OF THE EMERGENCY GENERATOR
SCALE: NONE
REPLACEMENT NATURAL GAS METER ASSEMBLY
M-1-2
PLUG VALVE
REGULATOR
RELIEF VALVE
RELIEF VENT
UP TO 8'-0"
ABOVE GRADE
PLUG VALVE
PLUG VALVE
PLUG VALVE
BUILDING
METER
GENERATOR
METER
CONNECT TO
EXISTING BUILDING
SUPPLY PIPING IN
BASEMENT
EXISTING GRADE
ROUTE THRU
BUILDING BASEMENT
TO GENERATOR
ENTIRE METER MANIFOLD ASSEMBLY
PROVIDED AND INSTALLED BY THE
NATURAL GAS COMPANY
2"
3"
Scale: 1/4" = 1'-0"
GROUND LEVEL MECHANICAL PLAN EAST
M-1-2
N
KEY PLAN
MICHAEL
CHOW
E-64993
S
T
A
T
E
OF
O
H
I
O
R
E
G
I
S T
E
R
E
D
P
R
O
F
E
S
S
I
O
N
A L
E
N
G
I
N
E
E
R
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text B
AutoCAD SHX Text A
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 8'
AutoCAD SHX Text 16'
AutoCAD SHX Text
FOR OFFICIAL USE ONLY
AutoCAD SHX Text
UNITED STATES GOVERNMENT
AutoCAD SHX Text
PROPERTY OF THE
AutoCAD SHX Text
GREAT LAKES REGION 5
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
OF
AutoCAD SHX Text
DISCIPLINE
AutoCAD SHX Text
DRAWING NO.
AutoCAD SHX Text
DRAWN BY
AutoCAD SHX Text
DATE
AutoCAD SHX Text
PCN NO.
AutoCAD SHX Text
GSA PM
AutoCAD SHX Text
PROJ. DESC.
AutoCAD SHX Text
BLDG NO.
AutoCAD SHX Text
CITY/ST./ZIP
AutoCAD SHX Text
STREET
AutoCAD SHX Text
BLDG NAME
AutoCAD SHX Text
MARK
AutoCAD SHX Text
FLOOR NO.
AutoCAD SHX Text
DATE
AutoCAD SHX Text
DESCRIPTION
AutoCAD SHX Text
REVISION
AutoCAD SHX Text
TITLE
AutoCAD SHX Text
GENERAL SERVICES ADMINISTRATION
AutoCAD SHX Text
SHEET DESIGNATOR
AutoCAD SHX Text SENSITIVE BUT UNCLASSIFIED (SBU) - PROPERTY OF THE UNITED STATES GOVERNMENT. COPYING, DISSEMINATION, OR DISTRIBUTION OF THESE DRAWINGS, PLANS, OR SPECIFICATIONS TO UNAUTHORIZED PERSONS IS PROHIBITED. Do not remove this notice. Properly destroy documents when no longer needed.
AutoCAD SHX Text
SHEET SIZE
AutoCAD SHX Text
SUB A/E
AutoCAD SHX Text
PRIME A/E
AutoCAD SHX Text
CONS. CONTR.
AutoCAD SHX Text
A/E CON. NO.
AutoCAD SHX Text
CONTRACTORS
AutoCAD SHX Text
CONSTR. CON.
AutoCAD SHX Text
A/E TASK NO.
AutoCAD SHX Text
CONS. WORK
AutoCAD SHX Text
CONTRACTOR INFO
AutoCAD SHX Text
GENERAL SERVICES ADMINISTRATION
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
230 S. DEARBORN, CHICAGO IL
AutoCAD SHX Text
OH0195ZZ
AutoCAD SHX Text
EPM52751
AutoCAD SHX Text
AutoCAD SHX Text
BSMT
AutoCAD SHX Text 09/16/2022
AutoCAD SHX Text
AutoCAD SHX Text
REVISION
AutoCAD SHX Text 09/16/2022
AutoCAD SHX Text
LIMITED OFFICIAL USE ONLY
AutoCAD SHX Text
PLUG VALVE TYP OF 4
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 4'
AutoCAD SHX Text 8'
AutoCAD SHX Text
UP
AutoCAD SHX Text
DN
AutoCAD SHX Text
DN
AutoCAD SHX Text
UP
AutoCAD SHX Text
DN
AutoCAD SHX Text
DN
AutoCAD SHX Text
DN
AutoCAD SHX Text
AREAWAY
STAIR
ST4-B1
EX.ATS
41'-9 1/2"
5'-9"
EXIST
EXIST
EXIST.
PIPING
EXIST.
MECH.
REMOVE EXISTING GENERATOR,
BATTERY, CONCRETE PAD AND
ALL EXISTING COMPONENTS
AFTER INSTALLATION AND
TESTING OF NEW GENERATOR
AND COMPONENTS
XFMR
EXISTING PULL
BOXES
TO REMAIN
EXISTING PANEL BH
120/208V,3Ø,4W
EXISTING
PANEL 8A
277/480V,3Ø,4W
EXISTING 3,000A
SWITCHBOARD
277/480V,3Ø,4W
EXISTING 500A
EMERGENCY
277/480V,3Ø,4W
SECTION
EXISTING
BUCKET
TOOL
EXISTING
METER
EXISTING
EQUIPMENT
EXISTING
TRANSFORMER
REMOVE EXISTING ATS, CONCRETE
PAD AND ALL EXISTING COMPONENTS
AFTER INSTALLATION AND TESTING OF
NEW GENERATOR AND COMPONENTS.
CONTRACTOR SHALL COORDINATE,
SECURE AND PAY FOR ALL COSTS
INCLUDING PERMITS REQUIRED TO
REMOVE THE EXISTING GENERATOR
AND OTHER EQUIPMENT. THIS
INCLUDES ANY CRANE RENTALS,
PERMITTING REQUIREMENTS, O&M
COSTS, ROAD TRAFFIC SHUTDOWNS,
ETC. PATCH AND PAINT CONCRETE TO
MATCH EXISTING
REMOVE EXISTING GENERATOR
REMOTE TESTING COMPONENTS
AFTER INSTALLATION AND
TESTING OF NEW GENERATOR
AND COMPONENTS
EXISTING PANEL BC
120/208V,3Ø,4W
EXISTING
MECHANICAL
ROOM
B13
EXISTING WALL FAN AND CONTROL
DISCONNECT SWITCH TO REMAIN
E X
I S
T I N
G
V F
D S
EXISTING INLET SHUTTER TO
REMAIN
EXISTING PROPELLER
WALL FAN TO REMAIN
EXISTING
POWER
LOGIC
EXISTING
EMG PANEL
BXD AND
DISCONNECT
#2#1
FIRE PUMP
SEWAGE PUMPS
FIRE PUMP CONTROL
PANEL AND
AUTOMATIC
TRANSFER SWITCH.
DEMO CONDUIT AND CONDUCTOR
FROM (E)FIRE-PUMP & (E)JOCKEY
PUMP AND CONTROLS, BACK TO
(E)EMERGENCY SWITCHBOARD
JOCKEY PUMP
DEMO CONDUIT AND
CONDUCTOR BETWEEN
GENERATOR (E)ATS
SWITCHES AND MAIN
SWITCHBOARD
(E)SEWAGE PUMPS 1& 2
& STORM PUMP, DEMO
CONDUCTOR AND
CONDUIT BACK TO
(E)PANEL BXA
DEMO CONDUIT AND CONDUCTOR
BETWEEN (E)MCC-SECTION J AND
(E)EMERGENCY SWITCHBOARD
HARDLINES DESIGN
METRO CD ENGINEERING
24 X 36
45402-1443OHDAYTON
200 W SECOND STREET
RICE FEDERAL BUILDING
A. ADEJOBI
GENERATOR AND FIRE PUMP REPLACEMENT
ISSUED FOR
BID ADDENDUM 2
09/16/2022
MICHAEL
CHOW
E-64993
S
T
A
T
E
OF
O
H
I
O
R
E
G
I
S T
E
R
E
D
P
R
O
F
E
S
S
I
O
N
AL
E
N
G
I
N
E
E
R
RLK
E
ELECTRICAL BASEMENT DEMO PLAN
ED-1-1
SCALE: 1/4" = 1'-0"
ELECTRICAL BASEMENT DEMOLITION PLAN
ED-1
N
AutoCAD SHX Text L
AutoCAD SHX Text H
AutoCAD SHX Text J
AutoCAD SHX Text K
AutoCAD SHX Text M
AutoCAD SHX Text
UP
AutoCAD SHX Text
UNEXCAVATED
AutoCAD SHX Text
FOR OFFICIAL USE ONLY
AutoCAD SHX Text
UNITED STATES GOVERNMENT
AutoCAD SHX Text
PROPERTY OF THE
AutoCAD SHX Text
GREAT LAKES REGION 5
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
OF
AutoCAD SHX Text
DISCIPLINE
AutoCAD SHX Text
DRAWING NO.
AutoCAD SHX Text
DRAWN BY
AutoCAD SHX Text
DATE
AutoCAD SHX Text
PCN NO.
AutoCAD SHX Text
GSA PM
AutoCAD SHX Text
PROJ. DESC.
AutoCAD SHX Text
BLDG NO.
AutoCAD SHX Text
CITY/ST./ZIP
AutoCAD SHX Text
STREET
AutoCAD SHX Text
BLDG NAME
AutoCAD SHX Text
MARK
AutoCAD SHX Text
FLOOR NO.
AutoCAD SHX Text
DATE
AutoCAD SHX Text
DESCRIPTION
AutoCAD SHX Text
REVISION
AutoCAD SHX Text
TITLE
AutoCAD SHX Text
GENERAL SERVICES ADMINISTRATION
AutoCAD SHX Text
SHEET DESIGNATOR
AutoCAD SHX Text SENSITIVE BUT UNCLASSIFIED (SBU) - PROPERTY OF THE UNITED STATES GOVERNMENT. COPYING, DISSEMINATION, OR DISTRIBUTION OF THESE DRAWINGS, PLANS, OR SPECIFICATIONS TO UNAUTHORIZED PERSONS IS PROHIBITED. Do not remove this notice. Properly destroy documents when no longer needed.
AutoCAD SHX Text
SHEET SIZE
AutoCAD SHX Text
SUB A/E
AutoCAD SHX Text
PRIME A/E
AutoCAD SHX Text
CONS. CONTR.
AutoCAD SHX Text
A/E CON. NO.
AutoCAD SHX Text
CONTRACTORS
AutoCAD SHX Text
CONSTR. CON.
AutoCAD SHX Text
A/E TASK NO.
AutoCAD SHX Text
CONS. WORK
AutoCAD SHX Text
CONTRACTOR INFO
AutoCAD SHX Text
GENERAL SERVICES ADMINISTRATION
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
230 S. DEARBORN, CHICAGO IL
AutoCAD SHX Text
OH0195ZZ
AutoCAD SHX Text
EPM52751
AutoCAD SHX Text
AutoCAD SHX Text
BSMT
AutoCAD SHX Text 09/16/2022
AutoCAD SHX Text
AutoCAD SHX Text
REVISION
AutoCAD SHX Text 09/16/2022
AutoCAD SHX Text
LIMITED OFFICIAL USE ONLY
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 4'
AutoCAD SHX Text 8'
DN
EXISTING
SHED
EXISTING
GUARD
BOOTH
EXISTING
BUILDING
EXISTING
BUILDING
LOWER
ENTRY
11'-0"
MOVE SHED WALL IN 11'-0"
"A"
"A"
EXISTING
ASPHALT
PARKING #32
NO EXISTING PARKING SPACES WILL BE
REMOVED
GOVERNMENT
TO MOVE
EXISTING
RECYCLING BIN
FROM PARKING
SPOT #32 TO
PARKING SPOT
#34
NEW CONCRETE
GUARD POST .
SEE TYP. BOLLARD
DETAIL THIS SHEET
PARKING #33
PARKING #34
EX. MAN
HOLE
EXISTING DIESEL TANK AND CONCRETE PAD TO BE
DEMOLISHED AND REMOVED IN ITS ENTIRETY
NEW CONCRETE GUARD POST - TYP. OF 3
SEE TYP. BOLLARD DETAIL THIS SHEET
USE BLACK ASPHALT SEALANT TO PAINT OVER EXISTING
PARKING STRIP AS PARKING SPOT #34 WOULD NO
LONGER BE USED
CONTRACTOR TO ENSURE THERE ARE NO CONFLICTS
WITH MANHOLE
NEW SHED WALL AND
6'-4" DOOR ROUGH OPENING
RELOCATE (2) EXISTING
FEEDER CONDUITS FOR
GUARD BOOTH AS
NECESSARY TO AVOID ANY
CONFLICTS
NEW FREE-STANDING
800A
GENERATOR QUICK
CONNECTION BOX
EXISTING DUMPSTER
TO REMAIN
EXISTING SPRINKLER
CONNECTION AND
PROTECTIVE
CONCRETE GUARD
POST
ELECTRICAL CONTRACTOR SHALL RELOCATE EXISTING
SHED LIGHT FIXTURE. EXTEND EXISTING CONDUIT AND
WIRING AS REQUIRED. VERIFY EXACT REQUIREMENTS IN
FIELD PRIOR TO BID AND INCLUDE ALL COSTS IN BID.
ELECTRICAL CONTRACTOR SHALL RELOCATE EXISTING
SHED RECEPTACLE. EXTEND EXISTING CONDUIT AND
WIRING AS REQUIRED. VERIFY EXACT REQUIREMENTS IN
FIELD PRIOR TO BID AND INCLUDE ALL COSTS IN BID.
ELECTRICAL CONTRACTOR SHALL RELOCATE EXISTING
SHED LIGHT SWITCH. EXTEND EXISTING CONDUIT AND
WIRING AS REQUIRED. VERIFY EXACT REQUIREMENTS IN
FIELD PRIOR TO BID AND INCLUDE ALL COSTS IN BID.
MAXIMUM ALLOWABLE
GENERATOR FOOTPRINT. TO
MAINTAIN CORRECT
CLEARANCES, GENERATOR
MUST FIT WITHIN REGION
SHOWN
CONCRETE HOUSE-KEEPING
PAD
3' REQUIRED EQUIPMENT
CLEARANCE
17'-3"
5'-11"
EXISTING GATE
AND POURED
WALL TO
REMAIN
EXISTING
GRADE/
ASPHALT
EXISTING
WALL TO
REMAIN
EXISTING
BUILDING
3'-0"
CLEARANCE
AROUND NEW
GENERATOR
NEW MIN. 7"
CONCRETE PAD
W/ RE-BAR.
EXTEND 18"
AROUND ALL
SIDES OF NEW
GENERATOR
OUTLINE OF NEW SHED WALL
AND 6'-4" DOOR ROUGH OPENING
BEYOND NEW GENERATOR AND
EXISTING DOORS TO REMAIN
NEW
FREE-STANDING
800A
CAMLOCK QUICK
CONNECTION
CABINET ON 4"
CONCRETE
HOUSEKEEPING
PAD
NEW CONCRETE
GUARD POST -
TYP. OF 3. SEE TYP.
BOLLARD DETAIL
THIS SHEET
SYMBOLS / LEGEND
EQUIPMENT
CLEARANCES
CONCRETE
HOUSEKEEPING
EQUIPMENT PAD
EQUIPMENT
FOOTPRINT
HARDLINES DESIGN
METRO CD ENGINEERING
24 X 36
45402-1443OHDAYTON
200 W SECOND STREET
RICE FEDERAL BUILDING
A. ADEJOBI
GENERATOR AND FIRE PUMP REPLACEMENT
ISSUED FOR
BID ADDENDUM 2
09/16/2022
MICHAEL
CHOW
E-64993
S
T
A
T
E
OF
O
H
I
O
R
E
G
I
S T
E
R
E
D
P
R
O
F
E
S
S
I
O
N
AL
E
N
G
I
N
E
E
R
RLK
E
ELECTRICAL GROUND LEVEL PLAN
E-1-1
SCALE: 1/4" = 1'-0"
ELECTRICAL GROUND LEVEL PLAN
E-1-1
N
SCALE: 1/4" = 1'-0"
ELECTRICAL GROUND LEVEL ELEVATION "A"
E-1-1
SCALE: N.T.S.
TYP. CONCRETE BOLLARD DETAIL
E-1-1
CONCRETE CAP
2"
2'-0"
1'-0"
18" DIA.
3'-0"
3'-0"
6"Ø STANDARD GALVANIZED STEEL
PIPE FILLED W/ CONCRETE (APPLY
TWO COATS YELLOW PAINT) MIN. 0.185"
WALL THICKNESS OR 1/8" THICK HIGH
DENSITY POLYETHYLENE (HDPE)
BOLLARD COVER COLOR YELLOW
SLOPE CONCRETE BASE
EXISTING FINISHED SERVICE
AS PER PLANS
CONCRETE FOOTING
AutoCAD SHX Text
FOR OFFICIAL USE ONLY
AutoCAD SHX Text
UNITED STATES GOVERNMENT
AutoCAD SHX Text
PROPERTY OF THE
AutoCAD SHX Text
GREAT LAKES REGION 5
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
OF
AutoCAD SHX Text
DISCIPLINE
AutoCAD SHX Text
DRAWING NO.
AutoCAD SHX Text
DRAWN BY
AutoCAD SHX Text
DATE
AutoCAD SHX Text
PCN NO.
AutoCAD SHX Text
GSA PM
AutoCAD SHX Text
PROJ. DESC.
AutoCAD SHX Text
BLDG NO.
AutoCAD SHX Text
CITY/ST./ZIP
AutoCAD SHX Text
STREET
AutoCAD SHX Text
BLDG NAME
AutoCAD SHX Text
MARK
AutoCAD SHX Text
FLOOR NO.
AutoCAD SHX Text
DATE
AutoCAD SHX Text
DESCRIPTION
AutoCAD SHX Text
REVISION
AutoCAD SHX Text
TITLE
AutoCAD SHX Text
GENERAL SERVICES ADMINISTRATION
AutoCAD SHX Text
SHEET DESIGNATOR
AutoCAD SHX Text SENSITIVE BUT UNCLASSIFIED (SBU) - PROPERTY OF THE UNITED STATES GOVERNMENT. COPYING, DISSEMINATION, OR DISTRIBUTION OF THESE DRAWINGS, PLANS, OR SPECIFICATIONS TO UNAUTHORIZED PERSONS IS PROHIBITED. Do not remove this notice. Properly destroy documents when no longer needed.
AutoCAD SHX Text
SHEET SIZE
AutoCAD SHX Text
SUB A/E
AutoCAD SHX Text
PRIME A/E
AutoCAD SHX Text
CONS. CONTR.
AutoCAD SHX Text
A/E CON. NO.
AutoCAD SHX Text
CONTRACTORS
AutoCAD SHX Text
CONSTR. CON.
AutoCAD SHX Text
A/E TASK NO.
AutoCAD SHX Text
CONS. WORK
AutoCAD SHX Text
CONTRACTOR INFO
AutoCAD SHX Text
GENERAL SERVICES ADMINISTRATION
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
230 S. DEARBORN, CHICAGO IL
AutoCAD SHX Text
OH0195ZZ
AutoCAD SHX Text
EPM52751
AutoCAD SHX Text
AutoCAD SHX Text
BSMT
AutoCAD SHX Text 09/16/2022
AutoCAD SHX Text
AutoCAD SHX Text
REVISION
AutoCAD SHX Text 09/16/2022
AutoCAD SHX Text
LIMITED OFFICIAL USE ONLY
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 4'
AutoCAD SHX Text 8'
SCALE: 1/8"=1'-0"
FREE-STANDING TRANSFER SWITCHES
NEW 600A AUTOMATIC TRANSFER SWITCH -
LIFE SAFETY ATS-LS
UNIT HEIGHT 90"
NEW 4" CONCRETE HOUSEKEEPING PAD -
EXTEND 4" ALL SIDES
42" SIDE CLEARANCE FOR EXISTING FAN
DISCONNECT
37"
8"
40"
30"
8"
1'-8" 2'-5 5/16"
10'-11"
3'-1 5/16"
NEW 600A
MANUAL TRANSFER SWITCH - MTS
UNIT HEIGHT 84"
2'-5"
40" FRONT CLEARANCE FOR DOORS
37" SIDE CLEARANCE FOR LOUVER
NEW 200A AUTOMATIC
TRANSFER SWITCH - REQUIRED STAND-BY
ATS-RSB. UNIT HEIGHT 78.1"
SYMBOLS / LEGEND
EQUIPMENT
CLEARANCES
CONCRETE
HOUSEKEEPING
EQUIPMENT PAD
EQUIPMENT
FOOTPRINT
STAIR
ST4-B1
5'-9"
EXIST
EXIST.
MECH.
NEW 200A AUTOMATIC TRANSFER
SWITCH - REQUIRED STAND-BY ATS-RSB
5'-9"
EXISTING PANEL 8A 277/480V,3Ø,4W
EXISTING 3,000A SWITCHBOARD
277/480V,3Ø,4W
EXISTING EQUIP.
EXISTING TRANSFORMER
EXISTING PANEL BXD 277/480V,3Ø,4W
EXISTING PANEL BXA 277/480V,3Ø,4W
EXISTING ELECTRICAL EQUIPMENT
EXISTING DISCONNECT SWITCH
EXISTING TRANSFORMER T-3 HMT
TWO EXISTING TRANSFORMERS STACKED
EXISTING PANEL BXB 120/208V,3Ø,4W
EXISTING PANEL BC
120/208V,3Ø,4W
EXISTING ELECTRICAL EQUIPMENT
EXISTING ELECTRICAL EQUIPMENT
41'-9 1/2"
EXIST
APPROX. LOCATION IN PARKING LOT
NEW FREE-STANDING 800A
GENERATOR QUICK CONNECTION BOX
NEW
EQUIPMENT
ROOM
B13
NEW 600A MANUAL
TRANSFER SWITCH - MTS
NEW 600A AUTOMATIC
TRANSFER SWITCH -
LIFE SAFETY ATS-LS
RAE
NEW GENERATOR EMERGENCY
STOP BUTTON UNDER EXISTING FAN.
COORDINATE LOCATION IN FIELD
NEW GEN SET REMOTE ANNUNCIATOR UNDER EXISTING FAN
COORDINATE LOCATION IN FIELD
X F
M R
NEW 250A FUSED (DOUBLE LUGS) DISCONNECT SWITCH TO (E)
PNL BXC BASEMENT & (N) PNL RSB-1 IN PENTHOUSE
NEW PANEL RSBDP 200A, 277/480V, 3PH, 4W
NEW 75KVA TRANSFORMER T-RSB
NEW PANEL EMLSDPB 600A, 277/480V, 3P/4W
CONNECT TO NEW 500KW
GENERAC GENERATOR IN
PARKING LOT
EXISTING LOUVER INSTALLED
FLUSH IN WALL. PART OF
TRANSFER SWITCH IS IN FRONT OF
LOUVER BUT TRANSFER SWITCH
SITS 4 INCHES IN FRONT OF WALL.
MAINTAIN 42" WORKING CLEARANCE
FOR EXISTING FAN DISCONNECT
E X
I S
T I N
G
V F
D S
TO NEW REQUIRED STANDBY
PANEL RSB-1 IN PENTHOUSE
MECH RM P1
DEMO CONDUIT AND CONDUCTOR TO
EXISTING TRANSFORMER T-3 HMT
DEMO CONDUIT AND
CONDUCTOR TO EXISTING
PENTHOUSE PANEL PX
CONDUIT
ETR
TO EXISTING
TRANSFORMER
T-X DISCONNECT
ON 1ST FLOOR
FEEDING PANEL
1XB
T-3
HMT
EXISTING POWER LOGIC
EXISTING METER
EXISTING PULL BOXES TO
REMAIN
NEW 277/480V 3P/4W
400A PANEL BA-1
EXISTING BUCKET TOOL
EXIST.
PIPING
EXISTING PANEL BH
120/208V,3Ø,4W
EXISTING 600A EMERGENCY
SECTION 277/480V,3Ø,4W
NEW 120/208V 3P 4W 100A
PANEL BXB-1
NEW 45KVA TRANSFORMER
& 100A 480V 3P/4W FUSED
DISCONNECT T-BXB-1
(E)PANEL BXC
RE-FEED PANEL FROM
RSBDP
E X
I S
T I N
G
M
C C
BD
BDBB
#2#1
EXISTING PANEL BXD
DISC SW
P-2 NEW JOCKEY PUMP
P-1
NEW
FIRE
PUMP
SEWAGE
PUMPS
NEW JOCKEY PUMP CONTROL PANEL.
RELOCATED EXISTING SPRINKLER HEAD CABINETS APPROXIMATE
LOCATION. VERIFY LOCATION WITH EXISTING AND NEW CONDITIONS.
NEW WALL MOUNTED GRUNDFOS-PEERLESS "FIRE CONNECT" FIRE
PUMP MONITORING SYSTEM.
NEW FIRE PUMP CONTROL PANEL AND
AUTOMATIC TRANSFER SWITCH.
DEMO CONDUIT & CONDUCTOR
TO STORM PUMP SP-2, SEWAGE
EJECTOR PUMPS 1 & 2
PROVIDE CONDUCTOR AND CONDUIT
FOR…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .