This is Standard Form 30 (SF 30), Amendment 001 to Solicitation 47PB5126R0018, issued by the General Services Administration's (GSA) Public Buildings Service (PBS) Office of Acquisition Management on October 16, 2026. The amendment modifies the solicitation for General Contractor Services for Elevator Modernization at the Thurgood Marshall U.S. Courthouse in New York, New York.
The amendment incorporates three primary revisions: (1) updates to SF1442 documents for both Prevailing Labor Agreement (PLA) and Non-PLA compliance; (2) modification of the Agreement Document (C101) Section I.C, reducing the required timeframe for Substantial Completion of Work from 2,580 calendar days to 1,440 calendar days from the Notice to Proceed (NTP); and (3) adjustments to Contract Line Item Number (CLIN) schedules and performance durations, establishing a BASE period from 06/15/2027 to 05/25/2031 (1,440 calendar days), followed by six option periods for individual elevator modernization work (Options 01-04 and 05-06) ranging from 180 to 330 calendar days each, and a 60-calendar-day closeout period from 05/25/2031 to 07/24/2031. All other terms, conditions, and specifications of the original solicitation remain unchanged. The amendment is administered by PBS Capital Contracting Branch – Northeast, located at 1900 E Street NW, Washington, DC 20415. Offerors must acknowledge receipt of this amendment prior to the deadline specified in the solicitation.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PQAA
General Contractor for the Elevator Modernization Project at Thurgood Marshall U.S. Courthouse, New York, New York
Please see attached.
PBS Office of Acquisition Management/Capital Project Acquisition Delivery Division Capital Contracting Branch - Northeast 1900 E Street NW Washington, DC 20415 USA
47PB5126R0018
31772
1 3
10/16/2026
10/14/2026
INSTRUCTIONS (Back Page):
Instructions for items other than those that are self-explanatory, are as follows:
Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.
Item 3 (Effective date).
(1)
(2)
(3)
(4)
(5)
For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.
For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.
For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.
For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.
For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.
(a)
(b)
(c)
(d)
(e)
(f)
Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.
Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.
Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.
Item 12 (Accounting and Appropriation Data).
When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:
(2) Accounting classification Net decrease $
Include subject matter or short title of solicitation/contract where feasible.
Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.
(i)
NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".
Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)
Item 14 (Description of Amendment/Modification).
Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.
Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:
(i) Total contract price increased by $
(ii) Total contract price decreased by $
(iii) Total contract price unchanged.
State reason for modification.
When removing, reinstating, or adding funds, identify the contract items and accounting classifications.
(g)
(h)
When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --
(i) A reference to the letter determination; and
(ii) A statement of the net amount determined to be due in settlement of the contract.
(1)
(2)
(3)
(4)
(5)
(6)
STANDARD FORM 30 (REV. 11/2016) BACK
(1) Accounting classification Net increase $
General Contractor for the Elevator Modernization Project at Thurgood Marshall U.S.
Courthouse, New York, New York
Amendment 001 to Solicitation 47PB5126R0018 (General Contractor Services for Elevator Modernization at the Thurgood Marshall U.S. Courthouse, New York, NY) is issued to incorporate the following revisions and updates:
1. Revisions to SF1442 (PLA & NON-PLA):
- Update SF1442 PLA document.
- Update SF1442 NON-PLA document.
2. Revisions to the Agreement Document (C101):
- Section I.C. Period of Performance, Paragraph (2) Substantial Completion: Update the required timeframe to achieve Substantial Completion of the Work from 2580 calendar days to 1440 calendar days from the issuance of the Notice to Proceed (NTP).
3. Updates to CLIN Schedule & Contract Durations:
- Adjust individual Contract Line Item Number (CLIN) descriptions, start/end dates, and performance durations as follows:
• BASE [NTP to SCD]: 06/15/2027 to 05/25/2031 (1440 Calendar Days)
• Option 01 [Elev 19]: 04/10/2028 to 10/07/2028 (180 Calendar Days)
• Option 02 [Elev 20]: 10/07/2028 to 09/02/2029 (330 Calendar Days)
• Option 03 [Elev 21]: 09/02/2029 to 07/29/2030 (330 Calendar Days)
• Option 04 [Elev 18]: 11/26/2030 to 05/25/2031 (180 Calendar Days)
• Option 05 [DD]: 06/15/2027 to 05/25/2031 (1440 Calendar Days)
• Option 06 [TB]: 06/29/2030 to 05/25/2031 (330 Calendar Days)
• Closeout [SCD to CC]: 05/25/2031 to 07/24/2031 (60 Calendar Days)