2. Enclosure 1, Draft Contract 462624.pdf
PDF 248 KB Posted
- Attached to
- RFP 462624 - Power Control & Regulating System for AGS Motor Generator Set (Cycloconverter)
- Solicitation number
- 462624
- Issued by
-
Department of Energy Office of Science
About this file
This is a federal contract issued by Brookhaven Science Associates, LLC (BSA), acting under a prime contract with the U.S. Department of Energy (DOE), for the design, manufacturing, and delivery of a Cycloconverter – Power Control and Regulating System for the AGS Motor Generator Set at Brookhaven National Laboratory. The contract is a Firm Fixed Price agreement (Contract Number 462624) with a TBD overall value amount and a 104-week period of performance from contract award. The contractor must furnish all labor, services, materials, and equipment to provide the cycloconverter system in strict accordance with the attached Statement of Work, Technical Specification, and BNL Supplier Quality Assurance Requirements.
The contractor is required to deliver nine milestone deliverables with specific timelines and BSA approval requirements, including a Program Plan (6 weeks), Manufacturing/Inspection/Test Plan (8 weeks), Preliminary Design Review reports (10 working days before and after the PDR), Final Design Review reports (15 working days before and after the FDR), equipment delivery (85 weeks), and End Item Documentation (104 weeks). Payment will be made upon receipt and approval of milestone deliverables using a nine-phase milestone payment schedule tied to specific completion events, with payment terms of Net 30 Days (or Net 10 Days for small businesses). Freight terms specify FOB Destination with Freight Prepaid for North American shipments and DAP Incoterms for foreign shipments. The contractor must comply with detailed labeling, packing, and notification requirements, including special provisions for heavy/oversized shipments, vermiculite-free packaging, and 10+2 form submission for ocean shipments 72 hours before vessel departure. BSA's Contractual Representative is Jeanhei D. Christy, and signed contract acceptance must be returned to jchristy@bnl.gov.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
April 9, 2025 1 Rev. 10
BSA’s Contractual Representative
Overall Value Amount
Contract Type Contract Number
Jeanhei D. Christy TBD Firm Fixed Price 462624
BROOKHAVEN NATIONAL LABORATORY
Brookhaven Science Associates
P.O. Box 5000
UPTON, L.I., N.Y. 11973-5000
Name and Address of Contractor (TBD)
CONTRACT
This Contract (the “Contract”) is between the party named above (the “Contractor”), and Brookhaven Science Associates, LLC (“BSA”), the latter acting under a Prime Contract with the United States of America (the “Government”) represented by the United States Department of Energy (“DOE”).
I. SCOPE OF WORK
The Contractor shall furnish all labor, services, materials, and equipment to provide a Cycloconverter – Power Control and Regulating System for the AGS Motor Generator Set for the Alternating Gradient Synchrotron (AGS) at Brookhaven National Laboratory (“BNL”).
All work shall be conducted in strict accordance with the following attachments:
• Attachment A – Statement of Work (SOW), dated February 20, 2025
• Attachment B – Technical Specification, dated February 20, 2025
• Attachment C – BNL Supplier Quality Assurance Requirements, BNL-QA-101
A. Reports/Deliverables: The Contractor shall provide the following deliverable(s) to and as directed by BSA’s Technical Representative:
Item
Description Due
(counted from contract award)
BSA
Approval 1 Program Plan 6 weeks Yes 2 Technical and Progress Reporting 8 weeks starting; Biweekly thereafter No 3 Performance Reports 5th of each month after receipt of
Program Plan No
4 Manufacturing/Inspection/Test Plan 8 weeks Yes 5 Draft Preliminary Design Review Report 10 working days prior to Preliminary
Design Review (PDR) Yes
6 Final Preliminary Design Review Report 10 working days after PDR Yes
April 9, 2025 2 Rev. 10
7 Draft Final Design Review Report 15 working days prior to Final Design Review (FDR)
Yes
8 Final Design Review Report 15 working days after FDR Yes 9 BSA Review of FDR 25 working days after FDR Yes 10 Delivery of Equipment 85 weeks Yes 11 End Item Documentation 104 weeks Yes
II. PERIOD OF PERFORMANCE
This Contract shall be effective as of the date executed by both parties. It shall remain in effect through 104 weeks after contract award.
III. FIRM FIXED PRICE AND PAYMENT
A. Firm Fixed Price: In full consideration of the Contractor’s performance hereunder, BSA shall pay the Contractor the firm fixed price of TBD U.S. Dollars ($TBD).
The said sum shall constitute full compensation for all services and materials furnished hereunder.
B. Payment: Payment will be made upon receipt and approval of milestone deliverables and properly certified invoices. Payment will be in accordance with the following milestone payment schedule:
Item
Description Due
(counted from contract award)
Amount
(TBD)
1 Preliminary Design Review 8 weeks 2 Final Design Review 12 weeks 3 Wiring Schedules Complete and Delivered to BNL 50 weeks 4 Equipment Fabrication Complete 77 weeks 5 Factory Tests Complete 81 weeks 6 Delivery of Equipment to BNL 85 weeks 7 Installation and Wiring Complete 94 weeks 8 Commissioning and Testing at BNL 100 weeks 9 Delivery of End Item Documentation 104 weeks
Payment terms are Net 30 Days (or Net 10 Days for small businesses).
Invoices shall be directed to BSA’s Accounts Payable Department via electronic or regular mail.
Electronic invoice submittal is preferred by BSA. The Contractor shall make every effort to have systems in place that allow for electronic invoice transmittal. Invoices shall be submitted in PDF format, via email, to apinvoices@bnl.gov.
Hard copy invoices, if applicable, shall be directed to BSA's Accounts Payable Department, Contracts Division, Bldg. No. 400D.
The Contractor shall indicate the final invoice by clearly marking such invoice as mailto:apinvoices@bnl.gov
April 9, 2025 3 Rev. 10
“FINAL.” A copy of the final invoice must be submitted to BSA’s Contractual Representative.
C. Freight: Freight terms shall be:
• For North American shipments: FOB (Free on Board) Destination, BSA
National Laboratory, 98 Rochester Street, Building 928, Upton, Long Island, New York. Freight Prepaid
• For foreign shipments insert: DAP (Delivered At Place) Incoterms, BSA National Laboratory, 98 Rochester Street, Building 928, Upton, Long Island, New York.
D. Labelling, Packing, and Notification Requirements:
More detailed instructions are available at https://www.bnl.gov/shipping/ or by emailing WarehouseOperations@bnl.gov.
Labeling Requirements
All shipments must comply with the following labelling requirements. Failure to do so may result in delayed payments. Labels must be placed on the upper left portion of the container when possible and contain:
Brookhaven National Laboratory Brookhaven’s Contract Number 98 Rochester St.
Upton, NY 11973 Box Number / Number of Boxes
Packing List Requirements
Every shipping container must include a packing list. The packing list must be clearly identified and affixed to a side of the shipping container. At a minimum, the packing list should contain the following information:
• Ship from company name and address
• Supplier contact name
• Supplier telephone number
• Ship to address as instructed by Buyer/Contracts Specialist
• Brookhaven’s Contract number
• Part number, description, quantity, unit of measure, and corresponding BNL
Contract line number
Special Notification of Delivery
If a shipment is heavier than 3,000 lbs., longer than 8 feet in any direction, or has a high center of gravity, it will require rigging upon receipt and the shipper shall https://www.bnl.gov/shipping/ mailto:WarehouseOperations@bnl.gov
April 9, 2025 4 Rev. 10 provide a minimum of two (2) weeks’ advance notice of delivery to BNL’s Receiving Department via email to WarehouseOperations@bnl.gov. The shipper must obtain acknowledgement from BNL that delivery notification was received.
Failure to contact BNL will result in delays during delivery and any resulting demurrage will be at the shipper’s expense.
Marking of Outer Package
Each shipping container (transport package) with a gross weight equal to or greater than 400 lbs. (180 kilograms) must be marked with the center of gravity location and gross weight on at least one side or end panel. It must also meet the requirements of the latest revision of ASTM Standard D 3951, Standard Practice for Commercial Packaging. This applies to any item shipped (originally packaged or repackaged) to BNL or other locations cited in the Contract.
Protection of Material and Equipment
The Contractor shall employ procedures which ensure adequate protection of material and equipment during shipment and while in storage. Such protection shall include special environmental packaging as necessary. All items shipped (originally packaged or repackaged) to BNL or other locations cited in the PO or Contract shall comply with the requirements for preservation, packaging, and marking as stated in the latest revision of ASTM Standard D 3951-10, Standard Practice for Commercial Packaging.
Unacceptable Packing Material
Do not use vermiculite as a packaging material inside any shipments to BNL unless required by shipping regulation. “Vermiculite” as defined in this specification means the hydrous, silicate mineral classified as a phyllosilicate that has been expanded by heating. Vermiculite used as a packaging material in shipments must be determined to be free of asbestos (<1% chrysolite, amosite, crocidolite, tremolite, anthophyllite, and actinolite). All shipments containing vermiculite must be accompanied by documentation stating that the vermiculite used is certified asbestos-free. This documentation must be affixed to the outside of the package.
Ocean Shipments
Foreign shipments transported via ocean freight must use the 10+2 REQUIREMENTS Form (PDF). The form must be completed by the Contractor 72 hours before departure of the vessel. Send form to the following:
Interfreight Harmonized Logistics, Inc.
Fax: 516-371-6880 bnl@interfreight.net mailto:WarehouseOperations@bnl.gov https://www.astm.org/Standards/D3951.htm https://www.astm.org/Standards/D3951.htm https://www.bnl.gov/shipping/files/pdf/10-2-security-filing-bnl-interfreight.pdf https://www.bnl.gov/shipping/files/pdf/10-2-security-filing-bnl-interfreight.pdf mailto:bnl@interfreight.net
April 9, 2025 5 Rev. 10
Brookhaven National Laboratory WarehouseOperations@bnl.gov
Once the form is submitted to customs, an acceptance number will be provided.
Freight will not be loaded onto a vessel without an acceptance number. Failure to submit the 10+2 form may result in fines. It is the Contractor's responsibility to make sure the 10+2 form is submitted 72 hours prior to the vessel sailing. BSA shall withhold payment from the Contractor's final invoice for any penalties incurred by BSA due to late or incorrect ISF filing by the Contractor.
IV. AUTHORIZED REPRESENTATIVES
A. BSA’s Technical Representative: ____________, telephone no. __________, ___________(email), is BSA’s Technical Representative, and shall act as liaison between BSA and the Contractor in technical matters only.
B. BSA’s Contractual Representative: ________, telephone no. ___________, __________ (email), is BSA’s Contractual Representative. Any change or modification in the terms and conditions of this Contract shall require the written approval of BSA's Contractual Representative or designee.
C. Contractor’s Technical Representative: ________, telephone no. __________, ___________(email), is the Contractor’s authorized Technical Representative, and shall act as point of contact between BSA and the Contractor in technical matters only.
D. Contractor’s Contractual Representative: ______________, telephone no.
__________, ___________(email), is the Contractor’s authorized Contractual Representative and shall act as liaison between BSA and the Contractor.
V. ADDITIONAL TERMS
The provisions of Brookhaven Science Associates, LLC, General Terms and Conditions for Commercial Items and Services, Rev 23.0, May 2025, are incorporated herein and made a part hereof. (Please note: if a non-commercial product is offered, it must be specified and the terms and conditions will be changed accordingly.)
The provisions of Brookhaven Science Associates, LLC, Supplemental Terms and Conditions for Work by Contractors Onsite at Brookhaven National Laboratory, Rev 23.0, May 2025, are incorporated herein and made a part hereof.
This Contract is issued pursuant to Brookhaven Science Associates General and/or Supplemental Terms and Conditions listed above, which are incorporated herein by reference. The complete text of these terms and conditions can be viewed at PPM | Terms and Conditions. Should the Contractor have any questions and/or not have access to these terms and conditions, contact the Buyer or Contracts Specialist immediately.
The following documents attached hereto and made a part hereof, contain additional provisions of mailto:WarehouseOperations@bnl.gov https://www.bnl.gov/ppm/terms-and-conditions.php https://www.bnl.gov/ppm/terms-and-conditions.php
April 9, 2025 6 Rev. 10 this Contract:
• Attachment A – Statement of Work (SOW), dated February 20, 2025
• Attachment B – Technical Specification, dated February 20, 2025
• Attachment C – BNL Supplier Quality Assurance Requirements, BNL-QA-101
• Attachment D – BSA Commercial Terms and Conditions
• Attachment E – BSA Supplemental Terms and Conditions for Work on Site
This Contract does not bind nor purport to bind the Government of the United States.
ACCEPTED:
CONTRACTOR BROOKHAVEN SCIENCE
ASSOCIATES, LLC.
By: By:
Name: Name:
Title: Title:
Date: Date:
Should you accept this Contract without exception or alteration, a signed copy of the Contract shall be returned to BSA’s Contractual Representative at jchristy@bnl.gov. Should you take any exceptions or attempt to alter the Contract in any manner, BSA’s execution thereof shall be null and void. Should you wish to take exception(s)/alteration(s), you shall notify BSA’s Contractual Representative. BSA will consider the requested exception(s)/alteration(s) and notify you accordingly. No Contract shall exist unless and until such differences are resolved.
mailto:jchristy@bnl.gov
| Invoices shall be directed to BSA’s Accounts Payable Department via electronic or regular mail. |
| Electronic invoice submittal is preferred by BSA. The Contractor shall make every effort to have systems in place that allow for electronic invoice transmittal. Invoices shall be submitted in PDF format, via email, to apinvoices@bnl.gov. |
| Hard copy invoices, if applicable, shall be directed to BSA's Accounts Payable Department, Contracts Division, Bldg. No. 400D. |
| Ocean Shipments |
| Name: Name: |
| Title: Title: |