460-24-009 CLC and Fourth Floor Elopement ICRA.pdf
PDF 153 KB Posted
- Solicitation number
- 36C24427R0001
About this file
This is an Infection Control Risk Assessment (ICRA) document for the VA Medical Center in Wilmington, Delaware.
The assessment evaluates Project #460-24-009, the 4th Floor and CLC Patient Elopement System Replacement, using a three-step methodology. Step 1 classifies the construction project type as Type C, which encompasses work generating moderate to high dust levels or requiring demolition and removal of fixed building components. The assessment confirms that contractor staff will not face tuberculosis infection risk and no physical disruption of water systems is anticipated. Step 2 identifies the affected patient risk group as "Highest Risk," which includes areas such as Operating Rooms, Oncology, Intensive Care Units, Cardiac Cath Labs, and negative airflow rooms. Step 3 cross-references the Type C construction project with the Highest Risk patient group on the control matrix, resulting in a Class III/IV precautions requirement.
The Class III/IV infection control procedures mandate implementation during and after construction. During construction, the contractor must remove or isolate the HVAC system, establish critical barriers using materials such as sheetrock or plastic to seal the work area, maintain negative air pressure using HEPA-equipped filtration units, and contain construction waste in tightly covered containers. Upon completion, barriers must remain until inspected by Safety Management and Infection Control, after which the work area requires vacuuming with HEPA-filtered equipment and wet mopping with disinfectant. The project documentation notes two specific modifications: a sticky mat will be used during installation but removed nightly due to the corridor location, and the HVAC system will remain undisturbed since the work involves only erecting two walls.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Fourth Floor and CLC Layouts.pdf | ||
| 36C24427R0001_2.docx | DOCX document | |
| 36C24427R0001.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VAMC WILMINGTON, DE
Infection Control Risk Assessment (ICRA)
Step 1. Use the following chart to identify the Type of Construction Project Activity (Type A-D)
Type A Inspect and Non-invasive Activities: Includes, but not limited to:
Removal of ceiling tiles for visual inspection limited to 1 tile per 50 square feet Painting (but not sanding)
Wall covering, electrical trim work, minor plumbing, and activities which do not generate dust or require cutting of walls or access to ceilings other than for visual inspection
Type B
Small scale, short duration activities which create minimal dust: Includes, but not limited to:
Installation of telephone and computer cabling Access to chase spaces Cutting of walls or ceiling where dust migration can be controlled
Type C
Work that generates a moderate to high level of dust or requires demolition or removal of any fixed building components or assemblies: Includes, but not limited to:
Sanding of walls for painting or wall covering Removal of floor covering, ceiling tiles and casework New wall construction Minor duct work or electrical work above ceilings Major cabling activities Any activity which cannot be completed within a single work shift
Type D Major demolition and construction projects: Includes, but not limited to:
Activities that require consecutive work shifts.
Requires heavy demolition or removal of a complete cabling system.
New construction
Is it likely the Contractor's staff will be placed at risk for infection with tuberculosis? YES / NO Is it likely there will be physical disruption of the water system/lines during activity? YES / NO
Selected Type of Construction: ___C___
Step 2. Using the following table, identify the Patient Risk Group that will be affected.
If more than one group is affected, select the higher risk group.
Low Risk Medium Risk High Risk Highest Risk Office areas Cardiology
Echocardiography Endoscopy Nuclear Medicine Physical Therapy Radiology/MRI Respiratory Therapy
CCU
Emergency Room Laboratories Outpatient Surgery Pharmacy Post Anesthesia Care Unit Surgical Units
Any area caring for immunocompromised patients Cardiac Cath Lab Central Supply Intensive Care Units Medical Units Negative airflow rooms Oncology Operating Rooms
Select Patient Risk Group: ___Highest Risk____
Step 3. Match the Patient Risk Group with the planned Construction Project Type (A, B, C, D) on the following matrix, to find the Class of Precautions (I, II, III, and IV) or level of infection control activities required.
Patient Risk Group Type A Type B Type C Type D
Low risk I II II III/IV Medium risk I II III IV High risk I II III/IV IV Highest risk II III/IV III/IV IV
Select Control Procedures: ____III / IV____
During Construction Project Upon Completion of Projects
C la ss I 1. Execute work by method to minimize raising dust from construction operations
2. Immediately replace a ceiling tile displaced for visual inspection
1. Clean work upon completion of task
C la ss
II
1. Provide active means to prevent airborne dust from dispersing into atmosphere.
2. Water mist work surfaces to control dust while cutting
3. Seal unused doors with duct tape
4. Block off and seal air vents.
5. Place dust mat at entrance and exit of work area.
6. Remove or isolate HVAC system in areas where work is being performed.
1. Wipe work surfaces with disinfectant.
2. Contain construction waste before transport in tightly covered containers.
3. Wet mop &/or vacuum before leaving work area.
4. Remove isolation of HVAC system in area where work is being performed.
C la ss
II
I
1. Remove or isolate HVAC system in area where work is being done to prevent contamination of duct system.
2. Complete all critical barriers, i.e. sheetrock, plywood, plastic, to seal area from non-work area or implement control cube method (cart with plastic covering & sealed connection to work site with HEPA vacuum for vacuuming prior to exit) before construction begins.
3. Maintain negative air pressure within worksite utilizing HEPA-equipped air filtration units.
4. Contain construction waste before transportation in tightly covered containers.
5. Cover transport receptacles or carts. Tape covering unless solid lid is used.
1. Do not remove barriers from work area until completed project is inspected by Safety Management & Infection Control & thoroughly cleaned by Environmental Management.
2. Remove barrier materials carefully to minimize spreading of dirt & debris associated with construction.
3. Vacuum work area with HEPA-filtered vacuums.
4. Wet mop with disinfectant.
5. Remove isolation of HVAC system in areas where work is being performed.
C la ss
IV
1. Isolate HVAC system in area where work is being done to prevent contamination of duct system.
2. Complete all critical barriers, i.e., sheetrock, plywood, plastic, to seal area from non-work area or implement control cube method (cart with plastic covering & sealed connection to work site with HEPA vacuum for vacuuming prior to exit) before construction begins.
3. Maintain negative air pressure within worksite utilizing HEPA-equipped air filtration units.
4. Seal holes, pipes, conduits and punctures appropriately.
5. Construct anteroom and require all personnel to pass through this room so they can be vacuumed using a HEPA vacuum cleaner before leaving work site; or the can wear cloth or paper coveralls that are removed each time they leave the work site.
6. All personnel entering the work site are required to wear shoe covers.
Shoe covers must be changed each time the worker exits the work area.
7. Do not remove barriers from work area until completed project is inspected by Safety Management & Infection Control & thoroughly cleaned by Environmental Management.
1. Remove barrier materials carefully to minimize spreading of dirt & debris associated with construction.
2. Contain construction waste before transport in tightly covered containers.
3. Cover transport receptacles or carts. Tape covering unless solid lid.
4. Vacuum work area with HEPA-filtered vacuums.
5. Wet mop with disinfectant.
6. Remove isolation of HVAC system in areas where work is being performed.
Project #:460-24-009 Project Name: 4th Floor and CLC patient Elopement System Replacement
- A sticky mat will be used during installation; however, it will be removed each night due to the work being located in a corridor
- HVAC system will be undisturbed since this project consists of simply erecting two walls.
| Removal of ceiling tiles for visual inspection limited to 1 tile per 50 square feet |
| Type D |
| During Construction Project |
| Upon Completion of Projects |
Type A