This document contains responses to a Request for Information (RFI) related to a federal contract opportunity for deep drilling. The key details are:

The scope of work requires the subcontractor to provide labor, equipment, materials, supplies, and fuel to drill a continuous wireline core boring to an approximate vertical depth of 6,930 feet. The core hole must have a minimum diameter of 3.7 inches at the terminal depth, and steel casing must be installed to 4,000 feet +/- 200 feet. The drilling is intended to provide geologic and geophysical data to characterize the site.

The RFI responses address various technical and logistical questions, including methods for correcting hole deviation, water table tracking, rod handling systems, disposal of drilling fluids and cuttings, work schedules, fuel storage, environmental risks, training requirements, and site restrictions. The contract is not a small business set-aside and has no Davis-Bacon or union requirements.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2621 Losee Road, N. Las Vegas, NV 89030-4129 | P.O. Box 98521, M/S NLV018, Las Vegas, NV 89193-8521

1 August 2024

432954-MC-24 RVDC DEEP DRILLING

RFI RESPONSES:

1. If the hole deviates, do we have a planned method of correction? Wedge/directional mud motor? This will be for the vendor to propose.

2. Tracking the water table is near impossible on a core rig while drilling without a lot of added down time when testing and risk of compromising the hole. Is this necessary? Or will our mud levels suffice if we were to lose circulation? We need to Identify the water table when we first encounter it, but after – tracking mud levels is sufficient.

3. Is a rod handling system required on this site? It is not required

4. What is the desired method of disposal of drilling fluid and cuttings. If mud pits are used – The subcontractor can allow the pits to dry out and the NNSS will remove the cuttings. If cutting tanks are used – NNSS will provide roll-off dumpsters.

5. Will there be the option to work though federal holidays.- Yes

6. Can we haul fuel in everyday on work trucks or will we be required to have a stationary tank on site. The vendor can bring their own diesel on site as long as the tank there are using has a capacity of less than 119 gallons. In the SOW we also require that they need to have 4 days’ worth of fuel stored on site.

7. Please define the environmental risks and exposures.- Exhibit E has all environmental, if further clarifications are needed, specify which section you are referring.

8. What is the desired start date and performance period. – Provide Schedule in proposal- not an award determining factor

9. Just to clarify this is not Davis bacon rate. – This is a government service subcontract, see attachment 8.6 SCA Wage determination – no DBA

10. Just to clarify this project has no ties or union requirements. – There are NO union Requirements

11. Project labor agreement wage does not apply.- PLA does NOT apply

12. Please verify that there will be adequate housing for the crew (7 Rooms) – Information in Solicitation documents, attachment 8.3. Housing Services

13. Will it be ok to work 24 hour operations 7 days a week. - Yes

14. Please clarify who is expected to be on site for the duration of the project. The lead driller and drilling crew can rotate as needed during the course of the project. There must be a site safety supervisor identified for each shift – this is a stand-alone position. The superintendent and project manager do not need to be on site 24/7.

15. Small Business Set-Aside? This is not a Small Business Set-Aside; this is Full & Open.

16. Scheduling/timeline? Vendors will submit their own schedule/timelines

17. Please provide Exhibit B training and requirements:

4 Hours – Exhibit A has been updated. Courses can be found in exhibit E, E-11

18. Restrictions on site: Alcohol is not allowed to be brought onto the site or purchased and brought into the hotel accommodations.

19. what depth is the historical water table anticipated. ~1,400 bgs Who is setting the instrumentation in the hole after the TD is achieved. NNSS construction will be setting the instrument. This is not part of the drilling scope

20. Do we need to cap the Well when we’re completed? No, the well needs to be accessible

21. Would it be OK to include the geophysical logging in our proposal with our affiliate company (internal). – this is not in the SOW and not required for this procurement.

22. Fire suppression systems - What quantity of fuel and oil requires a fire suppression system? No suppression needed. Handheld fire extinguisher is sufficient

23. Is a fire suppression system needed on flammable cabinets? No suppression system needed. Handheld fire extinguisher is sufficient.

24. May we utilize a standard Nevada bentonite and polymer drilling fluid program? (All products will be NSF-approved) All drilling fluids must be NSF 61 Approved.

25. We want to confirm that cell phones will not be allowed on the drill site. And if this is the case, will a Star link system be permitted for communication? Cell Phones are allowed on site. Hot spots or cell modems that emit a WIFI signal are not allowed on site. Cell modem must be connected or tethered to a computer to use for internet connection. Star link will need to be approved by cyber security

26. Do you have a preferred start date? As soon as drill rig and crew are readily available post- award

27. Portable Bathrooms will be provided.

28. Tortoise issues? If a tortoise is found too close to the site, stop-work is required for environmental to come out and remove it. While they do sweeps of the area, if you see a tortoise that has been killed on the road, please also notify environmental so they can properly dispose of it. This will not negatively impact the company in any way, they just want to ensure it’s taken care of properly. Help reduce wildlife on work sites by removing all food/trash.

29. Water to the rig? Storage of 20K tanks are provided, up to two (2) can be provided. However, vendor is not allowed to drive water truck, this is MSTS responsibility. Please ask if you need more clarification on this.

30. Closest fuel? 30 Minute drive 1-way, directions can be provided upon request.

MSTS is a contractor to the National Nuclear Security Administrationwww.nnss.gov
MSTS is a contractor to the National Nuclear Security Administrationwww.nnss.gov

image1.jpg

File details come from the government source that posted it. Updated .