About this file
This is a template form (IBWC Form 245B(ESD)) used by the International Boundary & Water Commission to collect backup information supporting minimum qualifications for contract award. The form captures project experience data that contractors submit to demonstrate their capability to perform work similar in scope and complexity to a solicitation.
The form requires contractors to provide comprehensive details about relevant past projects, including company name, project name, contracting agency, entity with which the work was contracted, contract number, contract amount, start and end dates, and contracting officer information. Contractors must also identify the NAICS code for the type of construction performed. Critical sections require detailed descriptions of the work performed, quantified scope of work completed, and project complexity factors that demonstrate the contractor overcame difficulties requiring more than basic skills. The instructions emphasize that answers to the work description, quantities, and complexity sections must be sufficiently detailed to allow IBWC to determine whether the referenced project is similar in scope and complexity to the current solicitation. The form must be printed to PDF prior to submission to USIBWC and was last updated on November 28, 2018.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INTERNATIONAL BOUNDARY & WATER COMMISSION
MINIMUM QUALIFICATIONS FOR AWARD
Backup Information
IBWC Form 245B(ESD) Updated 11/28/2018 Page 1 of 2 www.ibwc.gov
Company Name
Project Name
Contracting Agency for Project Noted Above
Entity with whom you had a Contract
Number
Amount
Start Date End Date
Contracting Officer's Name
Contracting Officer's Telephone Number
Contracting Officer's Address
Type of Construction (NAICS) www.census.gov/eos/www/naics/
Brief Description of Work
Backup Information
IBWC Form 245B(ESD) Updated 11/28/2018 Page 2 of 2 www.ibwc.gov of Quantities of Work of Project Complexity
Backup Information
INSTRUCTIONS
IBWC Form 245B(ESD) Updated 11/28/2018 www.ibwc.gov
Company Name: Enter the name of the company completing the form, i.e. your name.
Project Name: Enter the name of the project that is being used to support your qualifications.
Contracting Agency for Project Noted Above: Enter the name of the company, state agency, or Federal agency that issued a contract for this project.
Entity with whom you had a Contract: Enter the name of the entity that you contracted with.
This might be the Contracting Agency above if you were the prime contractor or another contractor if you were a subcontractor on the project in question.
Contract Number: Enter the contract number assigned to this project by the Contracting Agency.
Contract Amount: Enter the dollar amount of your contract on this project.
Start Date: Enter your start date on this project. If you were a subcontractor, this may not match the project's start date.
End Date: Enter your end date on this project. If you were a subcontractor, this may not match the project's end date. If work not complete, enter your scheduled end data and the percentage of your work complete.
Contracting Officer's Name: Enter the Contracting Officer's name for the Contracting Agency above.
Contracting Officer's Telephone Number: If known, enter the Contracting Officer's phone number.
Contracting Officer's Address: If known, enter the Contracting Officer's address.
Type of Construction (NAICS): Provide the NAICS code for the type of construction for the referenced project. If you do not know, choose 'unknown' from the drop down list.
Brief Description of Work: Provide a description of the work that you performed on this project.
Description of Quantities of Work: Provide a numerical list or description of quantities of work that you performed on this project.
Description of Project Complexity: Describe any difficulties that required more than basic skills to complete as well as any other items that you had to overcome to complete this project.
Remember the note on Form 245/245A that states:
Scope refers to technical requirements of work.
Complexity refers to difficulty of performing work due to many varied interrelated parts.
Similar in scope refers to the same type of work with comparable or greater quantities.
Your answers to 'Brief Description of Work,' 'Description of Quantities of Work,' and 'Description of Project Complexity' need to be sufficient that we can judge the work to be similar in scope and complexity to our solicitation.
| Entity with whom you had a Contract: |
| Contract Number: |
| Contract Amount: |
| Start Date: |
| End Date: |
| Contracting Officers Name: |
| Contracting Officers Telephone Number: |
| Contracting Officers Address: |
| Brief Description of Work: |
| Description of Quantities of Work: |
| Description of Project Complexity: |
| NAICS: [Other Construction] |
| Print: |
| Button3: |
| Note: Form must be "printed" to pdf prior to submittal to USIBWC. |
| Contracting Agency: |
| Project Name: |
| Bidder Participant: |