4-Attachment B Scope of Work.docx

DOCX document 2 MB Posted

Attached to
AS27-121 Color Country Aerial Seeding
Solicitation number
AS27-121
Issued by
Utah

About this file

This is a Scope of Work document for an Invitation for Bid (IFB) issued by the State of Utah Division of Purchasing in cooperation with the Utah Division of Wildlife Resources, Bureau of Land Management, Utah Trust Lands Administration, and USDA Natural Resources Conservation Services. The project, designated AS27-121 Color Country Aerial Seeding 2026, requires aerial seeding services across approximately 5,574 acres in Iron and Kane Counties, Utah, covering six distinct project areas: Horse Hollow (1,195 acres), Shurtz Canyon (661 acres), Slide Canyon (1,116 acres), Yellow Jacket-Oak Flat (1,555 acres), Yellow Jacket-Willow Spring (791 acres), and Gold Springs (256 acres). Each area has specific seed application rates ranging from 7.73 to 14.45 pounds per acre, totaling approximately 59,854 pounds of seed that the contractor must pick up from the UDWR Great Basin Research Center in Ephraim, Utah. Work must commence no later than November 1, 2026, and be completed by November 20, 2026, with a maximum performance window of 30 calendar days from the Notice-to-Proceed. No pre-bid site visit is scheduled; however, bidders are strongly encouraged to conduct their own site inspections. A pre-work conference will be held at the project site prior to work commencement to review specifications, schedules, and administrative provisions.

Bidding is conducted on a per-acre price basis, with the winning bid extended across the total project acreage to establish the total contract price. All labor, equipment, mobilization, and operating costs must be included in the per-acre bid with no fuel surcharges or price adjustments permitted. Bidders must demonstrate a minimum of five years of experience in aerial seeding and must use only helicopters or fixed-wing aircraft equipped with GPS technology; unmanned aircraft systems and drones are prohibited. The contract will be awarded to the lowest responsive and responsible bidder meeting experience and equipment requirements. The contractor is responsible for all seed transport, storage, protection, and handling; equipment provision and mobilization; crew supervision; and site restoration and cleanup. Payment will be made in one lump-sum final payment following final inspection of completed acres, with partial payments available only at the State's discretion and with prior written approval. Minor Change Orders allowing up to 10 percent acreage modifications can be implemented at the original per-acre bid price, while Major Change Orders exceeding 10 percent may authorize price adjustments subject to State approval and a liability cap calculated as the per-acre bid price multiplied by 10 percent of remaining untreated acreage.

View the file

Other files

File Type Posted
2026_OakFlat_Seeding_11x17P 1.pdf PDF
2-Att.-A-PO-Terms-and-Conditions (20).docx DOCX document
20260921_HorseHollow_Seeding.kmz KMZ file
20260921_SlideCanyon_Seeding.kmz KMZ file
20260914_ShurtzCanyon_Seeding.kmz KMZ file
20260917_OakFlat_Seeding 1.kmz KMZ file
2025_HorseHollow_Seeding_11x17P.pdf PDF
20260917_GoldSpring_Seeding 1.kmz KMZ file
1-Vendor Prerequisites - IFB Agency.pdf PDF
2026_GoldSprings_Seeding_Vicinity_11x17P 1.pdf PDF
2026_WillowSpring_Seeding_11x17L.pdf PDF
2026_SlideCanyon_Seeding_Vicinity_11x17P.pdf PDF
2026_ShurtzCanyon_Seeding_11x17L.pdf PDF
20260917_GoldSpring_Seeding 1.zip ZIP file
2026_OakFlat_Seeding_Vicinity_11x17P 1.pdf PDF
20260914_ShurtzCanyon_Seeding.zip ZIP file
2026_GoldSprings_Seeding_11x17P 2.pdf PDF
2025_HorseHollow_Seeding_Vicinity_11x17P.pdf PDF
20260917_OakFlat_Seeding.zip ZIP file
20260917_WillowSpring_Seeding.zip ZIP file
20260917_WillowSpring_Seeding.kmz KMZ file
2026_WillowSpring_Seeding_Vicinity_11x17L.pdf PDF
2026 Aerial Seeding Contract.docx DOCX document
20260921_HorseHollow_Seeding.zip ZIP file
2026_SlideCanyon_Seeding_11x17P.pdf PDF
2026_ShurtzCanyon_Seeding_Vicinity_11x17L.pdf PDF
20260420_SlideCanyon_Seeding.zip ZIP file
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT B SCOPE OF WORK

#AS27-121

PROJECT: Color Country Aerial Seeding 2026 LOCATION: Work under this contract is located in, Iron and Kane Counties, Utah.

Introduction: Utah Division of Wildlife Resources in cooperation with the Kanab and Cedar City Field offices of Bureau of Land Management, Utah Trust Lands Administration and USDA Natural Resources Conservation Services are acquiring services for aerial seeding as part of the following projects; Horse Hollow, Shurtz Canyon, Yellow Jacket-Oak Flat, Yellow Jacket-Willow Spring, and Slide Canyon and Gold Springs. This task order includes the Contractor to furnish labor, equipment, supervision, transportation, operating supplies, and incidentals. The project area totals approximately 5,574 acres as identified on the attached site maps.

SECTION I – PROJECT REQUIREMENTS

SITE SPECIFICS:

Location and Description: This project is located on BLM, and Utah School and Institutional Trust Lands Administration in Iron, and Kane County Utah. Vicinity maps showing aerial seeding sites are attached. Only areas outlined on the project maps will be seeded.

The closest airports/landing zones are to be determined by the contractor. Contractor will also be responsible for picking up seed from the DWR’s seed warehouse in Ephraim, UT and transport seed to the airport/landing zones of their own choosing.

SPECIFIC TASKS:

Work Limits: Furnishing all labor, equipment, supplies, and materials to aerial seed approximately 5,574 acres. Contractor will need to provide enough labor and equipment to complete the work in the specified performance window. The project is split into the several distinct project areas (see maps). Each project will have its own seed mix and rate of application. It is the contractor’s responsibility to ensure that the proper seed mix and application rate is followed as described in this contract.

Acreage:

Horse Hollow = 1,195 acres @ approximately 14.45lbs./ac.

Shurtz Canyon = 661 acres @ approximately 8.28 lbs./ac.

Slide Canyon= 1,116 acres @ approximately 11.21 lbs./ac.
Yellow Jacket-Oak Flat= 1,555 acres @ approximately 9.23 lbs./ac.
Yellow Jacket-Willow Spring= 791 acres @ approximately 10.47 lbs./ac.
Gold Springs= 256 acres @ approximately 7.73 lbs./ac.

Approximate Total = 5,574 acres

Total Weight:

Seed will be bagged in 1,250 lb. sacks. Seed will need to be picked up by contractor. All the seed will be picked up from UDWR Great Basin Research Center in Ephraim Utah. Contractor will be solely responsible for loading all seed into broadcaster.

Horse Hollow= 1,195 acres x 14.45lbs. = Total 17,267lbs.
Shurtz Canyon= 661 acres x 8.28 lbs. = Total 5,476 lbs.
Slide Canyon= 1,116 acres x 11.21 lbs. = Total 12,501 lbs.
Yellow Jacket-Oak Flat= 1,555 acres x 9.23 lbs. = Total 14,350 lbs.
Yellowjacket-Willow Spring= 791 acres x 10.47 lbs. = Total 8,280 lbs.
Gold Springs= 256 acres x 7.73 lbs. = Total 1,980 lbs.

Approximate Total = 59,854 lbs.

Access to the site: Access to the project site is provided by a combination of paved highways, county dirt surface roads, and jeep trails. Four (4) wheel drive vehicles are recommended in and around the project area. It will be the contractor’s responsibility to get the equipment to the work site.

CONTRACTOR FURNISHED EQUIPMENT:

Equipment Requirements:

Application shall be conducted by helicopter or fixed-wing aircraft only. Unmanned aircraft systems (UAS), including drones, are not permitted. The aircraft must be equipped with a global positioning system (GPS) used to establish flight lines and document 100% coverage of the treatment areas. DWR will provide the Contractor with an electronic GIS file containing the treatment-area boundaries. Upon completion of each treatment area, or as required by the Contracting Officer, the Contractor shall provide an electronic file of the treatment coverage in Universal Transverse Mercator (UTM) projection, North American Datum of 1983 (NAD83), in a format compatible with Trimble, ArcInfo, or ArcView. A government representative may monitor the Contractor’s GPS data to verify compliance with contract specifications.

Seed Application:

The Contractor shall certify to DWR they have the capability to meet the requirements of the request for quote prior to performing any aerial work.

Seed Transport, Storage, and Handling:

The Contractor will be responsible for loading and transporting the UDWR-furnished seed from the DWR’s seed warehouse in Ephraim, UT to the worksites and shall be responsible for its protection from loss or damage during transport. The Contractor shall keep seed dry, protected from contamination, and identified by project throughout transport, storage, and application.

Radio Communication:

The Contractor shall provide a communication system so that contractor personnel engaged in the project at different locations can communicate at all times with each other and so that Government Project Inspectors may communicate with the contractor at any time to discuss performance matters.

The Contractor at no additional expense to the State will replace seed damaged or lost while in the custody of the Contractor. Unused seed shall be returned to the agreed upon location upon completion of work or termination of the Contract. Empty seed sacks upon request and all pallets shall be saved and returned to the State of Utah Seed Warehouse in Ephraim Utah by the Contractor.

GOVERNMENT FURNISHED PROPERTY:

UDWR will furnish the project-specific seed mixes (to be picked up by contractor from GBRC) and treatment-area maps and electronic boundary files.

EQUIPMENT AND WORKMANSHIP:

All equipment and/or materials incorporated into the work covered by this contract shall be of the most suitable grade for the purpose intended, unless otherwise specifically provided in this contract. All work under this contract shall be performed in a skillful and workmanlike manner. The State may require, in writing, that the contractor remove from the work any employee deemed by the State to be incompetent, careless, or otherwise objectionable.

Weather Conditions: The government reserves the right to postpone the seeding operation if wind speed exceeds 10 miles per hour

Tests for Uniformity: The Project Inspector will conduct tests to determine the uniformity of the Seeding.

CONTRACT TIME – must begin no later than November 1, 2026 be finished by: November 20, 2026

Project Performance Time: 30 calendar days from the official Notice-to-Proceed (NTP)

SECTION II – BID REQUIREMENTS/INFORMATION

SITE VISIT:

A site visit will NOT be held prior to bidding. It is strongly recommended that each potential bidder inspect the site where services are to be performed and satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.

It is strongly recommended that each potential bidder ensure that he/she has a complete understanding of the requirements of this project. Bidders are urged to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.

MAPS/FILES

Project Site maps Vicinity Maps KML and Shapefiles

Under no circumstances shall the shape/KML files be considered part of the contractual document. They will be provided for informational purposes only. Any .pdf files provided in this bid document, and the actual physical site location shall govern any contractual interpretation or dispute related to this project.

QUESTIONS:

Only questions specific to the site should be asked at the site visit (if held). Questions related to this solicitation, specifications, or bidding procedures MUST be asked in writing on the Q&A board within the solicitation to keep the process fair and transparent. There are no exceptions to this. Questions asked at the site visit and subsequent answers will be recorded and posted in the solicitation so that all potential bidders can review questions and answers.

BIDDING:

This contract will be bid on a per-acre price. The per-acre price will be extended based on the number of acres to show a total project price. The total price shall include all labor, equipment, and materials necessary to complete the job, which includes all mobilization and operating costs. There will be no fuel surcharges or adjustments negotiated.

MINIMUM EXPERIENCE:

For a bid to be considered for this project, the bidder must have a minimum of 5 years of experience in Aerial Seeding. Bidders who do not meet the experience requirement will not be considered for award.

EQUIPMENT:

All equipment and/or materials incorporated into the work covered by this contract shall be of the most suitable grade for the purpose intended, unless otherwise specifically provided in this contract. All work under this contract shall be performed in a skillful and workmanlike manner. The State may require, in writing, that the contractor remove from the work any employee deemed by the State to be incompetent, careless, or otherwise objectionable.

CONTRACT AWARD:

A contract will be awarded to the lowest responsive/responsible bidder who meets any experience and equipment requirements noted elsewhere in this solicitation.

USE OF SUBCONTRACTORS:

The Project Manager must approve the use of all subcontractors in writing prior to their performance of any work on the project. Any company or individual who submitted a bid on the project, was offered the project as the low bidder, and declined that award, or who defaulted on project after being awarded the contract, is ineligible to be a subcontractor for, or an employee of, the successful bidder.

SECTION III – ADDITIONAL REQUIREMENTS

ENVIRONMENTAL CONSIDERATIONS:

Project sites shall be cleaned up, and all refuse removed by the Contractor. The Contractor shall be responsible for the disposal of materials in a manner consistent with State, Federal, and local laws and for all expenses incurred with the disposal. Public or private access roads damaged by the Contractor shall be restored at the contractor's expense to the same condition they were in at the commencement of work.

Use of 2-wheel and 4-wheel vehicles is permitted in the project areas. Off-road driving will be prohibited when soils are wet and rutting may occur.

Hazardous Materials:

1. Use of Hazardous Materials and/or petroleum products requires that all appropriate State and Federal Regulations be complied with including, but not limited to, Materials Safety Data Sheets (MSDS) on hand and use of necessary Personal Protective Clothing (PPE).

2. On-site disposal of Hazardous Materials or Waste including hydrocarbons is not authorized. On-site disposal will subject the contractor to at least the cost of reclamation and the appropriate disposal of contaminated soil.

3. Incidental (de minimus) leaks from fittings, gaskets, or ruptured hoses will not subject the contractor to remedial requirements. They will be considered to be normal and unavoidable losses. Continual leaks will be noted on inspection reports and correction through maintenance is required.

4. Maintenance and repair operations that require the draining of engines or hydraulic systems may be conducted on-site only if the fluids are captured, containerized, and removed from public lands for proper disposal.

PUBLIC ACCESS:

Access into and through the project site shall remain open to the public at all times. The Contractor shall maintain roadways free of vehicles, tools, and debris.

SECURITY OF EQUIPMENT AND PROPERTY:

The Contractor may leave equipment at the work site, however, the Contractor shall be solely responsible for the protection of equipment and is solely responsible if the equipment is lost, stolen, or damaged.

CREW SUPERVISION:

1. The contractor shall designate one English-literate supervisor who will be on site during operation hours. Supervisors shall be identified during the pre-work conference. Any changes in supervisory designations must be submitted in writing to the Project manager at least 24 hours before the change takes effect.

2. The person designated by the Contractor, as supervisor must remain with and effectively direct the crew by (1) making periodic inspections of the crew’s work, (2) advising them as to improper work methods, (3) providing instructions for correcting any improper work methods encountered.

3. Emergency transportation will be provided by the Contractor at all times.

WORK CAMPS:

Work camps may be established only in locations authorized in advance by the Project Manager in coordination with the Government. Should such a camp be authorized, the Contractor shall maintain the camp in an orderly and sanitary manner. Upon vacating a camp and before final payment, the Contractor shall remove all refuse and other signs of occupancy to the satisfaction of the Project Manager.

WORK HOURS:

The contractor will be expected to begin seeding by 8:00 a.m. to avoid windy conditions and minimize seed drift. The government reserves the right to postpone the seeding operation if wind speed exceeds 10 miles per hour. Work may be done on Saturday, Sunday, and legal national holidays as mutually agreed between the Contractor and the Project Manager.

WORK SCHEDULE:

The work schedule shall be submitted at the pre-work conference.

DELAYS:

The contractor is expected to complete all contract performance in a timely manner, regardless of the contractor or subcontractor's other workload, including any work being performed under other state contracts. A delay or failure to perform may be considered excusable when the delay or failure arises from causes beyond the control and without the fault or negligence of the Contractor or subcontractor. Examples of these causes are (1) acts of God or of the public enemy, (2) acts of the State in either its sovereign or contractual capacity, (3) fires, (4) floods, (5) epidemics, (6) quarantine restrictions, (7) strikes, (8) freight embargoes, and (9) unusually severe weather. In each instance, the failure to perform must be beyond the control and without the fault or negligence of the Contractor or subcontractor.

Upon request of the Contractor, the Contracting Officer shall ascertain the facts and extent of the failure. If the Contracting Officer determines that any failure to perform results from one or more of the causes above, the delivery schedule may be revised, subject to the State’s contract termination rights under the contract.

Note: “Unusually severe weather” means weather that is outside the normal weather patterns for a specific area at a specific time of the year. For example, strong wind and snow storms in fall and winter, or strong wind, rain or hail storms in spring and summer are not considered unusually severe. An unusually severe snow, wind or rain storm is one that is worse than even the harshest normal conditions during a season.

PROJECT MEETINGS:

Pre-work Conference:

Location: Meetings shall be held at the project site, or as determined by the Project Manager.

Notification: A pre-work conference will be held prior to the start of work. The Contractor will be notified in advance of the meeting time, date and place. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the contract.

Attendance: The Contractor, subcontractors and the persons responsible for coordination of the work shall be present at the meeting.

Presentation: The Contractor shall be prepared to summarize and explain procedures planned for each project and present the work schedule requested in the specifications.

Progress Meetings:

Records and Notifications: The Contractor shall maintain adequate records to allow the BLM/UDWR to monitor contract progress and for the Contractor to be accountable for work quality. Contractor records shall include: 1) work dates, 2. number of acres completed, 3.) location of acres completed, 4.) supervisor/inspector name, 5.) work quality and percentage

Location: Meetings shall be held at the project site, or as determined by the Project Manager.

Notification: Meetings may be called by either the Project Manager or the Contractor. Request shall state who should attend.

FIRE DANGER SEASON:

If the Project Manager allows the Contractor to continue work during the periods of declared fire danger or season, the Contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed by the Project Manager

PRESERVATION OF HISTORICAL AND ARCHEOLOGICAL DATA:

The Contractor agrees that should he or any of his employees in the performance of this contract discover evidence of possible scientific, pre-historical, historical, or archeological data he will notify the Project Manager immediately giving the location and nature of the findings.

Where appropriate by reason of discovery, the Project Manager may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted.

The Contractor agrees to insert this paragraph in all subcontracts, which involve the performance of work on the terrain of the site.

PROTECTION OF CULTURAL RESOURCES:

Location of known historic or prehistoric sites, buildings, objects, and properties related to American history, architecture, archaeology, and culture, such as settler or Indian artifacts, protected by American Antiquities Act of 1906 (16 U.S.C. 431-433), National Historic Preservation Act of 1966 (16 U.S.C. 470) and the Archaeological Resources Protection Act of 1979 (16 U.S.C. 470aa-ll) (36 CFR 296.4 and 36 CFR 261.9(g)), shall be identified on the ground by the Government. The Government may unilaterally modify or cancel this contract to protect an area, object of antiquity, artifact, or similar object that is or may be entitled to protection under these Acts regardless of when the area, object, or artifact is discovered or identified. Discovery of such areas by either party shall be promptly reported to the other party and operations will be suspended at that location until the significance or potential significance of the site is determined.

The contractor shall protect all known and identified historic or prehistoric sites, buildings, objects, and properties related to American history, architecture, archaeology, and culture against destruction, obliteration, removal, or damage during the Contractor's operations. The contractor shall immediately notify the Government if disturbance occurs to any known site, and shall immediately halt operations in the vicinity of the site until the Government authorizes the Contractor to proceed. The contractor shall bear costs of evaluation and restoration in accordance with 36 CFR 296.14(c), provided that such payment shall not relieve the Contractor from civil or criminal remedies otherwise provided by law.

NOTICE TO PROCEED:

Unless notified by the project manager that notice-to-proceed will be delayed, receipt of the contract or purchase order by email shall constitute a Notice to Proceed. The Project Manager may issue a separate delayed notice-to-proceed for any reason including adverse soil, vegetative, climatologic, or other environmental conditions.

CONTRACT PERFORMANCE:

The Contractor shall begin work within seven (7) calendar days from the effective date of the notice to proceed and complete all work within 30 calendar days after that notice, but no later than November 20, 2026, unless extended through an authorized written contract modification. The Contractor shall continue the performance of the work under the contract without delay or interruption except by causes beyond his control identified in the Delays clause. Once the contractor is on site working, the contractor shall work diligently and complete all work within the project performance time in the Contract Time clause below.

It is the contractor’s sole responsibility to complete contract performance regardless of the contractor’s current workload, including other state contracts. If necessary, the contractor will be expected to take whatever means are necessary to ensure timely contract performance. At the discretion of the contractor, this may include sub-contracting, additional equipment/manpower, and/or any other necessary action. Any necessary action taken by the contractor to ensure timely completion shall be at no additional expense to the State of Utah beyond the original contract price.

INSPECTION:

Surveillance Plan: The Government will inspect completed acres and provide recommendations to improve work quality while work is in progress. The Contractor is responsible for providing quality control to ensure that work complies with the contract specifications.

Final Inspection:

Location: Meeting shall be held at the project sites, or as determined by the Project Manager.

Notification: The Contractor shall notify the Project Manager at least three (3) working days before the completion date so the Government can schedule the final inspection.

Deficiencies: The Contractor shall correct deficiencies and project areas will be re-inspected by the Project Manager.

ACCEPTANCE:

Based on inspection results, if the quality level falls below contract specifications, the Project Manager will immediately notify the Contractor in writing and instruct the Contractor to improve the quality of work. If the quality of the work is not raised to an acceptable level after written notification, the Project Manager may issue a suspension work order to resolve the problem, during which time contract time will continue to run.

If untreated or unsatisfactorily treated areas are the primary reason for unsatisfactory work, the Contractor shall rework acres designated by the Government until satisfactory work quality is obtained.

PAYMENT:

One lump-sum final payment will be made for the actual number of acres completed following a final inspection of the completed project, and consistent with the payment clause in the State’s standard terms and conditions. Normally, requests for partial payments will not be considered. However, if a partial payment request is considered, approval of said request shall be at the total discretion of the State. The contractor must get a partial payment request approved in writing before submitting an invoice for partial payment. Partial payment invoices received without prior approval will be returned to the contractor as not proper for payment.

CHANGE ORDERS:

Minor Change Order. If the State determines that a change in the Scope of Work is necessary, they may modify acreage totals or parcel configuration by up to 10% of the originally proposed Project Area by providing written notice to the Contractor (“Minor Change Order”). Issuance of a Minor Change Order does not excuse the Contractor from their obligation to perform the work under their original per-acre bid price, nor does it excuse the State from paying Contractor for work completed to project specifications. Changes in acreage or parcel configuration will add or exchange work areas with characteristics similar to those in the original Project Area. When possible, a Minor Change Order should be implemented so as to leave a consolidated and contiguous project area having similar access to that originally described in the Scope of Work.

Major Change Order. If the State determines that a change in the Scope of Work is necessary, and that change does not qualify as a Minor Change Order, the State and the Contractor may negotiate a Major Change Order as an amendment to the original contract. Examples of Major Change Orders include: (1) a reduction or cancellation of acreage that is greater than 10% of the original Project Area or (2) a change in the Project Area such that the new project characteristics are not comparable to those described in the original Scope of Work. Major Change Orders may authorize an increase in the unit price of per-acre bid submitted by the Contractor, payment of part or all of equipment mobilization costs incurred by the Contractor, or a combination of both. Any Major Change Order shall be supported by documentation supporting the equitable adjustment in contract terms and is subject to approval by the State of Utah Division of Purchasing.

Change Order Limitations. The sum of all payments made under one or more Change Orders on a single contract may not exceed the liability cap for the contract, calculated by identifying the per-acre bid price, and multiplying that figure by 10% of the acreage within the Project Area that remains untreated. For example, the maximum payment authorized under a Major Change Order would be calculated as follows:

$50 per acre bid price x (10% of 500 acres left untreated) = $2,500 Maximum or $250 per acre bid price x (10% of 1250 acres left untreated) = $31,250 Maximum

Nothing in this Section relieves the Contractor from their obligation to perform as described in Section 1, unless the State determines that a change order is appropriate. Under no circumstances may a Change Order exceed the total approved contract price. In most cases, the actual Change Order amount will be substantially less than the maximum liability cap for the contract. Nothing herein shall be construed as eliminating or modifying a Contractor’s obligation to mitigate damages they may incur due to the circumstances necessitating a Major Change Order, or the State’s right to terminate an Agreement in lieu of issuing a Change Order.

6/22/2026