4 - 8-26-2025 BID SHEET - Chipseal-Slurry Seal.pdf
PDF 62 KB Posted
- Solicitation number
- 25-6
- Issued by
- Gilpin County, Colorado
About this file
This document is a bid schedule for the 2025 Gypsum Street Renovations Chipseal & Slurry Seal project for the Town of Gypsum, covering street maintenance and surface treatment work across multiple streets in two primary areas: Red Hill and Buckhorn. The project involves chipseal and fog coat treatments for streets in the Red Hill area (including Knob Ln, Sunset Ln, Strohm Cir, Cedar Dr, and Beacon Rd) and slurry seal treatments for streets in the Buckhorn area (including Indian Heights Way, Apache Dr, Aztec Ct, Cochise Dr, and several other streets). The non-mandatory pre-bid meeting is scheduled for September 9, 2025, with bid opening on September 16, 2025, and Town Council selection on September 23, 2025. The work is to be completed no later than October 24, 2025, with 100% completion and acceptance by October 31, 2025.
The bid schedule provides detailed square footage for preparation and treatment of each street, with separate sections for chipseal/fog coat and slurry seal work. While no specific pricing is filled in, the document specifies technical requirements such as using Type 1 chip seal with 1/4" chips, requiring a fog coat after chip sealing, and using Type 1 #200 x 1/8" slurry seal. The contractor will be responsible for public information outreach, traffic control, protecting infrastructure like manholes and valve boxes, and submitting invoices according to specific municipal guidelines. The project includes a two-year warranty, and the contractor must provide door knockers to notify residents of work one week in advance of starting.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2025 Gypsum Street Renovations Chipseal & SlurrySeal
A
B
C
D
E
F
G
H
I
J
K
L
DESCRIPTION QNTY Unit Unit Price Total
1 Mobilization for all Chipseal and Fog Coat work 1 LS -$ -$
1a Public Information Outreach (Red Hill Area) 1 LS -$ -$
Knob Ln
2 Prep work (Clean Road) 15,932 SF -$ -$
3 1/4" Chipseal and Fog Coat 470'x25 +fillets & 2 half moons= 11,750+4182 15,932 SF -$ -$
4 Traffic Control 1 LS -$ -$
Sunset Ln
5 Prep work (Clean Road) 26,432 SF -$ -$
6 1/4"Chipseal and Fog Coat 890'x25' + fillets & 2 half moons = 22,250+4,182 26,432 SF -$ -$
7 Traffic Control 1 LS -$ -$
Strohm Cir 8 Prep work (Clean Road) 84,386 SF -$ -$
9 1/4"Chipseal and Fog Coat 3336'x25' + fillets & 2 half moons = 83,400+986 84,386 SF -$ -$
10 Traffic Control 1 LS -$ -$
Cedar Dr 11 Prep work (Clean Road) 82,325 SF -$ -$
12 1/4"Chipseal and Fog Coat 2798'x25' 495'x25' + fillets & 2 half moons = 69950+2,81882,325 SF -$ -$
13 Traffic Control 1 LS -$ -$
Beacon Rd 14 Prep work (Clean Road) 52,374 SF -$ -$
15 1/4"Chipseal and Fog Coat 2080'x25' + fillets 52,000+374 52,374 SF -$ -$
16 Traffic Control 1 LS -$ -$
TOTAL -$
DESCRIPTION QNTY Unit Unit Price Total
17 Mobilization for all work and Slurry seal 1 LS -$ -$
17a Public Information Outreach (Buckhorn Area) 1 LS -$ -$
Indian Heights Way
18 Prep work (Clean Road) 21,400 SF 21,400 SF -$ -$
19 Slurry Seal 21,400 SF 856'x 25' 21,400 SF -$ -$
20 Traffic Control 1 LS -$ -$
Apache Dr
21 Prep work (Clean Road) 41,967 SF 41,967 SF -$ -$
22 Slurry Seal 41,967 SF 509'x25' 921'x25' 41,967 SF -$ -$
12,725 + 23,025 + 2 half moons 12,725 + 6,217
23 Traffic Control 1 LS -$ -$
Aztec Ct
24 Prep work (Clean Road) 12,804 SF 12,804 SF -$ -$
25 Slurry Seal 12,804 SF 413'x25' 10,325'+ half moons 2,404' 12,804 SF -$ -$
26 Traffic Control 1 LS -$ -$
Cochise Dr
27 Prep work (Clean Road) 35,200 SF 35,200 SF -$ -$
28 Slurry Seal 35,200 SF 1,408'x25' 35,200 SF -$ -$
29 Traffic Control 1 LS -$ -$
Coronado Ct
30 Prep work (Clean Road) 6,158 SF 6,158 SF -$ -$
31 Slurry Seal 6,158 SF 6,158 SF -$ -$
32 Traffic Control 1 LS -$ -$
Cochise Ct
33 Prep work (Clean Road) 8,303 SF 8,303 SF -$ -$
34 Slurry Seal 8,303 SF 8,303 SF -$ -$
35 Traffic Control 1 LS -$ -$
Buckhorn and Gypsum Creek Rd
Slurry Seal Should be Type 1 #200 x 1/8" (3.175mm)
2025 Chipseal and Fog Coat
Oil (CQS-1h,)
Oil Must be SRS2P and Chip 1/4
Standards and Definitions:
All construction specifications per the Gypsum Public Works Manual, and current ADA requirements.
Red Hill
2025 Slurry Seal
Notice to Proceed- as soon as all contract documents are signed and received from the Council selected bidder.
REV. 08/26/2025
Bid schedule critical times and dates:
Non-Mandatory Pre-bid meeting Tuesday, September 9, 2025 at 10:00 AM at Community Development Room
Bid Opening = Tuesday, September 16, 2025 at 10 AM at the Community Development Conference Room.
Town Council (T.C.) selection on September 23, 2025 at a 7 PM public meeting
See attached specifications for Chip Seals, Fog Coat, and Slurry Seals. Seal coats shall follow the requirments of the Fog Coat
Chip Seal shall be Type 1 chip seal with 1/4" Chips. A Fog Coat is required following the chip seal.
The contractor shall put out door knockers 1 week ahead of the work notifying residences and businesses and any impacts associated with the work and the duration of the impact.
The contractor shall ensure all manholes, inlets, valve boxes, etc. are protected during the work. A plan to protect the manholes, inlets, valve boxes, etc. during the work shall be submitted to the Town for approval prior to starting the work.
Invoices- Submitted before Noon on the 1st &/or 3rd Tues. of the month will be approved by Council for payment on the following Tues.
Work completed and ready for punch list No Later Than (NLT) Octobeer 24, 2025.
100% completed and accepted for Two-Year Warranty start NLT October 31, 2025.
Navajo
36 Prep work (Clean Road) 50,875 SF 50,875 SF -$ -$
37 Slurry Seal 50,875 SF 50,875 SF -$ -$
38 Traffic Control 1 LS -$ -$
Crocket Ct
39 Prep work (Clean Road) 13,407 SF 13,407 SF -$ -$
40 Slurry Seal 13,407 SF 13,407 SF -$ -$
41 Traffic Control 1 LS -$ -$
BlackHawk Rd
42 Prep work (Clean Road) 16,500 SF 16,500 SF -$ -$
43 Slurry Seal 16,500 SF 660'x25' 16,500 SF -$ -$
44 Traffic Control 1 LS -$ -$
Bowie Rd
45 Prep work (Clean Road) 16,000 SF 16,000 SF -$ -$
46 Slurry Seal 16,000 SF 633'x25' 16,000 SF -$ -$
47 Traffic Control 1 LS -$ -$
Arawak Way
48 Prep work (Clean Road) 5,825 SF 5,825 SF -$ -$
49 Slurry Seal 5,825 SF 233'x25' 5,825 SF -$ -$
50 Traffic Control 1 LS -$ -$
Bridger Dr
51 Prep work (Clean Road) 32,825 SF 32,825 SF -$ -$
52 Slurry Seal 32,825 SF 1313'x25' 32,825 SF -$ -$
53 Traffic Control 1 LS -$ -$
Mohawk Ct
54 Prep work (Clean Road) 7,162 SF 7,162 SF -$ -$
55 Slurry Seal 7,162 SF 7,162 SF -$ -$
56 Traffic Control 1 LS -$ -$
Custer Ct
57 Prep work (Clean Road) 10,062 SF 10,062 SF -$ -$
58 Slurry Seal 10,062 SF 10,062 SF -$ -$
59 Traffic Control 1 LS -$ -$
Maverick CT
60 Prep work (Clean Road) 11,629 SF 11,629 SF -$ -$
61 Slurry Seal 11,629 SF 11,629 SF -$ -$
62 Traffic Control 1 LS -$ -$
Powderhorn Dr
63 Prep work (Clean Road) 44,864 SF 44,864 SF -$ -$
64 Slurry Seal 44,864 SF 41,300'x25' 41,300+ Parking 3,564 44,864 SF -$ -$
65 Traffic Control 1 LS -$ -$
Buckhorn Valley Total TOTAL -$
Gypsum Creek Rd
Daggett Ln to Brightwater N Enterance 66 Mobilization for all work Gypsum Creek Rd 1 LS -$ -$
67 Removal existing stripes 1 LS -$ -$
68 Prep work (Clean Road) 5635'x30' 169,050 SF -$ -$
69 Slurry Seal 5635'x30' 169,050 SF -$ -$
70 Traffic Control 1 LS -$ -$
71 Striping with Reflective Beads 5,635 'x 4" Double Yellow 5,635 LF -$ -$
72 Striping with Reflective Beads 11,270' x 4" Single white 11,270 LF -$ -$
Gypsum Creek Total TOTAL -$
$0.00
$0.00
$0.00
TOTAL $0.00
Printed Name of Bidder Signature Date
Company Name $0.00
Gypsum Creek Rd
Type II Slurry Seal
Oil (CQS-1h)
SUMMARY of Bids:
Chipseal and Fog Coat Red Hill
(formula uses 1.5%, so change if your is different) Performance & Two Year Warranty Bond =
_____________________________________ ___________________________ , 2025
Amount to be read at the bid opening =
Slurry Seal Buckhorn
Slurry Seal Gypsum Creek
SUB TOTAL