4-2. BID-326-26 Specifications.pdf
PDF 224 KB Posted
- Attached to
- Boulder Canyon Trail Repair Project
- Solicitation number
- BID-326-26
- Issued by
- Boulder County, Colorado
About this file
This document is the specifications file for Boulder County Parks and Open Space (BCPOS) in Colorado for BID-326-26, the Boulder Canyon Trail Repair Project. The project involves construction of a grouted boulder slope protection wall and restoration of a 1.9-mile multi-use trail segment located west of downtown Boulder along Highway 119. The scope of work includes site preparation, demolition of temporary repair structures, placement of structural materials for the slope containment wall, trail surface restoration using native seed mixes, and operation of a courtesy shuttle service for trail users during the project closure. Major work items encompass securing applicable permits, mobilization, site preparation with best management practices, heavy equipment access via an existing low water crossing, protection of two existing 16-inch City of Boulder high-pressure water lines, clearing and grubbing, dewatering temporary excavations, and a minimum one-year warranty on re-vegetation efforts. The project schedule spans from late December 2026 through February 26, 2027, allowing 44 calendar days for completion with potential for seven-day-per-week work upon written request. Standard work hours are Monday through Friday, 8:00 a.m. to 5:00 p.m., with weekend and night work requiring written County approval.
The contractor is responsible for obtaining all required federal, state, and local permits prior to construction commencement, including Colorado Department of Public Health and Environment storm water and dewatering permits, Boulder County stormwater quality and flood plain development permits, building permits, and CDOT right-of-way and utility permits. Contractor responsibilities encompass equipment decontamination to prevent invasive species spread, procurement of all construction water (prohibited from Boulder Creek), biodegradable hydraulic fluid use for equipment operating in surface waters, provision of portable restroom facilities, and submission of critical path scheduling, traffic control plans, and stormwater management plans prior to mobilization. The document specifies that no site amenities are available, contractor must provide port-o-lets, and no construction water or electricity exists on-site. Haul routes are constrained to 8:30 a.m. to 4:00 p.m., Monday through Friday, with variable message boards required. All work product and data become exclusive property of Boulder County. The selected contractor must maintain appropriate licensing and provide complete disclosure of all subcontractors.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID-326-26 SPECIFICATIONS
PROJECT SITE AMENITIES:
1. No site amenities are available.
2. Contractor will be expected to provide port-o-lets for field operations.
3. No construction water or electricity available on-site.
a. Contractor to furnish as needed.
b. Boulder Creek water cannot be used for construction activities.
SPECIFICATIONS:
The Boulder Canyon Multi Use Trail, located immediately west of downtown Boulder, is regularly maintained by Boulder County Parks and Open Space (BCPOS). The 1.9 mile facility includes segments constructed with concrete trail tread as well as sections surfaced with crusher fines.
Originally built in the early 1990s through a partnership among the Colorado Department of Transportation (CDOT), the City of Boulder, and Boulder County, the trail lies primarily within CDOT right of way along Highway 119 and on unincorporated lands owned by the City of Boulder.
A Management and Maintenance Agreement dated December 17, 1992, and a Joint Management Agreement dated December 8, 2005, assign Boulder County responsibility for all capital improvements, including repairs and upgrades to the trail.
The proposed scope of work includes construction of a properly engineered and grouted boulder slope protection wall adjacent to the existing bridge abutment, as well as restoration of the approach trail to its pre scour condition.
The Project Consists of:
1. Construction of grouted boulder slope containment wall.
2. Construction of trail approach impacted by scour and any associate site activities.
3. Reclamation of all disturbed areas with different identified native seed mixes.
Major items of work include, but are not limited to:
1. Secure applicable permits prior to construction startup.
2. Mobilization and project controls.
3. Operation of a curtesy shuttle for duration of project to ensure the public who use the trail to commute have a safe route around the closure.
4. Site preparation includes a pre-construction survey, necessary Best Management
Practices (BMPs)/Stormwater Control Measures (CMs).
5. Access for heavy machinery and materials by way of existing low water crossing East and downstream of concentrated project work site. Return Low Water Crossing to pre-project condition or better.
6. PROTECTION OF EXISTING 16” CITY OF BOULDER HIGH PRESSURE WATER LINES (2EA.)
7. Clearing and grubbing within limits of disturbance.
8. Demolition and removal of existing temporary repair structures.
9. Unclassified excavation in conformity with the lines and grades shown in the construction drawings.
10. Dewatering temporary excavations.
11. Placement of structural materials as specified for linear/vertical construction.
12. Hauling excess material to predetermined disposal site.
13. Installation of perimeter control for resource preservation.
14. A minimum of one (1) year guarantee and warranty will be required for any re-vegetation efforts for survival rates.
15. Restoration of internal access/haul routes, staging areas and demobilization.
Site Access:
1. Site access will be off HW 119 at Low Water Crossing location. See the Site Plan Sheet of the Construction Drawings for proposed site access and staging area locations.
Schedule:
The tentative schedule for construction is late December 2026, Through February 26, 2027, unless weather or permit procurement delay the start and will go through cold weather conditions dependent upon final contract award and Notice to Proceed. The selected Contractor should be prepared and take all appropriate measures to ensure proper construction of all elements of the scope of work, including but not limited to:
1. Cold weather protection for grout at slope containment stone wall.
2. Proper compaction of structure subgrade and trail approach for trail surfacing.
3. Proper operation and maintenance of any de-watering equipment used.
These measures should be incorporated into the unit costs of each line item in the Bid Tab and will not be paid as extra costs.
CONTRACTOR RESPONSIBILITIES:
1. Drawings And Specifications:
a. The selected Contractor shall agree to work in a timely and efficient manner, and in accordance with the Drawings and Specifications attached with this BID, to accomplish the tasks specified in this Project.
2. Permitting:
a. The selected Contractor shall be responsible for obtaining permits and licenses as required by all Federal, State and Local regulations.
b. The selected Contractor will obtain permits required for construction, collectively herein after referred to as, Contractor Required Permits, including but not limited to the following:
i. Colorado Department of Public Health and Environment (CDPHE) Water Quality Control Division Storm Water General Permit for Construction Activities.
ii. CDPHE Construction Dewatering Permit (if applicable).
iii. Colorado Division of Water Resources Notice of Intent to Dewater (if applicable).
c. Boulder County Stormwater Quality Permit (SWQP).
d. Boulder County Flood Plain Development Permit.
e. Boulder County Building permit – Slope protection wall.
f. Contractor will provide information to BCPOS as part of the Boulder County
Permits. Documentation shall include:
i. Traffic Control Plan (including haul routes, access points, fueling locations, staging areas, access routes, construction sequencing with proposed quantities and a Traffic Control Plan developed a certified traffic control supervisor).
ii. Boulder County Access permit (if applicable).
iii. Boulder County Oversize/Overweight permit (if applicable).
iv. CDOT Right of Way (ROW)Permit (if applicable)
v. CDOT Utility/Special Use permit (Required)
Permitting will commence within (3) days of the date of the execution of the Contract and upon written Notice to Proceed from the County. All Contractor-required permit applications will be submitted to applicable approval agencies within ten (10) days of the execution of the Contract and upon written Notice to Proceed from the County. Project mobilization will commence within
(4) days of approval of all Contractor-required permits. The Project is to be completed on or before February 26, 2027.
3. Equipment:
a. All equipment and vehicles utilized by the selected Contractor shall meet all the requirements of Federal, State and Local regulations without limitation, including all U.S. Department of Transportation (USDOT), and Colorado Department of Transportation (CDOT) safety regulations.
b. Equipment operating within or adjacent to any surface waters shall be free of fluid leaks. Biodegradable hydraulic fluids shall be utilized for all equipment operating in surface waters.
i. The contractor shall submit a list of equipment operating with certified non-toxic, biodegradable hydraulic fluids to the engineer prior to use.
c. All fueling, oiling, or maintenance of equipment shall be performed in designated locations, with adequate Best Management Practices to contain potential spills in accordance with the Plans and Specifications.
d. All equipment that comes into contact with Boulder Creek will need to be properly sanitized/disinfected to prevent introduction of aquatic invasive species, mud, or other contaminated debris from entering into the[SC14.1] riparian area.
e. All equipment must be maintained and in good working order. Continuous, excessive oil and hydraulic fluid leakage will not be tolerated and will be cause to have the machinery removed from the project site and include removal of any contaminated soil by the selected Contractor.
f. All operators shall have the skills to operate the machinery in a responsible, safe, and efficient manner while being conscientious of the natural resource values.
g. The selected Contractor will be responsible for providing on-site portable restroom facilities for their staff.
4. Biodegradable Hydraulic Fluids:
a. Equipment operating within or adjacent to any surface waters shall be free of fluid leaks. Biodegradable hydraulic fluids shall be utilized for all equipment operating below the ordinary high-water level.
i. The contractor shall submit a list of equipment operating with certified non-toxic, biodegradable Hydraulic fluids to the Engineer prior to use.
ii. All fueling, oiling, or maintenance of equipment shall be performed in designated upland locations, with adequate BMPs to contain potential spills.
iii. Acceptable biodegradable fluids must meet Section 12 of the MSDS Data Sheets which states:
b. AQUATIC/ECOTOXICITY: Based on previous studies, LC50/EC50 is greater than 3,000 ppm (3000 mg/L) (amount of substance that kills 50 percent of the test animals in a given time).
c. BIODEGRADATION: Ultimate Biodegradation is listed as “Readily biodegradable” >60% after 28 days (inherently biodegradable is not sufficient) *.
d. PERSISTENCE AND DEGRADABILITY: Readily biodegradable >60% after 28 days
e. BIOACCUMULATION: Non-bioaccumulating .
f. A spill kit, including absorbent socks and booms, shall be kept onsite during all work with machinery (emergency pollutant isolation and clean-up materials, with procedures).
g. All crew members shall be trained on how to use the spill kit equipment and where the materials are kept onsite.
h. The Project Manager shall approve the Contractor’s plan for leaking equipment extraction from the creek (spill plan information to be included in SWMP).
5. Heavy Equipment Operations And Maintenance:
a. To minimize the spread of invasive plant species, all equipment and gear shall be free of all mud, vegetative matter, organic material, seeds and other debris prior to its delivery to the project site.
i. All equipment shall be thoroughly cleaned, including the undercarriages, tracks, turrets, buckets, drags, teeth, tires, etc.
b. To minimize the spread of aquatic nuisance species (ANS), decontamination practices should be employed if equipment and gear were used in another stream, river, lake, reservoir, pond or wetland.
c. Equipment that shall be treated for ANS includes all parts of heavy machinery and vehicles of all types and sizes that are operating below the ordinary high-water mark.
d. Gear that must be treated for ANS includes boots, waders, hand tools, and all other materials and attire used previously in the live water.
e. If pumping out of a creek or other waterbody, all water pumps and hoses must be cleaned and disinfected prior to use on the project to prevent introduction of invasive aquatic organisms into the watershed.
f. To decontaminate equipment and gear the Contractor shall use one of the following treatments:
i. Remove all mud and debris and organic material from equipment (tracks, turrets, buckets, drags, teeth, etc.) and gear. Spray/soak equipment and gear with a solution of commercial grade quaternary ammonium disinfectant compound containing at least 8.0% active ingredient diluted in solution to achieve at least 0.8% concentration (roughly twelve (12) ounces of product per gallon of water).
1. Specifically, a 1:15 solution of Quat 4 or Super HDQ Neutral institutional cleaner and water, could be used for effective treatment.
2. Treated equipment and gear should be kept moist for at least ten
(10) minutes. Treated equipment and gear should be rinsed with water from ANS free source, managing reinstate as a solid waste in accordance with local, County, State, or Federal regulations.
ii. Remove all mud and debris and organic material from equipment (tracks, turrets, buckets, drags, teeth, etc.) and gear.
1. Spray/soak equipment and gear with water hotter than 140 degrees Fahrenheit for at least ten (10) minutes.
2. Do not move water from one water body to another. Be sure Equipment is dry before use.
g. Prior to mobilizing equipment and gear to the project site, the Contractor shall submit to BCPOS a written list of the equipment and gear certifying that it was cleaned and if needed, that it was decontaminated using one (1) of the two (2) methods specified above.
i. Equipment and gear shall be inspected following treatment and prior to unloading at the project site to ensure mud, vegetative matter, organic material, seeds and other debris has been removed and none remains.
ii. BCPOS staff shall inspect equipment prior to unloading at the project site and reserve the right to reject and request additional cleaning of any piece of equipment deemed not to be cleaned satisfactorily.
h. After project completion, equipment and gear should be treated prior to use in another stream river, lake, pond, or wetland.
4. Wildlife Conservation Measures:
a. This project is in an area of many protected plants and wildlife, and as such, there are special provisions that are outlined in applicable permits, which must be strictly adhered to.
5. Construction Water:
a. The selected contractor will be responsible for procuring all water that will be used for construction activities.
i. This includes, but is not limited to: dust abatement, soil compaction, grout/concrete mixing, equipment washing, or other consumptive use activity.
ii. At no time is the contractor permitted to use water from Boulder Creek for any construction activities.
6. Water Discharge Requirements:
a. Contractor shall protect water quality by complying with the lawful requirements of Boulder County’s Illegal Discharge Ordinance (No. 2012-4), MS4 permit (COR090000), and MS4 Program Description Documents regarding discharges to storm drainage systems or other watercourses in Boulder County’s jurisdiction.
7. Traffic Control Plan:
a. Traffic Control Plan shall include haul routes, access points, fueling locations, staging areas, site access routes, construction sequencing and proposed quantities and a Traffic Control Plan developed by a certified traffic control supervisor.
b. Designated haul routes for import of material or removal of material beyond the project boundaries have to meet all Federal, State, and Local regulations. This will include the following conditions:
c. The selected Contractor shall submit a Traffic Control Plan (TCP) including a haul plan to the Engineer for approval at the pre-construction meeting.
i. The TCP shall be in conformance to the Manual of Uniform Traffic Control Devices (MUTCD) and CDOT standards and be developed by a certified Traffic Control Supervisor.
ii. The TCP and haul plan will be reviewed by the Boulder County Community Planning & Permitting, BCPOS and the Engineer prior to the Grading permit submittal.
d. A final haul plan and TCP developed by the selected Contractor shall be provided to Boulder County project representative for review and approval.
e. Hours of hauling shall be from 8:30 AM to 4:00 PM, Monday through Friday, to limit impacts on regular vehicular traffic, especially during peak commuter periods.
f. Flaggers and/or other traffic control measures may be required at the intersections of the access points to roadways and along off-site haul routes during hauling operations.
g. Variable Message Boards will be required along off-site haul routes during hauling operations.
h. Flaggers and all necessary traffic control devices shall be supplied and installed by the Contractor.
i. The TCP and haul plan shall address the above conditions at a minimum, as well as depict intended circulation (internal to site, between sites, off-site) for haul traffic, anticipated truck traffic volumes per haul route (daily and project total), and timing of hauling based on construction sequencing.
j. Preliminary staging areas, access points, access routes and haul routes are identified on the Plans. The selected Contractor shall be responsible for the final haul routes and obtaining approval from Boulder County/CDOT for all final staging areas, access points, internal access routes and external haul routes.
8. Curtesy Shuttle:
a. See traffic control specification section TRAFFIC CONTROL 01 55 26
b. Contractor shall include all costs and required permits/approval to provide
Courtesy Shuttle Service to pedestrians and cyclists impacted by the Boulder Canyon Trail closure.
c. The Courtesy Shuttle Service will provide transport to and from [see shuttle map Attachment E].
i. The hours of operation are 7 days a week, 8:00 a.m. to 6:00 p.m. for the following date ranges:
1. Mobilization date and Trail closure through project completion and re-opening of the Boulder Canyon trail segment impacted by project.
9. Submittal Schedule and Log:
a. Submittal schedule will be compiled within two (3) days after Notice to Proceed is provided. Review, approval, rejection, and revision of submittals will be recorded and tracked separately through submittal log.
b. A single submittal transmittal form shall be used for each technical specification section, item, class of material or equipment for which a submittal is required.
c. A single submittal covering multiple specification sections will not be accepted.
Substitution requests will be initiated through a Request for Information (RFI).
10. Request For Information (RFI) Log:
a. Prepare, maintain, and submit a tabular log of RFI on a weekly basis.
11. Deficiency Log:
a. Boulder County representatives will identify, document and maintain deficiency log for handling deficient and non-conforming work.
i. The cause of such conditions shall be determined and documented and measures implemented to prevent recurrence.
12. Protection Of Existing Utilities:
a. Contact and coordinate with utility companies regarding protection of existing utilities and special requirements at utility crossing locations, as well as other conditions where the Work is nearby existing utilities.
i. Contractor shall be responsible for all costs of coordination with utilities including, but not limited to outages, protection or support and any fees for costs from the utility.
b. Where the drawings indicate utilities have been field located during design or certain utility locations will be exposed as part of the Work, make exploratory excavations as deemed necessary to determine the exact locations and depths of utilities which may interfere with the Work.
i. All such exploratory excavations shall be performed within a sufficient time, in advance of construction, to avoid possible delays.
ii. Notify the County if such exploratory excavations show the noted utility locations to be in error.
c. Protect underground utilities and other improvements which may be impaired during construction operations, regardless of whether or not the utilities are indicated on the drawings.
i. Take all possible precautions for the protection of unforeseen utility lines to provide for uninterrupted service and to provide such special protection as may be necessary.
13. Hazardous Material:
a. Contractor and/or Subcontractors will properly handle, package, transport, and dispose of hazardous materials and/or waste in accordance with all Local, State, and Federal regulations, laws, and ordinances.
b. If hazardous substances are released to the project area during construction, these Federal, State, and Local requirements must be followed in response and cleanup.
14. Cultural Resources:
a. If during the course of work, unmarked graves, burials, human remains, or archaeological artifacts (prehistoric or historic) are discovered, the contractor shall stop work in the vicinity of the discovery, secure the site, and take all reasonable measures to avoid or minimize harm to the finds.
b. All archaeological findings will be secured and access to the sensitive area restricted. The contractor shall notify Boulder County immediately if any cultural resources are discovered during construction, and Boulder County will notify SHPO(State Historic Preservation Office/THPO (Tribal Historic Presevation Officer) immediately.
15. Safety Plan:
a. Contractor shall submit one (1) Site Specific Health and Safety Plan for all project activities.
16. Stormwater Management Plan (SWMP):
a. Contractor shall submit one (1) SWMP for all project activities.
17. Spill Prevention, Control, And Countermeasure (SPCC) Plan:
a. Contractor shall submit one (1) site specific SPCC Plan for all project activities.
18. Material Disposal:
a. Contractor shall submit all documentation of all material that is disposed of off-site; including disposal location, associated landfill permits and load tickets.
COUNTY RESPONSIBILITIES:
1. Pre-Construction:
a. Provide the Contractor with a Notice to Proceed (NTP) indicating approval to proceed with the work.
b. Designate a person to act as the County’s contact with respect to the services related to this project. The County will review the limits of disturbance, monitor all scope of work and be available during normal construction hours and days of the week to answer any questions or address any issues that may arise.
c. Provide the contractor with all available information pertinent to completing project.
2. Engineer Coordination:
a. Boulder County will serve as the point of contact between the Design Engineers and selected Contractor.
b. They will also coordinate with the Design Engineers and selected Contractor to address any construction issues and provide design changes or clarifications as needed.
3. Drawings And Specifications:
a. BCPOS will provide digital Drawings and Specifications files as needed by the selected Contractor in order to fulfill the terms of the Contract.
4. Permitting:
a. BCPOS will support the selected Contractor in obtaining permits and licenses.
BCPOS has already begun the process of obtaining the following permits:
i. U.S. Army Corps of Engineers Jurisdictional Determination and 404 Permit.
ii. U.S. Fish and Wildlife Service Endangered Species Act Section 7 Review.
iii. State Historical Preservation Office (SHPO) National Historic Preservation Act Section 106 Review.
iv. Colorado Parks and Wildlife SB40 Review.
v. Boulder County Food Plain Development Permit – No rise status.
vi. Boulder County Building Permit – Slope Protection wall.
vii. Boulder County Stormwater Quality Permit (SWQP).
5. Staging Areas:
a. Staging areas and stockpile areas are identified on all attached Drawings.
6. Additional Information:
a. Pre-Construction Meeting:
i. Prior to commencement of work, the selected Contractor, any subcontractors and the people responsible for coordination of the work shall meet with representatives from Boulder County.
ii. The meeting will be held at the Boulder County Parks and Open Space Administrative Building at 5201 St. Vrain Road, Longmont, Colorado 80503.
iii. The detailed pre-construction conference agenda will be provided to the selected Contractor for review prior to the meeting.
iv. The selected Contractor will be responsible for providing a base line schedule to the County’s representative at the meeting.
v. Weekly periodic progress meetings will be conducted at the project site to discuss schedule, progress, coordination, submittals, and job-related topics.
vi. The County representative may be present at all or some of the designated weekly progress meetings.
DELIVERABLES:
1. Critical path construction schedule – Prior to mobilization
2. Copy of all applicable permits/Traffic Control Plans’s – Prior to mobilization
3. Complete submittal log – Prior to mobilization
4. Confirmation of operational shuttle service for trail users impacted by trail closure – Prior to mobilization.
PERMITS, LICENSES, LOCATES AND CODES:
The selected Contractor shall have full responsibility for identifying and obtaining, prior to the start of work, and for maintaining throughout the term of the Project, any permits and licenses which may be required in order to carry out the work. The Contractor shall also be responsible for following all State and County codes, which may be required in order to carry out the Project.
The Contractor shall also be responsible for all "locates" of all public utilities related to performing work under the terms of this Contract. The Contractor shall also be responsible for insuring that any of its subcontractors performing work on the Project satisfy the provisions of this paragraph.
Contractor is responsible to contact and coordinate with utility companies regarding protection of existing utilities and special requirements at utility crossing locations, as well as, other conditions where work is nearby existing utilities. Contractor shall be responsible for all costs of coordination with utilities including, but not limited to, outages, protection or support and any fees for costs from the utility.
CONTRACTOR LICENSING:
It is the responsibility of the selected Contractor to apply for and ensure the appropriate Contractor’s license is obtained.
General contractors, HVAC contractors, and roofing contractors require licensing through the Boulder County Community Planning and Permitting Department. Electricians and plumbers are required to be licensed through the State of Colorado and registered with the Boulder County Community Planning and Permitting Department. Furthermore, it is required for all Architects, Professional Engineers and Professional Land Surveyors to be fully-licensed through the State of Colorado.
SUBCONTRACTORS:
Contractor is required to disclose to County the complete business name(s) of all potential subcontractors that will be assigned to this Project, should the Contractor be selected. Contractor acknowledges that it is completely responsible for the actions or inactions of its subcontractors.
Contractor shall be responsible for the compliance of all subcontracting parties with the terms of the Contract and with any applicable local, state or federal laws or regulations. Contractor shall be solely responsible for timely payment of its subcontractors.
PROJECT COMPLETION SCHEDULE:
The date of completion will be based on the date of Notice to Proceed. The project will allow a 44-day calendar schedule. Time is of the essence so the County will likely allow work 7-days a week per written request.
CONFLICT OF INTEREST:
Any party that has developed, designed or drafted specifications, requirements, statements of work and/or has participated in planning activities for this Project may be excluded from consideration for the award of this Project.
CHANGE ORDERS:
Any unplanned, change orders, modifications or additional services to this Project, shall be submitted by the Contractor, in a separate, written document, including a fee schedule and completion schedule and presented to the County for review. Approval from the County, in writing, must accompany all change order requests.
OVERNIGHT CAMPING:
Boulder County prohibits any overnight camping; all operational staff, including designated security staff, are not authorized to be present at Project site from sunset to sunrise, the open space property will remain closed during these hours to the contractor and its subcontractors and/or designated representatives and/or agents, unless specifically authorized by a BCPOS representative.
HOURS OF OPERATION:
Contractor work hours shall be designated as Monday through Friday, 8:00 a.m. to 5:00 p.m.
Work on Saturdays and Sundays, nights, and designated Federal Holidays shall not be allowed unless approved, in writing, by the County. We do anticipate Saturday and possibly Sunday work if requested in writing by the contractor. Hauling during the weekend days will still be constrained per the contract documents.
OWNERSHIP OF WORK PRODUCT:
All work product, property, data, documentation, information or materials conceived, discovered, developed or created by the selected Contractor pursuant to this bid and subsequent Contract will be owned exclusively by the County. To the extent possible, any Work Product will be deemed to be a work made for hire. The selected Contractor unconditionally and irrevocably transfers and assigns to the County all right, title and interest in and to any Work Product.
The selected Contractor will agree to keep confidential all County Data, and will agree not to sell, copy, modify, reproduce, republish, assign, distribute, data mine, search or disclose any such confidential information to any other person or entity without the County’s written permission, including metadata (e.g. aggregations of county data or analysis of county data content).
The Contractor shall not access County accounts or County Data, except in the event as required by the express terms of a written contract between the mutual Parties and/or at the express written request of the County. All data obtained by the Contractor in the performance of this solicitation resulting in a contract shall become and remain the property of the County. The Contractor shall not use any information collected in connection with the service issued from this solicitation for any purpose other than fulfilling a County contract for this BID.