This is an Invitational Low Bid Solicitation document issued by the State of Utah Division of Facilities Construction and Management (DFCM) for construction services at Camp Williams Building 6150 in Bluffdale, Utah. The project involves removal and replacement of five packaged rooftop units (RTUs), updated HVAC controls, new architectural finishes, and related gas, electrical, and controls connections. The solicitation is extended exclusively to six invited contractors: Halverson Mechanical, Innovative Sheet Metal, Mechanical Service & Systems, Rocky Mountain Mechanical, Salmon Mechanical, and Todd Packer Heating and Air. A mandatory in-person meeting is scheduled for July 16, 2026, at 10:00 AM at the Camp Williams jobsite, which all prime contractors must attend and sign in to remain eligible to bid. The questions deadline is July 22, 2026, at 3:00 PM, the addendum deadline is July 27, 2026, at 3:00 PM, the bid and bid bond deadline is July 30, 2026, at 3:00 PM via the U3P website, and the subcontractor lists deadline is July 31, 2026, with submission to dfcmcontracts@utah.gov. The project has a substantial completion date of December 3, 2026. Two additive alternates are available: roof access from the interior with a hand-operated roof hatch and guard rails, and a wall and door to bifurcate the break room and provide a new mechanical controls room.
The construction budget is $80,000.00 with liquidated damages assessed at $200 per day for delays. Bids must be accompanied by a 5% bid bond on the AIA Document A310-2010 form or equivalent from a surety authorized to do business in Utah. The project is tax-exempt and has energy incentives available. All contractors must submit a DFCM Subcontractors List Form by the bid deadline, certify they are not debarred or suspended from government contracts, and comply with Utah state licensure requirements. DFCM intends to award the contract to the lowest responsive and responsible bidder and execute a Short Form Construction Contract. Contractors must conduct site visits, examine all solicitation documents, and submit bids via the U3P website; bids received after the deadline will be disqualified. The DFCM Project Manager is Rachael Strait-Neal, and all communications during the selection process must be directed to DFCM representatives only.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Division of Facilities Construction and Management Taylorsville State Office Building 4315 South 2700 West, 3rd Floor
Taylorsville, Utah 84129 dfcm.utah.gov | 801.957.7270
Invitational Low Bid Procurement for Construction Services
Project budgets up to $150,000
July 13, 2026
Camp Williams Bldg. 6150 RTU and HVAC Upgrades Utah National Guard
Bluffdale, Utah
DFCM Project #26327480 U3P Reference # DA27004
Project design provided by WHW Engineering
DFCM Invitational Low Bid for Construction Services, 5.15.2026 2
Solicitation Summary The State of Utah Division of Facilities Construction and Management (DFCM) is requesting bids for Construction services for the project below. Only the Contractors listed below are invited to bid on this project. Bids submitted by Contractors not listed below will not be considered for award.
- Halverson Mechanical - dave@halversonmechanical.com
- Innovative Sheet Metal - amanda@ismduct.com
- Mechanical Service & Systems - mikebaldassari@mss84.com
- Rocky Mountain Mechanical - rtygesen@rockymtnmech.com
- Salmon Mechanical - brandon@salmonmechanical.com
- Todd Packer Heating and Air - todpacker@gmail.com
Camp Williams Bldg. 6150 RTU and HVAC Upgrades Utah National Guard Bluffdale, Utah DFCM Project #26327480 | U3P Reference # DA27004
Communication during the selection process shall be directed to the DFCM Representatives below only.
DFCM Project Manager: Rachael Strait-Neal rachael.s.straitneal.nfg@army.mil 801-878-5104 Brief Project Description: Removal and replacement of existing RTU’s, updated controls, new architectural finishes.
Substantial Completion Date: December 3, 2026 Liquidated Damages: $200 per day Construction Budget: $80,000.00 Tax Exempt: Yes ☐ No ☒ Energy Incentives: Yes ☐ No ☒
Solicitation Schedule Event Date Time Location
Solicitation Posting Monday, July 13, 2026 9:00 AM U3P
Mandatory Meeting Thursday, July 16, 2026 10:00 AM
☒In person:
Camp Williams - Bldg. 6150 17800 South 1700 West Bluffdale, Utah Valid Drivers license required
Questions Deadline Wednesday, July 22, 2026 3:00 PM U3P
Addendum Deadline Monday, July 27, 2026 3:00 PM U3P
Bid and Bid Bond Deadline Thursday, July 30, 2026 3:00 PM U3P
Subcontractor Lists Deadline Friday, July 31, 2026 3:00 PM Email to:
dfcmcontracts@utah.gov mailto:DAVE@HALVERSONMECHANICAL.COM mailto:brandon@salmonmechanical.com https://utah.bonfirehub.com/portal/?tab=openOpportunities https://utah.bonfirehub.com/portal/?tab=openOpportunities https://utah.bonfirehub.com/portal/?tab=openOpportunities https://utah.bonfirehub.com/portal/?tab=openOpportunities mailto:dfcmcontracts@utah.gov
DFCM Invitational Low Bid for Construction Services, 5.15.2026 3
Project Details Detailed Project Description/Base Bid:
This shall include: the removal and replacement of 5 packaged rooftop units. Gas, electrical, and controls connections shall be replaced and units shall be selected to minimize roofing work. All units shall be provided with factory start up and test and balance.
Additive Alternate No. 1: Provide roof access from interior. New hand operated roof hatch with guard rails.
Additive Alternate No. 2: Provide wall and door to bifurcate the existing break room and provide new mechanical controls room.
Map Mandatory Meeting – Access to Camp Williams: Visitors to Camp Williams must show a valid drivers license at the security gate for entrance. Contractors may be escorted to the jobsite as needed.
Project Requirements:
- DFCM Approved Fabricator List
- DFCM Design Management Documents
- DFCM Roofing Design Requirements
- State of Utah High Performance Building Standard and all appendixes https://dfcm.utah.gov/construction-management/building-official/inspections-and-testing/ https://dfcm.utah.gov/construction-management/standard-documents/ https://dfcm.utah.gov/construction-management/roofing-program/ https://dfcm.utah.gov/construction-management/high-performance-building-program/
DFCM Invitational Low Bid for Construction Services, 5.15.2026 4
Solicitation Documents The solicitation documents consist of all documents listed below and referenced within this solicitation.
Solicitation Documents and Forms The following project specific documents and forms can be accessed in the U3P project for this solicitation.
Project specific documents:
- Invitational Low Bid Solicitation
- Approved Plans
- Approved Specifications
- Hazmat Survey
Standard documents and forms:
- DFCM Subcontractor List Form & Instructions
DFCM Construction Management Standard Reference Documents All DFCM standard documents referenced in this solicitation can be accessed by visiting the DFCM Construction Management – Standard Documents page of the DFCM website.
http://www.dfcm.utah.gov/
DFCM Invitational Low Bid for Construction Services, 5.15.2026 5
Procurement Process
1. Mandatory Meeting A mandatory meeting will be held on the date and time and at the location specified on the Solicitation Schedule. All prime Contractors wishing to bid on this project must attend and sign in. Contractors not in attendance at this meeting are ineligible to bid on this project. Subcontractors and suppliers are invited to attend this meeting, but it is not mandatory.
During the mandatory meeting, a presentation will be made describing the overall scope of work and intended project schedule. Interested Contractors may ask questions and request clarification about the project and the procurement process.
2. Requests for Information, Questions and Addendum All project related requests for information, clarifications, and questions must be submitted to DFCM via the U3P website no later than the time and date specified on the Solicitation Schedule. An addendum in response will be posted on the U3P website no later than the time and date specified on the Solicitation Schedule. All addenda issued shall become part of the solicitation, and any changes or additional requirements shall be incorporated into the Contractor’s proposal and/or bid.
a) Interpretation of Drawings and Specifications If any person or entity contemplating submitting a proposal or bid is in doubt as to the meaning of any part of the drawings, specifications or other contract documents, such person shall submit a request for an interpretation to DFCM via the U3P website no later than the time and date specified on the Solicitation Schedule. Any interpretation of the proposed documents will be made only by addenda posted on the U3P website. Neither DFCM nor A/E will be responsible for any other explanations or interpretations of the proposed documents. The A/E is deemed to be the architect or engineer hired by DFCM as the A/E or Consultant for the project.
b) Product Approvals Where reference is made to one or more proprietary products in the contract documents, but restrictive descriptive materials of one or more manufacturer(s) is referred to in the contract documents, the products of other manufacturers will be accepted, provided they equal or exceed the standards set forth in the drawings and specifications and are compatible with the intent and purpose of the design, subject to the written approval of the A/E. Such written approval must occur prior to the time and date specified on the Solicitation Schedule for the final addendum. The A/E’s written approval will be issued in an addendum. If the descriptive material is not restrictive, the products of other manufacturers specified will be accepted without prior approval provided they are compatible with the intent and purpose of the design as determined by the A/E.
3. Bidding, Bid Deadline, and Bid Bonds Bids must be submitted via the U3P website no later than the time and date specified on the Solicitation Schedule.
Contractors attempting to submit a bid through U3P website after the bid deadline has passed will not be successful and therefore disqualified from consideration of award of this project. It is the sole responsibility of the Contractor to confirm their bid is successfully submitted into U3P prior to the bid deadline.
Technical questions related to bidding in U3P should be directed to u3padmin@utah.gov.
After the bid deadline listed on the Solicitation Schedule has passed, the bid tabulation will be available within the following 24 hours in U3P and the Contract award will go to the Contractor submitting the lowest responsive and responsible bid.
Before submitting a bid, the Contractor shall carefully examine the solicitation; shall visit the site of the Work; shall fully inform themselves as to all existing conditions and limitations; and shall include in their bid the cost of all items required by the solicitation. If the Contractor observes that portions of the Contract Documents are at variance with applicable laws, building codes, rules, regulations or contain obvious erroneous or uncoordinated information, the Contractor shall promptly notify the DFCM Project Manager, and the necessary changes shall be accomplished by addendum.
https://utah.bonfirehub.com/portal/?tab=openOpportunities https://utah.bonfirehub.com/portal/?tab=openOpportunities https://utah.bonfirehub.com/portal/?tab=openOpportunities https://utah.bonfirehub.com/portal/?tab=openOpportunities https://utah.bonfirehub.com/portal/?tab=openOpportunities https://utah.bonfirehub.com/portal/?tab=openOpportunities https://utah.bonfirehub.com/portal/?tab=openOpportunities https://utah.bonfirehub.com/portal/?tab=openOpportunities mailto:u3padmin@utah.gov
DFCM Invitational Low Bid for Construction Services, 5.15.2026 6
By submitting a bid, in any format, the Bidder / Offeror / Vendor certifies that: (1) no product to be supplied by the Bidder / Offeror / Vendor in connection with this Solicitation is a “forced labor product” as that term is defined in Utah Code 63G-6a-121; and (2) to the extent, if any, that this Solicitation involves technology, or technology services, networks or systems, the Bidder / Offeror / Vendor is not a “restricted foreign entity” as that term is defined in Utah Code 63G-6a-121.
a) Bid Bonds A bid bond properly signed by the Contractor and a qualified surety and submitted on the AIA Document A310 – 2010 Bid Bond form, or equivalent, in the amount of 5% of the bid, must accompany the bid submitted within U3P. If the bid bond is not provided with the bid, the bid is nonresponsive, and the Contractor may be disqualified from the selection process.
The bid bond must be submitted on the AIA document A310 – 2010 Bid Bond Form, or equivalent, to be accepted unless only one bid is received by DFCM, or the failure to comply with the bid bond requirements is determined by the Director of DFCM to be immaterial based on the following:
1. the bid bond is submitted on a form other than the AIA Document A310 – 2010 Bid Bond form, or equivalent, and the bid bond meets all other requirements including being issued by a surety firm authorized to do business in the State of Utah and be listed in the U.S. Department of the Treasury Circular 570, Companies Holding Certificates of Authority as Acceptable Securities on Federal Bonds and as Acceptable Reinsuring Companies for an amount not less than the amount of the bond to be issued. A co-surety may be utilized to satisfy this requirement; and
2. the Contractor provides a bid bond properly signed by a qualified surety and on the AIA Document A310 – 2010 Bid Bond form, or equivalent, by the close of business of the next business day after DFCM notifies the Contractor of the defective bid bond.
4. Termination and Debarment By submitting a bid, the Contractor certifies that neither it nor its principals, including project nor site managers, have been, or are under consideration for, debarment or suspension, or any action that would exclude such from participation in a construction Contract by any governmental department or agency. If the Contractor cannot certify this statement, provide a detailed written explanation to dfcmcontracts@utah.gov by the time and date specified as the bid deadline on the Solicitation Schedule. DFCM reserves the right to reject the Contractor’s explanation and disqualify them from the selection process.
5. Listing of Subcontractors All Contractors are required to submit their DFCM Subcontractors List Form to dfcmcontracts@utah.gov by the time and date specified on the Solicitation Schedule. The DFCM Subcontractors List Form & Instructions can be found on the DFCM website – Construction Management - Standard Documents page and is also posted in U3P.
If the DFCM Subcontractors List Form is not provided by the time and date specified on the Solicitation Schedule, the bid is nonresponsive, and the Contractor may be disqualified from the selection process.
DFCM retains the right to audit or take other steps necessary to confirm compliance with requirements for the listing and changing of subcontractors. Any Contractor who is found incompliant with these requirements is subject to a debarment hearing and may be debarred from consideration for award of DFCM contracts for a period not to exceed three years.
6. Withdrawal of Bids Bids may be withdrawn on written request received from bidder prior to the time fixed for opening. Negligence on the part of the bidder in preparing the bid confers no right for the withdrawal of the bid after it has been opened.
7. DFCM Reservation of Rights The Division of Facilities Construction and Management reserves the right to reject any or all proposals or bids or to waive any formality or technicality in any proposal or bid in the best interest of the State.
mailto:dfcmcontracts@utah.gov mailto:dfcmcontracts@utah.gov
DFCM Invitational Low Bid for Construction Services, 5.15.2026 7
8. Contract and Bonding Requirements DFCM intends to enter into a Short Form Construction Contract with the Contractor submitting the lowest responsive and responsible bid. A copy of the Short Construction Contract and the corresponding Contract Conditions can be found on the DFCM website – Construction Management - Standard Documents page.
9. Licensure The Contractor shall comply with and require all subcontractors to comply with the license laws as required by the State of Utah.
10. Financial Responsibility of Contractors, Subcontractors and Sub-subcontractors Contractors shall respond promptly to any inquiry in writing by DFCM to any concern of financial responsibility of the Contractor, Subcontractor or Sub-subcontractor.