4-04 Construction Narrative Combined.pdf
PDF 80 KB Posted
- Solicitation number
- Not on record
- Issued by
- Montgomery County, Pennsylvania
About this file
This is a Construction Narrative for the Sumneytown Pike (SR 0063) Signal System Upgrade project submitted by Bowman Project No. 314081-01-009 on behalf of Towamencin Township, Montgomery County, Pennsylvania. The project encompasses a comprehensive signal system upgrade across ten intersections within Towamencin Township, with sealed proposals due by 10:00 a.m. on December 18th, 2025, via PennBid. The scope of work includes furnishing and installing new Econolite Cobalt ATC Controllers with EOS software, IP addressable MMU2-1600GE Malfunction Management Units, and Wavetronix ARC processors (models 5 and 6) across all ten intersections. Additionally, the project requires obtaining Edaptive licenses for all ten intersections, integrating them into the Econolite Edaptive System, and providing five-year subscription services. The contractor must install ATSPM zones of detection in accordance with project specifications and the Detector Mapping Matrix shown on System Permit #I-0009, which includes furnishing and maintaining various video and radar detection systems tailored to each intersection's requirements. All work must conform to PennDOT Publication 408 and PennDOT TC-8800 series standards. Towamencin Township must be present at the pre-construction meeting and receive all shop drawings, catalog cuts, construction schedules, and as-built plans upon project completion.
All bidders must submit a bid bond or certified check equal to 10% of the total bid amount and provide names and references of all proposed subcontractors. Both bidders and subcontractors are required to be PennDOT prequalified in accordance with 67 PA Code Chapter 457 and PennDOT Form 408/2020. The project is subject to the Pennsylvania Prevailing Wage Act requirements. Bids cannot be withdrawn for sixty days after opening, during which the Township will review qualifications and investigate bidder competency. Questions regarding the proposal must be submitted via PennBid by December 15th, 2025, at 5:00 p.m. Plans and specifications are available online at no charge through PennBid. The Township reserves the right to waive minor informalities, irregularities, or defects in bids or to reject any or all bids submitted.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCTION NARRATIVE
SUMNEYTOWN PIKE (SR 0063) SIGNAL SYSTEM UPGRADE
Bowman Project No. 314081-01-009
October 29, 2025
PROJECT WIDE
a. All work shall conform to PennDOT Publication 408 and PennDOT TC-8800 series standards.
b. For all ten intersections, obtain Edaptive licenses, integrate into the Econolite Edaptive System, and provide five-year subscription services.
c. For all ten intersections, provide ATSPM zones of detection in accordance with this project’s
Technical Specifications and the Detector Mapping Matrix shown on System Permit #I-0009.
a. Towamencin Township must be made aware of and present at the pre-construction meeting.
b. Provide Towamencin Township with all shop drawings and catalog cuts for review and approval.
c. Provide Towamencin Township with the construction schedule and notify them 24 hours prior to work commencing, so that they may be present for any significant construction.
d. Upon completion of final inspection, submit as-built plans to Towamencin Township.
1. SUMNEYTOWN PIKE (SR 0063) AND OLD FORTY FOOT ROAD (SR 1006) – FILE #2917
a. Furnish and install new Econolite Cobalt ATC Controller with EOS software, SD card and memory stick in existing controller cabinet.
b. Furnish and install new IP addressable MMU2-1600GE Malfunction Management Unit in existing controller cabinet.
c. Furnish and install new Wavetronix ARC 5 processor.
d. Adjust the Video Detection for both approaches of Sumneytown Pike (SR 0063) to provide stop bar detection on all lanes.
e. Maintain the Stop Bar Video Detection for all lanes on Forty Foot Road (SR 1006).
f. Maintain the Advance Radar Detection for both approaches of Sumneytown Pike (SR 0063).
2. SUMNEYTOWN PIKE (SR 0063) AND PA TURNPIKE RAMPS – FILE #2629
a. Furnish and install new IP addressable MMU2-1600GE Malfunction Management Unit in existing controller cabinet.
b. Furnish and install new Wavetronix ARC 5 processor.
c. Adjust the Video Detection for eastbound Sumneytown Pike (SR 0063) to provide stop bar detection on all lanes.
d. Furnish and install Radar Detection (matrix) for westbound Sumneytown Pike (SR 0063) to provide stop bar detection on all lanes.
e. Maintain the Stop Bar Video Detection for all lanes on northbound PA Turnpike Off Ramps.
f. Maintain the Stop Bar Video Detection for all lanes on southbound PA Turnpike Off Ramps.
g. Maintain the Advance Radar Detection for both approaches of Sumneytown Pike (SR 0063).
Bowman Project No. 314081-01-009
3. SUMNEYTOWN PIKE (SR 0063) AND TOWAMENCIN AVENUE – FILE #3068
controller cabinet.
b. Furnish and install new Wavetronix ARC 5 processor.
c. Adjust the Video Detection for eastbound Sumneytown Pike (SR 0063) to provide stop bar detection on all lanes.
d. Furnish and install Radar Detection (matrix) for westbound Sumneytown Pike (SR 0063) to provide stop bar detection on all lanes.
e. Maintain the Stop Bar Video Detection for all lanes on northbound Hotel/Convenience Store access.
f. Maintain the Stop Bar Video Detection for all lanes on southbound Towamencin Avenue.
4. SUMNEYTOWN PIKE (SR 0063) AND BUSTARD ROAD/FORTY FOOT ROAD – FILE #1062
controller cabinet.
b. Furnish and install new Wavetronix ARC 6 processor.
c. Maintain the Stop Bar Radar Detection for all lanes on eastbound Sumneytown Pike (SR 0063).
d. Maintain the Stop Bar Radar Detection for all lanes on westbound Sumneytown Pike (SR 0063).
e. Maintain the Stop Bar Radar Detection for all lanes on northbound Bustard Road.
f. Maintain the Stop Bar Radar Detection for all lanes on southbound Forty Foot Road.
5. SUMNEYTOWN PIKE AND TOWAMENCIN CORPORATE CENTER ACCESS – FILE #3290
controller cabinet.
b. Furnish and install new Wavetronix ARC 6 processor.
c. Furnish and install Radar Detection (matrix) for eastbound Sumneytown Pike (SR 0063) to provide stop bar detection on all lanes.
d. Furnish and install Radar Detection (matrix) for westbound Sumneytown Pike (SR 0063) to provide stop bar detection on all lanes.
e. Furnish and install Radar Detection (matrix) for northbound Towamencin Corporate Center to provide stop bar detection on all lanes.
f. Furnish and install Radar Detection (matrix) for southbound Private Driveway to provide stop bar detection on all lanes.
Bowman Project No. 314081-01-009
6. SUMNEYTOWN PIKE AND GREEN LANE ROAD – FILE #2164
controller cabinet.
b. Furnish and install new Wavetronix ARC 5 processor.
c. Adjust the Radar Detection for westbound Sumneytown Pike (SR 0063) to provide stop bar detection on all lanes.
d. Furnish and install Radar Detection (matrix) for eastbound Sumneytown Pike (SR 0063) to provide stop bar detection on all lanes.
e. Maintain the Stop Bar Video Detection for all lanes on northbound Green Lane Road.
f. Maintain the Stop Bar Video Detection for all lanes on southbound Private Driveway.
7. SUMNEYTOWN PIKE AND TROXEL ROAD (SR 1004) – FILE #2741
stick in existing controller cabinet.
b. Furnish and install new IP addressable MMU2-1600GE Malfunction Management Unit in existing controller cabinet.
c. Furnish and install new Wavetronix ARC 5 processor.
d. Furnish and install Radar Detection (matrix) for eastbound Sumneytown Pike (SR 0063) to provide stop bar detection on all lanes.
e. Furnish and install Radar Detection (matrix) for westbound Sumneytown Pike (SR 0063) to provide stop bar detection on all lanes.
f. Furnish and install Radar Detection (matrix) for southbound Troxel Road (SR 1004) to provide stop bar detection on all lanes.
8. FORTY FOOT ROAD (SR 0063) AND TOWAMENCIN AVENUE/TAPESTRY WAY – FILE #3069
controller cabinet.
b. Furnish and install new Wavetronix ARC 5 processor.
c. Furnish and install Radar Detection (matrix) for eastbound Forty Foot Road (SR 0063) to provide stop bar detection on all lanes.
d. Furnish and install Radar Detection (matrix) for westbound Forty Foot Road (SR 0063) to provide stop bar detection on all lanes.
e. Furnish and install Radar Detection (matrix) for northbound Tapestry Way to provide stop bar detection on all lanes.
f. Maintain Stop Bar Video Detection for all lanes on southbound Towamencin Avenue.
g. Maintain Advance Radar Detection for both approaches of Forty Foot Road (SR 0063).
Bowman Project No. 314081-01-009
9. FORTY FOOT ROAD (SR 0063) AND DETWILER ROAD/QUARRY ROAD – FILE #2173
controller cabinet.
b. Furnish and install new Wavetronix ARC 6 processor.
c. Adjust Stop Bar Radar Detection for eastbound Forty Foot Road (SR 0063) to provide stop bar detection on all lanes.
d. Furnish and install Radar Detection (matrix) for westbound Forty Foot Road (SR 0063) to provide stop bar detection on all lanes.
e. Maintain Stop Bar Radar Detection for all lanes on northbound Quarry Road.
f. Maintain Stop Bar Radar Detection for all lanes on southbound Detwiler Road.
g. Maintain Advance Radar Detection for both approaches of Forty Foot Road (SR 0063).
10. BUSTARD ROAD (SR 1002) AND RITTENHOUSE ROAD – FILE #2941
stick in existing controller cabinet.
b. Furnish and install new IP addressable MMU2-1600GE Malfunction Management Unit in existing controller cabinet.
c. Furnish and install new Wavetronix ARC 5 processor.
d. Furnish and install Radar Detection (matrix) for eastbound Bustard Road (SR 1002) to provide stop bar detection on all lanes.
e. Furnish and install Radar Detection (matrix) for westbound Bustard Road (SR 1002) to provide stop bar detection on all lanes.
f. Maintain Stop Bar Radar Detection for all lanes on northbound Park Access.
g. Maintain Stop Bar Radar Detection for all lanes on southbound Rittenhouse Road.
h. Maintain Advance Radar Detection for both approaches of Bustard Road (SR 1002).
V:\314081 - Towamencin Township\314081-01-009 (TRA) - 2024_GLG Adaptive System\Engineering\Const_Services\01_Bid Documents\2025-10-29_Construction Narrative_Combined.docx