This is a technical specification document for transformer pad and vault installation requirements issued by Ameren, the utility provider for the EV Charging Station Installation project at the Microtel Inn by Wyndham in Champaign, Illinois. The specification outlines requirements for a 750kVA utility transformer installation that will support the 625kVA power cabinet serving four Tesla V4 Superchargers. The project encompasses civil work including transformer site preparation, concrete pad installation, conduit routing for primary and secondary electrical connections, grounding rod installation, and protective barrier installation. The transformer site must be truck-accessible with a compacted rock and dirt base measuring 4 inches thick, extending 12 inches beyond the pad perimeter, and installed to within plus or minus 2 inches of final grade. All settling and shifting must be eliminated through proper compaction procedures.
The specification details precise technical requirements for underground and above-ground raceway installation, including conduit material specifications (Schedule 40 or 80 PVC), minimum burial depths (36-48 inches for primary conduit, 24-36 inches for secondary), bend radius requirements (36 inches for primary sweeps, 30 inches for secondary sweeps), and maximum bending limits of 270 degrees per run. All raceways must include 2500-pound minimum-rated pull tape. Clearance requirements around the transformer pad are specified as 56 inches or 4 feet 8 inches for back access, 45 inches or 3 feet 9 inches for each side, and 120 inches or 10 feet for front access. The vault and pad, weighing 1200 pounds, are provided by Ameren and available for pickup at the local operating center, with installation performed by the customer. A 5/8-inch by 8-foot ground rod will be installed by Ameren, and protective barriers must consist of 6-inch concrete-filled tube installed at minimum 36-inch depth with at least 60 inches of above-grade extension.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMEREN TRANSFORMER SITE REQUIREMENTS
Transformer site shall conform to all clearance and access requirements
Transformer site shall be truck accessible.
1. CA6 or Road pack sub base shall be provided and installed by customer.
2. Pad shall be installed on 4" of level, well compacted, 1" minus rock extending 12" outside of pad. Dirt under the rock must first be well compacted. Avoid filling pad opening before cable or conduit is installed.
3. Base shall be level and installed +/- 2" of final grade.
4. Base shall be compacted to eliminate settling or shifting.
5. Vault and Pad will be provided by Ameren and installed by Customer where required
Vault and pad (1200LBS) are available for pick up at local operating center with form Pick up form to be provided by local Ameren Engineering Rep.
(1) 5/8" X 8' Ground rod will be installed by Ameren. See note below for location
BACK CLEARANCE = 56" OR 4' 8"
SIDE CLEARANCE =
45" OR 3' 9"
SIDE CLEARANCE =
45" OR 3' 9"
FRONT CLEARANCE = 120" OR 10'
*The 5/8" x 8' ground rod can be located where most convenient in the pad opening to avoid the incoming and outgoing conduit elbows.
c152850 Highlight c152850 Highlight
3 Phase or 1 Phase conduit layout
The number of Primary and Secondary conduits may vary. The maximum number of 12 secondary conduits per phase.
All conduit shall be symmetrically (similar path) located within a 20" x 24" area as shown above.
Ameren Engineering will determine if the number of conduits is acceptable or if a vault will be required.
All conduits shall be PVC schedule 40 sweeps or approved alternate conduit.
Cut conduits must have a conduit bushing/bell end coupling. Both primary AND secondary.
Ameren Conduit Requirements
Raceway underground shall be Schedule 40 or greater, can be HDPE suitable for Electrical use.
Raceway coming above ground shall be Schedule 80 for a min. of 10' or 120".
Raceway sweeps used for Primary shall be 36" or greater radius.
Raceway sweeps used for secondary shall be 30" or greater radius.
Primary conduit shall be buried at min. depth of 36" to 48" from the top of conduit.
Secondary conduit shall be buried at min. depth of 24" to 36" from the top of conduit.
Raceway shall be installed with no more than 270 degrees in bends per run.
ALL Raceways shall have a flat Pull tape (Mule Tape) installed rated at 2500LBS min.
All primary riser conduit material to be provided by customer and installed by Ameren. 1 stick of schedule 80 conduit, 2 sticks of schedule 40 conduit, and weather head.
Ameren Protective Barrier Requirements
Barrier shall be 6" tube concrete filled or equivalent pre-approved alternative.
Barrier shall be installed at min. of 36" of depth and set in a concrete base.
Barrier shall extend a min. of 60" above grade or pre-approved alternative height.
Barrier shall be installed to allow for full opening of Equipment access doors being installed.
SECONDARY CONDUIT PRIMARY CONDUIT
C152850 Highlight
Three Phase Transformer Vault Spec 01/01/2022
The primary and secondary conduits may enter the box vault from the sides (as shown in drawings), from the front, or from the back.
All conduits shall be rigid PVC Schedule 40 or approved PVC flexible conduit. If bends are cut off, apply a bell end coupling over the end of each conduit.
The opening of the flat pad should be centered over the box vault. Note that the box vault opening is 57-3/4” x 27-3/4” and the flat pad opening is slightly smaller at 52” x 20”