36E77619B0008-0002008.pdf

PDF 14 MB Posted

Attached to
Upgrade USP 800 Pharmacy Compounding Requirements at the John L. McClellan Memorial Veterans Hospital
Solicitation number
36E77619B0008
Issued by

About this file

36E77619B0008 0002 Attachment 4 -DRAWINGS E001 - E601.pdf

View the file

Other files

File Type Posted
36E77619B0008-0004001.pdf PDF
36E77619B0008-0004000.docx DOCX document
36E77619B0008-0003004.pdf PDF
36E77619B0008-0003003.docx DOCX document
36E77619B0008-0003002.pdf PDF
36E77619B0008-0003010.pdf PDF
36E77619B0008-0003009.pdf PDF
36E77619B0008-0003008.pdf PDF
36E77619B0008-0003005.pdf PDF
36E77619B0008-0003001.docx DOCX document
36E77619B0008-0003000.docx DOCX document
36E77619B0008-0003007.pdf PDF
36E77619B0008-0003006.pdf PDF
36E77619B0008-0002000.docx DOCX document
36E77619B0008-0002005.pdf PDF
36E77619B0008-0002001.pdf PDF
36E77619B0008-0002004.pdf PDF
36E77619B0008-0002006.pdf PDF
36E77619B0008-0002002.pdf PDF
36E77619B0008-0002007.pdf PDF
36E77619B0008-0002009.pdf PDF
36E77619B0008-0002003.pdf PDF
36E77619B0008-0001000.docx DOCX document
36E77619B0008-0001001.pdf PDF
36E77619B0008-0001005.pdf PDF
36E77619B0008-0001003.pdf PDF
36E77619B0008-0001004.doc DOC document
36E77619B0008-0001002.pdf PDF
36E77619B0008-006.docx DOCX document
36E77619B0008-011.pdf PDF
36E77619B0008-009.pdf PDF
36E77619B0008-008.pdf PDF
36E77619B0008-005.docx DOCX document
36E77619B0008-007.pdf PDF
36E77619B0008-014.docx DOCX document
36E77619B0008-015.docx DOCX document
36E77619B0008-012.pdf PDF
36E77619B0008-010.pdf PDF
36E77619B0008-013.pdf PDF
36E77619B0008-000.docx DOCX document
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019

100% CONSTRUCTION DOCUMENTS FOR BID 06-21-2019

MOUNTING HEIGHTS FOR ELECTRICAL DEVICES

WIRE SIZING TABLE

GENERAL NOTES - DEMOLITIONELECTRICAL GENERAL NOTES

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019

100% CONSTRUCTION DOCUMENTS FOR BID 06-21-2019

GENERAL NOTES

ELECTRICAL SYMBOLS ELECTRICAL ABBREVIATIONS

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019

100% CONSTRUCTION DOCUMENTS FOR BID 06-21-2019

FIRE BARRIER LEGEND

PLAN KEY NOTES

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019

100% CONSTRUCTION DOCUMENTS FOR BID 06-21-2019

FIRE BARRIER LEGEND

DEMOLITION KEY NOTES

GENERAL DEMOLITION NOTES

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019

100% CONSTRUCTION DOCUMENTS FOR BID 06-21-2019

FIRE BARRIER LEGEND

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019

100% CONSTRUCTION DOCUMENTS FOR BID 06-21-2019

FIRE BARRIER LEGEND

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019

100% CONSTRUCTION DOCUMENTS FOR BID 06-21-2019

FIRE BARRIER LEGEND

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019

100% CONSTRUCTION DOCUMENTS FOR BID 06-21-2019

FIRE BARRIER LEGEND

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019

100% CONSTRUCTION DOCUMENTS FOR BID 06-21-2019

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019

100% CONSTRUCTION DOCUMENTS FOR BID 06-21-2019

FIRE BARRIER LEGEND

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019

100% CONSTRUCTION DOCUMENTS FOR BID 06-21-2019

FIRE BARRIER LEGEND

T: F:

www.bancroft-ae.com Bancroft-AE Project No. 17-119 www.bancroft-ae.com

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019

100% CONSTRUCTION DOCUMENTS FOR BID 06-21-2019

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019

100% CONSTRUCTION DOCUMENTS FOR BID 06-21-2019

www.bancroft-ae.com

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019

100% CONSTRUCTION DOCUMENTS FOR BID 06-21-2019

FIRE BARRIER LEGEND

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019

100% CONSTRUCTION DOCUMENTS FOR BID 06-21-2019

FIRE BARRIER LEGEND

www.bancroft-ae.com

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019

100% CONSTRUCTION DOCUMENTS FOR BID 06-21-2019

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019

100% CONSTRUCTION DOCUMENTS FOR BID 06-21-2019

FIRE BARRIER LEGEND

www.bancroft-ae.com

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019

100% CONSTRUCTION DOCUMENTS FOR BID 06-21-2019

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019

100% CONSTRUCTION DOCUMENTS FOR BID 06-21-2019

FIRE BARRIER LEGEND

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019

100% CONSTRUCTION DOCUMENTS FOR BID 06-21-2019

FIRE BARRIER LEGEND

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019

100% CONSTRUCTION DOCUMENTS FOR BID 06-21-2019

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019

100% CONSTRUCTION DOCUMENTS FOR BID 06-21-2019

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019

INPUT DEVICE

OUTPUT

KEY NOTES

GENERAL NOTES

T: F:

www.bancroft-ae.com Bancroft-AE Project No. 17-119 www.bancroft-ae.com

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

μ

42"

4"

~96"

4"

42"

±96"

4"

42"

±96"

4"

42"

±96"

GENERAL NOTES

KEY NOTES

T: F:

www.bancroft-ae.com Bancroft-AE Project No. 17-119 www.bancroft-ae.com

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019

Drawing Number

Project Title

Location

Issue Date Checked Drawn

100% CONSTRUCTION

DOCUMENTS FOR BID

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

STAMP UPGRADE FOR USP 800 PHARMACY

COMPOUNDING REQUIREMENTS

4300 WEST 7TH STREET, LITTLE ROCK, AR 72205

598-18-102

06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018

65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018

65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018

95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019

100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019