36E77619B0008-0002003.pdf
PDF 7 MB Posted
- Attached to
- Upgrade USP 800 Pharmacy Compounding Requirements at the John L. McClellan Memorial Veterans Hospital
- Solicitation number
- 36E77619B0008
About this file
36E77619B0008 0002 Attachment 4 -DRAWINGS - IQ101 - I621.pdf
View the file
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
100% CONSTRUCTION
DOCUMENTS FOR BID
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Phase
STAMP UPGRADE FOR USP 800 PHARMACY
COMPOUNDING REQUIREMENTS
4300 WEST 7TH STREET, LITTLE ROCK, AR 72205
598-18-102
06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018
65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018
65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018
95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019
100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019
BID DOCUMENTS- NOT FOR CONSTRUCTION 05-24-2019
100% CONSTRUCTION DOCUMENTS FOR BID 06-21-2019
Drawing Number
Project Title
Location
Issue Date Checked Drawn
100% CONSTRUCTION
DOCUMENTS FOR BID
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Phase
STAMP UPGRADE FOR USP 800 PHARMACY
COMPOUNDING REQUIREMENTS
4300 WEST 7TH STREET, LITTLE ROCK, AR 72205
598-18-102
06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018
65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018
65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018
95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019
100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019
Drawing Number
Project Title
Location
Issue Date Checked Drawn
100% CONSTRUCTION
DOCUMENTS FOR BID
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Phase
STAMP UPGRADE FOR USP 800 PHARMACY
COMPOUNDING REQUIREMENTS
4300 WEST 7TH STREET, LITTLE ROCK, AR 72205
598-18-102
06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018
65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018
65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018
95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019
100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019
Drawing Number
Project Title
Location
Issue Date Checked Drawn
100% CONSTRUCTION
DOCUMENTS FOR BID
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Phase
STAMP UPGRADE FOR USP 800 PHARMACY
COMPOUNDING REQUIREMENTS
4300 WEST 7TH STREET, LITTLE ROCK, AR 72205
598-18-102
06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018
65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018
65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018
95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019
100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019
Drawing Number
Project Title
Location
Issue Date Checked Drawn
100% CONSTRUCTION
DOCUMENTS FOR BID
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Phase
STAMP UPGRADE FOR USP 800 PHARMACY
COMPOUNDING REQUIREMENTS
4300 WEST 7TH STREET, LITTLE ROCK, AR 72205
598-18-102
06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018
65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018
65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018
95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019
100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019
Drawing Number
Project Title
Location
Issue Date Checked Drawn
100% CONSTRUCTION
DOCUMENTS FOR BID
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Phase
STAMP UPGRADE FOR USP 800 PHARMACY
COMPOUNDING REQUIREMENTS
4300 WEST 7TH STREET, LITTLE ROCK, AR 72205
598-18-102
06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018
65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018
65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018
95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019
100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019
Drawing Number
Project Title
Location
Issue Date Checked Drawn
100% CONSTRUCTION
DOCUMENTS FOR BID
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Phase
STAMP UPGRADE FOR USP 800 PHARMACY
COMPOUNDING REQUIREMENTS
4300 WEST 7TH STREET, LITTLE ROCK, AR 72205
598-18-102
06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018
65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018
65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018
95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019
100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019
Drawing Number
Project Title
Location
Issue Date Checked Drawn
100% CONSTRUCTION
DOCUMENTS FOR BID
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Phase
STAMP UPGRADE FOR USP 800 PHARMACY
COMPOUNDING REQUIREMENTS
4300 WEST 7TH STREET, LITTLE ROCK, AR 72205
598-18-102
06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018
65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018
65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018
95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019
100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019
Drawing Number
Project Title
Location
Issue Date Checked Drawn
100% CONSTRUCTION
DOCUMENTS FOR BID
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Phase
STAMP UPGRADE FOR USP 800 PHARMACY
COMPOUNDING REQUIREMENTS
4300 WEST 7TH STREET, LITTLE ROCK, AR 72205
598-18-102
06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018
65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018
65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018
95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019
100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019
Drawing Number
Project Title
Location
Issue Date Checked Drawn
100% CONSTRUCTION
DOCUMENTS FOR BID
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Phase
STAMP UPGRADE FOR USP 800 PHARMACY
COMPOUNDING REQUIREMENTS
4300 WEST 7TH STREET, LITTLE ROCK, AR 72205
598-18-102
06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018
65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018
65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018
95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019
100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019
Drawing Number
Project Title
Location
Issue Date Checked Drawn
100% CONSTRUCTION
DOCUMENTS FOR BID
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Phase
STAMP UPGRADE FOR USP 800 PHARMACY
COMPOUNDING REQUIREMENTS
4300 WEST 7TH STREET, LITTLE ROCK, AR 72205
598-18-102
06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018
65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018
65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018
95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019
100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019
Drawing Number
Project Title
Location
Issue Date Checked Drawn
100% CONSTRUCTION
DOCUMENTS FOR BID
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Phase
STAMP UPGRADE FOR USP 800 PHARMACY
COMPOUNDING REQUIREMENTS
4300 WEST 7TH STREET, LITTLE ROCK, AR 72205
598-18-102
06-21-201935% SCHEMATIC DESIGN SUBMITTAL 08-07-2018
65% DESIGN DEVELOPMENT SUBMITTAL 09-25-2018
65% DESIGN DEVELOPMENT RE-SUBMITTAL 11-03-2018
95% CONSTRUCTION DOCUMENT PROGRESS SUBMITTAL 01-18-2019
100% CONSTRUCTION DOCUMENTS- PROGRESS SET 02-28-2019
File details come from the government source that posted it.