This document appears to be an amendment to a solicitation for a government contract. The amendment is responding to several Requests for Information (RFIs) submitted by potential offerors. The key details include:
The contract opportunity is for the repair of the Committal Shelter, Columbarium, and Perimeter Fence at the Western North Carolina (WNC) National Cemetery, solicitation number 36C78625R0006. The work involves removing and replacing the existing roofing, gutters, and downspouts, as well as inspecting and repairing the plywood underlayment and roof structure as needed. There are some clarifications and additional details provided in response to the RFIs, such as confirming the use of steel roofing instead of copper, and that 20% bid bond or $3,000,000 (whichever is less) is required. The amendment also addresses requirements for temporary fencing, safety standards, and finish work for the fallen wall. The responses indicate the contracting agency is the Department of Veterans Affairs National Cemetery Administration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C78625R0006 0003.docx | DOCX document | |
| 36C78625R0006 0001.docx | DOCX document | |
| Photo Library.docx | DOCX document | |
| 013323ShopDrawingsProductData.docx | DOCX document | |
| Drawings_Volume 1.pdf | ||
| Drawings_Volume 2.pdf | ||
| 062000FinCarpentry.docx | DOCX document | |
| 061000RoughCarpentry.docx | DOCX document | |
| Lump Sum Division Spreadsheet.xlsx | XLSX spreadsheet | |
| SOW 907-MM-FY24-006 Repair Committal Shelter.doc | DOC document | |
| 076000FlashSheetMetal.docx | DOCX document | |
| Drawings_Volume 3.pdf | ||
| 36C78625R0006_1.docx | DOCX document | |
| Wage Determination_Multnomah County OR.txt | TXT text file | |
| 074113MetalRoof.docx | DOCX document |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 11-19-2024
907-MM-FY24-006
36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle
VA
22172 36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle
VA
22172 To all Offerors/Bidders
36C78625R0006 10-15-2024
X X X X This amendment is to respond to RFIs submitted.
See continuation page for details.
All other terms and conditions shall remain the same.
Auvorie Benson Contracting Officer
A.1 ADDITIONAL ATTACHMENTS
RFI Responses:
1. Drawing Number 7 clearly shows the area of work where we are only supposed to remove and install plywood, roofing, gutters, etc… However, sheet notes 1 through 3 on Drawing Number 7 states to remove “all”. Can we get clarification?
0. 1. Remove ALL existing roofing, gutters and downspouts.
2. Inspect ALL plywood underlayment. Besides apparent damage at tree fall area, inspect for other damage existing plywood is exposed.
1. The SOW has contradictions to Drawing 7 scope of work as well. For example, the SOW states to remove entire roof but 2 part (c) states to “use 10 sheets for our estimate.” I think the biggest question is are we just replacing the damaged areas of the building or are we fixing the entire structure (plywood, TJI roof joists, metal roof, gutters/downspouts, cedar soffit, Glu-lam Beam(s)) or maybe even a combination of both?
1. All roofing will be removed. Replace glu-lam, repair TJI in damaged area as required. Install new steel roofing (not copper) on entire structure. Gutters and downspouts to match. While roof is off. Inspect existing plywood for damage, dry rot, etc. and replace as necessary.
1. On the SOW 1(d) states to “removed damaged gutters and downspouts” but 2(d) states “Install new standing seam roof for entire structure with gutters/downspouts.” Please clarify.
2. Remove all of the existing metal roof and replace with matching gutters, downspouts.
1. The SOW states electronic document tracking software is required for this contract. Will ProCore be sufficient to use on this project?
3. Yes, Procore is acceptable to this requirement.
1. On drawing 3, Section 1, there is a note “Standing Seam Copper Roof,” Can you please confirm you want, copper roof, flashings, gutters, and downspouts?
4. Remove existing copper roof and replace with new steel standing seam roof with gutters and downspouts.
1. Since the roof is going to be replaced, would you want to add an alternate to the bid to replace the four skylights?
5. No
1. The solicitation, item 2.7.c, states that the gid guarantee shall be 10 percent of the bid price or $3,000,000.00 whichever is less. Standard bid bond percentage is 20 percent of the bid price, please verify that only 10 percent of the bid is expected.
6. 20% of bid price or $3,000,000. 10% is an error.
1. Do you have the name of the manufacturer of the existing fence?
7. No-match existing.
1. Will the mason be allowed to leave his truck on the road while working on the brick repair?
8. No
1. Are we required to use temporary fencing at the committal shelter?
9. Yes
1. What are the safety requirements for this project?
10. Standard OSHA requirements
1. Are we responsible for polishing any surface damage on the underside of the wall that fell over?
11. It needs to be brought back to condition before it fell.
1. The specs say install Aluminum-Zinc Alloy Coated Sheet a standing seam roof and provide a color chart. The drawings read new copper roof and copper gutters. Can you verify which product is to be installed?
12. Steel
End of Document Repair Committal Shelter/Columbarium/Perimeter Fence at WNC