CLIN SOW Description Unit of issue Est. Cost Est. Qty Total

0001 5b.1.1 Headstone receiving, preparation, and transportation EA $0.00 850 $0.00

5b.1.2

Headstone Installation and Setting, All First, Subequent (R2) Interment and All Replacement Headstones - Davis Bacon Wages

EA $0.00 850 $0.00

See guidance at bottom of page

0003 5b.1.3 Headstone Raise and Realign - Davis Bacon Wages EA $0.00 500 $0.00 See guidance at bottom of page

0004 5b.1.3 Fine Tune Alignment (Bump and Run) - Davis Bacon Wages EA $0.00 500 $0.00 See guidance at bottom of page

0005 5b.2.1 Sunken Grave and Grounds Repair - Davis Bacon Wages EA $0.00 150 $0.00 See guidance at bottom of page

5b.2.2

Gravesite Floral/Decoration collection/removal (Daily occurrence -

Invoiced Monthly)

MO $0.00 12 $0.00

0007 5b.2.3 Mass Floral, Decorations, Trash and Debris Pick-up/Removal EA $0.00 20 $0.00

0008 5b.3.1 Pond Algae Treatment MO $0.00 9 $0.00

5b.3.2 Pond Equipment Maintenance (Timers, Fountains, Aerators, Cables, etc.) JB $0.00 2 $0.00

0010 5b.4.1 Pump House Monitoring and Maintenance MO $0.00 12 $0.00

5b.4.2

Irrigation- Yearly Startup/Shut Down, & Monthly system check-Includes

Sprinkler adjustments as needed (Growing Season)

MO $0.00 10 $0.00

5b.4.2

Irrigation- Main Line/ Lateral PVC/Poly Repair/Replace 2" to 6" Breaks

Davis Bacon Wages

EA $0.00 5 $0.00

See guidance at bottom of page

0013 5b.4.2 Irrigation- In-Valve Head Repair/Replace- Davis Bacon Wages EA $0.00 5 $0.00 See guidance at bottom of page

5b.4.2

Irrigation-Popup Rotor,Mister Head and Electric Valve Solenoid

Repair/Replace (Includes rotor/mister adjustment with OEM nozzle present - Davis Bacon Wages

EA $0.00 15 $0.00

See guidance at bottom of page

5b.4.2 Irrigation- Electric & Gate valve Repair/Replace Davis Bacon Wages EA $0.00 5 $0.00

See guidance at bottom of page

5b.4.2

Irrigation- Lateral Line Repair/Replace 3/4"-1" PVC/ Poly - Davis Bacon

Wages

EA $0.00 5 $0.00

See guidance at bottom of page

5b.4.2

Irrigation- Controller Repair/ Replace/ Program to current Stand-alone(Hunter)

EA $0.00 3 $0.00

0018 5b.4.3 Mowing and turf edging, (Tifway 419 Bermuda) WK $0.00 43 $0.00

0019 5b.4.4 Mowing non-turf areas WK $0.00 43 $0.00

5b.4.5 Headstone, Marker, Monument and Other Vertical Surface Trimming WK $0.00 25 $0.00

0021 5b.4.6 Leaf, Trash and Debris Collection and Removal; (Daily occurrence - MO $0.00 12 $0.00

0022 5b.4.7 Extreme Weather Storm Damage and Debris Clean-up EV $0.00 3 $0.00

0023 5b.4.8 Sweeping/Blowing Off Roadways and Concrete Surfaces MO $0.00 12 $0.00

0024 5b.4.9 Maintenance of Benches, Concrete Pads, and Rocked Areas MO $0.00 12 $0.00

0025 5b.5.1 Maintenance of Plant Beds, Shrubs, and Bushes MO $0.00 6 $0.00

5b.5.2

Tree Maintenance-(tree trimming, canopy raise, new tree establishment, guying)

JB $0.00 6 $0.00

5b.5.3

Mulching - Removal, Replenish and/or Install All Areas

Cemetery defined

JB $0.00 2 $0.00

0028 5b.6.1 Casket/Vault Gravesite Sod Installation EA $0.00 900 $0.00

0029 5b.6.2 Core Aerification (Aeration) - Approx 27 acres - September JB $0.00 1 $0.00

5b.6.3

Dethatching - As necessary - Cemetery Discretion - Up to 27 acres of turfed grounds

JB $0.00 1 $0.00

5b.6.4

Fertilization- Bermuda (20-0-06 at 5lb N per 1000); Mar 5, April 15, Jun

1, Aug. 15, Oct 1

JB $0.00 5 $0.00

Alabama National Cemetery Grounds Maintenance Requirement

BASE YEAR

5b.6.5

Weed Control: Pre-Emerge Herbicide Application (Spring (Jan/Mar) and

Fall (Oct/Nov))

JB $0.00 2 $0.00

5b.6.5

Weed Control: Post Emerge Herbicide Treatment/Application-- All

Turf areas - Approx 27 acres (as needed or directed by COR)

JB $0.00 5 $0.00

5b.6.6

Lime( Gypsum) Calcuim Sulfate Application -

All Turf Areas-Early Spring Yearly - as indicated by soil test

JB $0.00 1 $0.00

5b.7.1

Insecticide( Mole Cricket, Stunt Mite control)Treatment/Application (as needed or directed by COR)

JB $0.00 5 $0.00

0036 5b.7.1 Fungicide Treatment/Application (as needed or directed by COR) JB $0.00 2 $0.00

0037 5b.7.2 Fire Ant Control/Monitoring - Daily Treatment Invoiced Monthly MO $0.00 12 $0.00

5b.8.1

Headstone Cleaning; 2 times (Bi-annually) a year. Cleaning shall be completed two weeks prior to Memorial Day and one week prior to

Veterans Day, or as scheduled by the COR

JB $0.00 2 $0.00

5b.8.2

Pressure/Power Washing: Curbs, Sidewalks, and Composite Enclosures; 2 times a year; once between April 1st through May 15th, and again between November 1st through December 1st, or as directed by COR

JB $0.00 2 $0.00

5b.8.3

Pressure/Power Washing: Entrance Ways, Walls, Caps, Brick Pylons, Areas (concrete pads/bases) under signs and Trash/Floral Receptacles; 2 times a year; once between April 15th and May 15th, and again between

November 1st through December 1st, or as directed by the COR

JB $0.00 2 $0.00

5b.8.4

Pressure/Power Washing: Flag Assembly Area; 2 times a year; once between March 1st and May 15, and again between September 1st and

November 15th, or as directed by COR

JB $0.00 2 $0.00

5b.8.5

Pressure/Power Washing: Columbarium, Memorial Walls, Concrete

Surfaces and Marble Niche Covers/Memorial Wall Markers; washed two

(2) times a year, two weeks prior to Memorial Day and one week prior to

Veterans Day, or as directed by the COR

JB $0.00 2 $0.00

5b.8.6

Pressure/Power Washing: Committal Shelters; quarterly (4 times per year, Nov., Feb., April, July)

JB $0.00 4 $0.00

5b.8.7

Pressure/Power Washing: Buildings and Surrounding Concrete Surfaces;

two (2) times a year, once between March 1st and May 15, and again between September 1st and November 15th or as directed by the COR

JB $0.00 2 $0.00

5b.8.8

Pressure/Power Washing: Floral Vase/Trash Receptacle Cleaning;

(quarterly (4 times per year), Nov., Feb., April, July)

JB $0.00 4 $0.00

0046 5b.9.1 Daily Committal Shelter Setup, Take Down, and Cleaning EA $0.00 375 $0.00

0047 5b.9.2 Weekend/Holiday Burial Support EA $0.00 11 $0.00

0048 5b.9.3 Ceremony Event Support to include set-up and take-down EV $0.00 3 $0.00

CLIN SOW Description Unit of issue Est. Cost Est. Qty Total

10001 5b.1.1 Headstone receiving, preparation, and transportation EA $0.00 900 $0.00

10002 5b.1.2

Headstone Installation and Setting, All First, Subequent (R2) Interment and All Replacement Headstones - Davis Bacon Wages

EA $0.00 900 $0.00

See guidance at bottom of page

10003 5b.1.3 Headstone Raise and Realign - Davis Bacon Wages EA $0.00 500 $0.00 See guidance at bottom of page

10004 5b.1.3 Bump and Run - Davis Bacon Wages EA $0.00 500 $0.00 See guidance at bottom of page

10005 5b.2.1 Sunken Grave and Grounds Repair - Davis Bacon Wages EA $0.00 150 $0.00 See guidance at bottom of page

10006 5b.2.2

Gravesite Floral/Decoration collection/removal (Daily occurrence -

Invoiced Monthly)

MO $0.00 12 $0.00

10007 5b.2.3 Mass Floral, Decorations, Trash and Debris Pick-up/Removal EA $0.00 20 $0.00

10008 5b.3.1 Pond Algae Treatment MO $0.00 9 $0.00

10009 5b.3.2 Pond Equipment Maintenance (Timers, Fountains, Aerators, Cables, etc.) JB $0.00 2 $0.00

10010 5b.4.1 Pump House Monitoring and Maintenance MO $0.00 12 $0.00

10011 5b.4.2

Irrigation- Yearly Startup/Shut Down, & Monthly system check-Includes

Sprinkler adjustments as needed (Growing Season)

MO $0.00 10 $0.00

10012 5b.4.2

Irrigation- Main Line/ Lateral PVC/Poly Repair/Replace 2" to 6" Breaks -

Davis Bacon Wages

EA $0.00 5 $0.00

See guidance at bottom of page

10013 5b.4.2 Irrigation- In-Valve Head Repair/Replace EA $0.00 5 $0.00 See guidance at bottom of page

10014

5b.4.2

Irrigation-Popup Rotor,Mister Head and Electric Valve Solenoid

Repair/Replace (Includes rotor/mister adjustment with OEM nozzle present - Davis Bacon Wages

EA $0.00 15 $0.00

See guidance at bottom of page

10015 5b.4.2 Irrigation- Electric & Gate valve Repair/Replace - Davis Bacon Wages EA $0.00 5 $0.00

See guidance at bottom of page

10016 5b.4.2 Irrigation- Lateral Line Repair/Replace 3/4"-1" PVC/ Poly EA $0.00 5 $0.00 See guidance at bottom of page

10017 5b.4.2

Irrigation- Controller Repair/ Replace/ Program to current Stand-alone(Hunter)

EA $0.00 3 $0.00

10018 5b.4.3 Mowing and turf edging, (Tifway 419 Bermuda) WK $0.00 43 $0.00

10019 5b.4.4 Mowing non-turf areas WK $0.00 43 $0.00

Base Year Total Estimate COST $0.00

OPTION YEAR 1

10020 5b.4.5 Headstone, Marker, Monument and Other Vertical Surface Trimming WK $0.00 25 $0.00

10021 5b.4.6

Leaf, Trash and Debris Collection and Removal; (Daily occurrence -

Invoiced Monthly)

MO $0.00 12 $0.00

10022 5b.4.7 Extreme Weather Storm Damage and Debris Clean-up EV $0.00 3 $0.00

10023 5b.4.8 Sweeping/Blowing Off Roadways and Concrete Surfaces MO $0.00 12 $0.00

10024 5b.4.9 Maintenance of Benches, Concrete Pads, and Rocked Areas MO $0.00 12 $0.00

10025 5b.5.1 Maintenance of Plant Beds, Shrubs, and Bushes MO $0.00 6 $0.00

10026 5b.5.2

Tree Maintenance-(tree trimming, canopy raise, new tree establishment, guying)

JB $0.00 6 $0.00

10027 5b.5.3

Mulching - Removal, Replenish and/or Install All Areas

Cemetery defined

JB $0.00 2 $0.00

10028 5b.6.1 Casket/Vault Gravesite Sod Installation EA $0.00 950 $0.00

10029 5b.6.2 Core Aerification (Aeration) - Approx 27 acres - September JB $0.00 1 $0.00

10030 5b.6.3

Dethatching - As necessary - Cemetery Discretion - Up to 27 acres of turfed grounds

JB $0.00 1 $0.00

10031 5b.6.4

Fertilization- Bermuda (20-0-06 at 5lb N per 1000); Mar 5, April 15, Jun

1, Aug. 15, Oct 1

JB $0.00 5 $0.00

10032 5b.6.5

Weed Control: Pre-Emerge Herbicide Application (Spring (Jan/Mar) and

Fall (Oct/Nov))

JB $0.00 2 $0.00

10033 5b.6.5

Weed Control: Post Emerge Herbicide Treatment/Application-- All

Turf areas - Approx 27 acres (as needed or directed by COR)

JB $0.00 5 $0.00

10034 5b.6.6

Lime( Gypsum) Calcuim Sulfate Application -

All Turf Areas-Early Spring Yearly - as indicated by soil test

JB $0.00 1 $0.00

10035 5b.7.1

Insecticide( Mole Cricket, Stunt Mite control)Treatment/Application (as needed or directed by COR)

JB $0.00 5 $0.00

10036 5b.7.1 Fungicide Treatment/Application (as needed or directed by COR) JB $0.00 2 $0.00

10037 5b.7.2 Fire Ant Control/Monitoring - Daily Treatment Invoiced Monthly MO $0.00 12 $0.00

10038

5b.8.1

Headstone Cleaning; 2 times (Bi-annually) a year. Cleaning shall be completed two weeks prior to Memorial Day and one week prior to

Veterans Day, or as scheduled by the COR

JB $0.00 2 $0.00

10039

5b.8.2

Pressure/Power Washing: Curbs, Sidewalks, and Composite Enclosures; 2 times a year; once between April 1st through May 15th, and again between November 1st through December 1st, or as directed by COR

JB $0.00 2 $0.00

10040

5b.8.3

Pressure/Power Washing: Entrance Ways, Walls, Caps, Brick Pylons, Areas (concrete pads/bases) under signs and Trash/Floral Receptacles; 2 times a year; once between April 15th and May 15th, and again between

November 1st through December 1st, or as directed by the COR

JB $0.00 2 $0.00

10041

5b.8.4

Pressure/Power Washing: Flag Assembly Area; 2 times a year; once between March 1st and May 15, and again between September 1st and

November 15th, or as directed by COR

JB $0.00 2 $0.00

10042

5b.8.5

Pressure/Power Washing: Columbarium, Memorial Walls, Concrete

Surfaces and Marble Niche Covers/Memorial Wall Markers; washed two

(2) times a year, two weeks prior to Memorial Day and one week prior to

Veterans Day, or as directed by the COR

JB $0.00 2 $0.00

10043 5b.8.6

Pressure/Power Washing: Committal Shelters; quarterly (4 times per year, Nov., Feb., April, July)

JB $0.00 4 $0.00

10044

5b.8.7

Pressure/Power Washing: Buildings and Surrounding Concrete Surfaces;

two (2) times a year, once between March 1st and May 15, and again between September 1st and November 15th or as directed by the COR

JB $0.00 2 $0.00

10045 5b.8.8

Pressure/Power Washing: Floral Vase/Trash Receptacle Cleaning;

(quarterly (4 times per year), Nov., Feb., April, July)

JB $0.00 4 $0.00

10046 5b.9.1 Daily Committal Shelter Setup, Take Down, and Cleaning EA $0.00 375 $0.00

10047 5b.9.2 Weekend/Holiday Burial Support EA $0.00 11 $0.00

10048 5b.9.3 Ceremony Event Support to include set-up and take-down EV $0.00 3 $0.00

CLIN SOW Description Unit of issue Est. Cost Est. Qty Total

20001 5b.1.1 Headstone receiving, preparation, and transportation EA $0.00 950 $0.00

20002 5b.1.2

Headstone Installation and Setting, All First, Subequent (R2) Interment and All Replacement Headstones - Davis Bacon Wages

EA $0.00 950 $0.00

See guidance at bottom of page

20003 5b.1.3 Headstone Raise and Realign - Davis Bacon Wages EA $0.00 500 $0.00 See guidance at bottom of page

20004 5b.1.3 Bump and Run - Davis Bacon Wages EA $0.00 500 $0.00 See guidance at bottom of page

20005 5b.2.1 Sunken Grave and Grounds Repair - Davis Bacon Wages EA $0.00 150 $0.00 See guidance at bottom of page

20006 5b.2.2

Gravesite Floral/Decoration collection/removal (Daily occurrence -

Invoiced Monthly)

MO $0.00 12 $0.00

20007 5b.2.3 Mass Floral, Decorations, Trash and Debris Pick-up/Removal EA $0.00 20 $0.00

20008 5b.3.1 Pond Algae Treatment MO $0.00 9 $0.00

20009 5b.3.2 Pond Equipment Maintenance (Timers, Fountains, Aerators, Cables, etc.) JB $0.00 2 $0.00

20010 5b.4.1 Pump House Monitoring and Maintenance MO $0.00 12 $0.00

20011 5b.4.2

Irrigation- Yearly Startup/Shut Down, & Monthly system check-Includes

Sprinkler adjustments as needed (Growing Season)

MO $0.00 10 $0.00

20012 5b.4.2

Irrigation- Main Line/ Lateral PVC/Poly Repair/Replace 2" to 6" Breaks -

Davis Bacon Wages

EA $0.00 5 $0.00

See guidance at bottom of page

20013 5b.4.2 Irrigation- In-Valve Head Repair/Replace - Davis Bacon Wages EA $0.00 5 $0.00 See guidance at bottom of page

20014

5b.4.2

Irrigation-Popup Rotor,Mister Head and Electric Valve Solenoid

Repair/Replace (Includes rotor/mister adjustment with OEM nozzle present - Davis Bacon Wages

EA $0.00 15 $0.00

See guidance at bottom of page

20015 5b.4.2 Irrigation- Electric & Gate valve Repair/Replace - Davis Bacon Wages EA $0.00 5 $0.00

See guidance at bottom of page

20016 5b.4.2 Irrigation- Lateral Line Repair/Replace 3/4"-1" PVC/ Poly EA $0.00 5 $0.00 See guidance at bottom of page

20017 5b.4.2

Irrigation- Controller Repair/ Replace/ Program to current Stand-alone(Hunter)

EA $0.00 3 $0.00

20018 5b.4.3 Mowing and turf edging, (Tifway 419 Bermuda) WK $0.00 43 $0.00

20019 5b.4.4 Mowing non-turf areas WK $0.00 43 $0.00

20020 5b.4.5 Headstone, Marker, Monument and Other Vertical Surface Trimming WK $0.00 25 $0.00

20021 5b.4.6

Leaf, Trash and Debris Collection and Removal; (Daily occurrence -

Invoiced Monthly)

MO $0.00 12 $0.00

20022 5b.4.7 Extreme Weather Storm Damage and Debris Clean-up EV $0.00 3 $0.00

20023 5b.4.8 Sweeping/Blowing Off Roadways and Concrete Surfaces MO $0.00 12 $0.00

20024 5b.4.9 Maintenance of Benches, Concrete Pads, and Rocked Areas MO $0.00 12 $0.00

OPTION YEAR 2

Option Year 1 Total Estimate COST $0.00

20025 5b.5.1 Maintenance of Plant Beds, Shrubs, and Bushes MO $0.00 6 $0.00

20026 5b.5.2

Tree Maintenance-(tree trimming, canopy raise, new tree establishment, guying)

JB $0.00 6 $0.00

20027 5b.5.3

Mulching - Removal, Replenish and/or Install All Areas

Cemetery defined

JB $0.00 2 $0.00

20028 5b.6.1 Casket/Vault Gravesite Sod Installation EA $0.00 1000 $0.00

20029 5b.6.2 Core Aerification (Aeration) - Approx 27 acres - September JB $0.00 1 $0.00

20030 5b.6.3

Dethatching - As necessary - Cemetery Discretion - Up to 27 acres of turfed grounds

JB $0.00 1 $0.00

20031 5b.6.4

Fertilization- Bermuda (20-0-06 at 5lb N per 1000); Mar 5, April 15, Jun

1, Aug. 15, Oct 1

JB $0.00 5 $0.00

20032 5b.6.5

Weed Control: Pre-Emerge Herbicide Application (Spring (Jan/Mar) and

Fall (Oct/Nov))

JB $0.00 2 $0.00

20033 5b.6.5

Weed Control: Post Emerge Herbicide Treatment/Application-- All

Turf areas - Approx 27 acres (as needed or directed by COR)

JB $0.00 5 $0.00

20034 5b.6.6

Lime( Gypsum) Calcuim Sulfate Application -

All Turf Areas-Early Spring Yearly - as indicated by soil test

JB $0.00 1 $0.00

20035 5b.7.1

Insecticide( Mole Cricket, Stunt Mite control)Treatment/Application (as needed or directed by COR)

JB $0.00 5 $0.00

20036 5b.7.1 Fungicide Treatment/Application (as needed or directed by COR) JB $0.00 2 $0.00

20037 5b.7.2 Fire Ant Control/Monitoring - Daily Treatment Invoiced Monthly MO $0.00 12 $0.00

20038

5b.8.1

Headstone Cleaning; 2 times (Bi-annually) a year. Cleaning shall be completed two weeks prior to Memorial Day and one week prior to

Veterans Day, or as scheduled by the COR

JB $0.00 2 $0.00

20039

5b.8.2

Pressure/Power Washing: Curbs, Sidewalks, and Composite Enclosures; 2 times a year; once between April 1st through May 15th, and again between November 1st through December 1st, or as directed by COR

JB $0.00 2 $0.00

20040

5b.8.3

Pressure/Power Washing: Entrance Ways, Walls, Caps, Brick Pylons, Areas (concrete pads/bases) under signs and Trash/Floral Receptacles; 2 times a year; once between April 15th and May 15th, and again between

November 1st through December 1st, or as directed by the COR

JB $0.00 2 $0.00

20041

5b.8.4

Pressure/Power Washing: Flag Assembly Area; 2 times a year; once between March 1st and May 15, and again between September 1st and

November 15th, or as directed by COR

JB $0.00 2 $0.00

20042

5b.8.5

Pressure/Power Washing: Columbarium, Memorial Walls, Concrete

Surfaces and Marble Niche Covers/Memorial Wall Markers; washed two

(2) times a year, two weeks prior to Memorial Day and one week prior to

Veterans Day, or as directed by the COR

JB $0.00 2 $0.00

20043 5b.8.6

Pressure/Power Washing: Committal Shelters; quarterly (4 times per year, Nov., Feb., April, July)

JB $0.00 4 $0.00

20044

5b.8.7

Pressure/Power Washing: Buildings and Surrounding Concrete Surfaces;

two (2) times a year, once between March 1st and May 15, and again between September 1st and November 15th or as directed by the COR

JB $0.00 2 $0.00

20045 5b.8.8

Pressure/Power Washing: Floral Vase/Trash Receptacle Cleaning;

(quarterly (4 times per year), Nov., Feb., April, July)

JB $0.00 4 $0.00

20046 5b.9.1 Daily Committal Shelter Setup, Take Down, and Cleaning EA $0.00 375 $0.00

20047 5b.9.2 Weekend/Holiday Burial Support EA $0.00 11 $0.00

20048 5b.9.3 Ceremony Event Support to include set-up and take-down EV $0.00 3 $0.00

CLIN SOW Description Unit of issue Est. Cost Est. Qty Total

30001 5b.1.1 Headstone receiving, preparation, and transportation EA $0.00 1000 $0.00

30002 5b.1.2

Headstone Installation and Setting, All First, Subequent (R2) Interment and All Replacement Headstones - Davis Bacon Wages

EA $0.00 1000 $0.00

See guidance at bottom of page

30003 5b.1.3 Headstone Raise and Realign - Davis Bacon Wages EA $0.00 500 $0.00 See guidance at bottom of page

30004 5b.1.3 Bump and Run - Davis Bacon Wages EA $0.00 500 $0.00 See guidance at bottom of page

30005 5b.2.1 Sunken Grave and Grounds Repair - Davis Bacon Wages EA $0.00 150 $0.00 See guidance at bottom of page

30006 5b.2.2

Gravesite Floral/Decoration collection/removal (Daily occurrence -

Invoiced Monthly)

MO $0.00 12 $0.00

30007 5b.2.3 Mass Floral, Decorations, Trash and Debris Pick-up/Removal EA $0.00 20 $0.00

30008 5b.3.1 Pond Algae Treatment MO $0.00 9 $0.00

30009 5b.3.2 Pond Equipment Maintenance (Timers, Fountains, Aerators, Cables, etc.) JB $0.00 2 $0.00

30010 5b.4.1 Pump House Monitoring and Maintenance MO $0.00 12 $0.00

30011 5b.4.2

Irrigation- Yearly Startup/Shut Down, & Monthly system check-Includes

Sprinkler adjustments as needed (Growing Season)

MO $0.00 10 $0.00

30012 5b.4.2

Irrigation- Main Line/ Lateral PVC/Poly Repair/Replace 2" to 6" Breaks -

Davis Bacon Wages

EA $0.00 5 $0.00

See guidance at bottom of page

30013 5b.4.2 Irrigation- In-Valve Head Repair/Replace - Davis Bacon Wages EA $0.00 5 $0.00 See guidance at bottom of page

30014

5b.4.2

Irrigation-Popup Rotor,Mister Head and Electric Valve Solenoid

Repair/Replace (Includes rotor/mister adjustment with OEM nozzle present - Davis Bacon Wages

EA $0.00 15 $0.00

See guidance at bottom of page

30015 5b.4.2 Irrigation- Electric & Gate valve Repair/Replace - Davis Bacon Wages EA $0.00 5 $0.00

See guidance at bottom of page

30016 5b.4.2 Irrigation- Lateral Line Repair/Replace 3/4"-1" PVC/ Poly EA $0.00 5 $0.00 See guidance at bottom of page

30017 5b.4.2

Irrigation- Controller Repair/ Replace/ Program to current Stand-alone(Hunter)

EA $0.00 3 $0.00

30018 5b.4.3 Mowing and turf edging, (Tifway 419 Bermuda) WK $0.00 43 $0.00

30019 5b.4.4 Mowing non-turf areas WK $0.00 43 $0.00

30020 5b.4.5 Headstone, Marker, Monument and Other Vertical Surface Trimming WK $0.00 25 $0.00

30021 5b.4.6

Leaf, Trash and Debris Collection and Removal; (Daily occurrence -

Invoiced Monthly)

MO $0.00 12 $0.00

30022 5b.4.7 Extreme Weather Storm Damage and Debris Clean-up EV $0.00 3 $0.00

30023 5b.4.8 Sweeping/Blowing Off Roadways and Concrete Surfaces MO $0.00 12 $0.00

30024 5b.4.9 Maintenance of Benches, Concrete Pads, and Rocked Areas MO $0.00 12 $0.00

30025 5b.5.1 Maintenance of Plant Beds, Shrubs, and Bushes MO $0.00 6 $0.00

30026 5b.5.2

Tree Maintenance-(tree trimming, canopy raise, new tree establishment, guying)

JB $0.00 6 $0.00

30027 5b.5.3

Mulching - Removal, Replenish and/or Install All Areas

Cemetery defined

JB $0.00 2 $0.00

30028 5b.6.1 Casket/Vault Gravesite Sod Installation EA $0.00 1050 $0.00

30029 5b.6.2 Core Aerification (Aeration) - Approx 27 acres - September JB $0.00 1 $0.00

Option Year 2 Total Estimate COST $0.00

OPTION YEAR 3

30030 5b.6.3

Dethatching - As necessary - Cemetery Discretion - Up to 27 acres of turfed grounds

JB $0.00 1 $0.00

30031 5b.6.4

Fertilization- Bermuda (20-0-06 at 5lb N per 1000); Mar 5, April 15, Jun

1, Aug. 15, Oct 1

JB $0.00 5 $0.00

30032 5b.6.5

Weed Control: Pre-Emerge Herbicide Application (Spring (Jan/Mar) and

Fall (Oct/Nov))

JB $0.00 2 $0.00

30033 5b.6.5

Weed Control: Post Emerge Herbicide Treatment/Application-- All

Turf areas - Approx 27 acres (as needed or directed by COR)

JB $0.00 5 $0.00

30034 5b.6.6

Lime( Gypsum) Calcuim Sulfate Application -

All Turf Areas-Early Spring Yearly - as indicated by soil test

JB $0.00 1 $0.00

30035 5b.7.1

Insecticide( Mole Cricket, Stunt Mite control)Treatment/Application (as needed or directed by COR)

JB $0.00 5 $0.00

30036 5b.7.1 Fungicide Treatment/Application (as needed or directed by COR) JB $0.00 2 $0.00

30037 5b.7.2 Fire Ant Control/Monitoring - Daily Treatment Invoiced Monthly MO $0.00 12 $0.00

30038

5b.8.1

Headstone Cleaning; 2 times (Bi-annually) a year. Cleaning shall be completed two weeks prior to Memorial Day and one week prior to

Veterans Day, or as scheduled by the COR

JB $0.00 2 $0.00

30039

5b.8.2

Pressure/Power Washing: Curbs, Sidewalks, and Composite Enclosures; 2 times a year; once between April 1st through May 15th, and again between November 1st through December 1st, or as directed by COR

JB $0.00 2 $0.00

30040

5b.8.3

Pressure/Power Washing: Entrance Ways, Walls, Caps, Brick Pylons, Areas (concrete pads/bases) under signs and Trash/Floral Receptacles; 2 times a year; once between April 15th and May 15th, and again between

November 1st through December 1st, or as directed by the COR

JB $0.00 2 $0.00

30041

5b.8.4

Pressure/Power Washing: Flag Assembly Area; 2 times a year; once between March 1st and May 15, and again between September 1st and

November 15th, or as directed by COR

JB $0.00 2 $0.00

30042

5b.8.5

Pressure/Power Washing: Columbarium, Memorial Walls, Concrete

Surfaces and Marble Niche Covers/Memorial Wall Markers; washed two

(2) times a year, two weeks prior to Memorial Day and one week prior to

Veterans Day, or as directed by the COR

JB $0.00 2 $0.00

30043 5b.8.6

Pressure/Power Washing: Committal Shelters; quarterly (4 times per year, Nov., Feb., April, July)

JB $0.00 4 $0.00

30044

5b.8.7

Pressure/Power Washing: Buildings and Surrounding Concrete Surfaces;

two (2) times a year, once between March 1st and May 15, and again between September 1st and November 15th or as directed by the COR

JB $0.00 2 $0.00

30045 5b.8.8

Pressure/Power Washing: Floral Vase/Trash Receptacle Cleaning;

(quarterly (4 times per year), Nov., Feb., April, July)

JB $0.00 4 $0.00

30046 5b.9.1 Daily Committal Shelter Setup, Take Down, and Cleaning EA $0.00 375 $0.00

30047 5b.9.2 Weekend/Holiday Burial Support EA $0.00 11 $0.00

30048 5b.9.3 Ceremony Event Support to include set-up and take-down EV $0.00 3 $0.00

Option Year 3 Total Estimate COST $0.00

OPTION YEAR 4

CLIN SOW Description Unit of issue Est. Cost Est. Qty Total

40001 5b.1.1 Headstone receiving, preparation, and transportation EA $0.00 1050 $0.00

40002 5b.1.2

Headstone Installation and Setting, All First, Subequent (R2) Interment and All Replacement Headstones - Davis Bacon Wages

EA $0.00 1050 $0.00

See guidance at bottom of page

40003 5b.1.3 Headstone Raise and Realign - Davis Bacon Wages EA $0.00 500 $0.00 See guidance at bottom of page

40004 5b.1.3 Bump and Run - Davis Bacon Wages EA $0.00 500 $0.00 See guidance at bottom of page

40005 5b.2.1 Sunken Grave and Grounds Repair - Davis Bacon Wages EA $0.00 150 $0.00 See guidance at bottom of page

40006 5b.2.2

Gravesite Floral/Decoration collection/removal (Daily occurrence -

Invoiced Monthly)

MO $0.00 12 $0.00

40007 5b.2.3 Mass Floral, Decorations, Trash and Debris Pick-up/Removal EA $0.00 20 $0.00

40008 5b.3.1 Pond Algae Treatment MO $0.00 9 $0.00

40009 5b.3.2 Pond Equipment Maintenance (Timers, Fountains, Aerators, Cables, etc.) JB $0.00 2 $0.00

40010 5b.4.1 Pump House Monitoring and Maintenance MO $0.00 12 $0.00

40011 5b.4.2

Irrigation- Yearly Startup/Shut Down, & Monthly system check-Includes

Sprinkler adjustments as needed (Growing Season)

MO $0.00 10 $0.00

40012 5b.4.2

Irrigation- Main Line/ Lateral PVC/Poly Repair/Replace 2" to 6" Breaks -

Davis Bacon Wages

EA $0.00 5 $0.00

See guidance at bottom of page

40013 5b.4.2 Irrigation- In-Valve Head Repair/Replace - Davis Bacon Wages EA $0.00 5 $0.00 See guidance at bottom of page

40014

5b.4.2

Irrigation-Popup Rotor,Mister Head and Electric Valve Solenoid

Repair/Replace (Includes rotor/mister adjustment with OEM nozzle present - Davis Bacon Wages

EA $0.00 15 $0.00

See guidance at bottom of page

40015 5b.4.2 Irrigation- Electric & Gate valve Repair/Replace - Davis Bacon Wages EA $0.00 5 $0.00

See guidance at bottom of page

40016 5b.4.2 Irrigation- Lateral Line Repair/Replace 3/4"-1" PVC/ Poly EA $0.00 5 $0.00 See guidance at bottom of page

40017 5b.4.2

Irrigation- Controller Repair/ Replace/ Program to current Stand-alone(Hunter)

EA $0.00 3 $0.00

40018 5b.4.3 Mowing and turf edging, (Tifway 419 Bermuda) WK $0.00 43 $0.00

40019 5b.4.4 Mowing non-turf areas WK $0.00 43 $0.00

40020 5b.4.5 Headstone, Marker, Monument and Other Vertical Surface Trimming WK $0.00 25 $0.00

40021 5b.4.6

Leaf, Trash and Debris Collection and Removal; (Daily occurrence -

Invoiced Monthly)

MO $0.00 12 $0.00

40022 5b.4.7 Extreme Weather Storm Damage and Debris Clean-up EV $0.00 3 $0.00

40023 5b.4.8 Sweeping/Blowing Off Roadways and Concrete Surfaces MO $0.00 12 $0.00

40024 5b.4.9 Maintenance of Benches, Concrete Pads, and Rocked Areas MO $0.00 12 $0.00

40025 5b.5.1 Maintenance of Plant Beds, Shrubs, and Bushes MO $0.00 6 $0.00

40026 5b.5.2

Tree Maintenance-(tree trimming, canopy raise, new tree establishment, guying)

JB $0.00 6 $0.00

40027 5b.5.3

Mulching - Removal, Replenish and/or Install All Areas

Cemetery defined

JB $0.00 2 $0.00

40028 5b.6.1 Casket/Vault Gravesite Sod Installation EA $0.00 1100 $0.00

40029 5b.6.2 Core Aerification (Aeration) - Approx 27 acres - September JB $0.00 1 $0.00

40030 5b.6.3

Dethatching - As necessary - Cemetery Discretion - Up to 27 acres of turfed grounds

JB $0.00 1 $0.00

40031 5b.6.4

Fertilization- Bermuda (20-0-06 at 5lb N per 1000); Mar 5, April 15, Jun

1, Aug. 15, Oct 1

JB $0.00 5 $0.00

40032 5b.6.5

Weed Control: Pre-Emerge Herbicide Application (Spring (Jan/Mar) and

Fall (Oct/Nov))

JB $0.00 2 $0.00

40033 5b.6.5

Weed Control: Post Emerge Herbicide Treatment/Application-- All

Turf areas - Approx 27 acres (as needed or directed by COR)

JB $0.00 5 $0.00

40034 5b.6.6

Lime( Gypsum) Calcuim Sulfate Application -

All Turf Areas-Early Spring Yearly - as indicated by soil test

JB $0.00 1 $0.00

40035 5b.7.1

Insecticide( Mole Cricket, Stunt Mite control)Treatment/Application (as needed or directed by COR)

JB $0.00 5 $0.00

40036 5b.7.1 Fungicide Treatment/Application (as needed or directed by COR) JB $0.00 2 $0.00

40037 5b.7.2 Fire Ant Control/Monitoring - Daily Treatment Invoiced Monthly MO $0.00 12 $0.00

40038

5b.8.1

Headstone Cleaning; 2 times (Bi-annually) a year. Cleaning shall be completed two weeks prior to Memorial Day and one week prior to

Veterans Day, or as scheduled by the COR

JB $0.00 2 $0.00

40039

5b.8.2

Pressure/Power Washing: Curbs, Sidewalks, and Composite Enclosures; 2 times a year; once between April 1st through May 15th, and again between November 1st through December 1st, or as directed by COR

JB $0.00 2 $0.00

40040

5b.8.3

Pressure/Power Washing: Entrance Ways, Walls, Caps, Brick Pylons, Areas (concrete pads/bases) under signs and Trash/Floral Receptacles; 2 times a year; once between April 15th and May 15th, and again between

November 1st through December 1st, or as directed by the COR

JB $0.00 2 $0.00

40041

5b.8.4

Pressure/Power Washing: Flag Assembly Area; 2 times a year; once between March 1st and May 15, and again between September 1st and

November 15th, or as directed by COR

JB $0.00 2 $0.00

40042

5b.8.5

Pressure/Power Washing: Columbarium, Memorial Walls, Concrete

Surfaces and Marble Niche Covers/Memorial Wall Markers; washed two

(2) times a year, two weeks prior to Memorial Day and one week prior to

Veterans Day, or as directed by the COR

JB $0.00 2 $0.00

40043 5b.8.6

Pressure/Power Washing: Committal Shelters; quarterly (4 times per year, Nov., Feb., April, July)

JB $0.00 4 $0.00

40044

5b.8.7

Pressure/Power Washing: Buildings and Surrounding Concrete Surfaces;

two (2) times a year, once between March 1st and May 15, and again between September 1st and November 15th or as directed by the COR

JB $0.00 2 $0.00

40045 5b.8.8

Pressure/Power Washing: Floral Vase/Trash Receptacle Cleaning;

(quarterly (4 times per year), Nov., Feb., April, July)

JB $0.00 4 $0.00

40046 5b.9.1 Daily Committal Shelter Setup, Take Down, and Cleaning EA $0.00 375 $0.00

40047 5b.9.2 Weekend/Holiday Burial Support EA $0.00 11 $0.00

40048 5b.9.3 Ceremony Event Support to include set-up and take-down EV $0.00 3 $0.00

BASE YEAR $0.00

OPTION YEAR # 1 $0.00

OPTION YEAR # 2 $0.00

OPTION YEAR # 3 $0.00

OPTION YEAR # 4 $0.00

TOTAL $0.00

Option Year 4 Total Estimate COST $0.00

Note:

Davis-Bacon Act WD # AL20230096 will be applied for CLINS Highlighted

Service Contract Act WD # 2015-4591 will be applied for all other CLINS.