36C78623B0014_1.docx

DOCX document 172 KB Posted

Attached to
Y1PZ--823-MM23-004: Replace Committal Shelter, Wood NC
Solicitation number
36C78623B0014
Issued by

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C78623B0014

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C78623B0014 X 05-10-2023 7743-000016

823MM23004

36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle VA 22172 Richard Adu Department of Veterans Affairs National Cemetery Administration Contracting Services Richard.Adu@va.gov Adu, Richard

(917) 951-0653 This Project will Replace Committal Shelter at the National Cemetery Administration, Wood National Cemetery, 5000 W National Ave. Bldg. 1301, Milwaukee, WI 53295-4000. The Contractor shall provide all materials, supplies, equipment, personnel necessary and required to provide construction services to accomplish project number 823MM23004 Replace Shelter in accordance with the Scope of Work, Drawing, Specifications applicable Local, State and Federal laws and regulations. Contractor will be responsible to coordinate and schedule work to minimize to short duration and shall be be expected to plan work typically during duty hours of 7:30 AM to 4:00 PM local time.

This i s a 100% Service Disabled Veteran Owned Small Business (SDVOSB) set aside procurement and will be conducted in accordance with Public Law 109 461. Bidders must be CVE verified prior to submitting a bid in accordance with VAAR 819 7003(B) and FAR Provision 52.204 7(a). All prospective bidders must be registered in System for Award Management (SAM) at www.sam.gov and have SAM Unique Entity Identifier (UEI) number, and are verified /visible/certified in SBA site https://veterans.certify.sba.gov/, Vets 4212 at https://www.dol.gov at the time of offer submission and before award of this procurement.

Magnitude o f Construction is Between $250,000 and $500,000 per FAR 36.204. The North American Industry Classification System Code (NAICS) is 236220 and Business Size Standard is $39.5 Million.

There i s an organized pre bid site visit scheduled. See 52.236 27 Site Visit for detailed site visit information.

NOTE: NO OTHER SITE VISITS WILL BE ALLOWED. INTERESTED BIDDERS ARE STRONGLY ENCOURAGED TO ATTEND.

To preserve the integrity of the procurement process, all prebid questions and request for information must be submitted in writing to Richard Adu, Administrative Contracting Officer via email at Richard.Adu@va.gov. Questions must be received no later than Wednesday May 24, 2023, at 4:00PM EST. See section A.3 item 8 QUESTIONS for details.

IAW FAR 36.209, No contract for the construction of a project shall be awarded to the firm that designed the project or its subsidiaries or affiliates, except with the approval of the head of the agency or authorized representative.

Fill in and return the attached Limitations on Subcontracting Certificate and FAR 52.219-28 Post-Award Small Business Program Rerepresentation (MAR 2023) and return them with your bid.

NOTE: CONTRACTORS MUST ACKNOWLEDGE ALL SOLICIATION AMENDMENTS.

X X 52.211-10 X

2:00 PM

EDT

06-12-2023 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

Base Bid Item #1__________________________________ 36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle VA 22172 http://www.tungsten-network.com/customer -campaigns/veterans-affairs/

1-877-752-0900 Richard Adu Contracting Officer

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
A.4 STATEMENT OF WORK9
A.5 STATEMENT OF BID11
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS12
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS14
2.1 52.214-31 FACSIMILE BIDS (DEC 1989)14
2.2 52.216-1 TYPE OF CONTRACT (APR 1984)14
2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)15
2.4 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)15
2.5 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)16
2.6 52.233-2 SERVICE OF PROTEST (SEP 2006)17
2.7 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)18
2.8 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)18
2.9 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)19
2.10 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)19
REPRESENTATIONS AND CERTIFICATIONS20
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2023)20
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)24
3.3 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021)26
3.4 52.229-11 TAX ON CERTAIN FOREIGN PROCUREMENTS—NOTICE AND REPRESENTATION (JUN 2020)28
GENERAL CONDITIONS30
4.1 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (NOV 2021)30
4.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984)31
4.3 52.211-12 LIQUIDATED DAMAGES—CONSTRUCTION (SEPT 2000)32
4.4 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (MAR 2023)33
4.5 52.223-99 ENSURING ADEQUATE COVID-19 SAFETY PROTOCOLS FOR FEDERAL CONTRACTORS (OCT 2021) (DEVIATION)36
4.6 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)37
4.7 52.236-4 PHYSICAL DATA (APR 1984)41
4.8 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)42
4.9 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022)44
4.10 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)45
4.11 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018)45
4.12 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR VERIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (NOV 2022)45
4.13 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING--CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (NOV 2022)48
4.14 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)49
4.15 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)50
4.16 VAAR 852.232-71 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (INCLUDING NAS– CPM) (NOV 2018)50
4.17 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)53
4.18 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)54
4.19 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)55
4.20 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)55
4.21 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)55
4.22 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)56
4.23 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)56
4.24 SUPPLEMENTAL INSURANCE REQUIREMENTS58
4.25 IT CONTRACT SECURITY58
4.26 WAGE RATE69

A.3 CONTRACT ADMINISTRATION DATA

1. CONTRACT ADMINISTRATION: All contract administration matters will be handled by the following individual(s):

a. CONTRACTOR: _____________________

Unique Entity ID: _____________________ UIE Number: _____________________ Contact Person: _____________________ Telephone #: _____________________ e-Mail Address: _____________________ Tax Identification Number: _____________________

NOTE: Starting Monday, April 4, 2022, the new Unique Entity ID from SAM.gov will be the official, Federal Government-wide identifier used for Federal contract awards.

b. GOVERNMENT: Contracting Officer (36C786) Department of Veterans Affairs, National Cemetery Administration Contracting Service 18434 Joplin Road Triangle, VA 22172

2. CONTRACTOR REMITTANCE ADDRESS: Effective January 1, 1999, all payments by the Government to the Contractor will be made in accordance with Federal Acquisition Regulation (FAR) Clause 52.232-34, Payment by Electronic Funds Transfer. Contractor must be registered in the System for Award Management (SAM) database in accordance with FAR Clause 52.212-1(k).

3. INVOICES: Invoices shall be submitted within ten (10) business days after performance and acceptance of services and must include the VA Project Number, Contract Number, Purchase Obligation Number, Dates of Service, Detailed description of the services provided and Total Amount Due. Payment for services provided under the terms of this contract will be made in arrears, within thirty (30) calendar days, upon receipt of properly executed invoice(s) in accordance with:

· 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2012)

· UPON ACCEPTANCE OF SERVICES

· In order to comply with the Improper Payment Elimination and Recovery Act of 2010 (IPERA), the VA has mandated electronic invoice submission to the Veterans Affairs Financial Services Center (VAFSC). VAFSC has partnered with OB10 e-Invoicing network, for submissions of all electronic invoices to VA. OB10 electronic invoicing is free to all VA vendors. In order to submit electronic invoices, all VA vendors must register with OB10 by submitting an email to VA.Registration@ob10.com or calling 1-877-752-0900 option 2 for Enrollment.

· Contractor shall submit an electronic invoice within ten (10) business days after performance and acceptance of services to the Veterans Affairs Financial Services Center (VAFSC) e-Invoice through the website at https://portal.tungsten-network.com/Login.aspx . For questions regarding the submission of VA electronic invoices, OB10 customer service may be contacted at 1-877-489-6135.

· All invoices shall reference the vendor’s name and address, customer name, contract number, appropriate obligation/funding order number, description of services provided, quantity provided, unit price, and total invoice amount (any additional info). Invoices shall also include any payment discount terms.

· For questions regarding invoice receipt or payment, please call VAFSC directly at 1-877-353-9791 or email vafsccshd@va.gov.

4. GOVERNMENT INVOICE ADDRESS: All invoices from the Contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 “Electronic Submission of Payment Requests.” to the following web address: http://www.fsc.va.gov/einvoice.asp.

FACSIMILE, E-MAIL, AND SCANNED DOCUMENTS ARE NOT ACCEPTABLE FORMS OF SUBMISSION FOR PAYMENT REQUESTS.

For assistance setting up e-Invoice, the below information is provided:

* Tungsten Network e-Invoice Setup Information: 1-877-489-6135

* Tungsten Network e-Invoice email: VA.Registration@ob10.com <http://VA.Registration@ob10.com/>

* FSC e-Invoice Contact Information: 1-877-353-9791

* FSC e-invoice email: vafsccshd@va.gov <http://va.gov/>

5. CONTRACT AUTHORITY: The Contracting Officer acting within the scope of the contract and his/her duties and responsibilities is the only person authorized to approve changes or modify any of the requirements of this request. The Contractor shall communicate with the Contracting Officer on all matters pertaining to Contract Administration. Only the Contracting Officer is authorized to make commitments or issue changes that affect pricing, quantities or quality of performance, delivery terms and conditions, or the term of the contract.

6. CONTRACTING OFFICER’S REPRESENTATIVE: Notwithstanding the Contractor’s responsibility for total management during the performance of the contract, the administration of the contract will require maximum coordination between the Government and the Contractor. The Contracting Officer will designate a Contracting Officer’s Representative (COR) for the project, of which all work coordination shall be made through the COR. The Contractor shall be provided a copy of the COR’s Delegation of Authority letter outlining the scope of the COR’s duties and responsibilities. No other person shall be authorized to act in such capacity unless appointed in writing by the Contracting Officer.

7. SUBMITTAL OF BIDS: In accordance with FAR 14.202-8, the government is authorizing electronic bids on this solicitation. ALL bids shall be emailed to the attention of the Richard Adu, Contracting Specialist at Richard.Adu@va.gov prior to the bid opening date/time specified. EMAIL SUBJECT LINE: Solicitation 36C78623B0014 Replace Committal Shelter – COMPANY NAME. The bids shall include copies of a bid bond. No hand-carried or mailed bids will be accepted. Please email your bids early to avoid delays related to bids going through VA security networks.

A public bid opening will occur on Microsoft Teams using the following:

Dial In: +1 347-566-4838 (United States, New York City) Phone Conference ID: 465214091# Click here to join the meeting

a. Bid package shall consist of the following minimum required documents:

· Company cover letter identifying the Solicitation number, Project Description, Company name and address, POC name, Phone number, Email address, Unique Entity ID Number, and Company’s DUNS number;

· Completed blocks 14-20c of the back of the SF 1442, ensuring full completion of all blocks;

· Completed Statement of Bid;

· Completed IFB Contractor Cost Estimate Worksheet;

· Completed, signed and attached SF30 Amendments (if applicable);

· Attached scanned digital copy of the Bid Bond (if applicable); (ensure to lightly darken raised seals)

NO FAX SUBMITTED BIDS WILL BE ACCEPTED.

Bids shall be subject to the terms and conditions of this solicitation.

8. QUESTIONS: All questions regarding this solicitation must be submitted in writing (email is acceptable) to: Richard.Adu@va.gov. Any prospective bidder desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing. No phone responses will be accepted. NOTE: All questions must reference the Solicitation number, Project number (if applicable) and the Description of the project in the Header or Opening Statement.

9. CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM:

a. FAR 42.1502 directs all Federal agencies to collect Past Performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One (1) or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.

b. The Past Performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.

c. It is requested that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than thirty (30) calendar days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the (CO). Information in the report must be protected as source selection sensitive information not releasable to the public.

d. When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.

e. Within sixty (60) calendar days after the end of a performance period, the CO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.

1. Contractor Representatives may then provide comments in response to the evaluation or return the evaluation without comment.

2. Your comments should focus on objective facts in the CO's narrative and should provide your views on the causes and ramifications of the assessed performance.

3. All information provided should be reviewed for accuracy prior to submission.

4. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.

5. Your response is due within sixty (60) calendar days after receipt of the CPAR. On day fifteen (15), the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.

6. If you do not sign and submit the CPAR within sixty (60) calendar days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."

f. The following guidelines apply concerning your use of the past performance evaluation:

1. Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions. Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.

2. Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.

g. If you wish to discuss a Past Performance evaluation, you should request a meeting in writing to the CO no later than seven (7) calendar days following your receipt of the evaluation. The meeting will be held via telephone or other means during your sixty (60) calendar day review period.

h. A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.

(End of Administration Data)

Page 1 of

A.4 STATEMENT OF WORK

STATEMENT OF WORK

PROJECT TITLE: 823MM23004: Replace Committal Shelter, Wood National Cemetery

STATEMENT OF WORK

The Contractor shall provide all Management, Supervision, Labor, Equipment, Materials, Parts, Tools, etc., required, and necessary to provide complete construction services to prepare site for building operations, including demolition and removal of existing structures, and furnish labor, materials, equipment, and services to construct and complete all work for Wood National Cemetery New Committal Shelter, as required by the project drawings and specifications.

PERIOD OF PERFORMANCE

The Contractor shall complete all work including submittals, reviews, quality control, repair/construction services, punch list corrections, clean up, invoicing and closeouts documentation submittal within One hundred and eighty (180) calendar days of Government issuance of the Notice to Proceed.

PLACE OF PERFORMANCE

Department of Veterans Affairs National Cemetery Administration Wood National Cemetery 5000 W National Ave. Bldg. 1301 Milwaukee, WI 53295-4000.

NATIONAL CEMETERY ADMINISTRATION DIGNITY STANDARDS

1. Every action by contractor personnel at a National Cemetery must be performed with the special care, reverence, dignity, and respect that acknowledge the cemetery as the final resting place that commemorates the service and sacrifice those service members, Veterans, and their families made for our Nation. Critically important is the awareness, required of the contractor employees, of the remains buried in the grounds where the work is performed. The utmost care must be given to these remains and the headstones and flat grave markers that mark those gravesites and memorialize the service of individuals.

0. Contractors cannot walk, stand, lean, sit or jump on headstones or markers. Nor can they drive over them. Contractor personnel should use tools approved by the Contracting Officer Representative (COR), such as shovels, pry bars or pinch bars to lift flat markers out of the ground; pickaxes are not an acceptable tool.

0. No tools, equipment or other items will be placed or leaned on headstones or markers. Once headstones/markers are removed from the socket, do not place on dirt piles or mud; they should be carefully placed on each associated gravesite and protected in such a way as to prevent any soiling and be out of the way of any other work.

0. Headstones shall be removed from their sockets using wooden and/or metal clamps. If metal clamps are used, the area that contacts the headstone must be protected with a rigid fabric that will prevent damage to and marking of the headstone. Clamps may be attached to a skid steer loader (i.e., Bobcat®) or similar machine to extract the headstone from the socket. When headstones are removed from their sockets, they shall be carefully stored on each associated gravesite; do not lean headstones against each other. Use care not to scratch or damage headstones in any manner. The headstones shall be laid with front inscription side up while the headstone is lying horizontally on the ground. The headstone shall be protected from direct ground contact while lying horizontally. The protection method shall be as approved by the COR and shall be free of deterioration in weather. An approved method is to support each headstone with two wood 4X4’s. Alternate methods can be approved. Cardboard shall not be used. Wood or other suitable appropriate and attractive material shall be used to keep the headstones from contact with the soil while lying horizontally during the construction period. This also shows respect towards the families visiting the gravesites and the remains that are buried.

0. Contractor shall be responsible for replacing damaged headstones and markers and for restoring turf damaged during performance of this work.

0. Additionally, should any activity result in the exposure and/or damage to any remains, container for remains (i.e., casket or urn), or outer burial container, the Contractor must contact the COR, Director/Assistant Director, and Contracting Officer (CO) for guidance.

1. Any doubts as to proper procedures shall be brought to the attention of the COR, Director/Assistant Director, and CO for guidance or resolution.

1. The Contractor is required to discuss the guidance with their employees and have each employee sign a statement of compliance and deliver the signed statement to the COR before work may begin.

SITE INVESTIGATION INSPECTION

Per FAR 52.236-3, Contractor should survey / inspect the site prior to submitting a bid/proposal/quote in order to be fully aware of the Scope of Services required and to adequately gather existing unit’s product information, model numbers and all necessary and matching standards and requirements. Contractor shall perform a ‘Site Investigation’ to verify the magnitude of all dimensions/measurements and site conditions before start of the work or the ordering of any equipment, parts and or materials. Failure to do so shall not relieve the successful offeror from performing in accordance with the strict intent and meaning of the specifications without additional cost to the Government.

Any electrical work shall be in accordance with the latest edition of the National Electrical Code (NEC) and local building codes. Failure to do so shall not relieve the Contractor from performing in accordance with the strict intent and meaning of the specifications without additional cost to the Government.

MATERIAL SUBMITTALS

All submittals, samples, etc., called for by the specification requirements shall be approved by the COR and/or the Contracting Officer before any work associated with or required by said submittal, samples, etc., is to begin. The Contractor shall prepare and submit all submittals as specified in the contract or as requested by the COR and/or the Contracting Officer.

a. Be advised and reminded that the COR cannot approve submittals that would result in a change to the contract terms or conditions, or that would affect a cost or time change; The Contracting Officer is the only person authorized to approve and issue supplemental agreements, change orders, stop order, modifications, payments, etc., on the Government behalf.

The Contractor must acquire the COR’s approval once materials has been approved to start the work.

All work shall be performed in a professional workmanship like manner, adhere to NCA standards, be done in strict accordance with the requirements set forth herein, manufacturer’s requirements, installation guidelines; and be in accordance with applicable Federal, State and Local codes and regulations; inclusive of applicable OSHA Construction Safety Guidelines.

SPECIFICATIONS AND DRAWINGS:

In the case of any differences between the Statement of Work, Specification and/or Drawings, the specifications will prevail and govern over the Statement of Work and/or Drawings. Any Statement of Work, Specification and/or Drawings discrepancies should be brought to the immediate attention of the Contracting Officer and COR for clarification. Any errors or omissions in the Statement of Work, Specification and/or Drawings must be provided promptly to the Contracting Officer and COR, but in no case later than the start of related work; Site Investigation Inspection; and NCA's Dignity Standards.

A.5 STATEMENT OF BID

STATEMENT OF BID

Project Number 823MM23004 Replace Committal Shelter at Wood National Cemetery

1.2 STATEMENT OF BID ITEM (S)

A. ITEM I, GENERAL CONSTRUCTION: Provide all labor, materials, tools, equipment, and services to install:

1. Work includes general construction, alterations, roads, walks, grading, and drainage, for the new committal shelter.

B. ITEM II, DEMOLITION: Work to include all labor, materials, equipment and supervision to perform the required demolition work for removal of existing committal shelter.

BID SCHEDULE

ITEM No.
DESCRIPTION
DEDUCT
TOTAL BID
I
GENERAL CONSTRUCTION:
N/A
II
DEMOLITION
N/A
$
TOTAL BASE BID
N/A
$

BASE BID $ ___________________________

36C78623B0014

INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS

Page 1 of

Page 1 of

(a) Bidding materials consisting of Invitation for Bids, drawings, specifications and contract forms will be available on https://sam.gov/ in electronic format only by searching for solicitation number 36C78623B0014 _1. All interested parties (subs & primes) should register at https://sam.gov/ as an “Interested Vendor” so that others will know of our interest in participating in this procurement. A Bidder’s mailing list WILL NOT BE prepared by the Contract Specialist. SOLICITATION AMENDMENTS: Amendments to the solicitation will be posted at https://sam.gov/. Paper copies of the amendments will NOT be individually mailed. By registering to “Receive Notification”, you will be notified by e-mail of any new amendments that have been issued and posted. No other notification of amendments will be provided. Bidders are reminded that they are responsible for obtaining and acknowledging all amendments to this solicitation prior to the time for receipt of bids.

(b) If bid exceeds $150,000 a bid bond must be submitted. A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening of bids, will require rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.

(c) If the contract will exceed $150,000 (see FAR 28.102-1 for lesser amount), the bidder to whom award is made will be required to furnish two bonds, a Payment Bond, SF 25A, and a Performance Bond, SF 25, each in the penal sum as noted in the General Conditions of the Specification. Copies of SFs 25 and 25A may be obtained upon application to the issuing office.

(d) If the bid is between $30,000 - $150,000. The bidder to whom award is made will be required to furnish a Payment Bond, Standard Form 25A or alternative payment protection which conforms to the requirements set forth in FAR Clause 52.228-13, Alternative Payment Protections, as noted in the General Conditions of this Specification. Copies of the Standard Form of Payment Bond may be obtained upon application to the Issuing Office.

(e) FAR 52.228-1 Bid Guarantee (Sept 1996) a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid. (b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds- (1) To unsuccessful bidders as soon as practicable after the opening of bids; and (2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted. (c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000 whichever is less. (d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default. (e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(f) FAR 52.228-17 Individual Surety—Pledge of Assets (Feb 2021) (a)Offerors shall obtain from each person acting as an individual surety on a bid guarantee— (1)A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203-1; and (2) Standard Form 28, Affidavit of Individual Surety. (b)The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228-1, Bid Guarantee, or as otherwise established by the Contracting Officer. (c)The Contracting Officer may release the security interest on the individual surety's assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.

DESCRIPTION OF WORK: GENERAL CONSTRUCTION: The Contractor shall provide all Management, Supervision, Labor, Equipment, Materials, Parts, Tools, etc., required, and necessary to provide complete construction services to prepare site for building operations, including demolition and removal of existing structures, and furnish labor, materials, equipment, and services to construct and complete all work for Wood National Cemetery New Committal Shelter, as required by the project drawings and specifications.

Cost Range: Between $250,000 and $500,000 per FAR 36.204.

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 52.214-31 FACSIMILE BIDS (DEC 1989)

(a) Definition. "Facsimile bid," as used in this solicitation, means a bid, modification of a bid, or withdrawal of a bid that is transmitted to and received by the Government via electronic equipment that communicates and reproduces both printed and handwritten material.

(b) Bidders may submit facsimile bids as responses to this solicitation. These responses must arrive at the place and by the time, specified in the solicitation.

(c) Facsimile bids that fail to furnish required representations or information or that reject any of the terms, conditions, and provisions of the solicitation may be excluded from consideration.

(d) Facsimile bids must contain the required signatures.

(e) The Government reserves the right to make award solely on the facsimile bid. However, if requested to do so by the Contracting Officer, the apparently successful bidder agrees to promptly submit the complete original signed bid.

(f) Facsimile receiving data and compatibility characteristics are as follows:

(1) Telephone number of receiving facsimile equipment:

(2) Compatibility characteristics of receiving facsimile equipment (e.g., make and model number, receiving speed, communications protocol):

(g) If the bidder chooses to transmit a facsimile bid, the Government will not be responsible for any failure attributable to the transmission or receipt of the facsimile bid including, but not limited to, the following:

(1) Receipt of garbled or incomplete bid.

(2) Availability or condition of the receiving facsimile equipment.

(3) Incompatibility between the sending and receiving equipment.

(4) Delay in transmission or receipt of bid.

(5) Failure of the bidder to properly identify the bid.

(6) Illegibility of bid.

(7) Security of bid data.

(End of Provision)

2.2 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.4 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade
Goals for female participation for each trade
2.3 %
6.9 %

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is

(End of Provision)

2.5 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

2.6 52.233-2 SERVICE OF PROTEST (SEP 2006)

Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

Department of Veterans Affairs National Cemetery Administration Hand-Carried Address:

Contracting Office NCA Contracting Service Construction Services 18434 Joplin Road Triangle VA 22172.

Mailing Address:

Contracting Office NCA Contracting Service Construction Services 18434 Joplin Road Triangle VA 22172.

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of Provision)

2.7 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for Wednesday May 17, 2023, at 2:00 PM CST

(c) Participants will meet at Building 1301 Cemetery office at:

Department of Veterans Affairs National Cemetery Administration Wood National Cemetery 5000 W National Ave. Bldg. 1301 Milwaukee, WI 53295-4000.

Bidders interested in attending the Site Visit should contact the Mr. Aaron Dishaw, email Aaron.Dishaw@va.gov, Phone # (414) 690-8609 to confirm attendance.

Due to limited capacity of the cemetery, attendance is limited to no more than three (3) individuals per interested bidder/company/firm.

(End of Provision)

2.8 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/

(End of Provision)

FAR Number
Title
Date
52.204-7
SYSTEM FOR AWARD MANAGEMENT
OCT 2018
52.204-16
COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING
AUG 2020
52.204-22
ALTERNATIVE LINE ITEM PROPOSAL
JAN 2017
52.214-3
AMENDMENTS TO INVITATIONS FOR BIDS
DEC 2016
52.214-4
FALSE STATEMENTS IN BIDS
APR 1984
52.214-5
SUBMISSION OF BIDS
DEC 2016
52.214-6
EXPLANATION TO PROSPECTIVE BIDDERS
APR 1984
52.214-7
LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS
NOV 1999
52.214-18
PREPARATION OF BIDS—CONSTRUCTION
APR 1984
52.214-19
CONTRACT AWARD—SEALED BIDDING—CONSTRUCTION
AUG 1996
52.214-34
SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE
APR 1991
52.214-35
SUBMISSION OF OFFERS IN U.S. CURRENCY
APR 1991
52.228-1
BID GUARANTEE
SEP 1996
52.228-17
INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE)
FEB 2021

2.9 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)

(a) Any protest filed by an interested party shall—

(1) Include the name, address, fax number, email and telephone number of the protester;

(2) Identify the solicitation and/or contract number;

(3) Include an original signed by the protester or the protester’s representative and at least one copy;

(4) Set forth a detailed statement of the legal and factual grounds of the protest, including a description of resulting prejudice to the protester, and provide copies of relevant documents;

(5) Specifically request a ruling of the individual upon whom the protest is served;

(6) State the form of relief requested; and

(7) Provide all information establishing the timeliness of the protest.

(b) Failure to comply with the above may result in dismissal of the protest without further consideration.

(c) Bidders/offerors and Contracting Officers are encouraged to use alternative dispute resolution (ADR) procedures to resolve protests at any stage in the protest process. If ADR is used, the Department of Veterans Affairs will not furnish any documentation in an ADR proceeding beyond what is allowed by the Federal Acquisition Regulation.

(End of Provision)

2.10 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)

(a) As an alternative to filing a protest with the Contracting Officer, an interested party may file a protest by mail or electronically with: Executive Director, Office of Acquisition and Logistics, Risk Management and Compliance Service (003A2C), Department of Veterans Affairs, 810 Vermont Avenue NW, Washington, DC 20420 or Email: EDProtests@va.gov.

(b) The protest will not be considered if the interested party has a protest on the same or similar issue(s) pending with the Contracting Officer.

(End of Provision)

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2023)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 236220.

(2) The small business size standard is $39.5 Million.

(3) The small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition—

(i) Is set aside for small business…