This request for proposal solicits competitive proposals for renovating a maintenance building at Fort Harrison National Cemetery in Virginia. The Department of Veterans Affairs seeks a firm fixed-price contract to provide all labor, materials, equipment, and supervision to complete the project. Offerors must submit electronic proposals through the VA vendor portal by September 9th, 2022. Proposals will be evaluated using lowest price technically acceptable criteria. The procurement is fully set aside for service-disabled veteran-owned small businesses. The work must be completed within 180 calendar days of receiving the notice to proceed. There is no incumbent contractor.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C78622R0042

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE

DOCUMENTS (

Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C78622R0042 X 08-14-2022

TBD

F363345-22-0000047

849-NRM22-01

36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle VA 22172 Request for Proposal (RFP) See Section: INSTRUCTIONS CONDITIONS, CONDITIONS, AND OTHER STATEMENT TO

OFFERORS.

Sheryl Palacio-Davis 1-703-630-9343 Fort Harrison Nalt Cem | The Dept. of Veterans Affairs, Nalt Cem Adm. (NCA), anticipates Awarding a Firm, Fixed Price Contract; In Accordance With (IAW) FAR Part 15.203. & VAAR Part 815.2, Request for Proposal (RFP).

The Construction Contractor shall provide labor, material, tools, equipment, and professional supervision required to Renovate Maintenance Building; In Accordance With (IAW) the Solicitation Plans, Statement of Work (SOW), Drawings, Specifications and per Construction Documents for this project, located at the Fort Harrison National Cemetery, VA.

This is a 100% competitive Set-Aside for Service-Disabled Veteran Owned Small Business (SDVOSB) In Accordance With (IAW) the Veterans First Program, 38 USC 8127 and 8128. Only SDVOSB firms verified eligible in Vetbiz.gov, with the Certified Veteran Enterprise (CVE) Seal on their registration will be considered. The Vetbiz database will be checked both upon receipt of an offer and prior to award. Firms must also have current registration in the System for Award Management (SAM) database at www.Sam.gov and have completed online Representatives and Certifications prior to award.

NOTE: Offerors MUST complete below information, failure to fill out required Fill-Ins may result in your RFP submission being determined Non-Responsive and or Unacceptable and your BID may be removed for further consideration.

DUNS NO. _________________________ | UEI NO. __________________________

TAX ID NO.____________________

E-MAIL:_

______________________________________ | PHONE#________________________

An organized Site Visit is scheduled for 25 Aug 2022, at 11:00 A.M. (EST) in the Admin Bldg. at Ft. Harrison Natl Cem 8620 Varina Rd. Richmond, VA 23231. Please See clause 52.236-27 for Site-Visit information.

Questions shall be submitted to sheryl.palacio-davis@va.gov, NLT, 01 Sept 2022 at 2:00 P.M. (EST), after the Site-Visit.

Email subject line must contain line must contain the following in the subject line: Solicitation Number, Proj. Name & Project No. Questions received after 01 September 2022 WILL NOT be WILL NOT be accepted. Telephone inquiries are Not accepted during the Solicitation phases. Answers will be posted through an Amendment to the Solicitation.

1.) PROPOSAL DUE DATE & TIME:

09 SEPT

2022 @ 13:00 (1:0 P.M.) EST. Electronic Proposals received after 1:00 PM (EST) WILL NOT Be Accepted.

2.) The Period of Performance (POP) is One Hundred and Eighty (180) Calendar Days from the date of receipt of the NTP.

3.) The North American Industry Classification System (NAICS) Codes: 238110 - 238990 | Bus. Size Standard: $36.5M 4.) MAGNITUDE OF CONSTRUCTION: PURSUANT TO FAR 36.204 & PER VAA36.204; RANGE IS BETWEEN $100,000.00 AND $300,000.00

5.) This procurement is being conducted as a competitive, negotiated Request for Proposals (RFP) that is to be awarded after a “Lowest Price Technically Acceptable” (LPTA) Evaluation. Offeror’s pricing will be reviewed for reasonableness and realism. The Government may use various price analysis techniques and procedures to ensure a fair and reasonable Price. If the price of your proposal is determined to be outside of the Government Cost Estimate (IGCE) of price reasonableness for this Procurement, your Proposal will be Denied.

*Unless otherwise noted, all references to "day(s)" throughout the solicitation documents shall be Calendar Days* **This procurement is a 100% competitive Set-Aside for Service-Disabled Veteran Own Small Business (SDVOSB)** X 52.211-10 X 13:00

EDT

09-09-2022 X

A.7 PRICE/COST SCHEDULE

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

OFFERORS

SHALL FILL OUT SECTION PRICE/COST SCHEDULE &

PRICE/COST SCHEDULE DEDUCT ALTERNATES IN SECTION

A.7;

ON

PAGE #12.

36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle VA 22172 http://www.tungsten-network.com/customer -campaigns/veterans-affairs/

1-877-752-0900 Sheryl Palacio-Davis Contracting Officer (CO)

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
A.3 SOLICITATION DESCRIPTION5
A.4 CONTRACT ADMINISTRATION5
16. NOTICE TO CONTRACTORS - CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM:8
A.5 SBA ACT 8(d)(13)(B)10
A.6 DIGNITY STANDARDS10
A.7 PRICE/COST SCHEDULE11
ITEM INFORMATION11
ITEM INFORMATION11
A.8 DELIVERY SCHEDULE12
INFORMATION REGARDING OFFER/BIDDING MATERIAL, BID GUARANTEE AND BONDS12
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS15
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)15
2.2 52.212-2 EVALUATION—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2021)15
2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)17
2.4 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)17
2.5 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)18
2.6 52.228-1 BID GUARANTEE (SEP 1996)20
2.7 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021)20
2.8 52.233-2 SERVICE OF PROTEST (SEP 2006)21
2.9 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)21
2.10 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)22
2.11 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)22
2.12 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)22
REPRESENTATIONS AND CERTIFICATIONS24
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAY 2022) (JUL 2020) (DEVIATION)24
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)28
3.3 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021)30
GENERAL CONDITIONS33
4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)33
4.2 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (NOV 2021)33
4.3 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984)34
4.4 52.211-12 LIQUIDATED DAMAGES—CONSTRUCTION (SEPT 2000)34
4.5 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (SEP 2021)35
4.6 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020)38
4.7 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010)38
4.8 52.223-99 ENSURING ADEQUATE COVID-19 SAFETY PROTOCOLS FOR FEDERAL CONTRACTORS (OCT 2021) (DEVIATION)40
4.9 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (NOV 2021)40
4.10 SUPPLEMENTAL INSURANCE REQUIREMENTS44
4.11 52.236-4 PHYSICAL DATA (APR 1984)45
4.12 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997) ALTERNATE II (APR 1984)46
4.13 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)47
4.14 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020)48
4.15 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION)50
4.16 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018)52
4.17 VAAR 852.219-77 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (SEP 2021) (DEVIATION)53
4.18 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)54
4.19 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)56
4.20 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)57
4.21 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)57
4.22 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)57
4.23 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)58
4.24 VAAR 852.246-75 WARRANTY OF CONSTRUCTION—GUARANTEE PERIOD SERVICES (OCT 2018)59

A.3 SOLICITATION DESCRIPTION

DESCRIPTION OF SOLICITATION FOR FORT HARRISON NATIONAL CEMETERY

CEMETERY: FORT HARRISON NATIONAL CEMETERY, VIRGINIA (VA)

PROJECT NO. 849-NRM22-01

DESCRIPTION: RENOVATE MAINTENANCE BUILDING

SUBJECT:

The Department of Veterans Affairs (VA), National Cemetery Administration (NC), is Soliciting Proposals under Solicitation Number 36C78622R0042, for the Fort Harrison National Cemetery, located at 8620 Varina Rad; Richmond, VA 23231. The Acquisition type will be a Request for Proposal (RFP) for the Renovation of Maintenance Building at Ft. Harrison Natl Cem (VA). The RFP will utilize the Electronic Proposal via the VA Portal and SAM. The process will be outlined in the forthcoming Solicitation.

DESCRIPTION:

The Department of Veterans Affairs, National Cemetery Administration (NCA) has a requirement for a Firm Fixed Price (FFP) Contract and the Contractor shall provide all labor, tools, materials, equipment, services, testing. submittals, approvals, and professional supervision related work to Renovate Maintenance Building Project (849-NRM22-01), Base Contract & Deduct Alts 0001 Thru 0004, located at the Fort Harrison National Cemetery. The work Shall be completed In Accordance With (IAW) the Statement of Work (SOW), Specifications, and Drawings.

EVALUATION: LOWEST PRICE TECHNICALLY ACCEPTABLE (LPTA): Please see 52.212-2 within this Solicitation.

This procurement is a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside. This procurement is being conducted as a competitive, negotiated Request for Proposals (RFP) that is to be awarded after a “Lowest Price Technically Acceptable” (LPTA) Evaluation. Offeror’s pricing will be reviewed for reasonableness and realism. The Government may use various price analysis techniques and procedures to ensure a fair and reasonable price. If the price of your proposal is determined to be outside of the Government Cost Estimate (IGCE) of price reasonableness for this procurement, your Proposal will be Denied.

A.4 CONTRACT ADMINISTRATION

1. Contract Administration: All contract administration matters will be handled by the following individuals:

1. CONTRACTOR: TBD

b. GOVERNMENT:

Contracting Officer (CO): Sheryl Palacio-Davis U.S. Department of Veterans Affairs National Cemetery Administration (NCA) Contracting Service (43C) 18434 Joplin Rd Triangle, VA 22172 Business NO. 1-703-630-9343 Sheryl.palacio-Davis@va.gov

2. CONTRACTOR REMITTANCE ADDRESS: All payments by the Government to the contractor shall be made in accordance with:

[X] 52.232-34, Payment by Electronic Funds Transfer.

3. INVOICES: Invoices shall be submitted in arrears:

Other [X] [Monthly]

4. GOVERNMENT INVOICE ADDRESS:

All invoices from the contractor shall be sent electronically by following instruction as stated at website: http://www.fsc.va.gov/einvoice.asp See VAAR clause 852.232-72 Electronic Submission of Payment Requests (NOV 2012).

5. ACQUISITION: Total (100%) Service-Disabled Veteran Owned Small Business Set-Aside: This is a solicitation for construction services prepared in accordance with the format in FAR Part 14 and FAR Part 36. The contract will be awarded by Government to furnish those construction tasks as stated in the SOW, Specs and Drawings. The Government anticipates awarding this solicitation as a fixed-price contract.

Historical Data:

Incumbent Contractor: NONE

6. TYPE OF CONTRACT: This is a Firm Fixed-Price requirement contract in accordance with FAR 52.216-1 Type of Contract.

7. CONTRACT AWARD: The contract will become effective as soon as practical with no additional cost to the Government for any elapsed time from the original effective date. It is also, understood and agreed that the effective date of this contract will be contingent upon the availability of appropriated funds and in the event, appropriations are not available.

8. ACKNOWLEDGEMENT OF AMENDMENTS:

The Offeror acknowledges receipt of Amendments to the Solicitation numbered and dated as follows:

AMENDMENT NO
DATE

9. AUTHORITIES OF GOVERNMENT PERSONNEL: Notwithstanding the Contractors responsibility for total management during the performance of this contract, the administration of the contract will require maximum coordination between the Government and the Contractor. The Government will provide, at the time of contract award, a list of Government personnel authorized to act as the Contracting Officer's Representatives (COR). Only the Contracting Officer has the authority to make changes to the contract.

10. CONTRACTOR’S FOREMAN/SUPERVISOR: Contractor must provide an English-speaking foreman /Supervisor at all times while performing the duties of the contract. This is to ensure proper communication between the Contractor and COR.

11. SITE VISIT: See 52.236-27 for site visit information

12. PRE-CONSTRUCTION CONFERENCE: Prior to commencement of work, Contractor shall attend a pre-construction conference to assure that all parties understand all contractual obligations and the role that each party serves.

13. FEDERAL HOLIDAYS:

January
New Year’s Day
January
Martin Luther King’s Birthday
February
President’s Day
May
Memorial Day
June
Juneteenth Independence Day
July
Independence Day
September
Labor Day
October
Columbus Day
November
Veterans Day & Thanksgiving Day
December
Christmas Day

Including any other day specifically declared by the President of the United States to be a national holiday.

14. LIMITATIONS ON SUBCONTRACTING – MONITORING AND COMPLIANCE:

This contract includes (VAAR) 852.219-10, VA Notice of Total Service-Disabled Veteran-Owned Small Business Set- Aside. The Contractor is advised in performing contract administration functions, the CO may use the services of a support contractor(s) retained by VA to assist in assessing the contractor’s compliance with the limitations on subcontracting or percentage of work performance requirements specified in the clause. To that end, the support contractor(s) may require access to contractor’s offices where the contractor’s business records, or other proprietary data are retained and to review such business records regarding the contractor’s compliance with this requirement. All support contractors conducting this review on behalf of VA will be required to sign an “Information Protection and Non-Disclosure and Disclosure of Conflicts of Interest Agreement” to ensure the contractor’s business records or other proprietary data reviewed or obtained in the course of assisting the CO in assessing the contractor for compliance are protected to ensure information or data is not improperly disclosed or other impropriety occurs. Furthermore, if VA determines any services the support contractor(s) will perform in assessing compliance are advisory and assistance services as defined in FAR 2.101, Definitions, the support contractor(s) must also enter into an agreement with the contractor to protect proprietary information as required by FAR 9.505-4, Obtaining Access to Proprietary Information, paragraph (b). The contractor is required to cooperate fully and make available any records as may be required to enable the CO to assess the contractor’s compliance with the limitations on subcontracting or percentage of work performance requirement.

15. RELEASE OF CLAIMS:

After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relation to the contract. The Release of Claims form provided by the CO shall be used for this purpose. The form provides for exception of specified claims from the operation of release. Request a copy from the CO.

16. NOTICE TO CONTRACTORS - CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM:

1. FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.

1. The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.

1. We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.

1. When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.

1. Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.

1. Contractor Representatives may then provide comments in response to the evaluation or return the evaluation without comment.

1. Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.

1. All information provided should be reviewed for accuracy prior to submission.

1. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.

1. Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.

1. If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."

1. The following guidelines apply concerning your use of the past performance evaluation:

0. Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions. Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.

0. Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.

If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.

A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.

[END OF ADMINISTRATION DATA]

A.5 SBA ACT 8(d)(13)(B)

(B) NOTICE. —

(i) IN GENERAL.—A Prime Contractor for a covered contract shall notify in writing the Contracting Officer for the covered contract if the Prime Contractor pays a reduced price to a Subcontractor for goods and services upon completion of the responsibilities of the Subcontractor or the payment to a Subcontractor is more than 90 days past due for goods or services provided for the covered contract for which the Federal agency has paid the Prime Contractor.

(ii) CONTENTS. —A Prime Contractor shall include the reason for the reduction in a payment to or failure to pay a Subcontractor in any notice made under clause (i).

A.6 DIGNITY STANDARDS

1. Every action by contractor personnel at a National Cemetery must be performed with the special care, reverence, dignity, and respect that acknowledge the cemetery as the final resting place that commemorates the service and sacrifice those service members, Veterans, and their families made for our Nation. Critically important is the awareness, required of the contractor employees, of the remains buried in the grounds where the work is performed. The utmost care must be given to these remains and the headstones and flat grave markers that mark those gravesites and memorialize the service of individuals.

a. Contractors cannot walk, stand, lean, sit or jump on headstones or markers. Nor can they drive over them. Contractor personnel should use tools approved by the Contracting Officer Representative (COR), such as shovels, pry bars or pinch bars to lift flat markers out of the ground; pick axes are not an acceptable tool.

b. No tools, equipment or other items will be placed or leaned on headstones or markers. Once headstones/markers are removed from the socket, do not place on dirt piles or mud; they should be carefully placed on each associated gravesite and protected in such a way as to prevent any soiling and be out of the way of any other work.

c. Headstones shall be removed from their sockets using wooden and/or metal clamps. If metal clamps are used, the area that contacts the headstone must be protected with a rigid fabric that will prevent damage to and marking of the headstone. Clamps may be attached to a skid steer loader (i.e., Bobcat®) or similar machine to extract the headstone from the socket. When headstones are removed from their sockets, they shall be carefully stored on each associated gravesite; do not lean headstones against each other. Use care not to scratch or damage headstones in any manner. The headstones shall be laid with front inscription side up while the headstone is lying horizontally on the ground. The headstone shall be protected from direct ground contact while lying horizontally. The protection method shall be as approved by the COR and shall be free of deterioration in weather. An approved method is to support each headstone with two wood 4X4’s. Alternate methods can be approved. Cardboard shall not be used. Wood or other suitable appropriate and attractive material shall be used to keep the headstones from contact with the soil while lying horizontally during the construction period. This also shows respect towards the families visiting the gravesites and the remains that are buried.

d. Contractor shall be responsible for replacing damaged headstones and markers and for restoring turf damaged during performance of this work.

e. Additionally, should any activity result in the exposure and/or damage to any remains, container for remains (i.e., casket or urn), or outer burial container, the Contractor must contact the COR, Director/Assistant Director, and Contracting Officer (CO) for guidance.

1. Any doubts as to proper procedures shall be brought to the attention of the COR, Director/Assistant Director, and CO for guidance or resolution.

1. The Contractor is required to discuss the guidance with their employees and have each employee sign a statement of compliance and deliver the signed statement to the COR before work may begin.

A.7 PRICE/COST SCHEDULE

Contractor shall provide all labor, tools, materials, equipment, services, testing. submittals, approvals, and professional supervision related work to Renovate Maintenance Building Project (849-NRM22-01), Base Contract & Deduct Alts 0001 Thru 0004, located at the Fort Harrison National Cemetery. The work Shall be completed In Accordance With (IAW) the Statement of Work (SOW), Specifications, and Drawings

ITEM INFORMATION

Contract Line Item
Description
Quantity
Unit
Unit Price
Total Price
0001
BASE BID: Renovate Maintenance Building
1
JB

TOTAL BASE BID / CLINS 0001

TOTAL PRICE WRITTEN:

PRICE/COST SCHEDULE DEDUCT ALTERNATES

Contractor shall provide all labor, tools, materials, equipment, services, testing. submittals, approvals, and professional supervision related work for the Renovate Maintenance Building Project (849-NRM22-01), Deduct Alternates, located at the Fort Harrison National Cemetery. The work Shall be completed In Accordance With (IAW) the Statement of Work (SOW), Specifications, and Drawings

ITEM INFORMATION

CONTRACT LINE ITEM
DESCRIPTION
QUANTITY
UNIT
UNIT PRICE
TOTAL PRICE
0001
REMOVE ASPHALT PAVEMENT SECTION.

INSTALL NEW CONCRETE PAVEMENT. DEDUCT ALTERNATE #1.

JB

0002
LIGHTNING PROTECTION FOR FLAMMABLE STORAGE AND MAINTENANCE BUILDINGS. DEDUCT ALTERNATE #2.

JB

0003
WORK ITEMS AT CEMETERY ENTRANCE - ADA WARNING PLATE, ENTRY GATE STOP AND CANE BOLT, BRONZE ENTRY SIGN. DEDUCT ALTERNATE #3.

JB

0004
GARAGE ACCESSORIES.

DEDUCT ALTERNATE #4.

JB

NOTE: ALL DEDUCT ALTS ARE DEPICTED IN THE DRAWINGS, SPECS AND SOW OF THIS PROCUREMENT.

TOTALS: CLINS 0001 THRU 0004

TOTAL PRICE WRITTEN:

A.8 DELIVERY SCHEDULE

ITEM NUMBER
QUANTITY
DELIVERY DATE
1
ARO: 180 Calendar Days After Receipt of Notice to Proceed (NTP).

Page 1 of Page 1 of

INFORMATION REGARDING OFFER/BIDDING MATERIAL, BID GUARANTEE AND BONDS

1. GENDER: Whenever the masculine gender is used in this solicitation and contract documents, it shall be considered to include feminine.

1. AMENDMENTS: Amendments to Solicitation will be posted at https://beta.sam.gov/search?index=opp. Paper copies of the amendments will NOT be individually mailed. Register to the receive email notifications list at https://beta.sam.gov/search?index=opp, and potential bidders will be notified by e-mail of any new amendments that have been issued and posted. No other notification of amendments will be provided. Potential bidders are advised that they are responsible for obtaining and acknowledging any amendments to the solicitation. Failure to acknowledge an amendment may result in your bid being considered non-responsive.

1. PROPOSAL SUBMISSION:

a) All Proposals Shall be submitted electronically. All Interested Offerors must be registered with the Department of Veterans Affairs eCMS Vendor Portal at https://www.vendorportal.ecms.va.gov. Offerors who require registration shall proceed to the Vendor Portal’s Login section and shall click on Request a user account to register. In the event an Offeror is unable to submit a proposal through the vendor portal domain, prior to the proposal closing date, contact the VAAS helpdesk at 1-877-634-3739, or via email at VA.Acquisition.Systems@va.gov. Please DO NOT wait until the last day to upload BID Documents. Offerors are highly encouraged to submit BID packages 2-3 days in advance to avoid system lock outs.

b) If an Offeror is still having difficulties in submitting a quote via the Vendor Portal the Contracting Officer may accept an Offeror’s quote via email under the following circumstances:

1. Offeror must provide evidence that an email discussions or verbal discussion with the VAAS helpdesk could not resolve registration issues.

2. Proposal submitted must meet the time constraints as set forth in the solicitation.

3. Proposals submitted via email without set requirements will not be accepted and will be considered to be nonresponsive. Late or incomplete Quotes will also be considered to be nonresponsive.

a.) Proposal package shall be submitted via the Vendor Portal. Late or incomplete Proposals will also be considered to be nonresponsive. Offers are NOT authorized to submit Proposal packages by US mail; CD versions; Fax; or Email, (Unless portal difficulties have been proven as noted above than email submission may be permitted by the CO prior to the bid opening time).

b.) Document naming convention. S00_Bid $_ (Company Name)_(Solicitation Number)

i. EXAMPLE: S00_Bid $1,000,000.00_ABC Company_36C78620R0000 c.) Proposal package shall be One (1) PDF document combining the following minimum required documents in the following order:

· Company cover letter with Solicitation number, POC name, phone number, email address, and DUNS number.

· Completed front and back blocks 14-20 of the SF 1442 and signed block 20b

· Completed schedule B pricing for each CLIN and grand total.

· Completed S02_Attachment-16 _IFB Contractor Cost Estimate Worksheet.

· Complete and signed SF30 Amendments.

· Scanned digital copy of the Bid Bond. (Ensure to lightly darken all raised seals)

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.2 52.212-2 EVALUATION—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2021)

(a) The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, Price and other factors considered. The following factors shall be used to evaluate offers:

· TECHNICAL EVALUATION CRITERIA

· TECHNICAL QUALIFICATIONS:

· PAST PERFORMANCE

(a) The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation that provides the best benefit to the Government, price and other factors considered. Offers will be evaluated by performing a comparative evaluation in accordance with FAR 13.106-2(b)(3) to determine which response represents the “best” as a whole. Comparative Evaluations is the act of comparing two or more offers or proposal in response to the RFP. Proposals will be evaluated by performing a direct comparison of one offer with another in a uniform manner to determine which provides the government with is needed, as identified in the RFP. The comparison also performed to compare each offeror to one another to determine which provides the best benefit to the government. The government reserves the right to consider a response that offers more than the minimum and select that response if it provides a benefit to the government. The government has the discretion to accept other than the lowest priced offeror that provides additional benefits. The government also has the has the discretion to make an award based on whether the lowest priced of the quotations/offers having the highest past performance rating possible represents the best benefit to the government. The following factors shall be used to evaluate offers:

1. The following Technical Evaluation Criteria should be used for this requirement:

A. Experience: The Contractor shall provide sufficient project details with their technical proposal to demonstrate experience with at least three (3) direct-bury utility projects of similar size, scope, and using similar materials and methods over the past five (5) years. Each contract submitted must have been satisfactorily completed, or if not yet completed, must be marked by satisfactory progress. The Government will not consider a contract that is less than 50% complete or an effort that concluded more than 5 years ago. Contractor shall provide customer points of contact for each project listed.

B. Qualifications of Contractor Supervisor/Superintendent: The Contractor On-Site Supervisor must have not less than five (5) years of experience as a direct supervisor of direct-bury utility projects. Offerors shall submit a resume for the Contractor On-Site Supervisor as part of the technical proposal. All permanent substitutions, whether of prime supervisors or sub-contractors, will be identified and reported to the COR and Contracting Officer, if not prior to, as soon as possible after occurrence.

C. Past Performance Questionnaire (PPQ) forms provided in the solicitation shall be completed and submitted as specified in the Instructions to Offerors. They will be evaluated to assess the degree of confidence the Government has in an Offeror's ability to supply products and services that meet users' needs based on a demonstrated record of recent and relevant work similar to the work described in this solicitation. Recent or relevant work is defined as similar work within the past four (4) years.

(b) A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party. Before the offer's specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.

Technical Qualifications:

At a minimum, offerors shall provide the following information:

1. The Contractor shall describe the methodology to be implemented to accomplish the requirements of the SOW and detail how the proposed approach will effectively achieve the performance objective of window restoration. A statement, such as, “the Contractor will abide by all contract requirements” is not acceptable for determining technical acceptability. The Contractor’s approach shall demonstrate a clear understanding of current industry standards and processes utilized in accomplishing the requirements set forth in the SOW.

2. The Contractor to provide sufficient project details with their technical proposal to demonstrate their abilities in regard to ornamental fencing projects (installation and repair); re-coating of steel ornamental fencing of similar size, scope; using similar materials and methods.

3. Draft schedule showing work tasks from start to completion within the performance period.

Past Performance:

Past performance will be evaluated for quality, schedule (i.e. recent), price control, business relations, management of key personnel and relevance (i.e. experience in providing services similar in size, scope, and complexity as described in the SOW). If no past performance information is readily available (FAR 15.305(a) (2) (iv)), the Offeror’s past performance will be evaluated neither favorably nor unfavorably.

NOTE: The Contractor shall provide sufficient project details with their technical proposal to demonstrate experience with at least three (3) and not more than five (5) Replace Rotor Sprinkler Heads and Install Sprinkler Protectors projects of similar size, scope, and using similar materials and methods over the past five (5) years. Each past performed contract information submitted must have been satisfactorily completed, or if not yet completed, must be marked by satisfactory progress. The Government will not consider a contract that is less than 50% complete or an effort that concluded more than 5 years ago. Contractor shall provide customer points of contact for each project listed. Offerors shall us the solicitation attachment named (Business Management-Past Performance Questionnaire).

A Responsibility Determination will be made in accordance with FAR 9.1 Responsible Prospective Contractors. The Government will research information and data bases to aid in establishing contractor’s responsibility and ability to perform. The databases include, but are not limited to Experian, PPIRS, EPLS, VetBiz and SBA. If the Contracting Officer (CO) is not able to determine responsibility, a request for Certificate of Competency (COC) will be submitted to SBA.

END OF EVALUATION CRITERIA

2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.4 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade
Goals for female participation for each trade
24.9 %
6.9 %

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is

RICHMOND, VA

(End of Provision)

2.5 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

2.6 52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20% percent of the bid price or , whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of Provision)

2.7 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021)

(a) Offerors shall obtain from each person acting as an individual surety on a bid guarantee—

(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203–1; and

(2) Standard Form 28, Affidavit of Individual Surety.

(b) The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228–1, Bid Guarantee, or as otherwise established by the Contracting Officer.

(c) The Contracting Officer may release the security interest on the individual surety’s assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.

(End of Provision)

2.8 52.233-2 SERVICE OF PROTEST (SEP 2006)

Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

Sheryl Palacio-Davis (CO) Contracting Officer

Hand-Carried Address:

National Cemetery Administration Contracting Service Department 18434 Joplin Rd Triangle VA 22172

Mailing Address:

National Cemetery…