36C78620B0006-005.pdf
PDF Posted
- Solicitation number
- 36C78620B0006
About this file
This pre-solicitation notice announces the Department of Veterans Affairs' intent to issue a solicitation for gravesite expansion services at Fort Smith National Cemetery. The project involves expanding burial sites and is valued between $2 million to $5 million. Responses are due on or around May 11, 2020. The solicitation and all amendments will be posted on beta.sam.gov. The acquisition is set aside 100% for verified Service-Disabled Veteran Owned Small Businesses. Firms must be registered in Vendor Information Pages and System for Award Management databases prior to proposal submission. Questions should be directed to the contracting officer.
36C78620B0006 S02_Attachment-2_SPECIFICATIONS_Ft Smith Burial Expansion_847CM3019.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C78620B0006 0001.docx | DOCX document | |
| S06_Amendment 0001_Attachment 2_02 41 10 DEMO SITE CLEARING.pdf | ||
| 36C78620B0006-006.pdf | ||
| 36C78620B0006-011.pdf | ||
| 36C78620B0006-010.pdf | ||
| 36C78620B0006-012.pdf | ||
| 36C78620B0006-008.pdf | ||
| 36C78620B0006-007.pdf | ||
| 36C78620B0006-003.docx | DOCX document | |
| 36C78620B0006-014.xlsx | XLSX spreadsheet | |
| 36C78620B0006-004.pdf | ||
| 36C78620B0006-013.pdf | ||
| 36C78620B0006-009.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NCA SPECIFICATIONS
FT. SMITH NATIONAL CEMETERY
FT. SMITH, SEBASTIAN COUNTY, ARKANSAS
PROJECT NO. 847CM3019
BURIAL EXPANSION
Prepared for:
Prepared by:
COX DESIGN ASSOCIATES
5121 Bee Caves Rd., Ste 203
Austin, TX 78746
03 April 2020
NCA SPECIFICATIONS
FT. SMITH NATIONAL CEMETERY
FT. SMITH, SEBASTIAN COUNTY, ARKANSAS
PROJECT NO. 847CM3019
BURIAL EXPANSION
Prepared for:
Robert H. Cox Chad D. Weinand Douglas R. Klassen
Architect Landscape Architect Civil Engineer
Cox Design Associates GLMV Architecture MKEC
FORT SMITH NATIONAL CEMETERY
PROJECT NO. 847CM3019
03 APRIL 2020
00 01 10-1
TABLE OF CONTENTS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 10 Table of Contents
00 01 15 List of Drawing Sheets 05-10
DIVISION 01 - GENERAL REQUIREMENTS
01 00 02 General Requirements 06-14
01 32 17 Network Analysis Schedules 10-10
01 33 23 Shop Drawings, Product Data, and Samples 06-14
01 42 19 Reference Standards 06-14
01 45 29 Testing Laboratory Services 06-14
01 57 19 Temporary Environmental Controls 06-14
01 74 19 Construction Waste Management 06-14
01 81 13 Sustainable Construction Requirements 08-16
DIVISION 02 – EXISTING CONDITIONS
02 21 00 Site Surveys 06-14
DIVISION 03 – CONCRETE
03 30 53 Short-Form Cast in Place Concrete
03 48 21 Precast Concrete Burial Crypts (Double Depth Lawn Crypt) 06-14
03 48 24 Precast Concrete Columbarium Units 06-14
DIVISION 04 – MASONRY
04 05 13 Masonry Mortaring 06-14
04 20 00 Unit Masonry 06-14
04 43 00 Natural Stone Veneer 10-18
04 72 10 Stone Masonry 06-14
04 73 00 Columbarium Niche Covers
DIVISION 05 – METALS
-NOT USED-
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 11 13 Bituminous Dampproofing
07 60 00 Flashing and Sheet Metal
PROJECT NO. 847CM3019
00 01 10-2
07 92 00 Joint Sealants
DIVISION 08 - OPENINGS
DIVISION 09 – FINISHES
DIVISION 10 – SPECIALTIES
10 14 00 Exterior Signage
10 14 19 Dimensional Letter Signage
DIVISION 11 - EQUIPMENT
DIVISION 12 – FURNISHINGS
DIVISION 13 - SPECIAL CONSTRUCTION
DIVISION 22 – PLUMBING
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING
(HVAC)
DIVISION 25 – INTEGRATED AUTOMATION
DIVISION 26 – ELECTRICAL
DIVISION 27 – COMMUNICATIONS
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
DIVISION 31 – EARTHWORK
PROJECT NO. 847CM3019
00 01 10-3
31 20 00 Earth Moving 11-16
31 23 10 Excavation And Fill
31 23 19 Dewatering 11-16
31 23 30 Trenching, Backfilling And Compacting
31 25 10 Storm Water Discharges
31 50 10 Excavation Support And Protection
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements
32 11 15 Crushed Rock Subgrade
32 12 10 Hot-Mix Asphaltic Pavement
32 13 70 Pavement Joint Sealants
32 31 13 Chain-Link Fences and Gates
32 33 00 Site Furnishings
32 84 00 Planting Irrigation 01-17
32 90 00 Planting 11-16
DIVISION 33 – UTILITIES
33 11 10 Site Water Lines
33 41 00 Storm Utility Drainage Piping
33 46 00 Subdrainage
APPENDIX
Topographic, Utility, Landscape & Soil Survey
BURIAL EXPANSION PROJECT NO. 847CM3019
FORT SMITH NATIONAL CEMETERY 03 APRIL 2020
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
G-001 COVER SHEET
G-002 GENERAL NOTES
V-101 EXISTING CONDITIONS SURVEY
B-101 GEOTECHNICAL BORING LOGS FOR EXPANSION
CD101 DEMOLITION PLAN
C-101 EROSION CONTROL PLAN
C-501 EROSION CONTROL DETAILS
CS101 OVERALL BURIAL PLAN
CS102 PPC BURIAL SECTION 31 SECTION & CONTROL MARKERS
CS103 IGC BURIAL SECTION 29 SECTION & CONTROL MARKERS
CS104 BURIAL SECTION 31 CRYPT NUMBERING
CS105 BURIAL SECTION 29 IGC NUMBERING
CS107 SIGNAGE PLAN & DETAILS
CS501 CONTROL & SECTION MARKER DETAILS
CG101 OVERALL GRADING PLAN
CG102 COLUMBARIUM GRADING
CG301 PAVING TYPICAL SECTIONS
CG502 CRYPT DETAILS
CG503 CRYPT DETAILS
CP101 ROADWAY OVERALL VIEW
CP102 WEST DRIVE PLAN & PROFILE
CP103 SOUTH DRIVE PLAN & PROFILE
CP104 SOUTH 6TH STREET PLAN & PROFILE
CP105 COLUMBARIUM PARKING DIMENSION PLAN
CU101 OVERALL STORM DRAIN PLAN
CU102 SWS LINE 1 & 1A PLAN & PROFILE
CU103 SWS LINE 2 & 3 PLAN & PROFILE
CU104 CRYPT UNDERDRAIN
CU105 COLUMBARIUM UNDERDRAIN
CU501 SWS DETAILS
CU502 SWS DETAILS
AY101 COLUMBARIUM PLAZA PLAN FUTURE AND PROPOSED
BURIAL EXPANSION PROJECT NO. 847CM3019
FORT SMITH NATIONAL CEMETERY 03 APRIL 2020
00 01 15 - 2
AY102 COLUMBARIUM WALL ELEVATIONS AND PLANS
AY301 COLUMBARIUM WALL SECTIONS
AY501 COLUMBARIUM WALL DETAILS
LI101 IRRIGATION PLAN
LI501 IRRIGATION DETAILS
LI502 IRRIGATION DETAILS
LP101 PLANTING PLAN
S000 STRUCTURAL NOTES
S100 COLUMBARIUM FOUNDATION PLAN
S200 COLUMBARIUM FOUNDATION DETAILS
- - - END - - -
BURIAL EXPANSION PROJECT NO. 847CM3019
FORT SMITH NATIONAL CEMETERY 03 APRIL 2020
GENERAL REQUIREMENTS
01 00 02 - 1
SECTION 01 00 02
1.1 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor, materials, equipment and services and perform and complete all work for Burial Expansion – Fort Smith National Cemetery as required by drawings and specifications.
B. An organized site visit is planned. Details in the solicitation package.
C. Offices of COX DESIGN ASSOCIATES (A/E), may render certain technical services during construction.
Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Resident
Engineer/Contracting Officers Representative (RE/COR) or his duly authorized representative.
D. All Testing Laboratory services will be retained and paid for by the Contractor (see Spec Section 01 45
29, Testing Laboratory Services). However, the Department of Veterans Affairs may elect to retain its own
Testing Laboratory for any purpose. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the RE/COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the RE/COR.
E. All employees of general contractor and subcontractors shall comply with security requirements as established by the RE/COR, be identified by name and employer. They shall be restricted from unauthorized access.
F. Prior to commencing work, general contractor shall provide proof that a OSHA certified “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.
01 00 02 - 2
G. Training:
1. The general contractor’s job superintendents shall all have successfully completed the 30-hour OSHA certified Construction Safety course.
2. All employees of general contractor or subcontractors shall, at the minimum, have successfully completed the 10-hour OSHA certified Construction Safety course and/or other relevant competency training, as determined by VA CP.
3. Submit OSHA training records of all employees for approval before the start of work.
1.2 STATEMENT OF BID ITEM(S)
A. CLIN 0001: GENERAL CONSTRUCTION: Provide all labor, materials, tools, equipment and services to construct 2,040 pre-placed crypts and 1,515 in-ground cremains, and 1,280 niches for a total of 4,835 burial sites in this phase of work at the Fort Smith National Cemetery, including all work shown on the plans and described in the specifications. Work includes but is not limited to: demolition, site preparation and erosion control, excavation, backfilling and grading, construction of berms, planting of native grass seed mix for all disturbed areas, installation of crypts, construction of columbarium, storm drainage, utilities, roads, curbs, pedestrian paving, landscape planting, fabrication and installation of site amenities, irrigation system, and certain other items and specific tasks as further defined by the drawings and specifications. The overall performance period for this project is 360 calendar days from issuance of the notice-to proceed (NTP).
B. CLIN 0002: PRE-PLACE CRYPTS: Procure and Deliver 2,040 pre-placed crypts for Installation.
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Additional sets of drawings may be made by the Contractor, at Contractor's expense, from digital files furnished during the solicitation.
1,4 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub- contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the site without following the procedures approved by the RE/COR. They may also be subject to inspection of their personal effects when entering or leaving the project site.
01 00 02 - 3
2. For working outside the “regular hours” as defined in the contract, The General Contractor shall give minimum 3 days’ notice in writing to the RE/COR so that appropriate arrangements can be provided for the Cemetery employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the RE/COR.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the RE/COR.
C. Guards:
1. The General Contractor shall provide unarmed guards at the project site after construction hours when theft or vandalism warrants.
D. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the RE/COR for the purpose of security inspections of every area of project including tool boxes and parked machines, and to take any necessary emergency action.
E. Document Control:
1. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
1.5 FIRE SAFETY
A. Applicable Publications: Publications listed below form part of this Article to the extent referenced.
Publications are referenced in text by basic designations only.
1. American Society for Testing and Materials (ASTM):
E84-2009a Surface Burning Characteristics of Building Materials
2. National Fire Protection Association (NFPA):
10-2010 Standard for Portable Fire Extinguishers
30-2008 Flammable and Combustible Liquids Code
51B-2009 Standard for Fire Prevention During Welding, Cutting and Other Hot Work
70-2008 National Electrical Code
241-2009 Standard for Safeguarding Construction, Alteration, and Demolition Operations
3. Occupational Safety and Health Administration (OSHA):
29 CFR 1926 Safety and Health Regulations for Construction
01 00 02 - 4
B. Fire Safety Plan: Establish and maintain a fire protection program in accordance with 29 CFR 1926. Prior to start of work, prepare a plan detailing project-specific fire safety measures, including periodic status reports, and submit to RE/COR/Cemetery Director for review for compliance with contract requirements in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES. Prior to any worker for the contractor or subcontractor’s beginning work, they shall undergo a safety briefing provided by the General Contractor’s competent person per OSHA requirements. This briefing shall include information on the construction limits, safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of NCA equipment, etc. Documentation shall be provided to the RE/COR that individuals have undergone the Contractor’s safety briefing.
C. Site and Building Access: Maintain free and unobstructed access to emergency services and for fire, police and other emergency response forces in accordance with NFPA 241.
D. Separate temporary facilities, such as trailers, storage sheds, and dumpsters, from existing buildings and new construction by distances in accordance with NFPA 241. For small facilities with less than 6 m (20 feet) exposing overall length, separate by 3m (10 feet).
E. Hot Work: Perform and safeguard hot work operations in accordance with NFPA 241 and NFPA 51B.
Coordinate with RE/COR. Designate Contractor's responsible project-site fire prevention program manager to permit hot work. Coordinate with RE/COR.
F. Fire Hazard Prevention and Safety Inspections: Inspect entire construction areas weekly. Coordinate with, and report findings and corrective actions weekly to RE/COR.
G. Smoking: Smoking is prohibited in the cemetery except in designated smoking areas.
H. Dispose of waste and debris in accordance with NFPA 241. Remove from site weekly.
I. Perform other construction, alteration and demolition operations in accordance with 29 CFR 1926.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the RE/COR. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage trailers, office trailers) and utilities may be erected by the Contractor only with the approval of the RE/COR and shall be built with labor and materials furnished by the
Contractor without expense to the Government. The temporary buildings and utilities shall remain the
01 00 02 - 5 property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work.
C. The Contractor shall, under regulations prescribed by the RE/COR, use temporary roadways constructed by the Contractor when and as authorized by the RE/COR. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as shown on the drawings approved by the RE/COR with agreement of the Cemetery. Contractor parking will be only in areas and on roadways designated and agreed to by the RE/COR in agreement of the Cemetery.
E. Workmen are subject to rules of the Cemetery applicable to their conduct.
F. Execute work so as to interfere as little as possible with normal functioning of Cemetery as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.
1. Do not store materials and equipment in other than assigned areas.
2. Provide unobstructed access to the Cemetery areas required to remain in operation.
a. Whenever it is required that a connection fee be paid to a public utility provider for the construction project, for such items as water, sewer, electricity, payment of such fee shall be the responsibility of the Contractor.
G. Sequencing: To ensure such executions, the Contractor shall furnish the RE/COR with a schedule of approximate Sequencing dates on which the Contractor intends to accomplish work in each specific area of site. The sequencing dates are to be coordinated with the detailed construction sequencing plan submitted by the contractor. The sequencing plans are to show chain link fence alignments/ limits for each sequence and show temporary signage directing to public areas, public access and construction trailer parking area.
In addition, the Contractor shall notify the RE/COR two weeks in advance of the proposed date of starting work in each specific area of site. Arrange such phasing dates to insure accomplishment of this work in successive sequences mutually agreeable to the Cemetery Director, RE/COR and Contractor.
H. The Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Cemetery’s operations will not be hindered. The Contractor shall permit access to Cemetery personnel through other construction areas which serve as routes of access to such
01 00 02 - 6 affected areas and equipment. Coordinate alteration work in areas occupied by Cemetery Staff so that
Cemetery operations will continue during the construction period. The contractor shall also maintain to allow parking and pedestrian access to all existing public areas to the public during construction.
I. Construction Fence: Before construction operations begin, the Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks.
Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. The temporary fencing shall encompass the construction work area(s) to serve as a pedestrian barrier to alert cemetery patrons of the construction site. Remove the fence when directed by RE/COR.
The Fence locations are to be coordinated with the Cemetery Director prior to installation and covered chain link fence with 90% blockage green privacy/ wind screen.
J. Utilities Services: Maintain existing utility services for the Cemetery at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by RE/COR. All such actions shall be coordinated with the Utility Company involved.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of RE/COR. Electrical work shall be accomplished with all affected circuits or equipment de- energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without the RE/COR, and Cemetery Director’s prior knowledge and written approval. Refer to specification
Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATION for additional requirements.
2. The Contractor shall submit a request to interrupt any such services to both RE/COR and the
Cemetery Director in writing, 48 hours in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. The Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of the Cemetery. Interruption time approved by the Cemetery and RE/COR may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the RE/COR.
5. In case of a contract construction emergency, service will be interrupted on approval of RE/COR.
Such approval will be confirmed in writing as soon as practical.
01 00 02 - 7
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
K. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers and supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged.
L. To minimize interference of construction activities with flow of Cemetery traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times.
M. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the RE/COR. Coordinate the work for this contract with other construction operations as directed by RE/COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
N. Coordination of Construction with Cemetery Director: The burial activities at a National Cemetery shall take precedence over construction activities. The Contractor must cooperate and coordinate with the
Cemetery Director, through the RE/COR, in arranging construction schedule to cause the least possible interference with Cemetery activities in burial areas. Construction noise during the committal services shall not disturb the service. Trucks and workmen shall not pass through the service area during this period.
1. The Contractor is required to discontinue his work sufficiently in advance of Easter, Mother's Day, Father's Day, Memorial Day, Veteran's Day and/or Federal holidays, to permit him to clean up all areas of operation adjacent to existing burial plots before these dates.
2. Cleaning up shall include the removal of all equipment, tools, materials and debris and leaving the areas in a clean, neat condition.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the RE/COR of areas in which alterations occur, areas which are anticipated routes of access, and furnish a signed report, to the Contracting Officer. This report shall list:
1. Shall note any discrepancies between drawings and existing conditions at site.
2. Shall designate areas for working space, materials storage and routes of access to areas where alterations occur and which have been agreed upon by Contractor and RE/COR.
01 00 02 - 8
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of RE/COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by the Contractor with new items in accordance with specifications which will be furnished by the Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled
"DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR 852.236-
88).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and RE/COR together shall make a thorough re-survey of the areas involved. They shall furnish a report on conditions then existing and other surfaces as compared with conditions of same as noted in first condition survey report.
1. Re-survey report shall also list any damage caused by the Contractor to such surfaces, despite protection measures; and, will form the basis for determining extent of repair work required of the
Contractor to restore damage caused by the Contractor's workmen in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
1.8 ENVIRONMENTAL CONTROLS
A. Final Cleanup:
1. Upon completion of the project, or as work progresses, remove all construction debris.
1.9 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the
Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by
RE/COR.
2. tems not reserved shall become property of the Contractor and be removed by Contractor from the
Cemetery.
3. Items of portable equipment and furnishings located in spaces in which work is to be done under this contract shall remain the property of the Government. When spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and
01 00 02 - 9 specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.10 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the RE/COR.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the RE/COR may have the necessary work performed and charge the cost to the Contractor.
(FAR 52.236-9)
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A
National Pollutant Discharge Elimination System (NPDES) permit is required for this project. The
Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. The contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the Contractor's method of operations and operations planning and the Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:
1. Designating areas for equipment maintenance and repair;
2. Providing waste receptacles at convenient locations and provide regular collection of wastes;
3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;
01 00 02 - 10
4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and
5. Providing adequately maintained sanitary facilities.
1.11 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, gas, water, irrigation or electric work without approval of the RE/COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the RE/COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, electrical work, landscape stone, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At the Contractor's own expense, the Contractor shall immediately restore to service and repair any damage caused by the Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services fire protection systems communications systems (including telephone) irrigation system control and power which are indicated on drawings and which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled
"CHANGES" (FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS"
(FAR 52.236-2).
1.12 PHYSICAL DATA
A. Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the
Contractor.
1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by Cox Design Associates geotechnical consultant:
Terracon
9522 East 47TH Place, Unit D
Tulsa, OK 74145
Telephone No. 918 877 5913
01 00 02 - 11
(FAR 52.236-4)
B. Subsurface conditions have been developed by core borings and test pits. Logs of subsurface exploration conducted by Terracon are shown diagrammatically on drawings.
C. A copy of the geotechnical investigation is an Appendix to these specifications and shall be considered part of the contract documents.
D. The Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine the site of work and logs of borings and, after investigation, decide for themselves the character of materials and make their bids accordingly. Upon proper application to the Department of
Veterans Affairs, including approved scheduling bidders will be permitted to make subsurface explorations of their own at site.
1.13 PROFESSIONAL SURVEYING SERVICES
A. A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections. The
Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the
Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
1.14 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks indicated on the drawings and shall be responsible for all measurements in connection with the layout. The
Contractor shall furnish, at the Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the RE/COR. The
Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the RE/COR until authorized to remove them. If such marks are destroyed by the
Contractor or through Contractor's negligence before their removal is authorized, the RE/COR may replace them and deduct the expense of the replacement from any amounts due or to become due to the
Contractor.
(FAR 52.236-17)
B. Establish and plainly mark center lines for each gravesite control monument, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations
01 00 02 - 12 established for each such structure and/or addition, roads, gravesite control monuments, are in accordance with lines and elevations shown on contract drawings.
C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. The Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:
D. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the RE/COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.
E. During progress of work, the Contractor shall have lines, grades, locations and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings. Furnish such certification to the RE/COR before any major items of concrete work are placed. In addition, furnish to the RE/COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.
1. Lines of each addition.
2. Elevations of bottoms of footings.
3. Lines and elevations of sewers and of all outside distribution systems.
4. Lines of grave plot documentation.
5. Lines of elevations of all swales and interment areas.
6. Lines and elevations of roads, streets.
7. Lines and elevations and location of top of pre-placed crypts within their respective plots.
8. Lines and elevations of grade over pre-placed crypts.
9. Northing/Easting coordinate locations and elevation depth below finished grade of all water, sanitary, storm, gas and irrigation structures, directional fittings, control wire and lines.
10. Northing/Easting coordinate locations and elevation for each gravesite grid monument.
F. Upon completion of the work, the Contractor shall furnish the RE/COR with reproducible drawings, in
AutoCAD form, at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.
01 00 02 - 13
G. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of Article "Professional Surveying Services".
1.15 AS-BUILT DRAWINGS
A. The Contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, which will include all contract changes, modifications and clarifications.
1. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the RE/COR's review, as often as requested.
B. At substantial completion, the Contractor shall secure the services of a professional land surveyor, as defined in Section 1.10, to perform a site survey within the project limits in accordance with the NCA Site, Topographic, Utility, Landscape & Soil Survey scope of services, as listed in the appendix of this specification. Elements to be surveyed include, but are not limited to:
1. Location, alignment, and dimension of roads, curbs, walks, parking, and paved areas. Indicate road centerlines with true bearings and lengths by 15 m (50') stationing. Describe curves by designating the points of curvature and tangency by station. Include all curve data as well as location of radius and vertex points. Designate roads with curbs by double lines. Show equalities for intersecting roads by station.
2. Crown, grade, and climb of curb at road crossings contours.
3. Elevations on 50' centers on centerline of roads, edges of roads, and top and bottom of curbs.
4. Type of pavement of roads.
5. Surface elevations on a 50' grid pattern, except where terrain features require greater detail. At abrupt changes in grade, show elevations at the tops and bottoms of slopes to the nearest
0.1'.
6. Site features of every character identified and located with exact measurements. Include fences, walls, areaways, steps, ramps, railings, gratings, flumes, pads, sprinkler heads, telephone poles, signage, and site furnishings.
7. All underground, overhead, and surface electrical utilities and structures. Show size, depth, and top elevation of all electrical structures, based on actual site investigation.
8. All underground and surface civil and mechanical utilities and structures. Show size depth, invert and top elevation of all utility structures, such as manholes, catch basins and headwalls, based on actual site investigation. Indicate direction of flow and size of pipe for all sewers drains and connecting lines between manholes.
9. Grid monuments.
C. The Contractor shall deliver two approved completed sets of as-built drawings to the RE/COR within 15 calendar days after acceptance of the project by the RE/COR.
01 00 02 - 14
D. Section 1.15 shall also apply to all shop drawings.
1.16 USE OF ROADWAYS
A. For hauling, use only Contractor constructed temporary roads as indicated on the drawings which are necessary in the performance of contract work. Temporary roads shall be constructed or modified by the
Contractor at the Contractor's expense following approved plans that include construction, operation, maintenance and restoration. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
B. When new permanent roads are to be a part of this contract, the Contractor may construct them immediately to facilitate the Cemetery operations. These roads may be used by all who have business thereon within zone of the Cemetery operations.
1.17 RE/COR'S FIELD OFFICE
A. The Contractor shall, within fifteen (15) days after receipt of Notice to Proceed, provide within the contractor’s field office a temporary field office and furniture for use of the RE/COR. Office and furniture shall be like new.
B. The field office shall provide not less than 50 square feet of floor area. Installation of the office shall meet all local codes.
C. The Contractor shall, for the duration of the RE/COR's occupancy, provide the following:
1. Satisfactory conditions in and around the field office and parking area.
2. Maintenance of gravel surfaced area, including the area for parking, in an acceptable condition for vehicle and foot traffic at all times.
3. Maintenance of utility services.
4. Potable water, fuel and electric power for normal office uses, including lights, heating and air conditioning.
1.18 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water connections, or when approved by RE/COR provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
1.19 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for
01 00 02 - 15 chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner satisfactory to the RE/COR, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.
C. The Contractor shall install meters at the Contractor's expense and furnish the Cemetery a monthly record of the Contractor's usage of electricity as hereinafter specified.
D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials.
E. Electricity (for Construction and Testing): Furnish all temporary electric services.
F. Obtain electricity by connecting to the Cemetery electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Where not available or not convenient to connect to the Cemetery distribution system, the contractor shall supply power via portable generators at own expense. Generators shall be acoustically screened so as not to disturb committal services and/or visitation to the adjacent columbarium and gravesites.
G. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Cemetery irrigation distribution system. Backflow preventer may not be required at connections to the irrigation system. Water is available at no cost to the Contractor.
2. If potable water is required and convenient connection is available the contractor may connect to the
Cemetery potable water distribution system. The contractor shall install reduced pressure backflow preventer at each connection at own expense.
3. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at RE/COR's discretion) of use of water from the Cemetery's system.
4. Where not available or not convenient to connect to the Cemetery distribution system, the Contractor shall supply water via portable/temporary means at his own expense.
1.20 TESTS
A. Pre-test electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.
01 00 02 - 16
B. Conduct final tests required in various sections of specifications in presence of an authorized representative of the RE/COTR. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
C. Electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire complex which must be coordinated to work together during normal operation to produce results for which the system is designed.
D. All related components as defined above shall be functioning when any system component is tested.
Tests shall be completed within a reasonably short period of time during which operating and environmental conditions remain reasonably constant.
E. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.
1.21 INSTRUCTIONS
A. The Contractor shall furnish Maintenance and Operating manuals and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
B. Manuals: Maintenance and operating manuals (four copies each) for each separate piece of equipment shall be delivered to the RE/COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components.
Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item.
Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
C. Instructions: the Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed instructions to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system; shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed. This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the RE/COR and
01 00 02 - 17 shall be considered concluded only when the RE/COR is satisfied in regard to complete and thorough coverage. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the RE/COR, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.
1.22 GOVERNMENT-FURNISHED PROPERTY
A. The Government shall deliver to the Contractor, the Government-furnished property shown on drawings.
B. Materials furnished by the Government to be installed by the Contractor will be furnished to the
Contractor at the Cemetery.
C. Storage space for materials will be provided by the Contractor and the Contractor shall be prepared to unload and store such equipment therein upon its receipt at the Cemetery.
D. Notify RE/COR in writing, 60 days in advance, of date on which Contractor will be prepared to receive materials furnished by Government. Arrangements will then be made by the Government for delivery of materials.
1. Immediately upon delivery of materials, the Contractor shall arrange for a joint inspection thereof with a representative of the Government. At such time the Contractor shall acknowledge receipt of materials described, make notations, and immediately furnish the Government representative with a written statement as to its condition or shortages.
2. The Contractor thereafter is responsible for such material until such time as acceptance of contract work is made by the Government.
1.23 CONSTRUCTION SIGN
A. Provide a Construction Sign where directed by the RE/COR. All wood members shall be of framing lumber. Cover sign frame with 0.7 mm (24 gage) galvanized sheet steel nailed securely around edges and on all bearings. Sign face shall be 4 feet x 5 feet and 6 inches. Provide two 100 by 100 mm (4 inch by
4 inch) posts (or equivalent round posts) set 900 mm (three feet) into ground. Set bottom of sign level at
900 mm (three feet) above ground and secure to posts with through bolts. Make posts full height of sign.
Brace posts with 50mm x 100 mm (two by four inch) material as directed.
B. Paint all surfaces of sign and posts two coats of white semi-gloss paint. Border and letters shall be of black gloss paint, except project title which shall be blue gloss paint.
C. Maintain sign and remove it when directed by the RE/COR.
D. Detail Drawing of construction sign showing required legend and other characteristics of sign is included in the drawings.
1.24 SAFETY SIGN
01 00 02 - 18
A. Provide a Safety Sign where directed by RE/COR. Signboard shall be three feet x four feet, 19 mm (3/4-inch) thick exterior grade plywood. Provide two 100 mm by 100 mm (four by four inch) posts extending full height of sign and 900 mm (three feet) into ground. Set bottom of sign level at 1200 mm (four feet) above ground.
B. Paint all surfaces of Safety Sign and posts with one prime coat and two coats of white gloss paint. Letters and design shall be painted with gloss paint of colors noted.
C. Maintain sign and remove it when directed by RE/COR.
D. Detail Drawing of safety sign showing required legend and other characteristics of sign is included in the drawings.
E. Post the number of accident free days on a daily basis.
1.25 CONSTRUCTION DIGITAL IMAGES
A. During construction period through…