About this file

This document includes a statement of work and federal contract opportunity notice for expansion projects at the Fort Smith National Cemetery. The statement of work involves construction of 2,040 pre-placed crypts, 1,515 in-ground cremains, 1,280 niches, and other site work for a total of 4,835 new burial sites. The project performance period is 360 calendar days from notice to proceed. The contract opportunity is a 100% set-aside for service-disabled veteran-owned small businesses and seeks bids for the construction and delivery of the crypts. The solicitation number is 36C78620B0006 and bids must be submitted electronically. The estimated value is between $2-5 million. Offerors must register in SAM, Vendor Information Pages, and acknowledge any amendments which will be posted online rather than mailed. The contracting officer is Jerry L. Hodson Jr.

36C78620B0006 S02_Attachment-1_SOW_Ft Smith Burial Expansion_847CM3019.pdf

View the file

Other files

File Type Posted
36C78620B0006 0001.docx DOCX document
S06_Amendment 0001_Attachment 2_02 41 10 DEMO SITE CLEARING.pdf PDF
36C78620B0006-006.pdf PDF
36C78620B0006-011.pdf PDF
36C78620B0006-010.pdf PDF
36C78620B0006-005.pdf PDF
36C78620B0006-012.pdf PDF
36C78620B0006-008.pdf PDF
36C78620B0006-007.pdf PDF
36C78620B0006-003.docx DOCX document
36C78620B0006-014.xlsx XLSX spreadsheet
36C78620B0006-013.pdf PDF
36C78620B0006-009.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

BURIAL EXPANSION PROJECT NO. 847CM3019

Fort Smith National Cemetery, 522 Garland Ave and S. 6th Street, Fort Smith, AR 72901

A. CLIN 0001: GENERAL CONSTRUCTION: Provide all labor, materials, tools, equipment and services to construct 2,040 pre-placed crypts and 1,515 in-ground cremains, and 1,280 niches for a total of 4,835 burial sites in this phase of work at the Fort Smith National Cemetery, including all work shown on the plans and described in the specifications. Work includes but is not limited to: demolition, site preparation and erosion control, excavation, backfilling and grading, construction of berms, planting of native grass seed mix for all disturbed areas, installation of crypts, construction of columbarium, storm drainage, utilities, roads, curbs, pedestrian paving, landscape planting, fabrication and installation of site amenities, irrigation system, and certain other items and specific tasks as further defined by the drawings and specifications. The overall performance period for this project is 360 calendar days from issuance of the notice-to proceed

(NTP).

B. CLIN 0002: PRE-PLACE CRYPTS: Procure and Deliver 2,040 pre-placed crypts for Installation.