36C78620B0002-002.pdf

PDF Posted

Attached to
Fort Gibson National Cemetery Gravesite Expansion, Project Number 844CM3023
Solicitation number
36C78620B0002
Issued by

About this file

This pre-solicitation notice describes an upcoming solicitation for construction services at Fort Gibson National Cemetery. The Department of Veterans Affairs, National Cemetery Administration intends to issue a solicitation for the Fort Gibson National Cemetery Gravesite Expansion Project 844CM3023. The acquisition will be through an invitation for bid. The construction magnitude is between $2 million to $5 million under NAICS code 237990. The procurement is set aside 100% for service-disabled veteran owned small businesses. Firms must be registered in the System for Award Management and Vendor Information Pages databases and have veteran ownership verification to be considered. The response due date will be posted on Contract Opportunities at beta.sam.gov along with the full solicitation, specifications and drawings. Amendments will also be posted there rather than mailed. Interested parties should monitor the website for additional details and deadlines.

36C78620B0002 S02_Attachment-1_Specs_844CM3023.pdf

View the file

Other files

File Type Posted
36C78620B0002-0004001.pdf PDF
36C78620B0002-0004000.docx DOCX document
36C78620B0002-0003013.pdf PDF
36C78620B0002-0003012.docx DOCX document
36C78620B0002-0002000.docx DOCX document
36C78620B0002-0002002.pdf PDF
36C78620B0002-0002001.pdf PDF
36C78620B0002-0001000.docx DOCX document
36C78620B0002-008.pdf PDF
36C78620B0002-010.pdf PDF
36C78620B0002-003.pdf PDF
36C78620B0002-006.pdf PDF
36C78620B0002-001.docx DOCX document
36C78620B0002-007.pdf PDF
36C78620B0002-009.xlsx XLSX spreadsheet
36C78620B0002-004.pdf PDF
36C78620B0002-005.pdf PDF
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NCA SPECIFICATIONS

FT. GIBSON NATIONAL CEMETERY

FT. GIBSON, MUSKOGEE COUNTY, OKLAHOMA

PROJECT NO. 844CM3023

BURIAL EXPANSION AND ROAD IMPROVEMENTS

Prepared for:

Prepared by:

COX DESIGN ASSOCIATES

5121 Bee Caves Rd., Ste 203

Austin, TX 78746

29 October 2019

NCA SPECIFICATIONS

FT. GIBSON NATIONAL CEMETERY

FT. GIBSON, MUSKOGEE COUNTY, OKLAHOMA

PROJECT NO. 844CM3023

BURIAL EXPANSION AND ROAD IMPROVEMENTS

Prepared for:

Robert H. Cox Chad D. Weinand Douglas R. Klassen

Architect Landscape Architect Civil Engineer

Cox Design Associates GLMV Architecture MKEC

BURIAL EXPANSION AND ROAD IMPROVEMENTS 10-29-19

FORT GIBSON NATIONAL CEMETERY

00 01 10-1

TABLE OF CONTENTS

Section 00 01 10

DIVISION 00 - SPECIAL SECTIONS DATE

00 01 10 Table of Contents

00 01 15 List of Drawing Sheets 05-10

DIVISION 01 - GENERAL REQUIREMENTS

01 00 02 General Requirements 06-14

01 32 17 Network Analysis Schedules 10-10

01 33 23 Shop Drawings, Product Data, and Samples 06-14

01 35 26 Safety Requirements

01 42 19 Reference Standards 06-14

01 45 29 Testing Laboratory Services 06-14

01 57 19 Temporary Environmental Controls 06-14

01 74 19 Construction Waste Management 06-14

01 81 13 Sustainable Construction Requirements 08-16

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition

DIVISION 03 – CONCRETE

03 10 10 Concrete Forms and Accessories

03 20 10 Concrete Reinforcement

03 30 50 Miscellaneous Cast-In Place Concrete

03 48 21 Precast Concrete Burial Crypts (Double Depth Lawn

Crypt)

06-14

DIVISION 04 – MASONRY

-NOT USED-

DIVISION 05 – METALS

DIVISION 06 – WOOD,PLASTICS AND COMPOSITES

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

DIVISION 08 - OPENINGS

00 01 10-2

DIVISION 09 – FINISHES

DIVISION 10 – SPECIALTIES

10 14 00 Exterior Signage

DIVISION 11 - EQUIPMENT

DIVISION 12 – FURNISHINGS

DIVISION 13 - SPECIAL CONSTRUCTION

DIVISION 22 – PLUMBING

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

DIVISION 25 – INTEGRATED AUTOMATION

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 07-17

26 05 19 Low-Voltage Electrical Power Conductors and Cables 07-17

26 05 26 Grounding and Bonding for Electrical Systems 07-17

26 05 33 Raceway and Boxes for Electrical Systems 07-17

26 05 41 Underground Electrical Construction 07-17

26 27 26 Wiring Devices 07-17

DIVISION 27 – COMMUNICATIONS

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

DIVISION 31 – EARTHWORK

00 01 10-3

31 10 10 Site Clearing

31 20 00 Earth Moving 11-16

31 23 10 Excavation And Fill

31 23 19 Dewatering 11-16

31 23 30 Trenching, Backfilling And Compacting

31 25 10 Storm Water Discharges

31 50 10 Excavation Support And Protection

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 11 15 Crushed Rock Subgrade

32 12 10 Hot-Mix Asphaltic Pavement

32 13 70 Pavement Joint Sealants

32 14 16 Brick Unit Paving 11-16

32 17 10 Pavement Marking

32 33 00 Site Furnishings

32 84 00 Planting Irrigation 01-17

32 90 00 Planting 11-16

DIVISION 33 – UTILITIES

33 11 10 Site Water Lines

33 41 00 Storm Utility Drainage Piping

33 46 00 Subdrainage

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

G-001 COVER SHEET

G-002 GENERAL NOTES

G-003 PAVEMENT IMPROVEMENTS GENERAL NOTES

G-004 CONSTRUCTION SEQUENCING MAP

V-101 SURVEY FOR EXPANSION

V-102 SURVEY FOR ROAD IMPROVEMENTS

B-101 GEOTECHNICAL BORING LOGS FOR EXPANSION

B-102 GEOTECHNICAL BORING LOGS FOR ROAD IMPROVEMENTS

B-103 GEOTECHNICAL BORING LOGS FOR ROAD IMPROVEMENTS

CD101 EXISTING CONDITIONS & DEMOLITION PLAN

CS101 OVERALL BURIAL PLAN

CS102 PPC BURIAL SECTION 26 & 27 – SECTION & CONTROL

MARKERS

CS103 IGC BURIAL SECTION 29 – SECTION & CONTROL

MARKERS

CS104 BURIAL SECTION 26 CRYPT NUMBERING

CS105 BURIAL SECTION 27 CRYPT NUMBERING

CS106 BURIAL SECTION 29 IGC NUMBERING

CS107 SIGNAGE PLAN & DETAILS

CS501 MISC. DETAILS

CG101 OVERALL GRADING MAP

CG102 DETAILED GRADING

CG103 DETAILED GRADING

CG104 EROSION CONTROL PLAN

CG301 PAVING TYPICAL SECTIONS

CG501 EROSION CONTROL DETAILS

CG502 EROSION CONTROL DETAILS

CG503 CRYPT DETAILS

CG504 CRYPT DETAILS

CP101 ROADWAY OVERALL VIEW

CP102 ROAD 1 PLAN & PROFILE

CP103 ROAD 1 PLAN & PROFILE

00 01 15 - 2

CU101 OVERALL STORM DRAIN PLAN

CU102 BURIAL EXPANSION SWS LINES 1 PLAN & PROFILE

CU103 BURIAL EXPANSION SWS LINES 2 & 3 PLAN & PROFILE

CU104 BURIAL SECTION CRYPT UNDERDRAIN

CU501 RCB LINE 1 DETAILS

CU502 RCB LINE 2 DETAILS

CI101 OVERALL PAVING PLAN

CI102 ENTRANCE DRIVE DETAILED

CI103 INTERSECTION PAVING & GRADING

CI104 CURB EXTENSIONS

CI105 PARKING LOT EXPANSION

CI106 MAINTENANCE PARKING

CI107 PAVEMENT IMPROVEMENTS SWS LINES 1 & 2 PLAN AND

PROFILE

CI108 PAVEMENT IMPROVEMENTS SWS LINE 3 PLAN AND

PROFILE

CI109 SOUTH EDGE DRAINS

CI110 CHANNEL 1 PLAN & PROFILE

CI111 CHANNEL 1 (CONT) PLAN & PROFILE

CI112 CHANNEL 2 PLAN & PROFILE

CI113 CHANNEL 2 (CONT) PLAN & PROFILE

CI501 PAVING DETAILS

CI502 PAVING DETAILS

CI503 STORMWATER DETAILS

LP101 PLANTING PLAN

LI101 IRRIGATION PLAN

LI501 IRRIGATION DETAILS

LI502 IRRIGATION DETAILS

- - - END - - -

GENERAL REQUIREMENTS

01 00 02 - 1

1.1 GENERAL INTENTION

SECTION 01 00 02

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor, materials, equipment and services and perform and complete all work for Gravesite Expansion and Roadway Pavement Restoration – Fort

Gibson National Cemetery as required by drawings and specifications.

B. Visits to the site by Bidders may be made only by appointment with the Cemetery Director.

C. The Cox Design Associates Project Team, Architect-Engineers (A/E), may render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officers Representative (COR) or his duly authorized representative.

D. All Testing Laboratory services will be retained and paid for by the

Contractor (see Spec Section 01 45 29, Testing Laboratory Services).

However, the Department of Veterans Affairs may elect to retain its own

Testing Laboratory for any purpose. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.

E. All employees of general contractor and subcontractors shall comply with security requirements as established by the COR, be identified by name and employer. They shall be restricted from unauthorized access.

F. Prior to commencing work, general contractor shall provide proof that a

OSHA certified “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.

01 00 02 - 2

G. Training:

1. The general contractor’s job superintendents shall all have successfully completed the 30-hour OSHA certified Construction

Safety course.

2. All employees of general contractor or subcontractors shall, at the minimum, have successfully completed the 10-hour OSHA certified

Construction Safety course and/or other relevant competency training, as determined by VA CP.

3. Submit OSHA training records of all employees for approval before the start of work.

1.2 STATEMENT OF BID ITEM(S)

A. CLIN 01: GENERAL CONSTRUCTION:

1. Provide all labor, materials, tools, equipment, and services to install 3,000 pre-placed crypts, 3,035 in-ground cremains sites, construct roadway renovations, and site drainage renovations in this phase of work at the Fort Gibson National Cemetery. Include all work shown on the plans and described in the specifications. Work includes but is not limited to: demolition, site preparation and erosion control, excavation, backfilling and grading, construction of berms, planting of native grass seed mix for all disturbed areas, installation of crypts, storm drainage, utilities, roads, curbs, pedestrian paving, landscape planting, fabrication and installation of site amenities, irrigation system, and certain other items and specific tasks as further defined by the drawings and specifications.

B. CLIN 02: PRE-PLACED CRYPTS: Work includes furnishing and delivery of

3,000 pre-placed crypts.

1.3 SPECIFICANTIONS AND DRAWINGS FOR CONTRACTOR

A. AFTER AWARD OF CONTRACT, one set of electronic specifications and drawings will be furnished.

B. Additional sets of drawings may be made by the Contractor, at

Contractor's expense, from digital files furnished by the Issuing

Office.

1.3 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

01 00 02 - 3

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the site without following the procedures approved by the COR. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. For working outside the “regular hours” as defined in the contract, The General Contractor shall give minimum 3 days’ notice in writing to the COR so that appropriate arrangements can be provided for the Cemetery employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the COR.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the COR.

C. Guards:

1. The General Contractor shall provide unarmed guards at the project site after construction hours when theft or vandalism warrants.

D. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the COR for the purpose of security inspections of every area of project including tool boxes and parked machines, and to take any necessary emergency action.

E. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of

“sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.

01 00 02 - 5 status reports, and submit to COR/Cemetery Director for review for compliance with contract requirements in accordance with Section 01 33

23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES. Prior to any worker for the contractor or subcontractor’s beginning work, they shall undergo a safety briefing provided by the General Contractor’s competent person per OSHA requirements. This briefing shall include information on the construction limits, safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of NCA equipment, etc.

Documentation shall be provided to the COR that individuals have undergone the Contractor’s safety briefing.

C. Site and Building Access: Maintain free and unobstructed access to emergency services and for fire, police and other emergency response forces in accordance with NFPA 241.

D. Separate temporary facilities, such as trailers, storage sheds, and dumpsters, from existing buildings and new construction by distances in accordance with NFPA 241. For small facilities with less than 6 m (20 feet) exposing overall length, separate by 3m (10 feet).

E. Hot Work: Perform and safeguard hot work operations in accordance with

NFPA 241 and NFPA 51B. Coordinate with COR. Designate Contractor's responsible project-site fire prevention program manager to permit hot work. Coordinate with COR.

F. Fire Hazard Prevention and Safety Inspections: Inspect entire construction areas weekly. Coordinate with, and report findings and corrective actions weekly to COR.

G. Smoking: Smoking is prohibited in the cemetery except in designated smoking areas.

H. Dispose of waste and debris in accordance with NFPA 241. Remove from site weekly.

I. Perform other construction, alteration and demolition operations in accordance with 29 CFR 1926.

1.5 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the COR. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage trailers, office trailers) and

01 00 02 - 6 utilities may be erected by the Contractor only with the approval of the COR and shall be built with labor and materials furnished by the

Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work.

C. The Contractor shall, under regulations prescribed by the COR, use temporary roadways constructed by the Contractor when and as authorized by the COR. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The

Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

(FAR 52.236-10)

D. Working space and space available for storing materials shall be as shown on the drawings approved by the COR with agreement of the

Cemetery. Contractor parking will be only in areas and on roadways designated and agreed to by the COR in agreement of the Cemetery.

E. Workmen are subject to rules of the Cemetery applicable to their conduct.

F. Execute work so as to interfere as little as possible with normal functioning of Cemetery as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.

1. Do not store materials and equipment in other than assigned areas.

2. Provide unobstructed access to the Cemetery areas required to remain in operation.

a. Whenever it is required that a connection fee be paid to a public utility provider for the construction project, for such items as water, sewer, electricity, payment of such fee shall be the responsibility of the Contractor.

3. Phasing: To insure such executions, the Contractor shall furnish the

COR with a schedule of approximate Phasing dates on which the

Contractor intends to accomplish work in each specific area of site. The sequencing dates are to be coordinated with the detailed construction sequencing plan submitted by the contractor.

01 00 02 - 7

In addition, the Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site.

Arrange such phasing dates to insure accomplishment of this work in successive sequences mutually agreeable to the Cemetery Director, COR and Contractor.

G. The Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Cemetery’s operations will not be hindered. The Contractor shall permit access to Cemetery personnel through other construction areas which serve as routes of access to such affected areas and equipment. Coordinate alteration work in areas occupied by Cemetery Staff so that Cemetery operations will continue during the construction period. The contractor shall also maintain to allow parking and pedestrian access to all existing public areas to the public during construction.

H. Construction Fence: Before construction operations begin, the

Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches).

Bottom of fences shall extend to 25mm (one inch) above grade.

The temporary fencing shall encompass the construction work area(s) to serve as a pedestrian barrier to alert cemetery patrons of the construction site. Remove the fence when directed by COR. The Fence locations are to be coordinated with the

Cemetery Director prior to installation and covered chain link fence with 90% blockage green privacy/ wind screen.

I. Utilities Services: Maintain existing utility services for the Cemetery at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.

Where necessary to cut existing water, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such

01 00 02 - 8 indication, where directed by COR. All such actions shall be coordinated with the Utility Company involved.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de- energized.

When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without the COR, and Cemetery Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL

INSTALLATION for additional requirements.

2. The Contractor shall submit a request to interrupt any such services to both COR and the Cemetery Director in writing, 48 hours in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. The Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of the Cemetery. Interruption time approved by the Cemetery and COR may occur at other than

Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers and supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls

01 00 02 - 9 or partitions; so that they are completely behind the finished surfaces.

J. To minimize interference of construction activities with flow of

Cemetery traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

K. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF

ROADWAYS.

L. Coordination of Construction with Cemetery Director: The burial activities at a National Cemetery shall take precedence over construction activities. The Contractor must cooperate and coordinate with the Cemetery Director, through the COR, in arranging construction schedule to cause the least possible interference with

Cemetery activities in burial areas. Construction noise during the committal services shall not disturb the service. Trucks and workmen shall not pass through the service area during this period.

1. The Contractor is required to discontinue his work sufficiently in advance of Easter, Mother's Day, Father's Day, Memorial Day, Veteran's Day and/or Federal holidays, to permit him to clean up all areas of operation adjacent to existing burial plots before these dates.

2. Cleaning up shall include the removal of all equipment, tools, materials and debris and leaving the areas in a clean, neat condition.

1.6 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR of areas in which alterations occur, areas which are anticipated routes of access, and furnish a signed report, to the Contracting Officer. This report shall list:

1. Shall note any discrepancies between drawings and existing conditions at site.

01 00 02 - 10

2. Shall designate areas for working space, materials storage and routes of access to areas where alterations occur, and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of

COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by the Contractor with new items in accordance with specifications which will be furnished by the Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR

52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR 852.236-88).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas involved. They shall furnish a report on conditions then existing and other surfaces as compared with conditions of same as noted in first condition survey report.

1. Re-survey report shall also list any damage caused by the

Contractor to such surfaces, despite protection measures; and, will form the basis for determining extent of repair work required of the

Contractor to restore damage caused by the Contractor's workmen in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

1.7 ENVIRONMENTAL CONTROLS

A. Final Cleanup:

1. Upon completion of the project, or as work progresses, remove all construction debris.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations

01 00 02 - 11 in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from the Cemetery.

3. Items of portable equipment and furnishings located in spaces in which work is to be done under this contract shall remain the property of the Government. When spaces are vacated by the

Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND

IMPROVEMENTS

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The

Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the COR.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the

Contractor fails or refuses to repair the damage promptly, the COR may have the necessary work performed and charge the cost to the

Contractor.

(FAR 52.236-9)

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and

01 00 02 - 12

"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.

D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge

Elimination System (NPDES) permit is required for this project. The

Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. The contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the Contractor's method of operations and operations planning and the Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:

1. Designating areas for equipment maintenance and repair;

2. Providing waste receptacles at convenient locations and provide regular collection of wastes;

3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;

4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and

5. Providing adequately maintained sanitary facilities.

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, gas, water, irrigation or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged.

Existing work (walls, electrical work, landscape stone, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed

01 00 02 - 13 before commencing work.

C. At the Contractor's own expense, the Contractor shall immediately restore to service and repair any damage caused by the Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services fire protection systems communications systems

(including telephone) irrigation system control and power which are indicated on drawings and which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"

(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR

52.236-2).

1.11 PHYSICAL DATA

A. Data and information furnished or referred to below is for the

Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by COX DESIGN

ASSOCIATES’ Geotechnical Consultant Terracon:

Terracon

9522 East 47TH Place, Unit D

Tulsa, OK 74145

Telephone No. 918 877 5913

(FAR 52.236-4)

B. Subsurface conditions have been developed by core borings and test pits. Logs of subsurface exploration conducted by Terracon

Geotechnical Consultants are shown diagrammatically on drawings.

C. A copy of the geotechnical investigation is an Appendix to these specifications and shall be considered part of the contract documents.

D. The Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders

01 00 02 - 14 are expected to examine the site of work and logs of borings and, after investigation, decide for themselves the character of materials and make their bids accordingly. Upon proper application to the Department of Veterans Affairs, including approved scheduling bidders will be permitted to make subsurface explorations of their own at site.

1.12 PROFESSIONAL SURVEYING SERVICES

A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections.

The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.

1.13 LAYOUT OF WORK

A. The Contractor shall lay out the work from Government established base lines and bench marks indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The

Contractor shall furnish, at the Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the COR. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the COR until authorized to remove them. If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the COR may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.

(FAR 52.236-17)

B. Establish and plainly mark center lines for each gravesite control monument, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, roads, gravesite control monuments, are in accordance with lines and elevations shown on contract drawings.

C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper

01 00 02 - 15 alignment, orientation, and grade of all major features of work. The

Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:

1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.

D. During progress of work, the Contractor shall have lines, grades, locations and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings. Furnish such certification to the COR before any major items of concrete work are placed. In addition, furnish to the COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.

1. Lines of each addition.

2. Elevations of bottoms of footings.

3. Lines and elevations of sewers and of all outside distribution systems.

4. Lines of grave plot documentation.

5. Lines of elevations of all swales and interment areas.

6. Lines and elevations of roads, streets.

7. Lines and elevations and location of top of pre-placed crypts within their respective plots.

8. Lines and elevations of grade over pre-placed crypts.

9. Northing/Easting coordinate locations and elevation depth below finished grade of all water, sanitary, storm, gas and irrigation structures, directional fittings, control wire and lines.

10. Northing/Easting coordinate locations and elevation for each gravesite grid monument.

E. Upon completion of the work, the Contractor shall furnish the COR with reproducible drawings, in AutoCAD form, at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.

01 00 02 - 16

F. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of

Article "Professional Surveying Services".

1.14 AS-BUILT DRAWINGS

A. The Contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, which will include all contract changes, modifications and clarifications.

1. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the RE/COR's review, as often as requested.

B. At substantial completion, the Contractor shall secure the services of a professional land surveyor, as defined in Section 1.10, to perform a site survey within the project limits in accordance with the NCA Site, Topographic, Utility, Landscape & Soil Survey scope of services, as listed in the appendix of this specification. Elements to be surveyed include, but are not limited to:

1. Location, alignment, and dimension of roads, curbs, walks, parking, and paved areas. Indicate road centerlines with true bearings and lengths by 15 m (50') stationing. Describe curves by designating the points of curvature and tangency by station. Include all curve data as well as location of radius and vertex points. Designate roads with curbs by double lines. Show equalities for intersecting roads by station.

2. Crown, grade, and climb of curb at road crossings contours.

3. Elevations on 50' centers on centerline of roads, edges of roads, and top and bottom of curbs, .

4. Type of pavement of roads.

5. Surface elevations on a 50' grid pattern, except where terrain features require greater detail. At abrupt changes in grade, show elevations at the tops and bottoms of slopes to the nearest 0.1'.

6. Site features of every character identified and located with exact measurements. Include fences, walls, areaways, steps, ramps, railings, gratings, flumes, pads, sprinkler heads, telephone poles, signage, and site

01 00 02 - 17 furnishings.

7. All underground, overhead, and surface electrical utilities and structures. Show size, depth, and top elevation of all electrical structures, based on actual site investigation.

8. All underground and surface civil and mechanical utilities and structures. Show size depth, invert and top elevation of all utility structures, such as manholes, catch basins and headwalls, based on actual site investigation. Indicate direction of flow and size of pipe for all sewers drains and connecting lines between manholes.

9. Grid monuments.

C. The Contractor shall deliver two approved completed sets of as-built drawings to the RE/COR within 15 calendar days after acceptance of the project by the RE/COR.

D. Section 1.12 shall also apply to all shop drawings.

1.15 USE OF ROADWAYS

A. For hauling, use only Contractor constructed temporary roads as indicated on the drawings which are necessary in the performance of contract work. Temporary roads shall be constructed or modified by the

Contractor at the Contractor's expense following approved plans that include: construction, operation, maintenance and restoration. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

B. When new permanent roads are to be a part of this contract, the

Contractor may construct them immediately to facilitate the Cemetery operations. These roads may be used by all who have business thereon within zone of the Cemetery operations.

1.16 COR'S FIELD OFFICE (NOT USED)

1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT (NOT USED)

1.18 TEMPORARY TOILETS

A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water connections, or when approved by COR provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.

1.19 AVAILABILITY AND USE OF UTILITY SERVICES

01 00 02 - 18

A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.

B. The Contractor, at Contractor's expense and in a workmanlike manner satisfactory to the COR, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the

Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.

C. The Contractor shall install meters at the Contractor's expense and furnish the Cemetery a monthly record of the Contractor's usage of electricity as hereinafter specified.

D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials.

E. Electricity (for Construction and Testing): Furnish all temporary electric services.

1. Obtain electricity by connecting to the Cemetery electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Where not available or not convenient to connect to the Cemetery distribution system, the contractor shall supply power via portable generators at own expense. Generators shall be acoustically screened so as not to disturb committal services and/or visitation to the adjacent columbarium and gravesites.

F. Water (for Construction and Testing): Furnish temporary water service.

1. Obtain water by connecting to the Cemetery irrigation distribution system. Backflow preventer may not be required at connections to the irrigation system. Water is available at no cost to the Contractor.

2. If potable water is required and convenient connection is available

01 00 02 - 19 the contractor may connect to the Cemetery potable water distribution system. The contractor shall install reduced pressure backflow preventer at each connection at own expense.

3. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR's discretion) of use of water from the Cemetery's system.

4. Where not available or not convenient to connect to the Cemetery distribution system, the Contractor shall supply water via portable/temporary means at his own expense.

1.20 NEW TELEPHONE EQUIPMENT (NOT USED)

1.21 TESTS

A. Pre-test electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests.

Final test will not be conducted unless pre-tested.

B. Conduct final tests required in various sections of specifications in presence of an authorized representative of the RE/COTR. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.

C. Electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire complex which must be coordinated to work together during normal operation to produce results for which the system is designed.

D. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably short period of time during which operating and environmental conditions remain reasonably constant.

E. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.

1.22 INSTRUCTIONS

A. The Contractor shall furnish Maintenance and Operating manuals and verbal instructions when required by the various sections of the specifications and as hereinafter specified.

B. Manuals: Maintenance and operating manuals (four copies each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of

01 00 02 - 20 equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.

C. Instructions: the Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed instructions to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system; shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed.

This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COR, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.

1.23 GOVERNMENT-FURNISHED PROPERTY

A. The Government shall deliver to the Contractor, the

Government-furnished property shown on drawings.

B. Materials furnished by the Government to be installed by the Contractor will be furnished to the Contractor at the Cemetery.

01 00 02 - 21

C. Storage space for materials will be provided by the Contractor and the

Contractor shall be prepared to unload and store such equipment therein upon its receipt at the Cemetery.

D. Notify COR in writing, 60 days in advance, of date on which

Contractor will be prepared to receive materials furnished by

Government. Arrangements will then be made by the Government for delivery of materials.

1. Immediately upon delivery of materials, the Contractor shall arrange for a joint inspection thereof with a representative of the

Government. At such time the Contractor shall acknowledge receipt of materials described, make notations, and immediately furnish the

Government representative with a written statement as to its condition or shortages.

2. The Contractor thereafter is responsible for such material until such time as acceptance of contract work is made by the Government.

1.24 RELOCATED EQUIPMENT ITEMS (NOT USED)

1.25 CONSTRUCTION SIGN

A. Provide a Construction Sign where directed by the COR. All wood members shall be of framing lumber. Cover sign frame with 0.7 mm (24 gage) galvanized sheet steel nailed securely around edges and on all bearings. Sign face shall be 4 feet x 5 feet and 6 inches. Provide two 100 by 100 mm (4 inch by 4 inch) posts (or equivalent round posts) set 900 mm (three feet) into ground. Set bottom of sign level at 900 mm (three feet) above ground and secure to posts with through bolts.

Make posts full height of sign. Brace posts with 50mm x 100 mm (two by four inch) material as directed.

B. Paint all surfaces of sign and posts two coats of white semi-gloss paint. Border and letters shall be of black gloss paint, except project title which shall be blue gloss paint.

C. Maintain sign and remove it when directed by the COR.

D. Detail Drawing of construction sign showing required legend and other characteristics of sign is included in the drawings.

1.26 SAFETY SIGN

A. Provide a Safety Sign where directed by COR. Signboard shall be shall be three feet x four feet, 19 mm (3/4-inch) thick exterior grade plywood. Provide two 100 mm by 100 mm (four by four inch) posts extending full height of sign and 900 mm (three feet) into ground. Set

01 00 02 - 22 bottom of sign level at 1200 mm (four feet) above ground.

B. Paint all surfaces of Safety Sign and posts with one prime coat and two coats of white gloss paint. Letters and design shall be painted with gloss paint of colors noted.

C. Maintain sign and remove it when directed by COR.

D. Detail Drawing of safety sign showing required legend and other characteristics of sign is included in the drawings.

E. Post the number of accident free days on a daily basis.

1.27 CONSTRUCTION DIGITAL IMAGES

A. During construction period through completion, furnish Department of Veterans Affairs weekly color digital photographs of construction progress (8 to 10 images per week.) Photographs of the reinforcing steel shall be taken after all reinforcing steel, sleeves, inserts, etc. are in place but prior to setting of runways. Photographs must show distinctly, at as large a scale as possible, all parts of work embraced in picture.

B. Photographs are to be taken with a high-resolution digital camera, minimum 6 megapixels, with good wide-angle capability. The images shall be recorded in JPEG format with a minimum of 24-bit color and no reduction in actual picture size.

1. Compressed size of the file shall be no less than 80% or the original with no loss of information.

2. File names shall contain the Project number, the date the image was taken, and a unique sequential identifier, for example:

101CM3202_10-01-2013_0001.Use underscore, not spaces in digital file names.

C. The digital photo files shall become property of Government and will be both…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .